Procurement methods and recommendations
This part summarises the procurement methods and recommends for Taylor’s University. As the
dictionary definition stated that procurement is the act with the purpose of “to bring about” and “to
acquire”.The process includes preparation and processing of a demand and often be used by a company
asa strategyto purchase certainmaterials or services.A business will not be able to survive if the profits
are lesser than the price of procurement.
In construction industry, the client has the major choice to make decision on how to procure the
construction works that with most advantageous arrangement like for example an architect as the
building projector, an engineer for civil engineering projects, a quantity surveyor with preparations of
cost estimates and designer with preparation of drawing for the proposed scheme. There is a lot of
procurement systems used in the construction industry now a day because it is the process which
includes the steps of determination the criteria for the project, setting the contractual framework,
preparation tender and tendering process and awarding a contract that is very highly required in the
construction industry.
Procurement methods like traditional contract, design & build contract, management contract and
construction management contract are commonly used in construction industry in Malaysia. However,
the focus is only procurement methods that commonly used to be adopted in carrying out project of
building a multi-storey car park building in Taylor’s University campus. The two procurement systems
that can be considered as commonly used in construction industry are Traditional Contract and Design
& Build Contract.
1.1 Concept of Traditional Method
As we know that the word of “traditional” is defined as long- established which means traditional
method is the most common form of method that be used by different firms in past years. Traditional
method in procurement system is also known asDesign-Bid-Build (DBB).The construction is separated
from design which means by the contractor of the project has no responsibility for the design works
because client has control over the design through their appointed consultant asthe consultants are work
independently from the contractor in this method.
This is the way how it works, firstly the client will appoint consultants to produce a full design,
documentation and cost control. For example, architect will prepare a brief to the client about the
scheme outline and working drawings, quantity surveying will prepare cost estimate for client and so
on so forth. After that the client will invite tenders and administer the project by instructing and
inspecting the construction works. By using this traditional method, the client is able to have an in direct
contractual relationship with both the contractor and consultants.
1.1.1 Advantages
High standard quality and better control ofworks
By using this traditional procurement method, client will be able to have a high standard quality and
better control of the construction works because client is able to request any variation of works to
contractor and consultants.
Familiar with its working
Besides that, traditional method has been commonly used in construction industry now a day so
everyone will be familiar with its working. This is because many construction firms have been using it
since many years ago.
Cheaper cost ofconstruction
However for the cost of construction work, is usually be cheaper than other method however the design
risk is taken up by the employer because it is done under the client’s requirement.
Client’s interest is protected
On the other hand, client’s interest is protected by the consultant quantity surveyor, who serve as an
advisor for client in the building contracts.
1.1.2 Disadvantages
Outdated method
Now a day traditional method has be considered as anoutdated method for currentconstruction industry
which has been a standard practice in construction industry for many years. Getting more and more
better procurement method occurs in construction industry for example: D&B method and construction
management method.
Creates a “Them & us” attitude
This method has creates a “Them & us” attitude in the construction team because contractor and
consultants are doing their works separately as the contractor with the construction building works and
consultants with the preparation of design and cost control works.
Difficulty to communicate
There will be incompetent communication channel among the various consultants and cause the client
difficult to coordinate with them.
Longer duration of construction work
However, the construction works will be more longer duration because there are a lots of phases like
contractor have to wait for the design to start the construction works.
1.2 Concept of Design & Build Method
Design and build method is a procurement system that construction works and design works occur in
parallel which means an organization undertakes the responsibilities and risks on both construction and
design phased. This is because there are always problem arise in construction industry and when there
is a problem arise, the contractor will start to blame on the consultants and vice versa. The employer
may end up the half of project with the losing party. Besides that, there is a document called
“Employer’s Requirement” which is an agreement between Employer and Contractor. Contractor
design and build a project in accordance to the requirements stated in “Employer’s Requirements”.
In this Building & Build method, client will appoints consultants to prepare requirements, cost advice,
evaluate and select tenders. Then client’s contractor will have to produce a full design and completes
the design in parallel with the construction works. If the contractor has no design expertise in-house to
do the design, he might have to hire consultants to do the design job for him or take over the client’s
consultants through a process known as “novation”. With this design and build method, client will have
to appoint one contractor who completes all the designs and construction works. Client may appoints
independent advisor to monitor and administer the construction progress and quality of the work.
1.2.1 Advantages
Single point responsibility
By using this design and build method, the single point responsibility laid on the contractor who
responsible on both design work and construction services. So if there is any problem occurs, neither
contractor nor consultant shall put the blame on each other.
Saving time and cost
On the other hand, design and build method is able to save more time and cost of construction because
it is not essential for client to appoint consultants as the contractor have to do both design and
construction works.
Easier to communicate
Besides that, the client will be able to have a better communication channel with the contractor because
client only have to communicate with one party. The contractor will control over the subcontractors by
himself.
Speed ofprocurement
Other than that, the procurement will be faster because the design and construction work overlaps in
construction industry. The faster completion of the project brings benefits on the completion of
procurement.
1.2.2 Disadvantages
Quality of works and design will be compromised
Due to all the works are prepared by the independent contractor, so the quality of works and design will
be compromised in the view of contractor’s profit.
Higher professional fee outlay
Besides that, even the cost of construction works are lesser but the fee to employ a professional
experienced contractor is much higher compare with other methods. Better experienced independent
contractor is required to complete a full project which includes design and construct works.
Not flexible on design and construction work
Otherthan that, it will be much little flexibility to change on the design and construction method because
it all done by one contractor so the design possibilities are not explored in full.
Minimise the involvement ofthe client
Because of all the job will be completed by the independent contractor which includes design and
construction works, client will be seldom involve in the construction project.
1.3 Recommendation
Throughout the explanations above, Traditional method undergoes by client appoint a team of
consultants to prepare the design works and cost estimate, and select one independent contractor. This
method would bring the client a more accurate project cost, able to finish the project within the duration
that listed down in the contract, have a proper management on the material and workers and also able
to construct the project as the standard quality specified in the contract documentation. Although this
method brings a lot of disadvantages like it was an outdated method in construction industry, difficulty
on communication and longer duration of work but they will still able to continue and develop to change
and challenge the needs of society and construction industry.
However for the Design and Build method, even though it was a relatively fast method but there are
still a lot of disadvantages like quality of material and work comprised, high professional fee outlay and
not flexible on design and construct work. These problems are hardly solve because now a day in
construction industry, getting more and more professional independent contractors and there are a lot
of choices for client to choose whether which contractor has a better experience and production work.
Besides that, client has no direct power on control over the contractor’s performance and the contractor
design expertise might be limited because client has little say in the choice of contractor on choosing
the specialist sub-contractors.
So, as a director from Super QS Consultant Sdn. Bhd., I would like to recommend Traditional
procurement system because it is the better procurement system that should be considered. However,a
proper evaluation on procedures is recommended to develop a good practice in procurement and also
improve the reflection in construction industry.

