2. Weekly Progress Report # 70
SVC
JOUF
PREPARED BY:
2016
AJAZ UL KABIR
Project Manager- Qassim Group
SEC ‐ EHVPD , COA , SVC Al-Jouf-2
Mobile : 054 112 2637 , Email : absheikh@se.com.sa
REVIEWED BY:
ABDULRAHMAN AL-KADI
Group Leader- Qassim
Extra High Voltage Projects Department- COA
Mobile : 050 489 6906 , Email : EVPRC-QPGL@se.com.sa
26
October
Dynamic Reactive Power Compensation at Hail-2
(9031) & Al-Jouf-2 380kV Substations
SEC CONTRACT NO. 4400003963/00
3. AIM/ OBJECTIVE: CONTRACT DETAILS:
SEC intends to improve rapid voltage
support at Hail-2 (9031) and Al-Jouf-2
380kV Substations of SEC network by
providing Conventional or Hybrid Static
VAR Compensator Systems (SVC).
The SVCs at Hail-2 (9031) shall be
connected to spare 380kV Breaker. CB
position for SVC at Al-Jouf-2 .380kV
Substation will be provided by Al-Jouf-2
380kV Substation Contractor.
• Project Name ……………………….. DYNAMIC REACTIVE POWER
COMPENSATION AT HAIL-2 (9031)
& AL-JOUF-2 380KV SUBSTATIONS
• Contract No ………………………… 4400003963/00
• Owner ………………………………. SAUDI ELECTRIC COMPANY - COA
• SEC Project Manager ……………… ENGR. AJAZ UL KABIR
• Contractor ………………………...... SIEMENS LTD.
• Address ……………………………... SIEMENS COMPANY LIMITED,
P.O.BOX 9510, RIYADH 11423, KSA
• Contractor Project Manager ………. ENGR. REHAN ULHAQUE
• Contract Effective Date ……………. 03-JUNE-2014
• Contract Value ……………………... SAR 463,840,000.00
PROJECT DESCRIPTION & CONTRACT INFO
SVC ALJOUF-2
5. SVS set up
2x SVC PLUS
2x TSC
32kV
380 kV
15% at 450 MVA +/-5%
Q at 32 kV (1.0 pu)
2 x (0+143.1 Mvar) cap 2 x (-75+81.9 Mvar)
Ik=63kA
SVC PLUSSVC PLUS
TSC TSC
Installation of +450MVAr (Capacitive) & -150MVAr (Indutive) 380kV SVC System
SVC CONNECTION DIAGRAM
SVC ALJOUF-2
6. PROJECT SIGN BOARD
• Contract Signing : June 03, 2014
• Kick off Meeting : June 24, 2014
• Site Handover : June 26, 2014
• TCC: June 02, 2016
• PAC: August 02, 2016
• FAC: November 02, 2016
SVC ALJOUF-2
7. CONTROL ROOM
Protection & Control System / SAS / Alarms / Metering (SIEMENS)
Electrical:
Witnessing with CSD Engineer completed except the
following:
• SAS Close Loop Test 83% completed (remaining 17%
for which data entry update will be completed by
25/10/2016 in CRCC; SCADA Closed Loop Test will be
resumed on Wednesday 26/10/2016).
• Final Trip Test for Protection & Control is completed
• Interlock test completed
• Snag Clearance in progress
• Post Energization Test (to be done after Energization of
SVC Transformer & 13.8kV Auxiliary System after
receiving Energization Permit) : Need 10 Working Days
to put SVC in service
SVC ALJOUF-2
8. SVC ALJOUF-2
HVAC & FPS
Electro-Mechanical:
• HVAC installation – 100% completed ; Air-
Balancing and DDC Panel in progress
• Fire Alarm/Fighting Test: All walk through
requirements/comments from ISD (East
Division) – 100% completed ; request
already send to ISD / S&EPD-East to
confirm the date of Final Inspection or
issue Energization Clearance based on the
submitted Test results.
• Internal Testing of Fire alarm, Firefighting
and Hydrant system Completed.
9. Dynamic & Static Reactive Power Compensator at Al Jouf-2, 380kV Substation
Contractor Date of award 02/06/2016 TCC Handed Over
SIEMENS 03.06.2014
15/10/2016 Expected
Energization
26.06.2014
COMMISSIONING
STATUS
(99.2 % completed)
EQUIPMENT
REMARKS
(Delivery status –
100 % completed)
EXPECTED BUILDING
READINESS
BUILDINGEXP. DELIVERYSUPPLIEREQUIPMENTS/N
Witnessing with CSD – 100%
completed
OLT – 100% completed
CLT – 83% completed
Capacitor, Reactor, Resister,
Thyristor, IGBT, Cooling
System delivered
Foundations completedOutdoor Foundations30-12-2015SIEMENSSVC Equipment's1
Witnessing with CSD – 100%
completed
Delivered and InstalledFoundations completedTransformer Foundation15-12-2015SIEMENS450MVA Power Transformer's2
Witnessing with CSD – 99%
completed
Delivered and Installed
Building and foundation are
ready
Control Building15-12-2015
ALFANAR, KSA &
SIEMENS
13.8kV Switchgear & RMU3
Witnessing with CSD – 100%
completed
Delivered and InstalledFoundation readyTransformer Foundation15-02-2016UTEC, KSA
Auxiliary Transformer /
Grounding Transformer
4
Witnessing with CSD – 100%
completed
Delivered and Installed
Building ReadyControl Building
15-01-2016TBDProtection System5
Witnessing with CSD – 100%
completed
Delivered and Installed15-12-2015
HEPOCKEE &
BENNING
Battery & Battery Charger6
Witnessing with CSD – 100%
completed
Delivered and Installed30-12-2015TBDAC / DC Panel7
HV Cable termination
completed
Delivered and InstalledSteel structure installed
Trench and duct bank
ready
25-10-2015TBD & LS Cable
Steel Structures, Cables and Earthing
Materials
8