2. Tender
2.1 About
A tender is a bidding process that is open to all qualified bidders and where the sealed bids are
opened in public for scrutiny and are chosen on the basis of price and quality. Tender is used in
many areas other than construction and may differ depending on what kind of tender. In this case
the tender document is submitted by contractors or also known as tenderers that wish to
participate in a tender invitation. The tender process is also taken into account the procurement
method which is selected by the employer after discussion with the consultants. The tendering
methods chosen can affect the outcome of the project even if by a small degree. There are 3
common categories people look into which are cost,quality and time. There 3 categories will be
the main factors of which tendering method is best suited for the situation.
The three more common tendering methods are open tendering, selective tendering and
negotiated tendering.
2.2 Open Tendering
Open tendering is the most common amongst the three methods as it is basically a free-for-all
method for any contractors interested to tender for the job. It starts with an advertisement being
published publicly via newspapers,websites and various other mediums. The advertisement
contains information such as type of job, location of site, location of collection, closing date of
tender, document fee and tender deposit. The tender documents are then printed to suit the
number of participants which can be quite difficult to predict as it tends to vary from project to
project. Sometimes the number of participants may vary from 10 up to 25 participants. Upon
collection of the tender document the contractor will have to fill up the rates of all the materials
required for the construction project. After the price has been determined, the completed tender
document shall be submitted to the employer at the appointed location together with a tender
deposit stated in the advert. The employer together with 1 or 2 consultants will open and record
all the tender documents submitted. Out of all the tender documents submitted only one
contractor will get the job, so the employers has to make a decision on which contractor should
get the job. It is the consultants’ job to evaluate each individual tender and come out with a report
which shows the recommended choice of tender. The employer usually follows the
recommendations given by the consultants however he is not obliged to follow the
recommendations. When the decision is made, the successfultender will meet the employer and
consultants for further negotiation of price. Once the price has been set, the contract document is
produced by the consultants and distributed to all the parties involved in the project including the
newly appointed contractor. At this point construction can commence.
2.2.1 Advantages of Open Tender
Open to all qualified bidders
Having a project available to all contractors has a higher tendency to find new promising
contractors which can satisfy the cost to quality to time ratio of the employer. Open tenders also
provide a larger variety of options to choose from which doesn’t limit the composition of the
project.
No favouritism
Every participant has an equal chance of getting the project and is not bias to any single tenderer.
This not only allows new firms to enter the market but also promotes professional etiquette.
Highly competitive
Forces the contractors to submit competitive prices to obtain the project. This can prove to be
advantageous for the employer in getting value for money.
2.2.2 Disadvantages of Open Tender
High cost oftendering
The number of copies of tender will have to depend on the number of participants tendering.
Open tendering being the method with usually the most tenderers,cost of tendering is generally
higher.
Novice contractors
One of the risks of possibly selecting a new and unknown contractor is higher with open
tendering method. The contractor may also potentially not have the sufficient experience for the
job at hand.
Underpriced tenders
Since all the contractors are trying to beat each others’ prices for the tender, employers need to be
carefulof underpriced tenders. Underpriced tenders may include low quality materials, poor
quality of works and other factors to cut corners.
Long tender process
Open tender is generally longer since it calls all possible contractors to tender and upon
submission of tender it requires the consultants to go through every single one of the tenders
which is very time consuming.
2.3 Selective Tendering
Single stage selective tendering
Single stage selective tendering starts off where the employer invites a few known and reputable
contracts to tender for the job. The contractors are not obliged to accept this invitation but will be
blacklisted if they do so by the employer. The number of contractors involved ranges from 5-10
participants. Upon accepting the invitation, the contractors will purchase a copy of the tender
document and fill in the rates of all the materials like in an opening tendering method. The
completed tender documents are sent back to the employer to be opened and recorded together
with the consultants. The consultants will then evaluate each of the tender documents and come
out with a report of the recommended choice of contractor. The employer again is not obliged to
follow the recommendation but in most cases employers usually do follow them. Before
accepting the offers, the employer will usually call the severalpotential contracts to further
negotiate the price. This is without the contractors knowing where they stand in the list. After
