SlideShare a Scribd company logo
1 of 23
Meaning of Contract
Costing
It is one of the methods of costing which is
applicable in where construction activities
takes place.
The duration of the contract work is
generally more than a year and much time
requires in completing the construction
work.
It involves more investment and labour for
construction work.
Definition of Contract
Costing
According to CIMA, Contract costing is
defined as, ”A form of specific order
costing: attribution of costs to individual
contracts”.
Application of contract Costing
This method is applicable in construction of
building, bridges, roads, dams and canals
etc.,
This method is also called as Terminal
costing.
Contractor: is one who accepts the
construction work from the party to complete
in a definite period of time.
Contractee: is the owner of construction work
and for whom the construction work is
assigned to the contractor to complete the
construction work
Features /Importance of Contract
costing
 A contract generally takes more than a year to complete
 Work on contract generally starts at the site of the
contract and not in factory premises.
 Each contract undertaken is treated as a cost unit.
 Separate contract account to prepared to ascertain
profit or loss on each contract.
 Most of the expenses are treated as direct expenses for
the construction work.
 If contract work is not completed in a particular year,
only proportionate of profit is transferred to profit and
loss account based on the work completion.
 Sub- contractors may be apportioned for
other than construction work, such as
electrical fittings, welding work, interior
decoration etc.,
 Plant & Machinery may be purchased
for the site or hired for the site
 Contractee will pay the money to the
contractor after holding certain
percentage of money which is called
retention money to safeguard the future
construction work.
Similarities between Job
Costing and Contract Costing
Job Costing Contract Costing
It is one of the method of costing It is one of the method of costing
Commitment to customer special
requirement
Commitment to customer special
requirement
Each job is treated as separate
entity for the purpose of costing
Each Contract is treated as
separate entity for the purpose of
costing
Dissimilarities between Job
Costing and Contract Costing
Job Costing Contract Costing
Jobs are performed inside the
factory
Contract work is performed outside
the factory such as construction of
bridges, roads and dams etc.
The cost of each job is less The cost of each contract is huge
or more
The period of completion of each
job is shorter duration
The period of completion of each
job is longer duration
While executing the job, each job
is given as separate job number
and is executed by the same group
of workers.
While executing a contract sub-
contract are given
Calculation of profit or loss on
each job is to be calculated for a
period.
If contract work is not completed
during the period, Profit on each
such contract shall be calculated
proportionately.
Terms used in Contract Costing
Retention Money: Certain percentage of
money hold by the contractee while
making the payment to the contractor is
called Retention Money.
The contractee may pay a fixed
percentage of work certified, depending
upon the terms of Contract.
Escalation Clause
Contract generally takes long time to
complete and in this period there may be
possibility of change in prices. Escalation
clause which protects the contractor
against raise in the prices of materials or
labour.
The contractor is entitled to enhance the
contract price if cost arises beyond a given
percentage.
Cost Plus Contracts
Cost plus contract is a contract in which
the contract price is ascertained by adding
a specified amount or percentage of profit
to the cost allowed in the contract.
Cost plus contract is usually entered into
for executing special type of work like
construction of dams buildings, power
house etc.,
Work Certified
As per the terms of the contract, the
contractee advances certain percentage of
amount or money to the contractor on the
basis of the percentage of work done by
the contractor and work certificate issued
by the contractee’s architect or engineer
periodically
Work Uncertified
A Work is completed by the contractor but
which remains to be certified by the
architect on the date of accounting is
known as ‘work done but not yet
certified’
Contract Price
It is the value of the contract agreed to be
paid to the contractor by the contractee for
completion of work according to the
satisfaction of the contractee
Treatment of profit on
incomplete contract
Work certified +Work uncertified/contract Price*100
1. When work certified is less than1/4
(25%) of the contract price no profit is to
transferred to the profit and loss account
and the whole amount of such profit is
treated as notional profit and is transferred
to the reserve account
2. If work certified is ¼ (25%) or more than
¼(25%)of the contract price but less than
½ (50%) of the contract price then 1/3 of
the notional profit is transferred to the
profit and loss account and the balance is
to be transferred to the reserve account.
The profit to be transferred to the profit
and loss account is calculated as follows-
1/3 x notional profit x cash received / work certified
3. If work certified is ½ (50%) or more than
½ (50%)of the contract price but near to
the completion of the contract then½
(50%) of the contract price then 2/3 of the
notional profit is transferred to the profit
and loss account and the balance is to be
transferred to the reserve account. The
profit to be transferred to the profit and
loss account is calculated as follows-
2/3 x notional profit x cash received / work certified
4. When contract is near to the completion the
estimated profit is calculated on the contract
price. It is calculated as follows-
Estimated profit x work certified /contract price
OR
Estimated profit x cash received / contract price
Accounting Procedure
(Preparation of Contract Account)
Materials:
It includes the materials purchased directly from the
suppliers or materials issued from the stores against
materials requisition note.
The costs of both are debited to the contract account.
During the period if any materials found surplus and
are returned to the stores, they are credited to the
contract account.
In case any materials are transferred from the site to
other contracts, such materials also are credited to
the contract account, if any materials received from
other contracts are debited to the contract account.
Labour/Wages:
The wages payable to the workers engaged
on the contract are also debited
to the contract account. If any wages are
accrued or outstanding such outstanding
charges are added to the wages.
Plant and Machinery:
If any assets are purchased like plant and
machinery, tractors and any other assets are
debited to the contract account.
At the end of the year after depreciation the
net value of assets are credited to the
contract account. Alternatively only the
depreciation amount on the assets is debited
to the contract account.
Sub Contract:
Is to be debited to contract account
 Any Profit on the sale of assets or part of it is
debited to the contract account and credited
to profit and loss account.
 Any Loss or fire or destroyed of any
materials in transit or at the site are to be
debited to the profit and loss account and
credited to contract account.
Work in progress
 When contract work is not completed till the end of
accounting period then it is called work in progress.
 The contractor is required to value the work in
progress considering work certified and work
uncertified.
 Both work certified and work certified will appear on
the credit side of the contract account under the
heading Work in progress account.
a. Work certified: it is a part of work in progress
which refers to work has been completed and
approved and certified by an architect.
b. Work Uncertified: it is also a part of work in
progress , which refers to work on contract has
been completed but is not certified or not approved
by an architect.
Notional Profit
It is an estimate of earnings primarily used
in the building and the construction
industry. it is used to smooth out
fluctuation in reported revenue due to
contract that take a long time to complete.

