SlideShare a Scribd company logo
1 of 49
Download to read offline
1
Hinkley Point C - Industrial Collaboration
UK PROTECT COMMERCIAL
Hinkley
Point C
30 Years of Experience
Core Values
1. Integrity
2. Customer Satisfaction
3. Employee Engagement
4. Innovation
5. Sustainability
Automotive
BAA Terminal 5 Wembley Stadium
London 2012 Metronet Tubelines
10 Years pre HPC
5
Olympic Park, Assets
8 Olympic Park Sporting Venues
1 Broadcast / Media Centre (93,000 sq m) & Multi
Storey Car Park
26 bridges and 7 underpasses
12km of roads
2 million m3 of earthworks
Energy Centre
13km of tunnels
New utilities infrastructure and
32kv & 11kv utility diversions
79 hectares of Landscape
& Public Realm
21 PSAs and VSAs
Making NEC3 Work
Key Ingredients of Success
• Early Warning
• Change Management (Compensation Event
Notices)
• Accepted Programme
Key Enablers
• People
• Training
• Clear & Simple Processes
• Organisational Model
Some of the Dynamics
Volume of Change and Risk
13,501 EWNs
6,362 CENs
24,723 CI/CEs
750 Tier 2 Accounts
90 Assurance Reviews
120 Contracts
96 Tier 1’s 1
17,648 RFIs
14,321 EWNs
7,394 CENs
26,665 CI/CE’s
850 Tier 2 Accounts
123 Assurance Reviews
( Data correct as of 23rd March 2012)
NEC and Commercial Close Out
Well defined close out process
embedded
• ODA/CLM > Tier 1 > Tier 2
• Rigorous 3rd Party Assurance
adopted
• Commenced early 2010
The contract (NEC 3) has ‘enabled’
risk reduction and facilitated early
close out
Clients ‘Risk Profile’ has
dramatically reduced
69% complete by value
17 weeks before Games
(NEC Olympic Park Contracts)
Olympic Park
Delivery Strategy & Organisational Framework
1. NEC3 Contract Management:
Real Time
2. Supplier Management
• Tier 2 value for money
• Incentivisation
• Final account strategy
• Insolvency risk
3. Integration management
4. Contingency and risk management
5. Performance and control
(cost, time)
Contract
Management
Framework
Delivery
Management
FrameworkOlympicIntegratedView
Traditional
View
Risk
Management
Framework
Performance
Management
Framework
(Project Controls)
Delivering Major Programmes
(25 yrs Reflection)
Business Driver
Observations and Key
Learnings
Power station outages at
Nuclear Electric
Automotive Vehicle Systems
at Johnson Controls
Airport Infrastructure at
BAA
Underground Upgrade at
Metronet
London 2012 Olympics
(CLM Delivery Partner)
Lost Revenue
Time to Market
Capital Efficiency
27th July 2012 &
Affordability
Scope, Organisation,
Supply Chain
Process Discipline,
Operational Readiness
vs.
Supply Chain
Relationships
Commercial
Rigour
Integration
Management & NEC3
Private Investment
Scope, Change Control,
Common Alignment
NOT PROTECTIVELY MARKED12
Government Policy: Two National Concerns
0
10
20
30
40
50
60
70
80
90
2012/13
2013/14
2014/15
2015/16
2016/17
2017/18
2018/19
2019/20
2020/21
2021/22
2022/23
2023/24
2024/25
2025/26
2026/27
2027/28
2028/29
2029/30
GW
Existing and under construction generation
and contracted plant in Great Britain
2013-2030
Peak
Peak
Demand
80%
C02REDUCTION
BY 2050
Climate Change Act,
2008
Title of Presentation, Existing Nuclear NOT PROTECTIVELY MARKED/ RESTRICTED/CONFIDENTIAL (delete as
appropriate) BEG/FORM/COMM/026A
14
MEH Strategy ©April 2018 EDF Energy plc. All rights
Reserved.
1
5
Nuclear Fission
Nuclear Reactor (Simplified)
Primary Circuit (pressurised water)
Secondary Circuit (feed water)
Secondary Circuit (steam)
Cooling Water Circuit
Steam
Generator
Main Feed
Pump
Reactor
Coolant
Pump
Reactor Vessel
Pressuriser
Condensers
Cooling
Water
Pump
Generator
Turbine
Human & Industrial Adventure
18
1
9
Hinkley Point C
more than a Power
Station!!
HPC Emerging Complex Supply Chain
International, National & Local partners working
together to deliver Hinkley Point C
6Consortia
+£465m
Contract Value
+660 Jobs
Doing Business Differently
Local Supply Chain
22
Priorities – next 12 Months
23
Importance of Real Time Contract Management:
General Communications
Contract Communications 122,841
Formal Response Required 46,361
CE’s / Variations / Claims
Raised
6,267
Early Warnings Raised 12,054
Technical Queries Raised 4,036
Accepted Programmes 81 - Aligned to all key
contracts
1,933
2,283
2,321
1,942
2,166
2,722
2,385
2,451
1,468
2,307
2,897
3,792
55%
59%
