SlideShare a Scribd company logo
1 of 6
Progress Billing Definition
A construction project typically involves many different trades in order to
reach completion. Therefore, it can be just as daunting a task to submit for
payment to a client along the way. The Owner of a construction project
relies on the project architect, lender and sometimes a third party
inspection company to make certain that payment is applied for correctly
and within reason. Once the progress billing definition is truly understood
you will smoothly pass through the steps of preparing and submitting
everything needed to complete a construction project.
Start With a Good Schedule of Values
A schedule of values is a list with the dollar amount assigned to each area of
work that will be completed on a construction project. A construction
project is broken out by each scope of work and typically separated
according to the Construction Specifications Institute Divisions (CSI).
Therefore, it is best to separate a project’s Schedule of Values into basic CSI
divisions. Examples of these divisions are General Conditions, Sitework,
Utilities, Concrete, Steel, etc. Once the areas of the scope of work are
defined, then a corresponding value is assigned to each one so that a
percentage complete can be established for each item as progress is made
on the project. In the United States the industry standard format for a billing
schedule of values is per AIA form G703. Progress billing accounting issues
are common, so it is essential that a good schedule of values is established
early.
Establish the Rate of Construction Retainage
A construction contract will typically require that “Retainage” be withheld
from each application for payment in order to provide the Owner or lender
protection from the Contractor not completing the entire project. 5% or
10% may be withheld from each payment to the Contractor, and the funds
held in reserve until the project punch list is completed at the end of the
project. Therefore, each progress billing must take this retainage amount
into account on each line item of the schedule of values and ultimately on
the bottom line of the application.
Establish the Frequency of Progress Payments
A progress billing is exactly that, a billing that progresses towards
completion a percentage at a time. Therefore, it is necessary to establish the
frequency that each application shall be submitted. Often times, a progress
billing will be submitted to an Owner or Lender once per month but
complicated projects may require more frequency. A progress billing must
specify the current period percentage of completion and the cumulative
total and this must be done for both the individual items and the total.
Establish the Percentage of Completion
Vendors will submit their invoices for payment to a contractor for the
amount of work that they have completed over the period. A contractor
must confirm that the work has actually been completed according to this
percentage and then include the corresponding amount within the progress
billing to the Owner or Lender. This process is performed for each scope of
work and then all completed items percentages are totaled.
Submit it Right and Get PAID
Progress billings are often rejected by an Owner or Lender because of
incorrect completion percentages, incorrect math, or applications that are
submitted tardy. In order to achieve profitable progress billing revenue
recognition, effective processing is important. Be sure to review vendor
invoices and percentage completions with field supervision to avoid
over/under billings. Also, be certain to double check math calculations or
use construction software to avoid rejected payment applications due to
math mistakes. Finally, submit your progress billing forms on time! This is an
easy way to get credit with an Owner or Lender because it gives them ample
time to review the application.
Progress Billing Sample
UNCONDITIONAL FINAL WAIVER AND RELEASE OF LIENS AND CLAIMS
OWNER: Business X, LLC.
PROJECT NAME: PRIORITY MANAGEMENT
For and in exchange of the sum of $ , the sufficiency of
which is hereby acknowledged, the undersigned Contractor, subcontractor,
consultant, materialmen or laborer (hereinafter the “Undersigned”)
warrants and represents as follows:
(1) The Undersigned has been employed by Business X, LLC. to furnish labor,
materials, or services in connection with the construction of improvements
on or to the above referenced project.
(2) The Undersigned has performed all labor, materials, or services required
under its Contract, Subcontract or Purchase Order in full compliance with all
terms and conditions thereof, and all applicable plans and specifications.
(3) Any and all contractors, subcontractors, laborers, suppliers and
materialmen that have provided labor, material, or other services to the
Undersigned for use or incorporation into the construction of the
improvements to the Project have been paid in full for all amounts due and
owing to them on the Project, or shall be promptly paid in full from the
proceeds of the payment referenced above and there are no outstanding
claims of any character arising out of or related to the Undersigned’s
activities on or improvements to the Project. If this Waiver is signed by the
Prime Contractor, attached hereto as Exhibit A is a complete list of all
subcontractors and suppliers retained by such party as of the date of this
Waiver.
(4) The Undersigned waives and releases any and all liens, lien rights, claims
of liens, and any other claims for payment for labor, material or equipment
of any type or description that it may have against the Owner, the Owner’s
Project Manager, the Owner’s Engineering Consultant, the Architect for the
Project, the Prime Contractor (if this Waiver is signed by a subcontractor or
supplier) and/or any person with a legal or equitable interest in Project,
arising out of or in any fashion related to, any labor, materials or services
furnished by, through or under the Undersigned on, or used in connection
with, the Project, without exception.
(5) This Final Waiver and Release constitutes a representation by the Person
signing this document, for and on behalf of the Undersigned, that the
payment referenced above constitutes full and complete payment for all
work performed and costs or expense incurred (including, but not limited to,
costs for supervision, field office overhead, home office overhead, interest
on capital, profit and general conditions cost) by, through or under the
Undersigned relative to the work of improvements at the Project, including
all retainage. More specifically, the Undersigned hereby waives, quitclaims,
and releases any claim of damages due to delay, hindrance, interference,
acceleration, inefficiencies or extra work, or any other claims of any kind it
may have against the Prime Contractor (if this Waiver is signed by a
subcontractor or supplier), the Owner, the Owner’s Project Manager, the
Owner’s Engineering Consultant, the Architect for the Project, and/or any
other person or entity with legal or equitable interest in the Project.
IN WITNESS WHEROF, the person signing this document, acting for or on
behalf of the Undersigned and all of its employees, subcontractors, laborers,
suppliers and materialmen, executes this document this day
of , 20 .
By:
Title:
This instrument was executed and acknowledged before me on this day
of , 20 , by , on behalf of said
entity.
Notary Public
(Notary Seal)
My Commission Expires:
subcontractor or supplier), the Owner, the Owner’s Project Manager, the
Owner’s Engineering Consultant, the Architect for the Project, and/or any
other person or entity with legal or equitable interest in the Project.
IN WITNESS WHEROF, the person signing this document, acting for or on
behalf of the Undersigned and all of its employees, subcontractors, laborers,
suppliers and materialmen, executes this document this day
of , 20 .
By:
Title:
This instrument was executed and acknowledged before me on this day
of , 20 , by , on behalf of said
entity.
Notary Public
(Notary Seal)
My Commission Expires:

