This document summarizes the status of lead construction items for a project with a target completion date of May 31, 2014. It notes that civil works are tracking to complete on schedule, but there are delays to some electrical and mechanical equipment due to long lead times. Specifically, switch gears, cables, transformers, and pumps will be delayed 8-16 weeks due to material approval and inspection times. It recommends not submitting a recovery schedule, but instead extending the baseline schedule based on confirmed delivery dates of long lead items.