71%
64% 65%
67%
59%
64%
68%
72% 73%
64%
0%
10%
20%
30%
40%
50%
60%
70%
80%
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
Oct-
17
Nov-
17
Dec-
17
Jan-
18
Feb-
18
Mar-
18
Apr-
18
May-
18
Jun-
18
Jul-18 Aug-
18
Sep-
18
Communications Dealt with On Time
Volume of Communications
% Dealt with On Time
Contract Management (Key CEMAR Metrics)
24
Real Time Effective Contract Management: Overall Architecture
Accepted Programme
Contract
Deliverables
Risk
Management
Variations Payments
Target
Achievements
Contract AdministrationProcurement
Tendering
Selection
and
Award
Handover
and
Initiation
Contract
Manage-
ment
Contract
Close-Out
C o n t r a c t L i f e c y c l e
Challenge 1: No E2E Commercial Approach
Challenge 2: Money and ‘Claims’
25
The Contract Structure
Contract
Mechanisms
Key
Commercial
Terms +
Conditions
Constraints for
obligations
specific to EDF
nuclear site
license
Supporting
appendices
(works
information)
• Obligations of the parties
•Approach to risk management
•Issue resolution
•Price of the works (inc adjustments)
•Payments
•Protection of EDF commercial position
•Liability constraints
•Defect + handover management
•Key dates
•IP
•Unique requirement applicable to
•Technical requirements
•Performance specification
•Detail Project/contract workings + processes
•Constraints
•Project Requirements
Output
Definition of the
works to
Be performed +
Project
And site
requirements
Mechanisms for
Compensation
a) For the works
b) Variations
c) Default
Compliance with
ONR requirements
Expectations of
How the parties will
Deliver/manage the
works
behaviour
Corporate
B2BChallenge 3: Understanding of what a ‘Contract’ Actually is?
September 2016 © NNB Generation(HPC)Ltd - Not Protectively Marked26
Risk Management (Supplier Engagement)
Transactional
• well defined brief
•Design + build
•Simple asset-functionality of asset
performance does not greatly impact the client business
• Controllable site constraints
•Known risks – management solutions involve single party
•Minimal likelihood of change
•Single supplier environment and manageable interfaces
Collaborative
• Complex asset – clients future business
heavily dependent on asset performance
•Complex interfaces (both design + delivery)
•Unknown/unquantifiable risks
Management solutions involve many parties
• Integrated supply chain – multi hand over
hand back arrangements
•Employers design (first of kind)
•Complex supply chain – factory to site
•Multi site constraints – logistics
•IR has potential to ‘impact’ productivity
The contract establishes the architecture + behaviour of the parties
Restructured NEC/ FIDIC Contract Templates
WI
100
Core
Conditions
Guidance for
compiler.
Minimum WI
needs
identified
Core
Conditions
Appendices
(Employer’s
Requirements)
Guidance for
compiler.
Minimum
information
needs identified
WI
200
W I
etc.
App 1
App 2
App etc
FIDICNEC
Owner 1
Owner 2
Owner etc.
WI
following
NEC
Guidance
Note (Jan
2012)
WI 100
WI 2000
Appendices and
Employer
requirements
App 1
App 37
T’s & C’s
DMIC
T’s & C’s
DMS
T’s & C’s
Call Off
(DMIC, DM
“Clean”
T’s & C’s
Z Clauses
applicable to
all Contracts
Z Clauses
applicable to
each NEC
main Option
Z Clauses
project /
special
Document “spine”
EDF Standard
documentation
27
Z Clauses
selection
Works
Information
Guidance for
compiler.
Minimum WI
needs
identified
WI
100
WI
following
NEC
Guidance
Note (Jan
2012)
WI 100
WI 2000
Appendices and
Employer
requirements
App 1
App 16
Z Clauses
applicable
to each NEC
main
Option
Z Clauses
project /
special
Challenge 4: Different applications required different approaches!
28
Priorities – next 12 Months
NOT PROTECTIVELY MARKED2929
Supply Chain Engagement
• Poor quality: plant & delivery
• Lack of supplier alignment with the overall Project’s schedule + critical path
• Late handover (missed key dates)
• Cost increase
• Claims beyond scope additions + the employer’s unavoidable risks
• Safety incident
What risks are we trying to mitigate?
• Ultimate Risk ‘always’ resides with the client.
• Appropriate level of design completeness is
fundamental.
• Risk transfer is a myth.
• ‘Procurement’ represents the start of the Journey
…it does not guarantee the outcome!!
• Not a ‘one size fits all’.