More Related Content

What's hot

Managerial remuneration problems and sloution.pptx
Managerial remuneration problems and sloution.pptxManagerial remuneration problems and sloution.pptx
Managerial remuneration problems and sloution.pptxdefault default
 
Absorption Of Overheads-B.V.Raghunandan
Absorption Of Overheads-B.V.RaghunandanAbsorption Of Overheads-B.V.Raghunandan
Absorption Of Overheads-B.V.RaghunandanSVS College
 
Contract and Job costing
Contract and Job costing Contract and Job costing
Contract and Job costing Ashwitha shetty
 
Material Cost and Labour Cost PPT - Dr.J.Mexon
Material Cost and Labour Cost PPT - Dr.J.MexonMaterial Cost and Labour Cost PPT - Dr.J.Mexon
Material Cost and Labour Cost PPT - Dr.J.MexonDr. J.Mexon Fernando
 
5.capital and revenue
5.capital and revenue5.capital and revenue
5.capital and revenueKaran Kukreja
 
Valuation of goodwill
Valuation of goodwillValuation of goodwill
Valuation of goodwillItisha Sharma
 
Overheads and classifcation of overheads
Overheads and classifcation of overheads Overheads and classifcation of overheads
Overheads and classifcation of overheads geetarajan73
 
Cost accounting vs financial accounting
Cost accounting vs financial accountingCost accounting vs financial accounting
Cost accounting vs financial accountingCOMMERCEIETS
 
Appointment of Auditor
Appointment of AuditorAppointment of Auditor
Appointment of AuditorAnkit Agarwal
 
Chapter 07 Marginal Costing
Chapter 07   Marginal CostingChapter 07   Marginal Costing
Chapter 07 Marginal Costingayanthimadhumali
 
Verification and valuation of assets and liabilities
Verification and valuation of assets and liabilitiesVerification and valuation of assets and liabilities
Verification and valuation of assets and liabilitiesAtta Hussain Syed
 

What's hot (20)

Classification of costs
Classification of costsClassification of costs
Classification of costs
 
Managerial remuneration problems and sloution.pptx
Managerial remuneration problems and sloution.pptxManagerial remuneration problems and sloution.pptx
Managerial remuneration problems and sloution.pptx
 
Absorption Of Overheads-B.V.Raghunandan
Absorption Of Overheads-B.V.RaghunandanAbsorption Of Overheads-B.V.Raghunandan
Absorption Of Overheads-B.V.Raghunandan
 