More Related Content

What's hot

Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omittedAMILA GAYAN
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...SHKLaw
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation R.R.G.S Bandara
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractPavitrah Segaran
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfilejbonvier
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Intro. to management lecture 03
Intro. to management lecture 03Intro. to management lecture 03
Intro. to management lecture 03Haitham Sharnouby
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byseenyeeyong
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Lee Maserian R.D.I.
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contractsHafizul Mukhlis
 

What's hot (20)

Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omitted
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contract
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Intro. to management lecture 03
Intro. to management lecture 03Intro. to management lecture 03
Intro. to management lecture 03
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Design liability
Design liabilityDesign liability
Design liability
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contracts
 

Viewers also liked

My house duties
My house dutiesMy house duties
My house dutiesEgorBelous
 
A comparison of two solar radiation models using artificial neural networks a...
A comparison of two solar radiation models using artificial neural networks a...A comparison of two solar radiation models using artificial neural networks a...
A comparison of two solar radiation models using artificial neural networks a...mehmet şahin
 
Streaching - Dra. Deborah Gaebler
Streaching - Dra. Deborah GaeblerStreaching - Dra. Deborah Gaebler
Streaching - Dra. Deborah GaeblerTeletón Paraguay
 
20151121 大放 普賢行
20151121 大放 普賢行20151121 大放 普賢行
20151121 大放 普賢行明哲 李
 
Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2
Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2
Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2Valentina Durante
 
Gui nguoi ban quy
Gui nguoi ban quyGui nguoi ban quy
Gui nguoi ban quyNguyen Tang
 