• The ‘contract’ is the key link between client &
supply chain.
30
HPC Supply Chain & Contract Strategy
“The six Golden Rules”
31
1. In the first Instance the Contract should drive performance, and NOT be
used to protect EDF Energy in the event of Default
Doing Business Differently – The Contract & Supply Chain!
2. Management of the Contract should ALWAYS ensure the commercial interest of the parties
remain aligned, in order to avoid adverse impact on delivery
Contract Administration
Manual (‘Blue Book’)
Equipment Contract
Administration Manual (‘Red
Book’)
Manufacturing and Delivery
Management Manual
(‘Green Book’)
Contract Management Manuals:
Rigorous Contract Management
Balancing “Commercial Tension” & “Collaboration”
Launch of NEC Contract Management approach – ‘The HPC Way’
• Create a common Purpose and understand of
how the contract will be administered and the
key behavioural requirements.
• Inspire a level of collaboration and
togetherness not experienced before on a
project of this scale
• Invitees: 320 staff involved in HPC in the
management of the Key NEC contracts
• x17 Exhibition stands created to articulate key
learning and aspects of NEC and HPC :
• Accepted Programme
• Early Warnings
• Deliverables
• Subcontracting
• Compensation Events
• Equipment Supply
• CEMAR
• Project Controls
• Nuclear Site Licence & Intelligent Customer
• Collaborative Framework & Behaviours
• Apprenticeships & Assessment Centres
Key Enablers –
Technical & Procedural, plus Behavioural & Talent development
Contract Administration –
#17 Exhibition Stands
Launch of NEC Contract Management approach – ‘The HPC Way’
Launch of NEC Contract Management approach – ‘The HPC Way’
Launch of NEC Contract Management approach – ‘The HPC Way’
September 2016 © NNB Generation(HPC)Ltd - Not Protectively Marked39
Contract
Administration
Manual (‘Blue
Book’)
Equipment
Contract
Administration
Manual (‘Red
Book’)
Manufacturing and
Delivery
Management
Manual (‘Green
Book’)
Supply Chain Alignment: Ensure consistent and Common
understanding of Requirements
NEC Launch – 29 Nov 2017 (Bristol)
FIDIC/Equipment launch – Planned 22 Nov 2018
(Paris)
INTRODUCTION
3words to describe
the HPC event in Paris
3words to describe
the HPC event in Bristol
The world of Manufacturing The world of Construction
97% Material & Workshops Beneficial
98% Felt Inspired
100% Event good use of their Time
95% Material & Workshops Beneficial
98% Felt Inspired
95% Event good use of their Time
Title | BUSINESS UNITS (SNI) | PROTECT – LEGALLY PRIVILEGED | PROTECT – PROPRIETARY | PROTECT – COMMERCIAL & CONTRACTS | PROTECT –
PRIVATE | NOT PROTECTIVELY MARKED | ©1 Jan 2017 EDF Energy plc. All rights Reserved.
42
43
“Commercial Tension” & “Collaboration”
Rigorous Contract Management
‘…Change Control…’
Collaborative Working is all about….
RELATIONSHIPS
Relationships are all about ….
BEHAVIOURS
Critical Behavior in any Relationship Is…
TRUST
……Fairness…..
COLLABORATIVE
WORKING IS ABOUT
RELATIONSHIPS
ARE ALL ABOUT
THE CRITICAL
BEHAVIOUR IN ANY
RELATIONSHIP IS
RELATIONSHIPS BEHAVIOURS TRUST
MEH Erection Challenge!
45
BoQ’s & Equipment List (illustrative only)
380km of pipework, 20,000 valves, 200 pumps, 42 heat exchanges, 86 Filters, 120 Tanks, 6,325km of main power and I & C Cables , 404km
of Cable Containment, 51,700 Supports, 218 LV Switchboards, 136 Transformers, 43 HV Switchboards, 3,000km of small power Cables ,
47,000 Lighting units
MEH Alliance is Unique in ‘UK Industry’
46
(BoP, HVAC* Mech) (BNI Mech) (Electrical) (Services)
‘Joint & Several ‘for Deliver of Site Erection works; Unified by a Single Commercial Model
‘.. A £2bn Alliance within an overall Integrated £19bn
‘Mega Project’….’
Q. What do you See?
A. Different Way at
Looking at YOUR Career?
Mastering Your Career: 4 + 1 traits
1. Technical
your chosen field
2. Behavioural skills
influence, team work, co-operation
3. Business acumen
judgement, trade-offs etc
4. Ambiguity
coping with uncertainty
+1 Passion and Enthusiasm – no matter what!
49
“Commercial Tension” & “Collaboration”
Rigorous Contract Management
Collaborative Working is all about….
RELATIONSHIPS
Relationships are all about ….
BEHAVIOURS
Critical Behavior in any Relationship Is…
TRUST
……Fairness…..

