SlideShare a Scribd company logo
1 of 10
Welcome ……
Unrestricted
Weekly Progress Report # 70
SVC
JOUF
PREPARED BY:
2016
AJAZ UL KABIR
Project Manager- Qassim Group
SEC ‐ EHVPD , COA , SVC Al-Jouf-2
Mobile : 054 112 2637 , Email : absheikh@se.com.sa
REVIEWED BY:
ABDULRAHMAN AL-KADI
Group Leader- Qassim
Extra High Voltage Projects Department- COA
Mobile : 050 489 6906 , Email : EVPRC-QPGL@se.com.sa
26
October
Dynamic Reactive Power Compensation at Hail-2
(9031) & Al-Jouf-2 380kV Substations
SEC CONTRACT NO. 4400003963/00
AIM/ OBJECTIVE: CONTRACT DETAILS:
SEC intends to improve rapid voltage
support at Hail-2 (9031) and Al-Jouf-2
380kV Substations of SEC network by
providing Conventional or Hybrid Static
VAR Compensator Systems (SVC).
The SVCs at Hail-2 (9031) shall be
connected to spare 380kV Breaker. CB
position for SVC at Al-Jouf-2 .380kV
Substation will be provided by Al-Jouf-2
380kV Substation Contractor.
• Project Name ……………………….. DYNAMIC REACTIVE POWER
COMPENSATION AT HAIL-2 (9031)
& AL-JOUF-2 380KV SUBSTATIONS
• Contract No ………………………… 4400003963/00
• Owner ………………………………. SAUDI ELECTRIC COMPANY - COA
• SEC Project Manager ……………… ENGR. AJAZ UL KABIR
• Contractor ………………………...... SIEMENS LTD.
• Address ……………………………... SIEMENS COMPANY LIMITED,
P.O.BOX 9510, RIYADH 11423, KSA
• Contractor Project Manager ………. ENGR. REHAN ULHAQUE
• Contract Effective Date ……………. 03-JUNE-2014
• Contract Value ……………………... SAR 463,840,000.00
PROJECT DESCRIPTION & CONTRACT INFO
SVC ALJOUF-2
• Technical Completion Certificate (TCC) : 02-JUNE-2016
• Preliminary Acceptance Certificate (PAC) : 02-AUGUST-2016
• Final Acceptance Certificate (FAC) : 02-NOVEMBER-2016
TIME LINE
SVC ALJOUF-2
Contract Signing for SVC Hail &
Al-Jouf
(03-JUNE-2014)
Kick off Meeting
(24-JUN-2014)
Site Handover (SVC HAIL & AL
JOUF)
(26-JUN-2014)
TCC
SVC Hail & Al-Jouf
(02-JUN-2016)
PAC
SVC Hail & Al-Jouf
(02-AUG-2016)
FAC
SVC Hail & Al-Jouf
(2-NOV-2016)
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Aug-14
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15
Jul-15
Aug-15
Sep-15
Oct-15
Nov-15
Dec-15
Jan-16
Feb-16
Mar-16
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
SVS set up
2x SVC PLUS
2x TSC
32kV
380 kV
15% at 450 MVA +/-5%
Q at 32 kV (1.0 pu)
2 x (0+143.1 Mvar) cap 2 x (-75+81.9 Mvar)
Ik=63kA
SVC PLUSSVC PLUS
TSC TSC
Installation of +450MVAr (Capacitive) & -150MVAr (Indutive) 380kV SVC System
SVC CONNECTION DIAGRAM
SVC ALJOUF-2
PROJECT SIGN BOARD
• Contract Signing : June 03, 2014
• Kick off Meeting : June 24, 2014
• Site Handover : June 26, 2014
• TCC: June 02, 2016
• PAC: August 02, 2016
• FAC: November 02, 2016
SVC ALJOUF-2
CONTROL ROOM
Protection & Control System / SAS / Alarms / Metering (SIEMENS)
 Electrical:
Witnessing with CSD Engineer completed except the
following:
• SAS Close Loop Test 83% completed (remaining 17%
for which data entry update will be completed by
25/10/2016 in CRCC; SCADA Closed Loop Test will be
resumed on Wednesday 26/10/2016).
• Final Trip Test for Protection & Control is completed
• Interlock test completed
• Snag Clearance in progress
• Post Energization Test (to be done after Energization of
SVC Transformer & 13.8kV Auxiliary System after
receiving Energization Permit) : Need 10 Working Days
to put SVC in service
SVC ALJOUF-2
SVC ALJOUF-2
HVAC & FPS
 Electro-Mechanical:
• HVAC installation – 100% completed ; Air-
Balancing and DDC Panel in progress
• Fire Alarm/Fighting Test: All walk through
requirements/comments from ISD (East
Division) – 100% completed ; request
already send to ISD / S&EPD-East to
confirm the date of Final Inspection or
issue Energization Clearance based on the
submitted Test results.
• Internal Testing of Fire alarm, Firefighting
and Hydrant system Completed.
Dynamic & Static Reactive Power Compensator at Al Jouf-2, 380kV Substation
Contractor Date of award 02/06/2016 TCC Handed Over
SIEMENS 03.06.2014
15/10/2016 Expected
Energization
26.06.2014
COMMISSIONING
STATUS
(99.2 % completed)
EQUIPMENT
REMARKS
(Delivery status –
100 % completed)
EXPECTED BUILDING
READINESS
BUILDINGEXP. DELIVERYSUPPLIEREQUIPMENTS/N
Witnessing with CSD – 100%
completed
OLT – 100% completed
CLT – 83% completed
Capacitor, Reactor, Resister,
Thyristor, IGBT, Cooling
System delivered
Foundations completedOutdoor Foundations30-12-2015SIEMENSSVC Equipment's1
Witnessing with CSD – 100%
completed
Delivered and InstalledFoundations completedTransformer Foundation15-12-2015SIEMENS450MVA Power Transformer's2
Witnessing with CSD – 99%
completed
Delivered and Installed
Building and foundation are
ready
Control Building15-12-2015
ALFANAR, KSA &
SIEMENS
13.8kV Switchgear & RMU3
Witnessing with CSD – 100%
completed
Delivered and InstalledFoundation readyTransformer Foundation15-02-2016UTEC, KSA
Auxiliary Transformer /
Grounding Transformer
4
Witnessing with CSD – 100%
completed
Delivered and Installed
Building ReadyControl Building
15-01-2016TBDProtection System5
Witnessing with CSD – 100%
completed
Delivered and Installed15-12-2015
HEPOCKEE &
BENNING
Battery & Battery Charger6
Witnessing with CSD – 100%
completed
Delivered and Installed30-12-2015TBDAC / DC Panel7
HV Cable termination
completed
Delivered and InstalledSteel structure installed
Trench and duct bank
ready
25-10-2015TBD & LS Cable
Steel Structures, Cables and Earthing
Materials
8
THANK YOU ……