Presentacion licencia Creative Commonrs
Presentacion licencia Creative Commonrs Presentacion licencia Creative Commonrs
Presentacion licencia Creative Commonrs Mari Luz Grande
 
15 012 pensioenen cie szw
15 012 pensioenen cie szw15 012 pensioenen cie szw
15 012 pensioenen cie szwCNV Vakcentrale
 
powerpoint presentation
powerpoint presentationpowerpoint presentation
powerpoint presentationvrindhags
 
Microsoft PowerPoint - First Class- Virtual Towns and Schools
Microsoft PowerPoint - First Class- Virtual Towns and SchoolsMicrosoft PowerPoint - First Class- Virtual Towns and Schools
Microsoft PowerPoint - First Class- Virtual Towns and SchoolsAngela Carey
 

Viewers also liked (20)

My house duties
My house dutiesMy house duties
My house duties
 
A comparison of two solar radiation models using artificial neural networks a...
A comparison of two solar radiation models using artificial neural networks a...A comparison of two solar radiation models using artificial neural networks a...
A comparison of two solar radiation models using artificial neural networks a...
 
Star Campaign
Star CampaignStar Campaign
Star Campaign
 
Streaching - Dra. Deborah Gaebler
Streaching - Dra. Deborah GaeblerStreaching - Dra. Deborah Gaebler
Streaching - Dra. Deborah Gaebler
 
20151121 大放 普賢行
20151121 大放 普賢行20151121 大放 普賢行
20151121 大放 普賢行
 
FE-14-1748
FE-14-1748FE-14-1748
FE-14-1748
 
My c v last
My c v lastMy c v last
My c v last
 
Qualstars
QualstarsQualstars
Qualstars
 
CSIRO: Australian attitudes toward mining
CSIRO: Australian attitudes toward miningCSIRO: Australian attitudes toward mining
CSIRO: Australian attitudes toward mining
 
R06_15
R06_15R06_15
R06_15
 
Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled Presentation
 
Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2
Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2
Tendenze, moodboard, prodotti (e non possono mancare le storie) – Tema 2
 
Gui nguoi ban quy
Gui nguoi ban quyGui nguoi ban quy
Gui nguoi ban quy
 
Help Autism_2015
Help Autism_2015Help Autism_2015
Help Autism_2015
 
Presentacion licencia Creative Commonrs
Presentacion licencia Creative Commonrs Presentacion licencia Creative Commonrs
Presentacion licencia Creative Commonrs
 
15 012 pensioenen cie szw
15 012 pensioenen cie szw15 012 pensioenen cie szw
15 012 pensioenen cie szw
 
Convergence Summit Presentation
Convergence Summit PresentationConvergence Summit Presentation
Convergence Summit Presentation
 
powerpoint presentation
powerpoint presentationpowerpoint presentation
powerpoint presentation
 
Microsoft PowerPoint - First Class- Virtual Towns and Schools
Microsoft PowerPoint - First Class- Virtual Towns and SchoolsMicrosoft PowerPoint - First Class- Virtual Towns and Schools
Microsoft PowerPoint - First Class- Virtual Towns and Schools
 
Michaela R Sandoval CV
Michaela R Sandoval CVMichaela R Sandoval CV
Michaela R Sandoval CV
 

Similar to Progress billing definition

Item # 4 - Overland Agreement
Item # 4 - Overland AgreementItem # 4 - Overland Agreement
Item # 4 - Overland Agreementahcitycouncil
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coveragedtownsend
 
Issues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticeIssues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticePalecek & Palecek, PLLC
 
Sample Web Design Contract - Ferrigon Media
Sample Web Design Contract - Ferrigon MediaSample Web Design Contract - Ferrigon Media
Sample Web Design Contract - Ferrigon MediaFerrigon Media
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlowJeff Dixon
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfTarigTaha3
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Complex Procurement.doc
Complex Procurement.docComplex Procurement.doc
Complex Procurement.docTarigTaha3
 
