SlideShare a Scribd company logo
1 of 101
Presenter
                             Cian O’Donnchadha BEng CEng MIEI MIStrutE
4th Year Civil Engineering   Arup Consulting Engineers

                                                                         5th March 2009




 NUIG School of Engineering
Wexford Opera House
Presentation Overview

   • Structural Development
   • Precast Concrete – Voided Slab
   • Precast Concrete – Beams and Double T Units
   • Site Progress – August 2009 to November 2009
   • Fairfaced Concrete
   • Site Progress – Weather
   • Site Progress – Dec 2009 to March 2010




NUIG School of Engineering
Wexford Opera House
Structural Development




NUIG School of Engineering
Wexford Opera House
KEY STRUCTURAL CHOICE CRITERIA
 Architectural Issues at scheme stage– Grid
 • An initial planning grid of 1.5 m
 • A west wing width of 18.0 m and an east wing width of 11.0 metres.
 • A grid spacing along the building edge of 7.5 m
 • A notional building height of 4 storeys was assumed at concept stage.
 • Central Bay 30m long

 West Wing – Structural Grids

 4.5m Span + 9.0m Span + 4.5m Span                             2 No 9.0m Spans




 3 No 6.0m Spans




NUIG School of Engineering
Wexford Opera House
Other Factors Influencing Structural Choice
  In addition to the usual issues of cost and programme we have also considered issues such as adaptability,
  flexibility, partition systems, weights (foundation loads) etc.

  Site Disruption:
  •Amount of traffic into and out of site.
  •Nuisance caused by construction process (Noise, Vibration, Dust etc)
  •Equipment associated with the construction process.
  •Neighbour issues

  Adaptability:
  •Capacity for future service penetrations (both vertical and horizontal).
  •Ease of insertion or removal of stairs, lifts, floors.
  •Response to changes in loading requirements or capacity for late Client Changes.

  Services:
  •Ease of services integration. Flat soffits or limited steel beam depths are ideal. Can primary and secondary
  service runs follow beam/downstand layouts?
  •Are there problems associated with vertical ductwork.
  •Ease of addition of future services

  Procurement:
  •Lead in times and any effect on design programme/design freeze.




NUIG School of Engineering
Wexford Opera House
Buildability:
 •Achievement of good tolerances/good fit.
 •Sensitivity to weather conditions.
 •Lack of reliance on temporary works and following work (cleanliness)

 Cladding:
 •Ease of base and head fixings. Stiffness and stability provided by base structure.

 Soffit Quality:
 •This covers soffit treatment. Solutions such as precast slabs may require only painting, steel frames may require
 suspended ceilings. This will also have an effect on thermal issues.

 Partitions:
 •Ease of base and head fixings, flat soffit allows for easier and quicker installation.
 •Does the structural grid tie in with planning grid?

 Thermal:
 •Effect of structure mass on diurnal temperature fluctuations within building.
 •Ability to cool and heat a structure out of hours (night time cooling).
 •Ribbed soffits have more exposed area and are more efficient than flat soffits




NUIG School of Engineering
Wexford Opera House
Depth:
 •Influence of slab depth on services and building envelope.

 Sound/Acoustics:
 •Influence of structure mass and soffit on sound/acoustic characteristics

 Speed:
 •Influence of structural system on construction programme.
 •Early weather tightness and optimisation of following trades.

 Stability:
 •Lateral stability, ease of provision and effect on programme.
 •Construction of insitu concrete core walls may be on critical path.

 Foundations:
 •Influence on total building weight and thus on foundations. Limitations on pile numbers and rate of piling.

 Cost:
 •Overall cost (including effects of time). Fast construction may have higher cost for construction. Shorter overall construction
 programme may give lower total cost if cost of money is allowed for.