More Related Content

What's hot

Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project managementJohn Constance
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1tfkc1212
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 

What's hot (20)

Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1
 
Akinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedAkinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 Submitted
 
Pp report
Pp reportPp report
Pp report
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 

Viewers also liked (20)

Company profile
Company profileCompany profile
Company profile
 
Psychology report
Psychology reportPsychology report
Psychology report
 
Idea Journal 01
Idea Journal 01Idea Journal 01
Idea Journal 01
 
Game Tournament
Game TournamentGame Tournament
Game Tournament
 
ENBE- Future City
ENBE- Future CityENBE- Future City
ENBE- Future City
 
Journal2
Journal2Journal2
Journal2
 
Psychology presentation
Psychology presentationPsychology presentation
Psychology presentation
 
Creative Thinking Skills Project 1
Creative Thinking Skills Project 1Creative Thinking Skills Project 1
Creative Thinking Skills Project 1
 
IDJ Super Hero
IDJ Super HeroIDJ Super Hero
IDJ Super Hero
 
IDJ 5
IDJ 5IDJ 5
IDJ 5
 
Presentation enbe final projects 1
Presentation enbe final projects 1Presentation enbe final projects 1
Presentation enbe final projects 1
 
IDJ 4
IDJ 4IDJ 4
IDJ 4
 
TJ 03
TJ 03TJ 03
TJ 03
 
Measurement 3 assignment
Measurement 3 assignmentMeasurement 3 assignment
Measurement 3 assignment
 
TJ 04
TJ 04TJ 04
TJ 04
 
Symbiotic relationship in nature
Symbiotic relationship in natureSymbiotic relationship in nature
Symbiotic relationship in nature
 
Tj
TjTj
Tj
 
Site Visit
Site VisitSite Visit
Site Visit
 
ENBE Infographic poster
ENBE Infographic posterENBE Infographic poster
ENBE Infographic poster
 
Journal1
Journal1Journal1
Journal1
 

Similar to Purpose

Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement methodhiewliming
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Residential Design Build Whitepaper
Residential Design Build WhitepaperResidential Design Build Whitepaper
Residential Design Build WhitepaperBethany Jenkins
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project DeliverySHKLaw
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014SHKLaw
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)James Baker
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt2cd
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services Ashok Tundare
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016Chris Nash
 

