PROCUREMENT METHODS

COMPILED BY:
REV. SR LILIAN NWACHUKWU

SUBMITTED TO THE DEPARTMENT OF BUILDING
NNAMDI AZIKIWE UNIVERSITY, AWKA.

LECTURER-IN-CHARGE:
DR OKOLIE K.C
JULY 2012.
PROCUREMENT METHODS.
Introduction.
According to Encarta dictionary 2009, to procure means to acquire something: to obtain
something especially by effort. In construction terms, procurement refers to the process
of acquiring something. This process of acquiring something has different approaches
or methods; hence in the construction sense, procuring a building has different methods
to it.
When a project is dreamt about by the client, he works towards actualizing it. Apart
from funding and providing land for development, the client does not have the
requisite skill to actualize his dream. He has to employ the services of those who would
do so. The task of designing his dream and its subsequent construction are open to
different methods; hence to choose the most appropriate method for his project, he
needs professional advice. The method he chooses is dependent on some factors, which
in the end should satisfy his need.
What is procurement?
Procurement is a term used to describe all activities undertaken by the client in seeking
to bring about the construction of, or the refurbishment of a building. It is also referred
to as method or system which seeks to weigh the pros and cons and the financial
constraints which are likely to affect the project so as to select an effective contractual
arrangement. The simplest definition, according to Nagy, Kiss and Hornyak (n.d)
described Procurement as the merging of activities undertaken by the client to obtain a
building.
When a client wishes to choose any type of procurement method for realizing his
project, his major concerns are:
 To finish the project on time
 The cost of the project
 Performance or quality in relation to both design and construction of the
building.
There are four main procurement options, they are as follows:
Traditional method
Design and Build method
Management Contracting method
Public-Private Partnership (PPP) method.

Traditional
This method is as old as the construction industry. The major feature is that the design
process is separate from construction. It also requires full documentation before the
contractor can be invited to tender for the work. In summary, traditional method simply
involves the steps- design, bid and build.
Features of the Traditional System.
The traditional system is characterized by the following:
 Contractor is appointed by competitive tendering
 Designs should be fully prepared ahead of time before tendering procedure and
actual construction can begin.
 The client has control over design. There is no design responsibility on the
contractor.
 The duration of the project tends to be very long because of the separate
sequential process of design and construction.
 The construction cost is well known ahead of time and there may be need for
adjustment as provided for in the contract.
 The client appoints a professional consultant to administer the contract on his
behalf and to advice on aspects associated with design, progress and stage
payment which must be paid by the client.
The structure of the traditional system is shown below:
Source: Naggy et al. (n.d).

Analysis.
Although the traditional procurement method is very simple to understand by all
classes of client, the major problem it has, is that the contract period tends to be more
prolonged due to the fact that design process is separate, and determines the
commencement of the actual construction. Again the early and vital input of the Builder
is not tapped; hence, the product is likely to be deficient in buildability and
maintenability aspects.
Design and build.
In this method, the contractor is responsible for undertaking both the design and
construction of the work in return for a lump sum price.
To arrive at a choice of contractor, contractors are required to develop a design (from an
initial concept prepared by the consultant appointed to advice the client) to a certain
level, prepare a tender figure and submit the whole package which is termed a proposal
to be evaluated to meet the satisfaction of the client. A team of consultants will be
needed to assess each contractor’s proposal. Evaluation of tenders in this case is usually
difficult because the contractors are not working with one design. Tenderers should be
informed of the criteria to be used, and whether price is likely to be a prime factor.
Features of this method include:
 The contractor is often appointed by two-stage tendering i.e. the competitive
element and quality is preserved.
 The client can introduce changes to the design at the design stage, but once the
contract has been awarded to the contractor, he has no direct control over the
development of the design detail by the contractor.
 A major feature of this procurement method is that design and construction may
proceed in parallel, and so the project duration will be shortened.
 This procurement method makes no room for appointment of an independent
contract administrator. The client works directly with the contractor, or he may
appoint an agent to advice him, or act on his behalf.
 Valuation and payment matters are solely in the hands of the contractor.
 It is an obligation to complete the project within the contract period, however,
the client may accept a later date to account for delays resulting from reasons
listed in the contract.