negotiation, the employer will make his decision and the contract documents will be made and
sent out to all parties involved including the newly appointed contractor. At this point the
construction can begin.
Two stage selective tendering
Two stage selective tendering starts off where the employer chooses a few contractors by pre-
qualification. The prospective contractors are chosen based on their experience and financial
capabilities. Other criterions also include management of projects at hand, quality of
workmanship, type of company and reputation. After a hand-full of qualified contractors are
picked, they are invited to participate in the tender. Similar to single stage selective tendering,
they are not forced to accept this invitation but are blacklisted by the employer if they do so. The
number of contractors involved in the pre-qualification can reach up to 20 participants that will
then be knocked down to the default 5-10 tendering participants. The interested contractors will
then purchase a copy of the tender document and fill in the rates of the project. Upon completion,
the completed tender document will be sent back to the employer to be opened and recorded
together with the consultants. The consultants will evaluate each one of the tender documents
submitted and come up with a report of recommendations for the employer. Usually the employer
will abide to the recommendation. Once the contractor is selected, the contract document is made
and sent out to all parties involved. Construction can begin at this point.
2.3.1 Advantages of selective tendering
Better quality ofworkmanship
Since the average quality of workmanship has been raised it is natural to expect better than
quality of workmanship than compared to open tendering method.
Simplified tender evaluation
The contractors participating are all reputable contractors so the quality of materials and
workmanship will only differ slightly, hence consultants can just focus on the price of which
these services come at.
Shorter tendering process
Less contractors involved means less time spent on evaluating tender documents and better
management of the tendering process.
Lowcost ofdocumentation
Less tender documents are required to accommodate the participating contractors this lowers the
printing fee. This method also allow for the consultants to know the exact amount of copies of
tender documents to print which isn’t the case for open tendering.
2.3.2 Disadvantages of selective tendering
High price
Since the average quality of materials and workmanship is higher than the open tendering method,
the price of the project is bound to rise. This is also because it is not as competitive as there are
lesser contractors tendering for the job.
Employer incurs resources
Preparing the list of contractors for pre-qualification requires for the contractor to make his on list
using his own resources and means to do so.
2.4 Negotiated tender
Negotiated tender starts with the employer selecting only one contractor due to his reputation and
ability to perform. The contractor shall then proceed to directly price the Bill of Quantities. Upon
completing the pricing of the materials, the contractor will enter a negotiation stage with the
quantity surveyor for the best value for money possible. After the negotiation process, consultants
will prepare the contract documents and send it to all the parties involved in the project. At this
point construction can commence.
2.4.1 Advantages of negotiated tender
Quality assurance
Since a highly reputable contractor is engaged, quality is sure to exceedingly high. This can also
be said for experience for similar projects.
High successrate
The chance of the contractor successfully completing the project is high as the contractor has the
experience and resources to do so. This cannot be said for open tendering.
Suitable for emergencies
In case of an emergency, engaging a contractor is crucial and cannot rely on the long process of
an open tendering method.
2.4.2 Disadvantages of negotiated tender
Highest price
This method prioritizes construction quality and time but not cost. It is a method with a highest
cost when compared to open tendering and selective tendering.
Long negotiation period
Negotiation can end up in endless arguments on the price of which the project can be constructed.
Worst case scenario is the agreement is called off due to not being able to agree on a right price.
2.5 Recommendation
The building to be constructed is a multi-storey car park so it requires a considerable amount of
quality as it can be quite dangerous if any failure of components were to occur. Having said this,
it is also illogical to have too high a cost as it is only a car park. To acquire the optimal balance
between the 2 factors,selective tendering seems to be the right choice for this project. This is
because it provides higher than average quality without the need to incur too much cost. All the
contractors are reputable which makes this method generally low risk high reward. Seeing as how
Taylor’s University is not an active client in construction, it also helps to keep both the tendering
process and negotiation phase simple. Other advantages include having low documentation cost
which is an extra bonus to save cost. The tendering time is also shorter making the total
construction time shorter which allows for consumers to occupy the infrastructure in a shorter
period. As for consideration on single stage selective tendering or two stage selective tendering, it
will depend on Taylor’s University’s knowledge of any reputable contractors. If unsure of any, it
is recommended to use two stage selective tendering.