Construction plan
Construction planConstruction plan
Construction planMianusama14
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptxVasuV18
 
Build America Bonds
Build America BondsBuild America Bonds
Build America Bondsguest93bb92
 
Item # 9 - Overland Agreement
Item # 9 - Overland AgreementItem # 9 - Overland Agreement
Item # 9 - Overland Agreementahcitycouncil
 

Similar to Progress billing definition (20)

MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Item # 4 - Overland Agreement
Item # 4 - Overland AgreementItem # 4 - Overland Agreement
Item # 4 - Overland Agreement
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coverage
 
Issues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticeIssues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and Practice
 
IFC Package Brantley Scan
IFC Package Brantley ScanIFC Package Brantley Scan
IFC Package Brantley Scan
 
Sample Web Design Contract - Ferrigon Media
Sample Web Design Contract - Ferrigon MediaSample Web Design Contract - Ferrigon Media
Sample Web Design Contract - Ferrigon Media
 
ACH 216 Lecture 07 (Project Funding)
ACH 216 Lecture 07 (Project Funding)ACH 216 Lecture 07 (Project Funding)
ACH 216 Lecture 07 (Project Funding)
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Complex Procurement.doc
Complex Procurement.docComplex Procurement.doc
Complex Procurement.doc
 
Bkozlowski wpa
Bkozlowski wpaBkozlowski wpa
Bkozlowski wpa
 
Construction plan
Construction planConstruction plan
Construction plan
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 
Build America Bonds
Build America BondsBuild America Bonds
Build America Bonds
 
Item # 9 - Overland Agreement
Item # 9 - Overland AgreementItem # 9 - Overland Agreement
Item # 9 - Overland Agreement
 

Recently uploaded

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsmeharikiros2
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 

Recently uploaded (20)