Contract and Job costing
Contract and Job costing Contract and Job costing
Contract and Job costing
 
Material Cost and Labour Cost PPT - Dr.J.Mexon
Material Cost and Labour Cost PPT - Dr.J.MexonMaterial Cost and Labour Cost PPT - Dr.J.Mexon
Material Cost and Labour Cost PPT - Dr.J.Mexon
 
Goodwill
GoodwillGoodwill
Goodwill
 
Contract costing
Contract costingContract costing
Contract costing
 
Cost sheet ppt
Cost sheet pptCost sheet ppt
Cost sheet ppt
 
Job costing
Job costingJob costing
Job costing
 
Batch costing
Batch costingBatch costing
Batch costing
 
5.capital and revenue
5.capital and revenue5.capital and revenue
5.capital and revenue
 
Contract costing
Contract costingContract costing
Contract costing
 
Overheads
OverheadsOverheads
Overheads
 
Valuation of goodwill
Valuation of goodwillValuation of goodwill
Valuation of goodwill
 
Overheads and classifcation of overheads
Overheads and classifcation of overheads Overheads and classifcation of overheads
Overheads and classifcation of overheads
 
Cost accounting vs financial accounting
Cost accounting vs financial accountingCost accounting vs financial accounting
Cost accounting vs financial accounting
 
Appointment of Auditor
Appointment of AuditorAppointment of Auditor
Appointment of Auditor
 
Chapter 07 Marginal Costing
Chapter 07   Marginal CostingChapter 07   Marginal Costing
Chapter 07 Marginal Costing
 
Marginal costing
Marginal costingMarginal costing
Marginal costing
 
Verification and valuation of assets and liabilities
Verification and valuation of assets and liabilitiesVerification and valuation of assets and liabilities
Verification and valuation of assets and liabilities
 

Similar to Contract Costing.pptx

Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docxSreedeviPMenon
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingRai University
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)AmarnathRana1
 
Construction contract
Construction contractConstruction contract
Construction contractAqsa Shafique
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costingCollen Mahambo
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsPrakhar Jain
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxsulevrunda
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.pptmayuray
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Complex Procurement.doc
Complex Procurement.docComplex Procurement.doc
Complex Procurement.docTarigTaha3
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 

Similar to Contract Costing.pptx (20)

Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)
 
Contract costing
Contract costingContract costing
Contract costing
 
Construction contract
Construction contractConstruction contract
Construction contract
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
 
Contract account
Contract accountContract account
Contract account
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
 
Contracts
ContractsContracts
Contracts
 
Ias 11
Ias 11Ias 11
Ias 11
 
Complex Procurement.doc
Complex Procurement.docComplex Procurement.doc
Complex Procurement.doc
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 

Recently uploaded

Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 

Recently uploaded (20)

Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 

Contract Costing.pptx

  • 1.
  • 2. Meaning of Contract Costing It is one of the methods of costing which is applicable in where construction activities takes place. The duration of the contract work is generally more than a year and much time requires in completing the construction work. It involves more investment and labour for construction work.
  • 3. Definition of Contract Costing According to CIMA, Contract costing is defined as, ”A form of specific order costing: attribution of costs to individual contracts”.
  • 4. Application of contract Costing This method is applicable in construction of building, bridges, roads, dams and canals etc., This method is also called as Terminal costing. Contractor: is one who accepts the construction work from the party to complete in a definite period of time. Contractee: is the owner of construction work and for whom the construction work is assigned to the contractor to complete the construction work
  • 5. Features /Importance of Contract costing  A contract generally takes more than a year to complete  Work on contract generally starts at the site of the contract and not in factory premises.  Each contract undertaken is treated as a cost unit.  Separate contract account to prepared to ascertain profit or loss on each contract.  Most of the expenses are treated as direct expenses for the construction work.  If contract work is not completed in a particular year, only proportionate of profit is transferred to profit and loss account based on the work completion.
  • 6.  Sub- contractors may be apportioned for other than construction work, such as electrical fittings, welding work, interior decoration etc.,  Plant & Machinery may be purchased for the site or hired for the site  Contractee will pay the money to the contractor after holding certain percentage of money which is called retention money to safeguard the future construction work.
  • 7. Similarities between Job Costing and Contract Costing Job Costing Contract Costing It is one of the method of costing It is one of the method of costing Commitment to customer special requirement Commitment to customer special requirement Each job is treated as separate entity for the purpose of costing Each Contract is treated as separate entity for the purpose of costing
  • 8. Dissimilarities between Job Costing and Contract Costing Job Costing Contract Costing Jobs are performed inside the factory Contract work is performed outside the factory such as construction of bridges, roads and dams etc. The cost of each job is less The cost of each contract is huge or more The period of completion of each job is shorter duration The period of completion of each job is longer duration While executing the job, each job is given as separate job number and is executed by the same group of workers. While executing a contract sub- contract are given Calculation of profit or loss on each job is to be calculated for a period. If contract work is not completed during the period, Profit on each such contract shall be calculated proportionately.
  • 9. Terms used in Contract Costing Retention Money: Certain percentage of money hold by the contractee while making the payment to the contractor is called Retention Money. The contractee may pay a fixed percentage of work certified, depending upon the terms of Contract.
  • 10. Escalation Clause Contract generally takes long time to complete and in this period there may be possibility of change in prices. Escalation clause which protects the contractor against raise in the prices of materials or labour. The contractor is entitled to enhance the contract price if cost arises beyond a given percentage.
  • 11. Cost Plus Contracts Cost plus contract is a contract in which the contract price is ascertained by adding a specified amount or percentage of profit to the cost allowed in the contract. Cost plus contract is usually entered into for executing special type of work like construction of dams buildings, power house etc.,
  • 12. Work Certified As per the terms of the contract, the contractee advances certain percentage of amount or money to the contractor on the basis of the percentage of work done by the contractor and work certificate issued by the contractee’s architect or engineer periodically
  • 13. Work Uncertified A Work is completed by the contractor but which remains to be certified by the architect on the date of accounting is known as ‘work done but not yet certified’
  • 14. Contract Price It is the value of the contract agreed to be paid to the contractor by the contractee for completion of work according to the satisfaction of the contractee
  • 15. Treatment of profit on incomplete contract Work certified +Work uncertified/contract Price*100 1. When work certified is less than1/4 (25%) of the contract price no profit is to transferred to the profit and loss account and the whole amount of such profit is treated as notional profit and is transferred to the reserve account
  • 16. 2. If work certified is ¼ (25%) or more than ¼(25%)of the contract price but less than ½ (50%) of the contract price then 1/3 of the notional profit is transferred to the profit and loss account and the balance is to be transferred to the reserve account. The profit to be transferred to the profit and loss account is calculated as follows- 1/3 x notional profit x cash received / work certified
  • 17. 3. If work certified is ½ (50%) or more than ½ (50%)of the contract price but near to the completion of the contract then½ (50%) of the contract price then 2/3 of the notional profit is transferred to the profit and loss account and the balance is to be transferred to the reserve account. The profit to be transferred to the profit and loss account is calculated as follows- 2/3 x notional profit x cash received / work certified
  • 18. 4. When contract is near to the completion the estimated profit is calculated on the contract price. It is calculated as follows- Estimated profit x work certified /contract price OR Estimated profit x cash received / contract price
  • 19. Accounting Procedure (Preparation of Contract Account) Materials: It includes the materials purchased directly from the suppliers or materials issued from the stores against materials requisition note. The costs of both are debited to the contract account. During the period if any materials found surplus and are returned to the stores, they are credited to the contract account. In case any materials are transferred from the site to other contracts, such materials also are credited to the contract account, if any materials received from other contracts are debited to the contract account.
  • 20. Labour/Wages: The wages payable to the workers engaged on the contract are also debited to the contract account. If any wages are accrued or outstanding such outstanding charges are added to the wages. Plant and Machinery: If any assets are purchased like plant and machinery, tractors and any other assets are debited to the contract account. At the end of the year after depreciation the net value of assets are credited to the contract account. Alternatively only the depreciation amount on the assets is debited to the contract account.
  • 21. Sub Contract: Is to be debited to contract account  Any Profit on the sale of assets or part of it is debited to the contract account and credited to profit and loss account.  Any Loss or fire or destroyed of any materials in transit or at the site are to be debited to the profit and loss account and credited to contract account.
  • 22. Work in progress  When contract work is not completed till the end of accounting period then it is called work in progress.  The contractor is required to value the work in progress considering work certified and work uncertified.  Both work certified and work certified will appear on the credit side of the contract account under the heading Work in progress account. a. Work certified: it is a part of work in progress which refers to work has been completed and approved and certified by an architect. b. Work Uncertified: it is also a part of work in progress , which refers to work on contract has been completed but is not certified or not approved by an architect.
  • 23. Notional Profit It is an estimate of earnings primarily used in the building and the construction industry. it is used to smooth out fluctuation in reported revenue due to contract that take a long time to complete.