More Related Content

What's hot

Tendering documentation
Tendering documentationTendering documentation
Tendering documentationnipuna_bopage
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsKunal Kacholiya
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 

What's hot (20)

Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Site possession
Site possessionSite possession
Site possession
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Construction process
Construction processConstruction process
Construction process
 
Tender
TenderTender
Tender
 
BS course bldg diagnostic
BS course bldg diagnosticBS course bldg diagnostic
BS course bldg diagnostic
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 

Viewers also liked

The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & BiddingMoatasem Mabrouk
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessPrateek Kashyap
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 

Viewers also liked (7)

Negotiation
NegotiationNegotiation
Negotiation
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

Similar to Tender

Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment reportSyafiq Zariful
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptxjairam131
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender NoticeSakshi Kirar
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
eeec ppt001.pptx
eeec ppt001.pptxeeec ppt001.pptx
eeec ppt001.pptxAminMemon7
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavarubanthevaraja pavaruban
 
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAnalysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAI Publications
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
Business negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain managementBusiness negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain managementSajeena Justin
 

Similar to Tender (20)

Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment report
 
Tenders
TendersTenders
Tenders
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Tendering
TenderingTendering
Tendering
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Tender
TenderTender
Tender
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Tenders, their types and process
Tenders, their types and processTenders, their types and process
Tenders, their types and process
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
eeec ppt001.pptx
eeec ppt001.pptxeeec ppt001.pptx
eeec ppt001.pptx
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavaruban
 
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAnalysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Business negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain managementBusiness negotiations for purchasing and supply chain management
Business negotiations for purchasing and supply chain management
 

More from Jäkê Čhŷį Śêrñ (20)

Meas 4-presentation
Meas 4-presentationMeas 4-presentation
Meas 4-presentation
 
Purpose
PurposePurpose
Purpose
 
Shd group-report
Shd group-reportShd group-report
Shd group-report
 
Sustainable housing development assignment
Sustainable housing development assignmentSustainable housing development assignment
Sustainable housing development assignment
 
Management science
Management scienceManagement science
Management science
 
Measurement 3 assignment
Measurement 3 assignmentMeasurement 3 assignment
Measurement 3 assignment
 
Site surveying
Site surveying Site surveying
Site surveying
 
Telecommunication for high rise building
Telecommunication for high rise buildingTelecommunication for high rise building
Telecommunication for high rise building
 
Telecommunication for high rise building presentation
Telecommunication for high rise building presentationTelecommunication for high rise building presentation
Telecommunication for high rise building presentation
 
Building materials report 2
Building materials report 2Building materials report 2
Building materials report 2
 
Dulux paints
Dulux paintsDulux paints
Dulux paints
 
Building material report
Building material reportBuilding material report
Building material report
 
Assignment 2 edited
Assignment 2 editedAssignment 2 edited
Assignment 2 edited
 
Objective of site visit
Objective of site visitObjective of site visit
Objective of site visit
 
Business charity driveeee
Business charity driveeeeBusiness charity driveeee
Business charity driveeee
 
Journal2
Journal2Journal2
Journal2
 
Journal1
Journal1Journal1
Journal1
 
Assign 2
Assign 2Assign 2
Assign 2
 
The sponge
The spongeThe sponge
The sponge
 
Accounts project
Accounts projectAccounts project
Accounts project
 

Recently uploaded

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...Pooja Nehwal
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 

Recently uploaded (20)