More Related Content

What's hot

QA-QC ENGINEER
QA-QC ENGINEERQA-QC ENGINEER
QA-QC ENGINEERnader rizq
 
INPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPINPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPD. Alan Day
 
Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen Barkwitch
 
Ka Brodmeeting 110509
Ka  Brodmeeting 110509Ka  Brodmeeting 110509
Ka Brodmeeting 110509Timmy Tng
 
Alliance Implementation on HKD 2017
Alliance Implementation on HKD 2017Alliance Implementation on HKD 2017
Alliance Implementation on HKD 2017Arshaful Hoque
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6MUHAMMAD SALEEM
 
Fall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation SummaryFall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation SummaryAsh Abel
 
EKPRANGAREDDY2016
EKPRANGAREDDY2016EKPRANGAREDDY2016
EKPRANGAREDDY2016Ekp Reddy
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Abdul Alim Dewan
 
Fontiveros CV 2016 Instrument Technician-
Fontiveros CV 2016 Instrument Technician-Fontiveros CV 2016 Instrument Technician-
Fontiveros CV 2016 Instrument Technician-Apolinario Fontiveros
 
Production - Reducing Machine Setup Time - IEM
Production - Reducing Machine Setup Time - IEMProduction - Reducing Machine Setup Time - IEM
Production - Reducing Machine Setup Time - IEMGan Chun Chet
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysisAllan Leyte
 
Mahfuzur Fire & Gas Tech CV -2017
Mahfuzur Fire & Gas Tech CV -2017Mahfuzur Fire & Gas Tech CV -2017
Mahfuzur Fire & Gas Tech CV -2017Mahfuzur Rahman
 
Contractors Performance Scoreboard_DECEMBER 2015
Contractors Performance Scoreboard_DECEMBER 2015Contractors Performance Scoreboard_DECEMBER 2015
Contractors Performance Scoreboard_DECEMBER 2015Pete Cabrera
 

What's hot (19)

QA-QC ENGINEER
QA-QC ENGINEERQA-QC ENGINEER
QA-QC ENGINEER
 
INPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPINPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRP
 
Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioning
 
Ka Brodmeeting 110509
Ka  Brodmeeting 110509Ka  Brodmeeting 110509
Ka Brodmeeting 110509
 
Alliance Implementation on HKD 2017
Alliance Implementation on HKD 2017Alliance Implementation on HKD 2017
Alliance Implementation on HKD 2017
 
QGC
QGCQGC
QGC
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
E&I QC ENGINEER
E&I QC ENGINEERE&I QC ENGINEER
E&I QC ENGINEER
 
Fall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation SummaryFall 2014 Co-op Rotation Summary
Fall 2014 Co-op Rotation Summary
 
EKPRANGAREDDY2016
EKPRANGAREDDY2016EKPRANGAREDDY2016
EKPRANGAREDDY2016
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
Fontiveros CV 2016 Instrument Technician-
Fontiveros CV 2016 Instrument Technician-Fontiveros CV 2016 Instrument Technician-
Fontiveros CV 2016 Instrument Technician-
 
Production - Reducing Machine Setup Time - IEM
Production - Reducing Machine Setup Time - IEMProduction - Reducing Machine Setup Time - IEM
Production - Reducing Machine Setup Time - IEM
 
Contract Management
Contract ManagementContract Management
Contract Management
 
CV JHN 2015
CV JHN 2015CV JHN 2015
CV JHN 2015
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Mahfuzur Fire & Gas Tech CV -2017
Mahfuzur Fire & Gas Tech CV -2017Mahfuzur Fire & Gas Tech CV -2017
Mahfuzur Fire & Gas Tech CV -2017
 
Contractors Performance Scoreboard_DECEMBER 2015
Contractors Performance Scoreboard_DECEMBER 2015Contractors Performance Scoreboard_DECEMBER 2015
Contractors Performance Scoreboard_DECEMBER 2015
 

Viewers also liked

Technology Hill SMO PowerPoint
Technology Hill SMO PowerPointTechnology Hill SMO PowerPoint
Technology Hill SMO PowerPointTechnology Hill
 
MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....
MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....
MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....dr m m bagali, phd in hr
 
Solid Waste Management presentation to KSPCB
Solid Waste Management presentation to KSPCBSolid Waste Management presentation to KSPCB
Solid Waste Management presentation to KSPCBApnaComplex
 
Заявление министерства юстиции
Заявление министерства юстицииЗаявление министерства юстиции
Заявление министерства юстицииAnatol Alizar
 
Dhaka South City Corporation: Structure, Finance and Personal Management
Dhaka South City Corporation: Structure, Finance and Personal ManagementDhaka South City Corporation: Structure, Finance and Personal Management
Dhaka South City Corporation: Structure, Finance and Personal ManagementAhasan Uddin Bhuiyan
 
Las condiciones-del-aprendizaje por Dennis Montufar
Las condiciones-del-aprendizaje por Dennis MontufarLas condiciones-del-aprendizaje por Dennis Montufar
Las condiciones-del-aprendizaje por Dennis MontufarDennisito1995
 
environmental control of poultry farms PLC based project presentation
environmental control of poultry farms PLC based project presentationenvironmental control of poultry farms PLC based project presentation
environmental control of poultry farms PLC based project presentationAhsan Naeem Chaudary
 
Presentation 2 student x
Presentation 2 student xPresentation 2 student x
Presentation 2 student xAsma Wasim
 
Progetto Digital Strategy Amadori
Progetto Digital Strategy AmadoriProgetto Digital Strategy Amadori
Progetto Digital Strategy AmadoriTecla
 
Web analytics: i cruscotti
Web analytics: i cruscottiWeb analytics: i cruscotti
Web analytics: i cruscottiLeonardo Bellini
 
Need and Importance of ICT Based Library Services in ODL: With Special Refere...
Need and Importance of ICT Based Library Services in ODL: With Special Refere...Need and Importance of ICT Based Library Services in ODL: With Special Refere...
Need and Importance of ICT Based Library Services in ODL: With Special Refere...Anupama Chetia
 
ERTMS Presentation
ERTMS PresentationERTMS Presentation
ERTMS PresentationMartyn Tobin
 
Raggiungere 500 collegamenti su LinkedIn
Raggiungere 500 collegamenti su LinkedInRaggiungere 500 collegamenti su LinkedIn
Raggiungere 500 collegamenti su LinkedInLeonardo Bellini
 
[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안
[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안
[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안Lee Sung Hoon
 