More Related Content

What's hot

Swiss re building london
Swiss re building londonSwiss re building london
Swiss re building london
Ada Darmon
 
دليل تخطيط الاسواق الشعبية.pdf
دليل تخطيط الاسواق الشعبية.pdfدليل تخطيط الاسواق الشعبية.pdf
دليل تخطيط الاسواق الشعبية.pdf
HUSAM63
 
Sustainability in Architecture and Urban Design_Irena
Sustainability in Architecture and Urban Design_IrenaSustainability in Architecture and Urban Design_Irena
Sustainability in Architecture and Urban Design_Irena
Irena Itova
 

What's hot (20)

Greek Art in Munich at Glyptothek
Greek Art in Munich at GlyptothekGreek Art in Munich at Glyptothek
Greek Art in Munich at Glyptothek
 
Opus by Omniyat, UAE-lighting servecs report.pptx
Opus by Omniyat, UAE-lighting servecs report.pptxOpus by Omniyat, UAE-lighting servecs report.pptx
Opus by Omniyat, UAE-lighting servecs report.pptx
 
Koshino house by Tadao Ando
Koshino house by Tadao AndoKoshino house by Tadao Ando
Koshino house by Tadao Ando
 
Princess Tower Brochure English
Princess Tower Brochure EnglishPrincess Tower Brochure English
Princess Tower Brochure English
 
HE ART MUSEUM (2).pptx
HE ART MUSEUM (2).pptxHE ART MUSEUM (2).pptx
HE ART MUSEUM (2).pptx
 
Swiss re building london
Swiss re building londonSwiss re building london
Swiss re building london
 
دليل تخطيط الاسواق الشعبية.pdf
دليل تخطيط الاسواق الشعبية.pdfدليل تخطيط الاسواق الشعبية.pdf
دليل تخطيط الاسواق الشعبية.pdf
 
Sustainability in Architecture and Urban Design_Irena
Sustainability in Architecture and Urban Design_IrenaSustainability in Architecture and Urban Design_Irena
Sustainability in Architecture and Urban Design_Irena
 
FCSarch 36 Le Corbusier
FCSarch 36 Le Corbusier FCSarch 36 Le Corbusier
FCSarch 36 Le Corbusier
 
Bruj khalifa
Bruj khalifaBruj khalifa
Bruj khalifa
 
L'histoire de l'auto
L'histoire de l'autoL'histoire de l'auto
L'histoire de l'auto
 
Beirut Terraces
Beirut TerracesBeirut Terraces
Beirut Terraces
 
Shanghai World Financial Center
Shanghai World Financial CenterShanghai World Financial Center
Shanghai World Financial Center
 
c2329- Lecture3
c2329- Lecture3c2329- Lecture3
c2329- Lecture3
 
Supernova noida
Supernova   noidaSupernova   noida
Supernova noida
 
Presentation on burj khalifa
Presentation on burj khalifaPresentation on burj khalifa
Presentation on burj khalifa
 
CATV Headend (Basic)
CATV Headend (Basic)CATV Headend (Basic)
CATV Headend (Basic)
 
Centre of pompidou
Centre of pompidouCentre of pompidou
Centre of pompidou
 
Cayan tower,dubai
Cayan tower,dubaiCayan tower,dubai
Cayan tower,dubai
 
Intelligent Building (Dayabumi Complex)
Intelligent Building (Dayabumi Complex)Intelligent Building (Dayabumi Complex)
Intelligent Building (Dayabumi Complex)
 

Similar to APM Hinkley Point C - how to build a power station, Ken Owen, presentation

Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012
Eversheds Sutherland
 
Excellence in the New Era for Construction
Excellence in the New Era for ConstructionExcellence in the New Era for Construction
Excellence in the New Era for Construction
Clarkson Alliance
 
July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)
Richard Morwood
 
White Paper_RIBER_Kunal
White Paper_RIBER_KunalWhite Paper_RIBER_Kunal
White Paper_RIBER_Kunal
kunalparekh27
 
Trc investor presentation 05 13 final
Trc investor presentation 05 13 finalTrc investor presentation 05 13 final
Trc investor presentation 05 13 final
trcsolutions
 

Similar to APM Hinkley Point C - how to build a power station, Ken Owen, presentation (20)

Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
Kic InnoEnergy: Strategy, Maghrenov kickoff Barcelona - Day 2
 
Implementing Business Continuity in Crossrail: Europe's Largest Construction ...
Implementing Business Continuity in Crossrail: Europe's Largest Construction ...Implementing Business Continuity in Crossrail: Europe's Largest Construction ...
Implementing Business Continuity in Crossrail: Europe's Largest Construction ...
 