NUIG School of Engineering
Wexford Opera House
Scheme workshop with RMJM architects




NUIG School of Engineering
Wexford Opera House
Models of different Structural Solutions




NUIG School of Engineering
Wexford Opera House
Choice of Material
 Insitu Concrete Construction
  Advantages                                                Disadvantages

  •Increased thermal mass, particularly with ribbed         •An exposed concrete soffit can be expensive when
  forms of construction.                                    producing a high quality finish. (Costs may be offset
                                                            against suspended ceiling costs).
  •With flat slab construction, detailing of partitioning   •With the use of post tensioned concrete a limited
  systems is simple                                         number of contractors are available (2-3).
  •On a 7.5 m grid, good cladding support with              •A heavier form of construction (compared to steel),
  minimal deflection.                                       which can result in an increase in foundation costs.
  •On long span particularly post tensioned, vibration      •In general with insitu construction there is more
  and deflection can be more easily controlled              disruption to the site due to the construction process
  compared to steel                                         (Concrete deliveries etc)
  •Easier to accommodate changes to elements/details        •Longer site period compared to steel.
  at a later stage
  •Shallower form of construction compared to steel.
  •Short lead in, 6 – 8 weeks




NUIG School of Engineering
Wexford Opera House
Choice of Material
 Precast Concrete Construction
  Advantages                                             Disadvantages

  •Prestressed units control deflection, vibration and
                                                         •Not ideally suited to a 2 way spanning system.
  cracking.
  •High quality finish can be part of a factory-produced •Lead in times are comparable with steel (12 – 14
  product.                                               weeks).
  •Exposed concrete aids thermal mass particularly if    •Joints/details need careful attention and early
  ribbed.                                                resolution.
                                                         •If a high quality frame is required, only 2 –3
  •Good for one-way spanning systems.
                                                         contractors can supply a satisfactory product.




NUIG School of Engineering
Wexford Opera House
Choice of Material
 Steel Frame Construction
  Advantages                                       Disadvantages

  •Speed on site.                                  •Long span options tend to experience vibrations and
                                                   deflection problems.
  •Procurement – good range of locally available   •Unless structure and slab is exposed (with the
  subcontractors                                   resulting industrial type finish), little thermal mass
                                                   advantages are gained.
  •Minimal site disruption.                        •With the fabrication drawing and manufacture
                                                   programme, an earlier design freeze is required.
  •Lightest form of construction generally.        •Late alterations are more difficult to accommodate.
                                                   •Cladding support may cause problems on long
                                                   spans.
                                                   •A deeper form of construction, in many cases adding
                                                   to the overall building height as compared to other
                                                   alternatives.
                                                   •Lead in of 12-14 weeks required (from drawings to
                                                   steel on site).




NUIG School of Engineering
Wexford Opera House
Options for the West and East Wing
 The West Wing
 8 structural options have been developed on the basis of the 2 structural grids as highlighted
      •Grid Type A 14.0m span




      •Grid Type B 2No. x 7.75m spans




NUIG School of Engineering
Wexford Opera House
The following 8 options were investigated in the West Wing

 Option 1: Voided Flat Slab (Grid Type A).
 Option 2: Composite Concrete Wide Slab onto Cellular Beams (Grid Type A).
 Option 3: Post-Tensioned Concrete Rib Slab (Grid Type A).
 Option 4: Hollowcore Precast Floor and Steel Beams (Grid Type A).
 Option 5: Voided Concrete Flat Slab (Grid Type B).
 Option 6: Composite Concrete Wide Slab onto Steel Beams (Grid Type B).
 Option 7: Steel Metal Deck (Grid Type B).
 Option 8: In-Situ Flat Slab (Grid Type B).




NUIG School of Engineering
Wexford Opera House
Option 1: Voided Flat Slab (Grid Type A).
  Advantages for a two-way precast soffit system          Disadvantages
  (Voided Slab) reinforced
  •High quality, steel mould finish ready to paint.       •Long lead in 12-14 weeks.
  •Shallower form of construction compared to             •Expensive.
  traditional insitu concrete.
  •Good fire resistance / Acoustics                       •Limited specialist Sub-contractor (2).
  •Good thermally.                                        •Not previously used in UK or Ireland (European).
  •Good for partition head/base fixings.                  •Openings restricted to central areas.
  •Slim and lighter form of construction due to plastic
  void former.
  •Once on site quick installation.