Analysis.
The Design-Build approach gives the client a single point of contact. However, the client
commits to the cost of construction, as well as the cost of design, much earlier than with
the traditional approach. Whilst risk is shifted to the contractor, it is important that
design liability insurance is maintained to cover that risk. Changes made by the client
during design can be expensive, because they affect the whole of the Design-Build
contract, rather than just the design team cost.
Secondly, although the contract period is shortened, the process of assessing the
tenders, and selecting a contractor can be difficult due to the fact that all the tenderers
are working with different designs.
Management Procurement.
This method of procurement is based upon the client appointing a consultant who will
prepare project drawings and project specifications. Consequent upon this, a
management contractor is then selected by a process of tender and interviews. The
management contractor will not carry out construction work. This helps to preserve the
management contractor’s independence and reinforces a consultancy relationship with
the client. Payment is made to the management contractor on the basis of the cost of the
works packages plus the agreed fee. The success of this approach depends on the
contractor’s team. Unless the team is drawn from companies which are experienced in
this kind of team working, the benefits are not always realized.
There is less price certainty at the outset, because construction tends to start ahead of
completion of all design stages and at a point when many of the work packages are yet
to be tendered for. This often means that adjustments will be made to the design and
specification of works packages later in the programme to keep the project within
budget. However, the overall process of design and construction tends to be shorter
than in either the traditional or design and build methods. Another variant of
management contracting is construction management.
Construction Management
This is similar in concept to Management Contracting. The sub contractors or specialists
are contracted directly to the client and the construction manager manages the process
for the client on a simple consultancy basis. Construction Management requires
constant involvement of the client, so it is really only suitable for experienced clients.

Analysis.
This method is characterized by a high level of skillful input since the subcontractors
engaged are experts in their various fields. The result is that the construction process is
characterized by some level of precision synonymous with manufacturing industry.
There is equally minimal supervision and the whole arrangement seem to favour each
party. The major challenge in this method is organization, unless the team of
contractors are pulled from companies who are used to team working, the whole
system may be frustrating.