Excellence in the New Era for Construction
Excellence in the New Era for ConstructionExcellence in the New Era for Construction
Excellence in the New Era for Construction
 
MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptx
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015
 
Managing Third Party & Counterparty Relationship Risks
Managing Third Party & Counterparty Relationship RisksManaging Third Party & Counterparty Relationship Risks
Managing Third Party & Counterparty Relationship Risks
 
July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)
 
Toward Energy Management 4.0 – Delivering An Enterprise-wide Energy Managemen...
Toward Energy Management 4.0 – Delivering An Enterprise-wide Energy Managemen...Toward Energy Management 4.0 – Delivering An Enterprise-wide Energy Managemen...
Toward Energy Management 4.0 – Delivering An Enterprise-wide Energy Managemen...
 
Successful change - good culture and governance matter Conference - Boris Luc...
Successful change - good culture and governance matter Conference - Boris Luc...Successful change - good culture and governance matter Conference - Boris Luc...
Successful change - good culture and governance matter Conference - Boris Luc...
 
The Advent of International Construction Measurement Standards and their Cont...
The Advent of International Construction Measurement Standards and their Cont...The Advent of International Construction Measurement Standards and their Cont...
The Advent of International Construction Measurement Standards and their Cont...
 
The Battery Storage Revolution
The Battery Storage RevolutionThe Battery Storage Revolution
The Battery Storage Revolution
 
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
 
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
 
White Paper_RIBER_Kunal
White Paper_RIBER_KunalWhite Paper_RIBER_Kunal
White Paper_RIBER_Kunal
 
Trc investor presentation 05 13 final
Trc investor presentation 05 13 finalTrc investor presentation 05 13 final
Trc investor presentation 05 13 final
 
Laying the foundations for a financially sound industry - OECD.pdf
Laying the foundations for a financially sound industry - OECD.pdfLaying the foundations for a financially sound industry - OECD.pdf
Laying the foundations for a financially sound industry - OECD.pdf
 
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
 

More from Association for Project Management

Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 

More from Association for Project Management (20)

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 

Recently uploaded

Recently uploaded (20)

Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
 
VAMOS CUIDAR DO NOSSO PLANETA! .
VAMOS CUIDAR DO NOSSO PLANETA!                    .VAMOS CUIDAR DO NOSSO PLANETA!                    .
VAMOS CUIDAR DO NOSSO PLANETA! .
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategies
 
The Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFThe Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDF
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopal
 
ANTI PARKISON DRUGS.pptx
ANTI         PARKISON          DRUGS.pptxANTI         PARKISON          DRUGS.pptx
ANTI PARKISON DRUGS.pptx
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptx
 
An overview of the various scriptures in Hinduism
An overview of the various scriptures in HinduismAn overview of the various scriptures in Hinduism
An overview of the various scriptures in Hinduism
 
Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"
 
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
 
Climbers and Creepers used in landscaping
Climbers and Creepers used in landscapingClimbers and Creepers used in landscaping
Climbers and Creepers used in landscaping
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
An Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge AppAn Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge App
 
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
 
BỘ LUYỆN NGHE TIẾNG ANH 8 GLOBAL SUCCESS CẢ NĂM (GỒM 12 UNITS, MỖI UNIT GỒM 3...
BỘ LUYỆN NGHE TIẾNG ANH 8 GLOBAL SUCCESS CẢ NĂM (GỒM 12 UNITS, MỖI UNIT GỒM 3...BỘ LUYỆN NGHE TIẾNG ANH 8 GLOBAL SUCCESS CẢ NĂM (GỒM 12 UNITS, MỖI UNIT GỒM 3...
BỘ LUYỆN NGHE TIẾNG ANH 8 GLOBAL SUCCESS CẢ NĂM (GỒM 12 UNITS, MỖI UNIT GỒM 3...
 