NUIG School of Engineering
Wexford Opera House
Insitu Flat Slab




                                            Composite Steel Frame and metal decking




 Precast beams and Precast coffered slabs


NUIG School of Engineering
Wexford Opera House
Precast Concrete Voided Slab

 NUIG School of Engineering
Wexford Opera House
Oran Precast, Oranmore, Co Galway




 NUIG School of Engineering
 Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
Precast Concrete Beams & Double T units

 NUIG School of Engineering
Wexford Opera House
Banagher Concrete, Banagher , Co Offaly

 NUIG School of Engineering
 Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
Site Progress Photographs – Aug 2009 to Nov 2010

NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
Excavation & Replacement




NUIG School of Engineering
Wexford Opera House
Piling Operations – Set Out




NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
Concrete – Fairfaced Concrete

 NUIG School of Engineering
 Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
Site Progress – Weather

 NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
Site Progress – November 2009 to March 2010

 NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House
NUIG School of Engineering
Wexford Opera House

More Related Content

What's hot

Infilled frame,a type of tubular frame structural system
Infilled frame,a type of tubular frame structural systemInfilled frame,a type of tubular frame structural system
Infilled frame,a type of tubular frame structural systemMUSTAFEEZ UR RAHMAN
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT Nischay N Gowda
 
Development control rules and regulation
Development control rules and regulationDevelopment control rules and regulation
Development control rules and regulationMANINANDANSAHU
 
Modular coordination
Modular coordinationModular coordination
Modular coordinationAtul Verma
 
minggu 4 - rekayasa thermal.pdf
minggu 4 - rekayasa thermal.pdfminggu 4 - rekayasa thermal.pdf
minggu 4 - rekayasa thermal.pdfIyanRangga
 
SHANTHI PRIYA RESIDENCE- MURALI ARCHITECTS
SHANTHI PRIYA RESIDENCE- MURALI ARCHITECTSSHANTHI PRIYA RESIDENCE- MURALI ARCHITECTS
SHANTHI PRIYA RESIDENCE- MURALI ARCHITECTSmurugan Murali
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE VISHNU VIJAYAN
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structureVikas Mehta
 
revised implementing rules and regulations for bp 220 ... - dhsud
revised implementing rules and regulations for bp 220 ... - dhsudrevised implementing rules and regulations for bp 220 ... - dhsud
revised implementing rules and regulations for bp 220 ... - dhsudlysalols17
 
Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...oyinleye
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise BuildingsPrasad Thanthratey
 
Prefabrication - building construction
Prefabrication - building constructionPrefabrication - building construction
Prefabrication - building constructionMoksha Bhatia
 
Builiding Byes laws
Builiding Byes laws Builiding Byes laws
Builiding Byes laws Shourya Puri
 
Post tension Floor System
Post tension Floor SystemPost tension Floor System
Post tension Floor SystemAditya Shah
 
Contour Crafting
Contour CraftingContour Crafting
Contour CraftingTemy Peter
 

What's hot (20)

Infilled frame,a type of tubular frame structural system
Infilled frame,a type of tubular frame structural systemInfilled frame,a type of tubular frame structural system
Infilled frame,a type of tubular frame structural system
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT
 
Development control rules and regulation
Development control rules and regulationDevelopment control rules and regulation
Development control rules and regulation
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 
minggu 4 - rekayasa thermal.pdf
minggu 4 - rekayasa thermal.pdfminggu 4 - rekayasa thermal.pdf
minggu 4 - rekayasa thermal.pdf
 
SHANTHI PRIYA RESIDENCE- MURALI ARCHITECTS
SHANTHI PRIYA RESIDENCE- MURALI ARCHITECTSSHANTHI PRIYA RESIDENCE- MURALI ARCHITECTS
SHANTHI PRIYA RESIDENCE- MURALI ARCHITECTS
 