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 

Tender

  • 1. 2. Tender 2.1 About A tender is a bidding process that is open to all qualified bidders and where the sealed bids are opened in public for scrutiny and are chosen on the basis of price and quality. Tender is used in many areas other than construction and may differ depending on what kind of tender. In this case the tender document is submitted by contractors or also known as tenderers that wish to participate in a tender invitation. The tender process is also taken into account the procurement method which is selected by the employer after discussion with the consultants. The tendering methods chosen can affect the outcome of the project even if by a small degree. There are 3 common categories people look into which are cost,quality and time. There 3 categories will be the main factors of which tendering method is best suited for the situation. The three more common tendering methods are open tendering, selective tendering and negotiated tendering. 2.2 Open Tendering Open tendering is the most common amongst the three methods as it is basically a free-for-all method for any contractors interested to tender for the job. It starts with an advertisement being published publicly via newspapers,websites and various other mediums. The advertisement contains information such as type of job, location of site, location of collection, closing date of tender, document fee and tender deposit. The tender documents are then printed to suit the number of participants which can be quite difficult to predict as it tends to vary from project to project. Sometimes the number of participants may vary from 10 up to 25 participants. Upon collection of the tender document the contractor will have to fill up the rates of all the materials required for the construction project. After the price has been determined, the completed tender document shall be submitted to the employer at the appointed location together with a tender deposit stated in the advert. The employer together with 1 or 2 consultants will open and record all the tender documents submitted. Out of all the tender documents submitted only one contractor will get the job, so the employers has to make a decision on which contractor should get the job. It is the consultants’ job to evaluate each individual tender and come out with a report which shows the recommended choice of tender. The employer usually follows the recommendations given by the consultants however he is not obliged to follow the recommendations. When the decision is made, the successfultender will meet the employer and consultants for further negotiation of price. Once the price has been set, the contract document is produced by the consultants and distributed to all the parties involved in the project including the newly appointed contractor. At this point construction can commence.
  • 2. 2.2.1 Advantages of Open Tender Open to all qualified bidders Having a project available to all contractors has a higher tendency to find new promising contractors which can satisfy the cost to quality to time ratio of the employer. Open tenders also provide a larger variety of options to choose from which doesn’t limit the composition of the project. No favouritism Every participant has an equal chance of getting the project and is not bias to any single tenderer. This not only allows new firms to enter the market but also promotes professional etiquette. Highly competitive Forces the contractors to submit competitive prices to obtain the project. This can prove to be advantageous for the employer in getting value for money. 2.2.2 Disadvantages of Open Tender High cost oftendering The number of copies of tender will have to depend on the number of participants tendering. Open tendering being the method with usually the most tenderers,cost of tendering is generally higher. Novice contractors One of the risks of possibly selecting a new and unknown contractor is higher with open tendering method. The contractor may also potentially not have the sufficient experience for the job at hand. Underpriced tenders Since all the contractors are trying to beat each others’ prices for the tender, employers need to be carefulof underpriced tenders. Underpriced tenders may include low quality materials, poor quality of works and other factors to cut corners. Long tender process Open tender is generally longer since it calls all possible contractors to tender and upon submission of tender it requires the consultants to go through every single one of the tenders which is very time consuming.
  • 3. 2.3 Selective Tendering Single stage selective tendering Single stage selective tendering starts off where the employer invites a few known and reputable contracts to tender for the job. The contractors are not obliged to accept this invitation but will be blacklisted if they do so by the employer. The number of contractors involved ranges from 5-10 participants. Upon accepting the invitation, the contractors will purchase a copy of the tender document and fill in the rates of all the materials like in an opening tendering method. The completed tender documents are sent back to the employer to be opened and recorded together with the consultants. The consultants will then evaluate each of the tender documents and come out with a report of the recommended choice of contractor. The employer again is not obliged to follow the recommendation but in most cases employers usually do follow them. Before accepting the offers, the employer will usually call the severalpotential contracts to further negotiate the price. This is without the contractors knowing where they stand in the