MOOD STABLIZERS DRUGS.pptx
MOOD     STABLIZERS           DRUGS.pptxMOOD     STABLIZERS           DRUGS.pptx
MOOD STABLIZERS DRUGS.pptx
 

APM Hinkley Point C - how to build a power station, Ken Owen, presentation

  • 1. 1 Hinkley Point C - Industrial Collaboration UK PROTECT COMMERCIAL Hinkley Point C
  • 2. 30 Years of Experience
  • 3. Core Values 1. Integrity 2. Customer Satisfaction 3. Employee Engagement 4. Innovation 5. Sustainability Automotive
  • 4. BAA Terminal 5 Wembley Stadium London 2012 Metronet Tubelines 10 Years pre HPC
  • 5. 5 Olympic Park, Assets 8 Olympic Park Sporting Venues 1 Broadcast / Media Centre (93,000 sq m) & Multi Storey Car Park 26 bridges and 7 underpasses 12km of roads 2 million m3 of earthworks Energy Centre 13km of tunnels New utilities infrastructure and 32kv & 11kv utility diversions 79 hectares of Landscape & Public Realm 21 PSAs and VSAs
  • 6.
  • 7. Making NEC3 Work Key Ingredients of Success • Early Warning • Change Management (Compensation Event Notices) • Accepted Programme Key Enablers • People • Training • Clear & Simple Processes • Organisational Model
  • 8. Some of the Dynamics Volume of Change and Risk 13,501 EWNs 6,362 CENs 24,723 CI/CEs 750 Tier 2 Accounts 90 Assurance Reviews 120 Contracts 96 Tier 1’s 1 17,648 RFIs 14,321 EWNs 7,394 CENs 26,665 CI/CE’s 850 Tier 2 Accounts 123 Assurance Reviews ( Data correct as of 23rd March 2012)
  • 9. NEC and Commercial Close Out Well defined close out process embedded • ODA/CLM > Tier 1 > Tier 2 • Rigorous 3rd Party Assurance adopted • Commenced early 2010 The contract (NEC 3) has ‘enabled’ risk reduction and facilitated early close out Clients ‘Risk Profile’ has dramatically reduced 69% complete by value 17 weeks before Games (NEC Olympic Park Contracts)
  • 10. Olympic Park Delivery Strategy & Organisational Framework 1. NEC3 Contract Management: Real Time 2. Supplier Management • Tier 2 value for money • Incentivisation • Final account strategy • Insolvency risk 3. Integration management 4. Contingency and risk management 5. Performance and control (cost, time) Contract Management Framework Delivery Management FrameworkOlympicIntegratedView Traditional View Risk Management Framework Performance Management Framework (Project Controls)
  • 11. Delivering Major Programmes (25 yrs Reflection) Business Driver Observations and Key Learnings Power station outages at Nuclear Electric Automotive Vehicle Systems at Johnson Controls Airport Infrastructure at BAA Underground Upgrade at Metronet London 2012 Olympics (CLM Delivery Partner) Lost Revenue Time to Market Capital Efficiency 27th July 2012 & Affordability Scope, Organisation, Supply Chain Process Discipline, Operational Readiness vs. Supply Chain Relationships Commercial Rigour Integration Management & NEC3 Private Investment Scope, Change Control, Common Alignment
  • 13. Government Policy: Two National Concerns 0 10 20 30 40 50 60 70 80 90 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 GW Existing and under construction generation and contracted plant in Great Britain 2013-2030 Peak Peak Demand 80% C02REDUCTION BY 2050 Climate Change Act, 2008
  • 14. Title of Presentation, Existing Nuclear NOT PROTECTIVELY MARKED/ RESTRICTED/CONFIDENTIAL (delete as appropriate) BEG/FORM/COMM/026A 14
  • 15. MEH Strategy ©April 2018 EDF Energy plc. All rights Reserved. 1 5 Nuclear Fission
  • 16. Nuclear Reactor (Simplified) Primary Circuit (pressurised water) Secondary Circuit (feed water) Secondary Circuit (steam) Cooling Water Circuit Steam Generator Main Feed Pump Reactor Coolant Pump Reactor Vessel Pressuriser Condensers Cooling Water Pump Generator Turbine
  • 17. Human & Industrial Adventure
  • 18. 18
  • 19. 1 9 Hinkley Point C more than a Power Station!!
  • 20. HPC Emerging Complex Supply Chain International, National & Local partners working together to deliver Hinkley Point C
  • 21. 6Consortia +£465m Contract Value +660 Jobs Doing Business Differently Local Supply Chain