Addressing Safety Through Design for Dindoshi Terminal (Draft)
Addressing Safety Through Design for Dindoshi Terminal (Draft)Addressing Safety Through Design for Dindoshi Terminal (Draft)
Addressing Safety Through Design for Dindoshi Terminal (Draft)
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structure
 
revised implementing rules and regulations for bp 220 ... - dhsud
revised implementing rules and regulations for bp 220 ... - dhsudrevised implementing rules and regulations for bp 220 ... - dhsud
revised implementing rules and regulations for bp 220 ... - dhsud
 
Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Prefabrication - building construction
Prefabrication - building constructionPrefabrication - building construction
Prefabrication - building construction
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Builiding Byes laws
Builiding Byes laws Builiding Byes laws
Builiding Byes laws
 
Post tension Floor System
Post tension Floor SystemPost tension Floor System
Post tension Floor System
 
Contour Crafting
Contour CraftingContour Crafting
Contour Crafting
 
Additives & Admixtures
 Additives & Admixtures Additives & Admixtures
Additives & Admixtures
 
Gfrc
GfrcGfrc
Gfrc
 
Kevin lynch
Kevin lynchKevin lynch
Kevin lynch
 

Viewers also liked

3D printing
3D printing3D printing
3D printingStudent
 
Post Tension Services India Pvt. Ltd.
Post Tension Services India Pvt. Ltd.Post Tension Services India Pvt. Ltd.
Post Tension Services India Pvt. Ltd.Haituk Patel
 
Applications of 3D printers in construction industry - Nithin N
Applications of 3D printers in construction industry - Nithin NApplications of 3D printers in construction industry - Nithin N
Applications of 3D printers in construction industry - Nithin NNithin N
 
3D Printer in the civil engineering
3D Printer in the civil engineering3D Printer in the civil engineering
3D Printer in the civil engineeringIsmaël Hachim
 
Bubble Deck Technology Mukkara Raviteja
Bubble Deck Technology Mukkara RavitejaBubble Deck Technology Mukkara Raviteja
Bubble Deck Technology Mukkara RavitejaRaviteja Mukkara
 
M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge
M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge
M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge vaignan
 
CCTV HQ Model Building Process
CCTV HQ Model Building ProcessCCTV HQ Model Building Process
CCTV HQ Model Building Processetiennema
 
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, DubaiDesign, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, DubaiAr. Md Shahroz Alam
 
Multi storey structural steel structures
Multi storey structural steel structuresMulti storey structural steel structures
Multi storey structural steel structuresThomas Britto
 
3D PRINTER Seminar fair report (pdf)
3D PRINTER Seminar fair report (pdf)3D PRINTER Seminar fair report (pdf)
3D PRINTER Seminar fair report (pdf)Arjun Raveendran
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PROAli Meer
 
CCTV Building, A Structural Design Overview
CCTV Building, A Structural Design OverviewCCTV Building, A Structural Design Overview
CCTV Building, A Structural Design OverviewPeter Bach
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildingsKarthik Suresh
 

Viewers also liked (17)

3D printing
3D printing3D printing
3D printing
 
Post Tension Services India Pvt. Ltd.
Post Tension Services India Pvt. Ltd.Post Tension Services India Pvt. Ltd.
Post Tension Services India Pvt. Ltd.
 