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 

Progress billing definition

  • 1. Progress Billing Definition A construction project typically involves many different trades in order to reach completion. Therefore, it can be just as daunting a task to submit for payment to a client along the way. The Owner of a construction project relies on the project architect, lender and sometimes a third party inspection company to make certain that payment is applied for correctly and within reason. Once the progress billing definition is truly understood you will smoothly pass through the steps of preparing and submitting everything needed to complete a construction project. Start With a Good Schedule of Values A schedule of values is a list with the dollar amount assigned to each area of work that will be completed on a construction project. A construction project is broken out by each scope of work and typically separated according to the Construction Specifications Institute Divisions (CSI). Therefore, it is best to separate a project’s Schedule of Values into basic CSI divisions. Examples of these divisions are General Conditions, Sitework, Utilities, Concrete, Steel, etc. Once the areas of the scope of work are defined, then a corresponding value is assigned to each one so that a percentage complete can be established for each item as progress is made on the project. In the United States the industry standard format for a billing schedule of values is per AIA form G703. Progress billing accounting issues are common, so it is essential that a good schedule of values is established early. Establish the Rate of Construction Retainage A construction contract will typically require that “Retainage” be withheld from each application for payment in order to provide the Owner or lender
  • 2. protection from the Contractor not completing the entire project. 5% or 10% may be withheld from each payment to the Contractor, and the funds held in reserve until the project punch list is completed at the end of the project. Therefore, each progress billing must take this retainage amount into account on each line item of the schedule of values and ultimately on the bottom line of the application. Establish the Frequency of Progress Payments A progress billing is exactly that, a billing that progresses towards completion a percentage at a time. Therefore, it is necessary to establish the frequency that each application shall be submitted. Often times, a progress billing will be submitted to an Owner or Lender once per month but complicated projects may require more frequency. A progress billing must specify the current period percentage of completion and the cumulative total and this must be done for both the individual items and the total. Establish the Percentage of Completion Vendors will submit their invoices for payment to a contractor for the amount of work that they have completed over the period. A contractor must confirm that the work has actually been completed according to this percentage and then include the corresponding amount within the progress billing to the Owner or Lender. This process is performed for each scope of work and then all completed items percentages are totaled. Submit it Right and Get PAID Progress billings are often rejected by an Owner or Lender because of incorrect completion percentages, incorrect math, or applications that are submitted tardy. In order to achieve profitable progress billing revenue recognition, effective processing is important. Be sure to review vendor
  • 3. invoices and percentage completions with field supervision to avoid over/under billings. Also, be certain to double check math calculations or use construction software to avoid rejected payment applications due to math mistakes. Finally, submit your progress billing forms on time! This is an easy way to get credit with an Owner or Lender because it gives them ample time to review the application. Progress Billing Sample UNCONDITIONAL FINAL WAIVER AND RELEASE OF LIENS AND CLAIMS OWNER: Business X, LLC. PROJECT NAME: PRIORITY MANAGEMENT For and in exchange of the sum of $ , the sufficiency of which is hereby acknowledged, the undersigned Contractor, subcontractor, consultant, materialmen or laborer (hereinafter the “Undersigned”) warrants and represents as follows: (1) The Undersigned has been employed by Business X, LLC. to furnish labor, materials, or services in connection with the construction of improvements on or to the above referenced project. (2) The Undersigned has performed all labor, materials, or services required under its Contract, Subcontract or Purchase Order in full compliance with all terms and conditions thereof, and all applicable plans and specifications. (3) Any and all contractors, subcontractors, laborers, suppliers and materialmen that have provided labor, material, or other services to the Undersigned for use or incorporation into the construction of the improvements to the Project have been paid in full for all amounts due and
  • 4. owing to them on the Project, or shall be promptly paid in full from the proceeds of the payment referenced above and there are no outstanding claims of any character arising out of or related to the Undersigned’s activities on or improvements to the Project. If this Waiver is signed by the Prime Contractor, attached hereto as Exhibit A is a complete list of all subcontractors and suppliers retained by such party as of the date of this Waiver. (4) The Undersigned waives and releases any and all liens, lien rights, claims of liens, and any other claims for payment for labor, material or equipment of any type or description that it may have against the Owner, the Owner’s Project Manager, the Owner’s Engineering Consultant, the Architect for the Project, the Prime Contractor (if this Waiver is signed by a subcontractor or supplier) and/or any person with a legal or equitable interest in Project, arising out of or in any fashion related to, any labor, materials or services furnished by, through or under the Undersigned on, or used in connection with, the Project, without exception. (5) This Final Waiver and Release constitutes a representation by the Person signing this document, for and on behalf of the Undersigned, that the payment referenced above constitutes full and complete payment for all work performed and costs or expense incurred (including, but not limited to, costs for supervision, field office overhead, home office overhead, interest on capital, profit and general conditions cost) by, through or under the Undersigned relative to the work of improvements at the Project, including all retainage. More specifically, the Undersigned hereby waives, quitclaims, and releases any claim of damages due to delay, hindrance, interference, acceleration, inefficiencies or extra work, or any other claims of any kind it may have against the Prime Contractor (if this Waiver is signed by a
  • 5. subcontractor or supplier), the Owner, the Owner’s Project Manager, the Owner’s Engineering Consultant, the Architect for the Project, and/or any other person or entity with legal or equitable interest in the Project. IN WITNESS WHEROF, the person signing this document, acting for or on behalf of the Undersigned and all of its employees, subcontractors, laborers, suppliers and materialmen, executes this document this day of , 20 . By: Title: This instrument was executed and acknowledged before me on this day of , 20 , by , on behalf of said entity. Notary Public (Notary Seal) My Commission Expires:
  • 6. subcontractor or supplier), the Owner, the Owner’s Project Manager, the Owner’s Engineering Consultant, the Architect for the Project, and/or any other person or entity with legal or equitable interest in the Project. IN WITNESS WHEROF, the person signing this document, acting for or on behalf of the Undersigned and all of its employees, subcontractors, laborers, suppliers and materialmen, executes this document this day of , 20 . By: Title: This instrument was executed and acknowledged before me on this day of , 20 , by , on behalf of said entity. Notary Public (Notary Seal) My Commission Expires: