This document summarizes the status of lead construction items for a project with a target completion date of May 31, 2014. It notes that civil works are tracking to complete on schedule, but there are delays to some electrical and mechanical equipment due to long lead times. Specifically, switch gears, cables, transformers, and pumps will be delayed 8-16 weeks due to material approval and inspection times. It recommends not submitting a recovery schedule, but instead extending the baseline schedule based on confirmed delivery dates of long lead items.
14. • Resist Submittal of “Recovery Schedule”
• Fast Track Equipment/Material Approval
Procedures as Revision of Plan and
Construction will based from Size and
Specification of the Approved Materials.
• Nesma to Submit “ Extension of Time
Schedule” or Stretch of BASELINE schedule
based on LONG LEAD ITEMS DELIVERY after
confirmation of Material Actual Delivery
dates.