Robotics
RoboticsRobotics
Robotics
 
Applications of 3D printers in construction industry - Nithin N
Applications of 3D printers in construction industry - Nithin NApplications of 3D printers in construction industry - Nithin N
Applications of 3D printers in construction industry - Nithin N
 
3D Printer in the civil engineering
3D Printer in the civil engineering3D Printer in the civil engineering
3D Printer in the civil engineering
 
Bubble Deck Technology Mukkara Raviteja
Bubble Deck Technology Mukkara RavitejaBubble Deck Technology Mukkara Raviteja
Bubble Deck Technology Mukkara Raviteja
 
M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge
M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge
M.Tech Structural Engineering Project of Voided and Cellular Deck slab Bridge
 
CCTV HQ Model Building Process
CCTV HQ Model Building ProcessCCTV HQ Model Building Process
CCTV HQ Model Building Process
 
Hollow Block
Hollow Block Hollow Block
Hollow Block
 
Multi Storey Steel Structures
Multi Storey Steel StructuresMulti Storey Steel Structures
Multi Storey Steel Structures
 
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, DubaiDesign, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
 
Multi storey structural steel structures
Multi storey structural steel structuresMulti storey structural steel structures
Multi storey structural steel structures
 
3D PRINTER Seminar fair report (pdf)
3D PRINTER Seminar fair report (pdf)3D PRINTER Seminar fair report (pdf)
3D PRINTER Seminar fair report (pdf)
 
Burj Al Arab
Burj Al ArabBurj Al Arab
Burj Al Arab
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
CCTV Building, A Structural Design Overview
CCTV Building, A Structural Design OverviewCCTV Building, A Structural Design Overview
CCTV Building, A Structural Design Overview
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 

Similar to NUIG New Engineering Building

Precast concrete - drywall
Precast  concrete - drywallPrecast  concrete - drywall
Precast concrete - drywallDenis Patel
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingAnchitSharma17
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdfNithyashree594058
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
Finding the right build method
Finding the right build methodFinding the right build method
Finding the right build methodSelf Build Zone
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSakshiMahadik3
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structureNisshantSinghSaud
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSjagrutib22
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfGourhariBiswas1
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle SlabAkshay Gawade
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques Deepak Pradhan
 
retrofitting of existing rcc members Different strengthening techniques
retrofitting of existing rcc members Different strengthening techniquesretrofitting of existing rcc members Different strengthening techniques
retrofitting of existing rcc members Different strengthening techniquessuraj prasanna kumar
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1Natalie Ulza
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Rajesh Kolli
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptxdharmveersingh60
 

Similar to NUIG New Engineering Building (20)

Precast concrete - drywall
Precast  concrete - drywallPrecast  concrete - drywall
Precast concrete - drywall
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Precast Construction
Precast ConstructionPrecast Construction
Precast Construction
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
 
national building code
national building codenational building code
national building code
 
Finding the right build method
Finding the right build methodFinding the right build method
Finding the right build method
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
 
retrofitting of existing rcc members Different strengthening techniques
retrofitting of existing rcc members Different strengthening techniquesretrofitting of existing rcc members Different strengthening techniques
retrofitting of existing rcc members Different strengthening techniques
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptx
 

Recently uploaded

PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesShubhangi Sonawane
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 

Recently uploaded (20)

PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 

NUIG New Engineering Building

  • 1. Presenter Cian O’Donnchadha BEng CEng MIEI MIStrutE 4th Year Civil Engineering Arup Consulting Engineers 5th March 2009 NUIG School of Engineering Wexford Opera House
  • 2. Presentation Overview • Structural Development • Precast Concrete – Voided Slab • Precast Concrete – Beams and Double T Units • Site Progress – August 2009 to November 2009 • Fairfaced Concrete • Site Progress – Weather • Site Progress – Dec 2009 to March 2010 NUIG School of Engineering Wexford Opera House
  • 3. Structural Development NUIG School of Engineering Wexford Opera House
  • 4. KEY STRUCTURAL CHOICE CRITERIA Architectural Issues at scheme stage– Grid • An initial planning grid of 1.5 m • A west wing width of 18.0 m and an east wing width of 11.0 metres. • A grid spacing along the building edge of 7.5 m • A notional building height of 4 storeys was assumed at concept stage. • Central Bay 30m long West Wing – Structural Grids 4.5m Span + 9.0m Span + 4.5m Span 2 No 9.0m Spans 3 No 6.0m Spans NUIG School of Engineering Wexford Opera House
  • 5. Other Factors Influencing Structural Choice In addition to the usual issues of cost and programme we have also considered issues such as adaptability, flexibility, partition systems, weights (foundation loads) etc. Site Disruption: •Amount of traffic into and out of site. •Nuisance caused by construction process (Noise, Vibration, Dust etc) •Equipment associated with the construction process. •Neighbour issues Adaptability: •Capacity for future service penetrations (both vertical and horizontal). •Ease of insertion or removal of stairs, lifts, floors. •Response to changes in loading requirements or capacity for late Client Changes. Services: •Ease of services integration. Flat soffits or limited steel beam depths are ideal. Can primary and secondary service runs follow beam/downstand layouts? •Are there problems associated with vertical ductwork. •Ease of addition of future services Procurement: •Lead in times and any effect on design programme/design freeze. NUIG School of Engineering Wexford Opera House
  • 6. Buildability: •Achievement of good tolerances/good fit. •Sensitivity to weather conditions. •Lack of reliance on temporary works and following work (cleanliness) Cladding: •Ease of base and head fixings. Stiffness and stability provided by base structure. Soffit Quality: •This covers soffit treatment. Solutions such as precast slabs may require only painting, steel frames may require suspended ceilings. This will also have an effect on thermal issues. Partitions: •Ease of base and head fixings, flat soffit allows for easier and quicker installation. •Does the structural grid tie in with planning grid? Thermal: •Effect of structure mass on diurnal temperature fluctuations within building. •Ability to cool and heat a structure out of hours (night time cooling). •Ribbed soffits have more exposed area and are more efficient than flat soffits NUIG School of Engineering Wexford Opera House
  • 7. Depth: •Influence of slab depth on services and building envelope. Sound/Acoustics: •Influence of structure mass and soffit on sound/acoustic characteristics Speed: •Influence of structural system on construction programme. •Early weather tightness and optimisation of following trades. Stability: •Lateral stability, ease of provision and effect on programme. •Construction of insitu concrete core walls may be on critical path. Foundations: •Influence on total building weight and thus on foundations. Limitations on pile numbers and rate of piling. Cost: •Overall cost (including effects of time). Fast construction may have higher cost for construction. Shorter overall construction programme may give lower total cost if cost of money is allowed for. NUIG School of Engineering Wexford Opera House
  • 8. Scheme workshop with RMJM architects NUIG School of Engineering Wexford Opera House
  • 9. Models of different Structural Solutions NUIG School of Engineering Wexford Opera House