  • 23. 23 Importance of Real Time Contract Management: General Communications Contract Communications 122,841 Formal Response Required 46,361 CE’s / Variations / Claims Raised 6,267 Early Warnings Raised 12,054 Technical Queries Raised 4,036 Accepted Programmes 81 - Aligned to all key contracts 1,933 2,283 2,321 1,942 2,166 2,722 2,385 2,451 1,468 2,307 2,897 3,792 55% 59% 71% 64% 65% 67% 59% 64% 68% 72% 73% 64% 0% 10% 20% 30% 40% 50% 60% 70% 80% 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 Oct- 17 Nov- 17 Dec- 17 Jan- 18 Feb- 18 Mar- 18 Apr- 18 May- 18 Jun- 18 Jul-18 Aug- 18 Sep- 18 Communications Dealt with On Time Volume of Communications % Dealt with On Time Contract Management (Key CEMAR Metrics)
  • 24. 24 Real Time Effective Contract Management: Overall Architecture Accepted Programme Contract Deliverables Risk Management Variations Payments Target Achievements Contract AdministrationProcurement Tendering Selection and Award Handover and Initiation Contract Manage- ment Contract Close-Out C o n t r a c t L i f e c y c l e Challenge 1: No E2E Commercial Approach Challenge 2: Money and ‘Claims’
  • 25. 25 The Contract Structure Contract Mechanisms Key Commercial Terms + Conditions Constraints for obligations specific to EDF nuclear site license Supporting appendices (works information) • Obligations of the parties •Approach to risk management •Issue resolution •Price of the works (inc adjustments) •Payments •Protection of EDF commercial position •Liability constraints •Defect + handover management •Key dates •IP •Unique requirement applicable to •Technical requirements •Performance specification •Detail Project/contract workings + processes •Constraints •Project Requirements Output Definition of the works to Be performed + Project And site requirements Mechanisms for Compensation a) For the works b) Variations c) Default Compliance with ONR requirements Expectations of How the parties will Deliver/manage the works behaviour Corporate B2BChallenge 3: Understanding of what a ‘Contract’ Actually is?
  • 26. September 2016 © NNB Generation(HPC)Ltd - Not Protectively Marked26 Risk Management (Supplier Engagement) Transactional • well defined brief •Design + build •Simple asset-functionality of asset performance does not greatly impact the client business • Controllable site constraints •Known risks – management solutions involve single party •Minimal likelihood of change •Single supplier environment and manageable interfaces Collaborative • Complex asset – clients future business heavily dependent on asset performance •Complex interfaces (both design + delivery) •Unknown/unquantifiable risks Management solutions involve many parties • Integrated supply chain – multi hand over hand back arrangements •Employers design (first of kind) •Complex supply chain – factory to site •Multi site constraints – logistics •IR has potential to ‘impact’ productivity The contract establishes the architecture + behaviour of the parties
  • 27. Restructured NEC/ FIDIC Contract Templates WI 100 Core Conditions Guidance for compiler. Minimum WI needs identified Core Conditions Appendices (Employer’s Requirements) Guidance for compiler. Minimum information needs identified WI 200 W I etc. App 1 App 2 App etc FIDICNEC Owner 1 Owner 2 Owner etc. WI following NEC Guidance Note (Jan 2012) WI 100 WI 2000 Appendices and Employer requirements App 1 App 37 T’s & C’s DMIC T’s & C’s DMS T’s & C’s Call Off (DMIC, DM “Clean” T’s & C’s Z Clauses applicable to all Contracts Z Clauses applicable to each NEC main Option Z Clauses project / special Document “spine” EDF Standard documentation 27 Z Clauses selection Works Information Guidance for compiler. Minimum WI needs identified WI 100 WI following NEC Guidance Note (Jan 2012) WI 100 WI 2000 Appendices and Employer requirements App 1 App 16 Z Clauses applicable to each NEC main Option Z Clauses project / special Challenge 4: Different applications required different approaches!
  • 29. NOT PROTECTIVELY MARKED2929 Supply Chain Engagement • Poor quality: plant & delivery • Lack of supplier alignment with the overall Project’s schedule + critical path • Late handover (missed key dates) • Cost increase • Claims beyond scope additions + the employer’s unavoidable risks • Safety incident What risks are we trying to mitigate?
  • 30. • Ultimate Risk ‘always’ resides with the client. • Appropriate level of design completeness is fundamental. • Risk transfer is a myth. • ‘Procurement’ represents the start of the Journey …it does not guarantee the outcome!! • Not a ‘one size fits all’. • The ‘contract’ is the key link between client & supply chain. 30 HPC Supply Chain & Contract Strategy “The six Golden Rules”