Similar to Purpose (19)

Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
p1p
p1pp1p
p1p
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Residential Design Build Whitepaper
Residential Design Build WhitepaperResidential Design Build Whitepaper
Residential Design Build Whitepaper
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project Delivery
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Bridging Gt Apr09
Bridging Gt Apr09Bridging Gt Apr09
Bridging Gt Apr09
 
PP1 report
PP1 reportPP1 report
PP1 report
 
ARTSCAPE_Introduction
ARTSCAPE_IntroductionARTSCAPE_Introduction
ARTSCAPE_Introduction
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016
 

More from Jäkê Čhŷį Śêrñ (18)

Meas 4-presentation
Meas 4-presentationMeas 4-presentation
Meas 4-presentation
 
Tender
TenderTender
Tender
 
Shd group-report
Shd group-reportShd group-report
Shd group-report
 
Sustainable housing development assignment
Sustainable housing development assignmentSustainable housing development assignment
Sustainable housing development assignment
 
Site surveying
Site surveying Site surveying
Site surveying
 
Telecommunication for high rise building
Telecommunication for high rise buildingTelecommunication for high rise building
Telecommunication for high rise building
 
Telecommunication for high rise building presentation
Telecommunication for high rise building presentationTelecommunication for high rise building presentation
Telecommunication for high rise building presentation
 
Building materials report 2
Building materials report 2Building materials report 2
Building materials report 2
 
Dulux paints
Dulux paintsDulux paints
Dulux paints
 
Building material report
Building material reportBuilding material report
Building material report
 
Assignment 2 edited
Assignment 2 editedAssignment 2 edited
Assignment 2 edited
 
Objective of site visit
Objective of site visitObjective of site visit
Objective of site visit
 
Business charity driveeee
Business charity driveeeeBusiness charity driveeee
Business charity driveeee
 
Assign 2
Assign 2Assign 2
Assign 2
 
The sponge
The spongeThe sponge
The sponge
 
Accounts project
Accounts projectAccounts project
Accounts project
 
Maths
MathsMaths
Maths
 
Group Component
Group ComponentGroup Component
Group Component
 

Recently uploaded

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 

Recently uploaded (20)