Public-Private Partnership.
This procurement method refers to the collaboration between public and private sector
in order to achieve financing, management or maintenance of a project or the provision
of services. According to Obozuwa (2011), Public–private partnership (PPP) describes a
government service or private business venture which is funded and operated through
a partnership of government and one or more private sector companies. PPP is,
therefore, regarded as a tool for infrastructure development.
Public and Private sectors may co-operate in the following sectors:
transport,
public health,
education,
safety,
waste management,
water supply and energy
A PPP project is not different from the other procurement forms. It is the financing of
the project that is different.
The responsibility of each of the sectors in the realization of a project are as follows:
The Private sector :
is responsible to provide the whole, or part of the project financing
is responsible for the risks that are related to the construction or operation of the
project.
has long term benefits from the project
designs the project (or part of the design)
manages and operates or maintains the facility
returns the project to the public after the completion of the contract period
The Public sector:
determines the drawing, technical, operational and financial requirements of the
project
assesses the proposal of the private sector
supports the construction of the project
monitors the project and makes sure the private sector conforms with the
contract
proceeds with payments to the private sector.
Models of Public-Private Partnership.
PPP agreement may take the following forms:
Design-Build (DB) or “Turnkey” contract: in this case, the private sector designs
and builds infrastructure according to public sector performance specifications for
a fixed price, thereby transferring the risk of cost overruns to the private sector.
Management contract: Here, the private sector contracts to manage a Government
owned project and manages the marketing and provision of a service.
Lease and operate contract: A private operator contracts to lease and assume all
management and operation of a government owned facility and associated
services, and may invest further in developing the service and provide the service
for a fixed term.
Design-Build-Finance-Operate (DBFO): The private sector designs, finances and
constructs a new facility. It is then required to operate the within a lease period.
The private partner then transfers the new facility to the public sector at the end of
the lease period.
Build-Operate-Transfer (BOT): A private entity receives the license to finance,
design, build and operate a facility for a specified period, after which ownership is
transferred back to the public sector. This has been used in telecommunications
service contracts.
Buy-Build-Operate (BBO): If there is need to revive a public asset, the
government can transfer it to a private or quasi-public entity usually under
contract that the assets are to be upgraded and operated for a specified period of
time. Public control is exercised through the contract at the time of transfer.
Build-Own-Operate (BOO): In this case, the private sector finances, builds, owns
and operates a facility or service in perpetuity. The public constraints are stated in
the original agreement and through on-going regulatory obligations.
Build-Own-Operate & Transfer (BOOT): The Private Sector builds, owns,
operates a facility for a specified period as agreed in the contract and then
transfers to the Public.
Operating License: A private operator receives a license or rights to build and
operate a public service, usually for a specified term. This is similar to BBO
arrangement and is often used in telecommunications and ICT projects.
Finance Only: A private entity, usually a financial services company, funds a
project directly or uses various mechanisms such as a long-term lease or bond
issue.
Advantages.
The Public sector gains the advantages the private sector offers such as: ability
to design, construct, manage and finance a project.
Public money is better used and at difficult economic periods for a government,
this method is good.
They promote and help the innovation in the public sectors with the transfer of
knowledge and new techniques.
Better quality infrastructure and better operation throughout the life of the
project (maintenance of the project by the private sector) is assured.
There is more efficient and more economical maintenance of the project.
Reduction of the construction cost and maintenance of the project.
Use of private sector in areas where there are ‘weaknesses’ in the public sector
such as: lack of expertise and qualified employees, no ability to promote new
technoeconomical solutions, lack of efficient and effective use of human
resources, lack of sensitivity and knowledge and expertise in the use of available
energy sources.
Disadvantanges.
The use of the project by the private sector is difficult for low income people.
However, it has the advantage that only the users pay and not the tax payer.
In some cases, there may be in the contract some clauses or provisions which do
not favour the public interest but aim at increasing the profit of the private
investor, allow monopoly or even allow the private sector to increase the price of
a service or a product after completion of the project.
Since much of funding the project is done by the private investor, there is every
tendency to aim at reducing the cost of a project which might lead to the use of
substandard materials and works
Generally, the public sector can get cheaper loans than the private sector.
Analysis.
The system has been applauded as important tool for improving economic
effectiveness, and a mechanism to fill infrastructure deficit (Shwarka and Anigbogu
2012). The system equally lends itself to the intervention of private entity whose sole
aim in development participation is more profit oriented than of social growth, for this
reason, it is necessary that government should balance its profit motive with social
growth. This can be achieved through government monitoring and imposition of
compliance

with

performance

standards

as

a

pre-requisite

in

development

participation.
Conclusion.
There is not just one method of procuring a building. The different methods that are
available provide a wide range of options for any promoter to realize his dream. The
choice of any method is dependent on the prime concerns of the client, (which are cost,
time and quality) and the type of project. Whatever choice of option that is made, must
not fail in any of these factors; hence, the client needs guidance and direction so that he
has cause to smile when his dream has been actualized.
The majority of clients are ignorant and quickly embrace the traditional method as the
only procurement option. The quick recourse to this option is due to its simplicity, age
and familiarity with the process. The result is that the wrong option is applied to wrong
projects, which may lead to problems ranging from waste of resources to dissatisfaction
with the final product. The need for professional advice is, therefore necessary to help
the clients make the right choice.
References.
Naggy, E. Kiss, L. and Hornyak, S. (n.d). Different procurement methods.
www.byggai.se/mats/cm1/procurementmethods.pptx
Obozuwa, D. (2011). PPP as a tool for infrastructure development in Nigeria (1).
www.businessdayonline.com/NG/index.php/law/cover/28768.
Shwarka, S and Anigbogu, (2012). The impact of public procurement options on
building projects
42nd National
Building

performance in Nigeria. A paper presented at the
conference/General Meeting of the Nigerian Institute of

More Related Content

What's hot

Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPTKEVINMISTRY8
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group AssignmentArissa Loh
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 

What's hot (20)

Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Contract management
Contract managementContract management
Contract management
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
RIBA plan of work
RIBA plan of workRIBA plan of work
RIBA plan of work
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Tender
TenderTender
Tender
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 

Similar to Procurement Methods and their Application.

Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
CRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project ManagementCRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project ManagementChris Gorga
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt2cd
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
Contracts in professional practice
Contracts in professional practiceContracts in professional practice
Contracts in professional practiceAditya Sanyal
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project DeliverySHKLaw
 

Similar to Procurement Methods and their Application. (20)

Purpose
PurposePurpose
Purpose
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp report
Pp reportPp report
Pp report
 
p1p
p1pp1p
p1p
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
CRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project ManagementCRG DevCo’s advantages of outsourcing Project Management
CRG DevCo’s advantages of outsourcing Project Management
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Contracts in professional practice
Contracts in professional practiceContracts in professional practice
Contracts in professional practice
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project Delivery
 

Recently uploaded

Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdfChristopherTHyatt
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfhans926745
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 

Recently uploaded (20)

Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 

Procurement Methods and their Application.

  • 1. AN ASSIGNMENT ON PROCUREMENT METHODS COMPILED BY: REV. SR LILIAN NWACHUKWU SUBMITTED TO THE DEPARTMENT OF BUILDING NNAMDI AZIKIWE UNIVERSITY, AWKA. LECTURER-IN-CHARGE: DR OKOLIE K.C JULY 2012.
  • 2. PROCUREMENT METHODS. Introduction. According to Encarta dictionary 2009, to procure means to acquire something: to obtain something especially by effort. In construction terms, procurement refers to the process of acquiring something. This process of acquiring something has different approaches or methods; hence in the construction sense, procuring a building has different methods to it. When a project is dreamt about by the client, he works towards actualizing it. Apart from funding and providing land for development, the client does not have the requisite skill to actualize his dream. He has to employ the services of those who would do so. The task of designing his dream and its subsequent construction are open to different methods; hence to choose the most appropriate method for his project, he needs professional advice. The method he chooses is dependent on some factors, which in the end should satisfy his need. What is procurement? Procurement is a term used to describe all activities undertaken by the client in seeking to bring about the construction of, or the refurbishment of a building. It is also referred to as method or system which seeks to weigh the pros and cons and the financial constraints which are likely to affect the project so as to select an effective contractual arrangement. The simplest definition, according to Nagy, Kiss and Hornyak (n.d) described Procurement as the merging of activities undertaken by the client to obtain a building. When a client wishes to choose any type of procurement method for realizing his project, his major concerns are:  To finish the project on time  The cost of the project  Performance or quality in relation to both design and construction of the building.
  • 3. There are four main procurement options, they are as follows: Traditional method Design and Build method Management Contracting method Public-Private Partnership (PPP) method. Traditional This method is as old as the construction industry. The major feature is that the design process is separate from construction. It also requires full documentation before the contractor can be invited to tender for the work. In summary, traditional method simply involves the steps- design, bid and build. Features of the Traditional System. The traditional system is characterized by the following:  Contractor is appointed by competitive tendering  Designs should be fully prepared ahead of time before tendering procedure and actual construction can begin.  The client has control over design. There is no design responsibility on the contractor.  The duration of the project tends to be very long because of the separate sequential process of design and construction.  The construction cost is well known ahead of time and there may be need for adjustment as provided for in the contract.  The client appoints a professional consultant to administer the contract on his behalf and to advice on aspects associated with design, progress and stage payment which must be paid by the client. The structure of the traditional system is shown below:
  • 4. Source: Naggy et al. (n.d). Analysis. Although the traditional procurement method is very simple to understand by all classes of client, the major problem it has, is that the contract period tends to be more prolonged due to the fact that design process is separate, and determines the commencement of the actual construction. Again the early and vital input of the Builder is not tapped; hence, the product is likely to be deficient in buildability and maintenability aspects.