  • 31. 31 1. In the first Instance the Contract should drive performance, and NOT be used to protect EDF Energy in the event of Default Doing Business Differently – The Contract & Supply Chain! 2. Management of the Contract should ALWAYS ensure the commercial interest of the parties remain aligned, in order to avoid adverse impact on delivery
  • 32. Contract Administration Manual (‘Blue Book’) Equipment Contract Administration Manual (‘Red Book’) Manufacturing and Delivery Management Manual (‘Green Book’) Contract Management Manuals:
  • 33. Rigorous Contract Management Balancing “Commercial Tension” & “Collaboration”
  • 34. Launch of NEC Contract Management approach – ‘The HPC Way’ • Create a common Purpose and understand of how the contract will be administered and the key behavioural requirements. • Inspire a level of collaboration and togetherness not experienced before on a project of this scale • Invitees: 320 staff involved in HPC in the management of the Key NEC contracts • x17 Exhibition stands created to articulate key learning and aspects of NEC and HPC : • Accepted Programme • Early Warnings • Deliverables • Subcontracting • Compensation Events • Equipment Supply • CEMAR • Project Controls • Nuclear Site Licence & Intelligent Customer • Collaborative Framework & Behaviours • Apprenticeships & Assessment Centres
  • 35. Key Enablers – Technical & Procedural, plus Behavioural & Talent development Contract Administration – #17 Exhibition Stands
  • 36. Launch of NEC Contract Management approach – ‘The HPC Way’
  • 37. Launch of NEC Contract Management approach – ‘The HPC Way’
  • 38. Launch of NEC Contract Management approach – ‘The HPC Way’
  • 39. September 2016 © NNB Generation(HPC)Ltd - Not Protectively Marked39
  • 40. Contract Administration Manual (‘Blue Book’) Equipment Contract Administration Manual (‘Red Book’) Manufacturing and Delivery Management Manual (‘Green Book’) Supply Chain Alignment: Ensure consistent and Common understanding of Requirements NEC Launch – 29 Nov 2017 (Bristol) FIDIC/Equipment launch – Planned 22 Nov 2018 (Paris)
  • 41. INTRODUCTION 3words to describe the HPC event in Paris 3words to describe the HPC event in Bristol The world of Manufacturing The world of Construction 97% Material & Workshops Beneficial 98% Felt Inspired 100% Event good use of their Time 95% Material & Workshops Beneficial 98% Felt Inspired 95% Event good use of their Time
  • 42. Title | BUSINESS UNITS (SNI) | PROTECT – LEGALLY PRIVILEGED | PROTECT – PROPRIETARY | PROTECT – COMMERCIAL & CONTRACTS | PROTECT – PRIVATE | NOT PROTECTIVELY MARKED | ©1 Jan 2017 EDF Energy plc. All rights Reserved. 42
  • 43. 43 “Commercial Tension” & “Collaboration” Rigorous Contract Management ‘…Change Control…’ Collaborative Working is all about…. RELATIONSHIPS Relationships are all about …. BEHAVIOURS Critical Behavior in any Relationship Is… TRUST ……Fairness…..
  • 44. COLLABORATIVE WORKING IS ABOUT RELATIONSHIPS ARE ALL ABOUT THE CRITICAL BEHAVIOUR IN ANY RELATIONSHIP IS RELATIONSHIPS BEHAVIOURS TRUST
  • 45. MEH Erection Challenge! 45 BoQ’s & Equipment List (illustrative only) 380km of pipework, 20,000 valves, 200 pumps, 42 heat exchanges, 86 Filters, 120 Tanks, 6,325km of main power and I & C Cables , 404km of Cable Containment, 51,700 Supports, 218 LV Switchboards, 136 Transformers, 43 HV Switchboards, 3,000km of small power Cables , 47,000 Lighting units
  • 46. MEH Alliance is Unique in ‘UK Industry’ 46 (BoP, HVAC* Mech) (BNI Mech) (Electrical) (Services) ‘Joint & Several ‘for Deliver of Site Erection works; Unified by a Single Commercial Model ‘.. A £2bn Alliance within an overall Integrated £19bn ‘Mega Project’….’
  • 47. Q. What do you See? A. Different Way at Looking at YOUR Career?
  • 48. Mastering Your Career: 4 + 1 traits 1. Technical your chosen field 2. Behavioural skills influence, team work, co-operation 3. Business acumen judgement, trade-offs etc 4. Ambiguity coping with uncertainty +1 Passion and Enthusiasm – no matter what!
  • 49. 49 “Commercial Tension” & “Collaboration” Rigorous Contract Management Collaborative Working is all about…. RELATIONSHIPS Relationships are all about …. BEHAVIOURS Critical Behavior in any Relationship Is… TRUST ……Fairness…..