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 

Purpose

  • 1. Procurement methods and recommendations This part summarises the procurement methods and recommends for Taylor’s University. As the dictionary definition stated that procurement is the act with the purpose of “to bring about” and “to acquire”.The process includes preparation and processing of a demand and often be used by a company asa strategyto purchase certainmaterials or services.A business will not be able to survive if the profits are lesser than the price of procurement. In construction industry, the client has the major choice to make decision on how to procure the construction works that with most advantageous arrangement like for example an architect as the building projector, an engineer for civil engineering projects, a quantity surveyor with preparations of cost estimates and designer with preparation of drawing for the proposed scheme. There is a lot of procurement systems used in the construction industry now a day because it is the process which includes the steps of determination the criteria for the project, setting the contractual framework, preparation tender and tendering process and awarding a contract that is very highly required in the construction industry. Procurement methods like traditional contract, design & build contract, management contract and construction management contract are commonly used in construction industry in Malaysia. However, the focus is only procurement methods that commonly used to be adopted in carrying out project of building a multi-storey car park building in Taylor’s University campus. The two procurement systems that can be considered as commonly used in construction industry are Traditional Contract and Design & Build Contract. 1.1 Concept of Traditional Method As we know that the word of “traditional” is defined as long- established which means traditional method is the most common form of method that be used by different firms in past years. Traditional method in procurement system is also known asDesign-Bid-Build (DBB).The construction is separated from design which means by the contractor of the project has no responsibility for the design works because client has control over the design through their appointed consultant asthe consultants are work independently from the contractor in this method. This is the way how it works, firstly the client will appoint consultants to produce a full design, documentation and cost control. For example, architect will prepare a brief to the client about the scheme outline and working drawings, quantity surveying will prepare cost estimate for client and so on so forth. After that the client will invite tenders and administer the project by instructing and inspecting the construction works. By using this traditional method, the client is able to have an in direct contractual relationship with both the contractor and consultants.
  • 2. 1.1.1 Advantages High standard quality and better control ofworks By using this traditional procurement method, client will be able to have a high standard quality and better control of the construction works because client is able to request any variation of works to contractor and consultants. Familiar with its working Besides that, traditional method has been commonly used in construction industry now a day so everyone will be familiar with its working. This is because many construction firms have been using it since many years ago. Cheaper cost ofconstruction However for the cost of construction work, is usually be cheaper than other method however the design risk is taken up by the employer because it is done under the client’s requirement. Client’s interest is protected On the other hand, client’s interest is protected by the consultant quantity surveyor, who serve as an advisor for client in the building contracts. 1.1.2 Disadvantages Outdated method Now a day traditional method has be considered as anoutdated method for currentconstruction industry which has been a standard practice in construction industry for many years. Getting more and more better procurement method occurs in construction industry for example: D&B method and construction management method. Creates a “Them & us” attitude This method has creates a “Them & us” attitude in the construction team because contractor and consultants are doing their works separately as the contractor with the construction building works and consultants with the preparation of design and cost control works. Difficulty to communicate There will be incompetent communication channel among the various consultants and cause the client difficult to coordinate with them. Longer duration of construction work However, the construction works will be more longer duration because there are a lots of phases like contractor have to wait for the design to start the construction works.
  • 3. 1.2 Concept of Design & Build Method Design and build method is a procurement system that construction works and design works occur in parallel which means an organization undertakes the responsibilities and risks on both construction and design phased. This is because there are always problem arise in construction industry and when there is a problem arise, the contractor will start to blame on the consultants and vice versa. The employer may end up the half of project with the losing party. Besides that, there is a document called “Employer’s Requirement” which is an agreement between Employer and Contractor. Contractor design and build a project in accordance to the requirements stated in “Employer’s Requirements”. In this Building & Build method, client will appoints consultants to prepare requirements, cost advice, evaluate and select tenders. Then client’s contractor will have to produce a full design and completes the design in parallel with the construction works. If the contractor has no design expertise in-house to do the design, he might have to hire consultants to do the design job for him or take over the client’s consultants through a process known as “novation”. With this design and build method, client will have to appoint one contractor who completes all the designs and construction works. Client may appoints independent advisor to monitor and administer the construction progress and quality of the work. 1.2.1 Advantages Single point responsibility By using this design and build method, the single point responsibility laid on the contractor who responsible on both design work and construction services. So if there is any problem occurs, neither contractor nor consultant shall put the blame on each other. Saving time and cost On the other hand, design and build method is able to save more time and cost of construction because it is not essential for client to appoint consultants as the contractor have to do both design and construction works. Easier to communicate Besides that, the client will be able to have a better communication channel with the contractor because client only have to communicate with one party. The contractor will control over the subcontractors by himself. Speed ofprocurement Other than that, the procurement will be faster because the design and construction work overlaps in construction industry. The faster completion of the project brings benefits on the completion of procurement.
  • 4. 1.2.2 Disadvantages Quality of works and design will be compromised Due to all the works are prepared by the independent contractor, so the quality of works and design will be compromised in the view of contractor’s profit. Higher professional fee outlay Besides that, even the cost of construction works are lesser but the fee to employ a professional experienced contractor is much higher compare with other methods. Better experienced independent contractor is required to complete a full project which includes design and construct works. Not flexible on design and construction work Otherthan that, it will be much little flexibility to change on the design and construction method because it all done by one contractor so the design possibilities are not explored in full. Minimise the involvement ofthe client Because of all the job will be completed by the independent contractor which includes design and construction works, client will be seldom involve in the construction project. 1.3 Recommendation Throughout the explanations above, Traditional method undergoes by client appoint a team of consultants to prepare the design works and cost estimate, and select one independent contractor. This method would bring the client a more accurate project cost, able to finish the project within the duration that listed down in the contract, have a proper management on the material and workers and also able to construct the project as the standard quality specified in the contract documentation. Although this method brings a lot of disadvantages like it was an outdated method in construction industry, difficulty on communication and longer duration of work but they will still able to continue and develop to change and challenge the needs of society and construction industry. However for the Design and Build method, even though it was a relatively fast method but there are still a lot of disadvantages like quality of material and work comprised, high professional fee outlay and not flexible on design and construct work. These problems are hardly solve because now a day in construction industry, getting more and more professional independent contractors and there are a lot of choices for client to choose whether which contractor has a better experience and production work. Besides that, client has no direct power on control over the contractor’s performance and the contractor design expertise might be limited because client has little say in the choice of contractor on choosing the specialist sub-contractors. So, as a director from Super QS Consultant Sdn. Bhd., I would like to recommend Traditional procurement system because it is the better procurement system that should be considered. However,a proper evaluation on procedures is recommended to develop a good practice in procurement and also improve the reflection in construction industry.