  • 10. Choice of Material Insitu Concrete Construction Advantages Disadvantages •Increased thermal mass, particularly with ribbed •An exposed concrete soffit can be expensive when forms of construction. producing a high quality finish. (Costs may be offset against suspended ceiling costs). •With flat slab construction, detailing of partitioning •With the use of post tensioned concrete a limited systems is simple number of contractors are available (2-3). •On a 7.5 m grid, good cladding support with •A heavier form of construction (compared to steel), minimal deflection. which can result in an increase in foundation costs. •On long span particularly post tensioned, vibration •In general with insitu construction there is more and deflection can be more easily controlled disruption to the site due to the construction process compared to steel (Concrete deliveries etc) •Easier to accommodate changes to elements/details •Longer site period compared to steel. at a later stage •Shallower form of construction compared to steel. •Short lead in, 6 – 8 weeks NUIG School of Engineering Wexford Opera House
  • 11. Choice of Material Precast Concrete Construction Advantages Disadvantages •Prestressed units control deflection, vibration and •Not ideally suited to a 2 way spanning system. cracking. •High quality finish can be part of a factory-produced •Lead in times are comparable with steel (12 – 14 product. weeks). •Exposed concrete aids thermal mass particularly if •Joints/details need careful attention and early ribbed. resolution. •If a high quality frame is required, only 2 –3 •Good for one-way spanning systems. contractors can supply a satisfactory product. NUIG School of Engineering Wexford Opera House
  • 12. Choice of Material Steel Frame Construction Advantages Disadvantages •Speed on site. •Long span options tend to experience vibrations and deflection problems. •Procurement – good range of locally available •Unless structure and slab is exposed (with the subcontractors resulting industrial type finish), little thermal mass advantages are gained. •Minimal site disruption. •With the fabrication drawing and manufacture programme, an earlier design freeze is required. •Lightest form of construction generally. •Late alterations are more difficult to accommodate. •Cladding support may cause problems on long spans. •A deeper form of construction, in many cases adding to the overall building height as compared to other alternatives. •Lead in of 12-14 weeks required (from drawings to steel on site). NUIG School of Engineering Wexford Opera House
  • 13. Options for the West and East Wing The West Wing 8 structural options have been developed on the basis of the 2 structural grids as highlighted •Grid Type A 14.0m span •Grid Type B 2No. x 7.75m spans NUIG School of Engineering Wexford Opera House
  • 14. The following 8 options were investigated in the West Wing Option 1: Voided Flat Slab (Grid Type A). Option 2: Composite Concrete Wide Slab onto Cellular Beams (Grid Type A). Option 3: Post-Tensioned Concrete Rib Slab (Grid Type A). Option 4: Hollowcore Precast Floor and Steel Beams (Grid Type A). Option 5: Voided Concrete Flat Slab (Grid Type B). Option 6: Composite Concrete Wide Slab onto Steel Beams (Grid Type B). Option 7: Steel Metal Deck (Grid Type B). Option 8: In-Situ Flat Slab (Grid Type B). NUIG School of Engineering Wexford Opera House
  • 15. Option 1: Voided Flat Slab (Grid Type A). Advantages for a two-way precast soffit system Disadvantages (Voided Slab) reinforced •High quality, steel mould finish ready to paint. •Long lead in 12-14 weeks. •Shallower form of construction compared to •Expensive. traditional insitu concrete. •Good fire resistance / Acoustics •Limited specialist Sub-contractor (2). •Good thermally. •Not previously used in UK or Ireland (European). •Good for partition head/base fixings. •Openings restricted to central areas. •Slim and lighter form of construction due to plastic void former. •Once on site quick installation. NUIG School of Engineering Wexford Opera House
  • 16. Insitu Flat Slab Composite Steel Frame and metal decking Precast beams and Precast coffered slabs NUIG School of Engineering Wexford Opera House
  • 17. Precast Concrete Voided Slab NUIG School of Engineering Wexford Opera House
  • 18. Oran Precast, Oranmore, Co Galway NUIG School of Engineering Wexford Opera House
  • 19. NUIG School of Engineering Wexford Opera House
  • 20. NUIG School of Engineering Wexford Opera House
  • 21. NUIG School of Engineering Wexford Opera House
  • 22. NUIG School of Engineering Wexford Opera House
  • 23. NUIG School of Engineering Wexford Opera House
  • 24. NUIG School of Engineering Wexford Opera House
  • 25. NUIG School of Engineering Wexford Opera House
  • 26. NUIG School of Engineering Wexford Opera House