Plan de Trabajo Min. Adolescente UPSur
Plan de Trabajo Min. Adolescente UPSurPlan de Trabajo Min. Adolescente UPSur
Plan de Trabajo Min. Adolescente UPSurAdventistas APC
 

Viewers also liked (20)

Unit ii
Unit   iiUnit   ii
Unit ii
 
Technology Hill SMO PowerPoint
Technology Hill SMO PowerPointTechnology Hill SMO PowerPoint
Technology Hill SMO PowerPoint
 
Shagree sintesi primovolotermico
Shagree sintesi primovolotermicoShagree sintesi primovolotermico
Shagree sintesi primovolotermico
 
MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....
MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....
MM Bagali,,,,,,,,, HR, HRM, HRD, PhD research, India.......High performance ....
 
Presentazione A@gres orientagate 2013
Presentazione A@gres  orientagate 2013Presentazione A@gres  orientagate 2013
Presentazione A@gres orientagate 2013
 
Biz Presentation 2013
Biz Presentation 2013Biz Presentation 2013
Biz Presentation 2013
 
Solid Waste Management presentation to KSPCB
Solid Waste Management presentation to KSPCBSolid Waste Management presentation to KSPCB
Solid Waste Management presentation to KSPCB
 
Заявление министерства юстиции
Заявление министерства юстицииЗаявление министерства юстиции
Заявление министерства юстиции
 
Dhaka South City Corporation: Structure, Finance and Personal Management
Dhaka South City Corporation: Structure, Finance and Personal ManagementDhaka South City Corporation: Structure, Finance and Personal Management
Dhaka South City Corporation: Structure, Finance and Personal Management
 
Las condiciones-del-aprendizaje por Dennis Montufar
Las condiciones-del-aprendizaje por Dennis MontufarLas condiciones-del-aprendizaje por Dennis Montufar
Las condiciones-del-aprendizaje por Dennis Montufar
 
environmental control of poultry farms PLC based project presentation
environmental control of poultry farms PLC based project presentationenvironmental control of poultry farms PLC based project presentation
environmental control of poultry farms PLC based project presentation
 
Presentation 2 student x
Presentation 2 student xPresentation 2 student x
Presentation 2 student x
 
Progetto Digital Strategy Amadori
Progetto Digital Strategy AmadoriProgetto Digital Strategy Amadori
Progetto Digital Strategy Amadori
 
Web analytics: i cruscotti
Web analytics: i cruscottiWeb analytics: i cruscotti
Web analytics: i cruscotti
 
EXPONENTES DEL CONDUCTISMO
EXPONENTES DEL CONDUCTISMO EXPONENTES DEL CONDUCTISMO
EXPONENTES DEL CONDUCTISMO
 
Need and Importance of ICT Based Library Services in ODL: With Special Refere...
Need and Importance of ICT Based Library Services in ODL: With Special Refere...Need and Importance of ICT Based Library Services in ODL: With Special Refere...
Need and Importance of ICT Based Library Services in ODL: With Special Refere...
 
ERTMS Presentation
ERTMS PresentationERTMS Presentation
ERTMS Presentation
 
Raggiungere 500 collegamenti su LinkedIn
Raggiungere 500 collegamenti su LinkedInRaggiungere 500 collegamenti su LinkedIn
Raggiungere 500 collegamenti su LinkedIn
 
[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안
[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안
[마케팅전략] 2012년 게임어플리케이션 마케팅 전략 및 실행안
 
Plan de Trabajo Min. Adolescente UPSur
Plan de Trabajo Min. Adolescente UPSurPlan de Trabajo Min. Adolescente UPSur
Plan de Trabajo Min. Adolescente UPSur
 

Similar to Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... dated 26.10.2016

Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...ATIF HUSSAIN
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Sarthak Panigrahi
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986sheik syedali
 
Zaheer Ahmed E&I Professional
Zaheer Ahmed E&I ProfessionalZaheer Ahmed E&I Professional
Zaheer Ahmed E&I ProfessionalZaheer Ahmed
 
Projects done by Stokholm Engineering
Projects done by Stokholm EngineeringProjects done by Stokholm Engineering
Projects done by Stokholm EngineeringKurt Stokholm
 
Engr. Ayaz Khan CV11 (1)
Engr.  Ayaz Khan CV11 (1)Engr.  Ayaz Khan CV11 (1)
Engr. Ayaz Khan CV11 (1)Engr.ayaz khan
 
Mushtaq Electrical_ENGINEER 2016
Mushtaq Electrical_ENGINEER 2016Mushtaq Electrical_ENGINEER 2016
Mushtaq Electrical_ENGINEER 2016dil mus
 