  • 5. Design and build. In this method, the contractor is responsible for undertaking both the design and construction of the work in return for a lump sum price. To arrive at a choice of contractor, contractors are required to develop a design (from an initial concept prepared by the consultant appointed to advice the client) to a certain level, prepare a tender figure and submit the whole package which is termed a proposal to be evaluated to meet the satisfaction of the client. A team of consultants will be needed to assess each contractor’s proposal. Evaluation of tenders in this case is usually difficult because the contractors are not working with one design. Tenderers should be informed of the criteria to be used, and whether price is likely to be a prime factor. Features of this method include:  The contractor is often appointed by two-stage tendering i.e. the competitive element and quality is preserved.  The client can introduce changes to the design at the design stage, but once the contract has been awarded to the contractor, he has no direct control over the development of the design detail by the contractor.  A major feature of this procurement method is that design and construction may proceed in parallel, and so the project duration will be shortened.  This procurement method makes no room for appointment of an independent contract administrator. The client works directly with the contractor, or he may appoint an agent to advice him, or act on his behalf.  Valuation and payment matters are solely in the hands of the contractor.  It is an obligation to complete the project within the contract period, however, the client may accept a later date to account for delays resulting from reasons listed in the contract. Analysis. The Design-Build approach gives the client a single point of contact. However, the client commits to the cost of construction, as well as the cost of design, much earlier than with
  • 6. the traditional approach. Whilst risk is shifted to the contractor, it is important that design liability insurance is maintained to cover that risk. Changes made by the client during design can be expensive, because they affect the whole of the Design-Build contract, rather than just the design team cost. Secondly, although the contract period is shortened, the process of assessing the tenders, and selecting a contractor can be difficult due to the fact that all the tenderers are working with different designs. Management Procurement. This method of procurement is based upon the client appointing a consultant who will prepare project drawings and project specifications. Consequent upon this, a management contractor is then selected by a process of tender and interviews. The management contractor will not carry out construction work. This helps to preserve the management contractor’s independence and reinforces a consultancy relationship with the client. Payment is made to the management contractor on the basis of the cost of the works packages plus the agreed fee. The success of this approach depends on the contractor’s team. Unless the team is drawn from companies which are experienced in this kind of team working, the benefits are not always realized. There is less price certainty at the outset, because construction tends to start ahead of completion of all design stages and at a point when many of the work packages are yet to be tendered for. This often means that adjustments will be made to the design and specification of works packages later in the programme to keep the project within budget. However, the overall process of design and construction tends to be shorter than in either the traditional or design and build methods. Another variant of management contracting is construction management. Construction Management This is similar in concept to Management Contracting. The sub contractors or specialists are contracted directly to the client and the construction manager manages the process
  • 7. for the client on a simple consultancy basis. Construction Management requires constant involvement of the client, so it is really only suitable for experienced clients. Analysis. This method is characterized by a high level of skillful input since the subcontractors engaged are experts in their various fields. The result is that the construction process is characterized by some level of precision synonymous with manufacturing industry. There is equally minimal supervision and the whole arrangement seem to favour each party. The major challenge in this method is organization, unless the team of contractors are pulled from companies who are used to team working, the whole system may be frustrating. Public-Private Partnership. This procurement method refers to the collaboration between public and private sector in order to achieve financing, management or maintenance of a project or the provision of services. According to Obozuwa (2011), Public–private partnership (PPP) describes a government service or private business venture which is funded and operated through a partnership of government and one or more private sector companies. PPP is, therefore, regarded as a tool for infrastructure development. Public and Private sectors may co-operate in the following sectors: transport, public health, education, safety, waste management, water supply and energy A PPP project is not different from the other procurement forms. It is the financing of the project that is different.
  • 8. The responsibility of each of the sectors in the realization of a project are as follows: The Private sector : is responsible to provide the whole, or part of the project financing is responsible for the risks that are related to the construction or operation of the project. has long term benefits from the project designs the project (or part of the design) manages and operates or maintains the facility returns the project to the public after the completion of the contract period The Public sector: determines the drawing, technical, operational and financial requirements of the project assesses the proposal of the private sector supports the construction of the project monitors the project and makes sure the private sector conforms with the contract proceeds with payments to the private sector. Models of Public-Private Partnership. PPP agreement may take the following forms: Design-Build (DB) or “Turnkey” contract: in this case, the private sector designs and builds infrastructure according to public sector performance specifications for a fixed price, thereby transferring the risk of cost overruns to the private sector. Management contract: Here, the private sector contracts to manage a Government owned project and manages the marketing and provision of a service. Lease and operate contract: A private operator contracts to lease and assume all management and operation of a government owned facility and associated