list. After negotiation, the employer will make his decision and the contract documents will be made and sent out to all parties involved including the newly appointed contractor. At this point the construction can begin. Two stage selective tendering Two stage selective tendering starts off where the employer chooses a few contractors by pre- qualification. The prospective contractors are chosen based on their experience and financial capabilities. Other criterions also include management of projects at hand, quality of workmanship, type of company and reputation. After a hand-full of qualified contractors are picked, they are invited to participate in the tender. Similar to single stage selective tendering, they are not forced to accept this invitation but are blacklisted by the employer if they do so. The number of contractors involved in the pre-qualification can reach up to 20 participants that will then be knocked down to the default 5-10 tendering participants. The interested contractors will then purchase a copy of the tender document and fill in the rates of the project. Upon completion, the completed tender document will be sent back to the employer to be opened and recorded together with the consultants. The consultants will evaluate each one of the tender documents submitted and come up with a report of recommendations for the employer. Usually the employer will abide to the recommendation. Once the contractor is selected, the contract document is made and sent out to all parties involved. Construction can begin at this point.
  • 4. 2.3.1 Advantages of selective tendering Better quality ofworkmanship Since the average quality of workmanship has been raised it is natural to expect better than quality of workmanship than compared to open tendering method. Simplified tender evaluation The contractors participating are all reputable contractors so the quality of materials and workmanship will only differ slightly, hence consultants can just focus on the price of which these services come at. Shorter tendering process Less contractors involved means less time spent on evaluating tender documents and better management of the tendering process. Lowcost ofdocumentation Less tender documents are required to accommodate the participating contractors this lowers the printing fee. This method also allow for the consultants to know the exact amount of copies of tender documents to print which isn’t the case for open tendering. 2.3.2 Disadvantages of selective tendering High price Since the average quality of materials and workmanship is higher than the open tendering method, the price of the project is bound to rise. This is also because it is not as competitive as there are lesser contractors tendering for the job. Employer incurs resources Preparing the list of contractors for pre-qualification requires for the contractor to make his on list using his own resources and means to do so.
  • 5. 2.4 Negotiated tender Negotiated tender starts with the employer selecting only one contractor due to his reputation and ability to perform. The contractor shall then proceed to directly price the Bill of Quantities. Upon completing the pricing of the materials, the contractor will enter a negotiation stage with the quantity surveyor for the best value for money possible. After the negotiation process, consultants will prepare the contract documents and send it to all the parties involved in the project. At this point construction can commence. 2.4.1 Advantages of negotiated tender Quality assurance Since a highly reputable contractor is engaged, quality is sure to exceedingly high. This can also be said for experience for similar projects. High successrate The chance of the contractor successfully completing the project is high as the contractor has the experience and resources to do so. This cannot be said for open tendering. Suitable for emergencies In case of an emergency, engaging a contractor is crucial and cannot rely on the long process of an open tendering method. 2.4.2 Disadvantages of negotiated tender Highest price This method prioritizes construction quality and time but not cost. It is a method with a highest cost when compared to open tendering and selective tendering. Long negotiation period Negotiation can end up in endless arguments on the price of which the project can be constructed. Worst case scenario is the agreement is called off due to not being able to agree on a right price.
  • 6. 2.5 Recommendation The building to be constructed is a multi-storey car park so it requires a considerable amount of quality as it can be quite dangerous if any failure of components were to occur. Having said this, it is also illogical to have too high a cost as it is only a car park. To acquire the optimal balance between the 2 factors,selective tendering seems to be the right choice for this project. This is because it provides higher than average quality without the need to incur too much cost. All the contractors are reputable which makes this method generally low risk high reward. Seeing as how Taylor’s University is not an active client in construction, it also helps to keep both the tendering process and negotiation phase simple. Other advantages include having low documentation cost which is an extra bonus to save cost. The tendering time is also shorter making the total construction time shorter which allows for consumers to occupy the infrastructure in a shorter period. As for consideration on single stage selective tendering or two stage selective tendering, it will depend on Taylor’s University’s knowledge of any reputable contractors. If unsure of any, it is recommended to use two stage selective tendering.