Rejith complete cv
Rejith complete cvRejith complete cv
Rejith complete cvrejith raman
 
andrew meaden february 2016 cv
andrew meaden february 2016 cvandrew meaden february 2016 cv
andrew meaden february 2016 cvAndrew Meaden
 
Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)Mahesh Chandra Manav
 

Similar to Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... dated 26.10.2016 (20)

Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
Projects Department Weekly Report - SVC Hail-2, Dynamic and Static React.... ...
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Satham Mohamed.A-CV..
Satham Mohamed.A-CV..Satham Mohamed.A-CV..
Satham Mohamed.A-CV..
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986
 
PM Ahmed Abdelhady CV
PM Ahmed Abdelhady CVPM Ahmed Abdelhady CV
PM Ahmed Abdelhady CV
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Zaheer Ahmed E&I Professional
Zaheer Ahmed E&I ProfessionalZaheer Ahmed E&I Professional
Zaheer Ahmed E&I Professional
 
Raghu Resume
Raghu Resume Raghu Resume
Raghu Resume
 
Wajid Ali Shah
Wajid Ali ShahWajid Ali Shah
Wajid Ali Shah
 
Projects done by Stokholm Engineering
Projects done by Stokholm EngineeringProjects done by Stokholm Engineering
Projects done by Stokholm Engineering
 
SISCO - Presentation
SISCO - PresentationSISCO - Presentation
SISCO - Presentation
 
Juliet Joseph
Juliet JosephJuliet Joseph
Juliet Joseph
 
NAVNATH UPDATED CV
NAVNATH UPDATED CVNAVNATH UPDATED CV
NAVNATH UPDATED CV
 
Engr. Ayaz Khan CV11 (1)
Engr.  Ayaz Khan CV11 (1)Engr.  Ayaz Khan CV11 (1)
Engr. Ayaz Khan CV11 (1)
 
Mushtaq Electrical_ENGINEER 2016
Mushtaq Electrical_ENGINEER 2016Mushtaq Electrical_ENGINEER 2016
Mushtaq Electrical_ENGINEER 2016
 
Rejith complete cv
Rejith complete cvRejith complete cv
Rejith complete cv
 
ANBARASAN R CV
ANBARASAN R CV ANBARASAN R CV
ANBARASAN R CV
 
andrew meaden february 2016 cv
andrew meaden february 2016 cvandrew meaden february 2016 cv
andrew meaden february 2016 cv
 
Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)
 

Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... dated 26.10.2016

  • 2. Weekly Progress Report # 70 SVC JOUF PREPARED BY: 2016 AJAZ UL KABIR Project Manager- Qassim Group SEC ‐ EHVPD , COA , SVC Al-Jouf-2 Mobile : 054 112 2637 , Email : absheikh@se.com.sa REVIEWED BY: ABDULRAHMAN AL-KADI Group Leader- Qassim Extra High Voltage Projects Department- COA Mobile : 050 489 6906 , Email : EVPRC-QPGL@se.com.sa 26 October Dynamic Reactive Power Compensation at Hail-2 (9031) & Al-Jouf-2 380kV Substations SEC CONTRACT NO. 4400003963/00
  • 3. AIM/ OBJECTIVE: CONTRACT DETAILS: SEC intends to improve rapid voltage support at Hail-2 (9031) and Al-Jouf-2 380kV Substations of SEC network by providing Conventional or Hybrid Static VAR Compensator Systems (SVC). The SVCs at Hail-2 (9031) shall be connected to spare 380kV Breaker. CB position for SVC at Al-Jouf-2 .380kV Substation will be provided by Al-Jouf-2 380kV Substation Contractor. • Project Name ……………………….. DYNAMIC REACTIVE POWER COMPENSATION AT HAIL-2 (9031) & AL-JOUF-2 380KV SUBSTATIONS • Contract No ………………………… 4400003963/00 • Owner ………………………………. SAUDI ELECTRIC COMPANY - COA • SEC Project Manager ……………… ENGR. AJAZ UL KABIR • Contractor ………………………...... SIEMENS LTD. • Address ……………………………... SIEMENS COMPANY LIMITED, P.O.BOX 9510, RIYADH 11423, KSA • Contractor Project Manager ………. ENGR. REHAN ULHAQUE • Contract Effective Date ……………. 03-JUNE-2014 • Contract Value ……………………... SAR 463,840,000.00 PROJECT DESCRIPTION & CONTRACT INFO SVC ALJOUF-2
  • 4. • Technical Completion Certificate (TCC) : 02-JUNE-2016 • Preliminary Acceptance Certificate (PAC) : 02-AUGUST-2016 • Final Acceptance Certificate (FAC) : 02-NOVEMBER-2016 TIME LINE SVC ALJOUF-2 Contract Signing for SVC Hail & Al-Jouf (03-JUNE-2014) Kick off Meeting (24-JUN-2014) Site Handover (SVC HAIL & AL JOUF) (26-JUN-2014) TCC SVC Hail & Al-Jouf (02-JUN-2016) PAC SVC Hail & Al-Jouf (02-AUG-2016) FAC SVC Hail & Al-Jouf (2-NOV-2016) Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
  • 5. SVS set up 2x SVC PLUS 2x TSC 32kV 380 kV 15% at 450 MVA +/-5% Q at 32 kV (1.0 pu) 2 x (0+143.1 Mvar) cap 2 x (-75+81.9 Mvar) Ik=63kA SVC PLUSSVC PLUS TSC TSC Installation of +450MVAr (Capacitive) & -150MVAr (Indutive) 380kV SVC System SVC CONNECTION DIAGRAM SVC ALJOUF-2
  • 6. PROJECT SIGN BOARD • Contract Signing : June 03, 2014 • Kick off Meeting : June 24, 2014 • Site Handover : June 26, 2014 • TCC: June 02, 2016 • PAC: August 02, 2016 • FAC: November 02, 2016 SVC ALJOUF-2
  • 7. CONTROL ROOM Protection & Control System / SAS / Alarms / Metering (SIEMENS)  Electrical: Witnessing with CSD Engineer completed except the following: • SAS Close Loop Test 83% completed (remaining 17% for which data entry update will be completed by 25/10/2016 in CRCC; SCADA Closed Loop Test will be resumed on Wednesday 26/10/2016). • Final Trip Test for Protection & Control is completed • Interlock test completed • Snag Clearance in progress • Post Energization Test (to be done after Energization of SVC Transformer & 13.8kV Auxiliary System after receiving Energization Permit) : Need 10 Working Days to put SVC in service SVC ALJOUF-2
  • 8. SVC ALJOUF-2 HVAC & FPS  Electro-Mechanical: • HVAC installation – 100% completed ; Air- Balancing and DDC Panel in progress • Fire Alarm/Fighting Test: All walk through requirements/comments from ISD (East Division) – 100% completed ; request already send to ISD / S&EPD-East to confirm the date of Final Inspection or issue Energization Clearance based on the submitted Test results. • Internal Testing of Fire alarm, Firefighting and Hydrant system Completed.
  • 9. Dynamic & Static Reactive Power Compensator at Al Jouf-2, 380kV Substation Contractor Date of award 02/06/2016 TCC Handed Over SIEMENS 03.06.2014 15/10/2016 Expected Energization 26.06.2014 COMMISSIONING STATUS (99.2 % completed) EQUIPMENT REMARKS (Delivery status – 100 % completed) EXPECTED BUILDING READINESS BUILDINGEXP. DELIVERYSUPPLIEREQUIPMENTS/N Witnessing with CSD – 100% completed OLT – 100% completed CLT – 83% completed Capacitor, Reactor, Resister, Thyristor, IGBT, Cooling System delivered Foundations completedOutdoor Foundations30-12-2015SIEMENSSVC Equipment's1 Witnessing with CSD – 100% completed Delivered and InstalledFoundations completedTransformer Foundation15-12-2015SIEMENS450MVA Power Transformer's2 Witnessing with CSD – 99% completed Delivered and Installed Building and foundation are ready Control Building15-12-2015 ALFANAR, KSA & SIEMENS 13.8kV Switchgear & RMU3 Witnessing with CSD – 100% completed Delivered and InstalledFoundation readyTransformer Foundation15-02-2016UTEC, KSA Auxiliary Transformer / Grounding Transformer 4 Witnessing with CSD – 100% completed Delivered and Installed Building ReadyControl Building 15-01-2016TBDProtection System5 Witnessing with CSD – 100% completed Delivered and Installed15-12-2015 HEPOCKEE & BENNING Battery & Battery Charger6 Witnessing with CSD – 100% completed Delivered and Installed30-12-2015TBDAC / DC Panel7 HV Cable termination completed Delivered and InstalledSteel structure installed Trench and duct bank ready 25-10-2015TBD & LS Cable Steel Structures, Cables and Earthing Materials 8