  • 27. NUIG School of Engineering Wexford Opera House
  • 28. NUIG School of Engineering Wexford Opera House
  • 29. NUIG School of Engineering Wexford Opera House
  • 30. NUIG School of Engineering Wexford Opera House
  • 31. Precast Concrete Beams & Double T units NUIG School of Engineering Wexford Opera House
  • 32. Banagher Concrete, Banagher , Co Offaly NUIG School of Engineering Wexford Opera House
  • 33. NUIG School of Engineering Wexford Opera House
  • 34. NUIG School of Engineering Wexford Opera House
  • 35. NUIG School of Engineering Wexford Opera House
  • 36. NUIG School of Engineering Wexford Opera House
  • 37. NUIG School of Engineering Wexford Opera House
  • 38. NUIG School of Engineering Wexford Opera House
  • 39. NUIG School of Engineering Wexford Opera House
  • 40. Site Progress Photographs – Aug 2009 to Nov 2010 NUIG School of Engineering Wexford Opera House
  • 41. NUIG School of Engineering Wexford Opera House
  • 42. NUIG School of Engineering Wexford Opera House
  • 43. NUIG School of Engineering Wexford Opera House
  • 44. Excavation & Replacement NUIG School of Engineering Wexford Opera House
  • 45. Piling Operations – Set Out NUIG School of Engineering Wexford Opera House
  • 46. NUIG School of Engineering Wexford Opera House
  • 47. NUIG School of Engineering Wexford Opera House
  • 48. NUIG School of Engineering Wexford Opera House
  • 49. NUIG School of Engineering Wexford Opera House
  • 50. NUIG School of Engineering Wexford Opera House
  • 51. NUIG School of Engineering Wexford Opera House
  • 52. NUIG School of Engineering Wexford Opera House
  • 53. NUIG School of Engineering Wexford Opera House
  • 54. NUIG School of Engineering Wexford Opera House
  • 55. NUIG School of Engineering Wexford Opera House
  • 56. NUIG School of Engineering Wexford Opera House
  • 57. Concrete – Fairfaced Concrete NUIG School of Engineering Wexford Opera House
  • 58. NUIG School of Engineering Wexford Opera House
  • 59. NUIG School of Engineering Wexford Opera House
  • 60. NUIG School of Engineering Wexford Opera House
  • 61. NUIG School of Engineering Wexford Opera House
  • 62. NUIG School of Engineering Wexford Opera House
  • 63. NUIG School of Engineering Wexford Opera House
  • 64. NUIG School of Engineering Wexford Opera House
  • 65. NUIG School of Engineering Wexford Opera House
  • 66. NUIG School of Engineering Wexford Opera House
  • 67. NUIG School of Engineering Wexford Opera House
  • 68. NUIG School of Engineering Wexford Opera House
  • 69. NUIG School of Engineering Wexford Opera House
  • 70. NUIG School of Engineering Wexford Opera House
  • 71. Site Progress – Weather NUIG School of Engineering Wexford Opera House
  • 72. NUIG School of Engineering Wexford Opera House
  • 73. NUIG School of Engineering Wexford Opera House
  • 74. NUIG School of Engineering Wexford Opera House
  • 75. NUIG School of Engineering Wexford Opera House
  • 76. NUIG School of Engineering Wexford Opera House
  • 77. NUIG School of Engineering Wexford Opera House
  • 78. NUIG School of Engineering Wexford Opera House
  • 79. NUIG School of Engineering Wexford Opera House
  • 80. NUIG School of Engineering Wexford Opera House
  • 81. Site Progress – November 2009 to March 2010 NUIG School of Engineering Wexford Opera House
  • 82. NUIG School of Engineering Wexford Opera House
  • 83. NUIG School of Engineering Wexford Opera House
  • 84. NUIG School of Engineering Wexford Opera House
  • 85. NUIG School of Engineering Wexford Opera House
  • 86. NUIG School of Engineering Wexford Opera House
  • 87. NUIG School of Engineering Wexford Opera House
  • 88. NUIG School of Engineering Wexford Opera House
  • 89. NUIG School of Engineering Wexford Opera House
  • 90. NUIG School of Engineering Wexford Opera House
  • 91. NUIG School of Engineering Wexford Opera House
  • 92. NUIG School of Engineering Wexford Opera House
  • 93. NUIG School of Engineering Wexford Opera House
  • 94. NUIG School of Engineering Wexford Opera House
  • 95. NUIG School of Engineering Wexford Opera House
  • 96. NUIG School of Engineering Wexford Opera House
  • 97. NUIG School of Engineering Wexford Opera House
  • 98. NUIG School of Engineering Wexford Opera House
  • 99. NUIG School of Engineering Wexford Opera House
  • 100. NUIG School of Engineering Wexford Opera House
  • 101. NUIG School of Engineering Wexford Opera House