  • 9. services, and may invest further in developing the service and provide the service for a fixed term. Design-Build-Finance-Operate (DBFO): The private sector designs, finances and constructs a new facility. It is then required to operate the within a lease period. The private partner then transfers the new facility to the public sector at the end of the lease period. Build-Operate-Transfer (BOT): A private entity receives the license to finance, design, build and operate a facility for a specified period, after which ownership is transferred back to the public sector. This has been used in telecommunications service contracts. Buy-Build-Operate (BBO): If there is need to revive a public asset, the government can transfer it to a private or quasi-public entity usually under contract that the assets are to be upgraded and operated for a specified period of time. Public control is exercised through the contract at the time of transfer. Build-Own-Operate (BOO): In this case, the private sector finances, builds, owns and operates a facility or service in perpetuity. The public constraints are stated in the original agreement and through on-going regulatory obligations. Build-Own-Operate & Transfer (BOOT): The Private Sector builds, owns, operates a facility for a specified period as agreed in the contract and then transfers to the Public. Operating License: A private operator receives a license or rights to build and operate a public service, usually for a specified term. This is similar to BBO arrangement and is often used in telecommunications and ICT projects. Finance Only: A private entity, usually a financial services company, funds a project directly or uses various mechanisms such as a long-term lease or bond issue.
  • 10. Advantages. The Public sector gains the advantages the private sector offers such as: ability to design, construct, manage and finance a project. Public money is better used and at difficult economic periods for a government, this method is good. They promote and help the innovation in the public sectors with the transfer of knowledge and new techniques. Better quality infrastructure and better operation throughout the life of the project (maintenance of the project by the private sector) is assured. There is more efficient and more economical maintenance of the project. Reduction of the construction cost and maintenance of the project. Use of private sector in areas where there are ‘weaknesses’ in the public sector such as: lack of expertise and qualified employees, no ability to promote new technoeconomical solutions, lack of efficient and effective use of human resources, lack of sensitivity and knowledge and expertise in the use of available energy sources. Disadvantanges. The use of the project by the private sector is difficult for low income people. However, it has the advantage that only the users pay and not the tax payer. In some cases, there may be in the contract some clauses or provisions which do not favour the public interest but aim at increasing the profit of the private investor, allow monopoly or even allow the private sector to increase the price of a service or a product after completion of the project. Since much of funding the project is done by the private investor, there is every tendency to aim at reducing the cost of a project which might lead to the use of substandard materials and works Generally, the public sector can get cheaper loans than the private sector.
  • 11. Analysis. The system has been applauded as important tool for improving economic effectiveness, and a mechanism to fill infrastructure deficit (Shwarka and Anigbogu 2012). The system equally lends itself to the intervention of private entity whose sole aim in development participation is more profit oriented than of social growth, for this reason, it is necessary that government should balance its profit motive with social growth. This can be achieved through government monitoring and imposition of compliance with performance standards as a pre-requisite in development participation. Conclusion. There is not just one method of procuring a building. The different methods that are available provide a wide range of options for any promoter to realize his dream. The choice of any method is dependent on the prime concerns of the client, (which are cost, time and quality) and the type of project. Whatever choice of option that is made, must not fail in any of these factors; hence, the client needs guidance and direction so that he has cause to smile when his dream has been actualized. The majority of clients are ignorant and quickly embrace the traditional method as the only procurement option. The quick recourse to this option is due to its simplicity, age and familiarity with the process. The result is that the wrong option is applied to wrong projects, which may lead to problems ranging from waste of resources to dissatisfaction with the final product. The need for professional advice is, therefore necessary to help the clients make the right choice.
  • 12. References. Naggy, E. Kiss, L. and Hornyak, S. (n.d). Different procurement methods. www.byggai.se/mats/cm1/procurementmethods.pptx Obozuwa, D. (2011). PPP as a tool for infrastructure development in Nigeria (1). www.businessdayonline.com/NG/index.php/law/cover/28768. Shwarka, S and Anigbogu, (2012). The impact of public procurement options on building projects 42nd National Building performance in Nigeria. A paper presented at the conference/General Meeting of the Nigerian Institute of