SlideShare a Scribd company logo
1 of 32
/06.02.12 1
Keeping collaborative delivery
arrangements in focus and on course
…a case of LBSR
Boris Lucic EMBA CEng MICE RPP
Programme Engineering Manager
London Bridge Station Redevelopment
/06.02.12 2
“The reality is that true collaboration
is difficult. It requires subordinating
individual goals to collective
achievement.”
Have you ever been
accused of not being
collaborative?
/6-Oct-16 3
This story is based on true events…
Strategy
Development
Strategy
Execution
Project
Review and
Interventions
Where we are
today
/06.02.12
Thameslink - achievements and challenges
4
 Transformational Change
 Scale
 Complexity
 People
 Communication
London Bridge Station
/06.02.12
Thameslink - achievements and challenges
5
 Super critical milestones
 Operational requirements take
precedent
 Cumulative complexity
 Constrained site
 Limited resources and supply chain
pool
Constraints
/06.02.12 6
Success Criteria
Safety
Schedule Performance
Cost Performance
Quality
Stakeholder Impact
Operational Performance
/06.02.12 7
Strategy in 2008
 Early Works Contractor
 Main Works Delivery Contractor
 Detailed Design and Build
 Early Contractor Involvement
 Early Sub-contractor Involvement
 Target Cost
 Co-located organisation
 One project identity-common brand
 Minimise man ‘man-marking’
 Collaborative, non-confrontational style
 Risk approach to quality assurance
 Multiple detailed design control points
 Co-ordination and stakeholder management
 Common IT platforms
 Common document management system
 One Schedule, one system
ORGANISATION & BEHAVIOURS SYSTEMS
PROCESSES PROCUREMENT
/06.02.12 8
Strategy Execution
/06.02.12 9
2011 2012 2013 2014 2015 2016 2017 2018
GRIP 4 ( OUTLINE DESIGN)
GRIP 5 (DETAILED DESIGN)
GRIP 6 – 8 (CONSTRUCTION - HANDBACK)
Feb 2012
Main Works
Contract Signature
Target Cost
Agreed
Mar. Stage 1 Completion
Early Works Contractor
Sept.. Stage 1a Completion
Jan. Stage 1 b Completion
May. Stage CC Completion
Jan. Stage2 Completion
July. Stage 2A (2A#) Completion
Apr.. Stage 3 Completion
Sept. Stage 4 Compl.
Strategy Execution
/06.02.12 10
Commercial Model
60% / 40%
£100.0M
£0.0M
Variable
Fee
Gainshare
Target
Cost
Saving
Total
Cost
TC + Fee
£100.0M
£40.0M
/Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11
/
Everything with people in mind
6-Oct-16 12
/06.02.12 13
Project Review
Jan 2015
/06.02.12 14
2011 2012 2013 2014 2015 2016 2017 2018
GRIP 4 ( OUTLINE DESIGN)
GRIP 5 (DETAILED DESIGN)
GRIP 6 – 8 (CONSTRUCTION - HANDBACK)
Feb 2012
Contract Signature
Supplemental
Agreeement
Project Review
and Restructuring
Mar. Stage 1 Completion
Enabling Works Contract
Sept.. Stage 1a Completion
Jan. Stage 1 b Completion
May. Stage CC Completion
Jan. Stage2 Completion
July. Stage 2A (2A#) Completion
Apr.. Stage 3 Completion
Sept. Stage 4 Compl.
Schedule Performance
/06.02.12 15
Commercial Performance
60% / 40%
£100.0M
£0.0M
Variable
Fee
Gainshare
Target
Cost
Saving
Total
Cost
TC + Fee
£100.0M
£40.0M
/6-Oct-16 16
UNDER
ASSESSMENT OF
COMPLEXITY
POORLY DEFINED
REFERENCE
DESIGN, TOO
SHORT TIME FOR
DETAILED DESIGN
COMPLEXITY
POOR
EFFICIENCY
Pressure to
Design to
Budget
Poorly defined
Reference
Design or late
design decisions
triggers cost
growth
The complexity
of Major Projects
is often
intangible and
not estimated
Optimum bias
about
completion dates
leads to minimal
estimate of
Prolongation
CostGrowth
Time constraints impacts Procurement & Construction quality inc
Temporary Services & Finishes
ESTIMATING DETAILED DESIGN CONSTRUCTION PROLONGATION FOR COMPLETION &
QUALITY
Optimism Bias
Political Pressure
Design & Construction
Overlap
Fixed
Milestones
Hand
Back
Drivers of tension in a constrained commercial
model
/Date 00.00.00 Create your footer by changing copy in the Header and Footer section 17
/Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18
Team Behaviours
 No conflict
 Commitment to project schedule delivery
 More compromise than collaboration
 Lack of challenge
 Reporting with insufficient clarity to support
effective management decisions
 Light touch governance
/
What it means to collaborate?
6-Oct-16 19
/08.06.15 20
Project Dynamics
/08.06.15 21
RISKLow High
Existing Incentivised
Target Cost
Guaranteed
Maximum Price
Commercial Model
• No threat to balance
sheet
• Driving defensive
behaviours
• Upward pressure on
target cost
• Threat to balance
sheet
• Limited negotiating
leverage
• Potential increase in
cost or fee due to risk
transfer
/
25% / 75%
60% / 40%
50% / 50%
40% / 60%
£31.8M
Target Cost £0.0M
New Incentivisation Model
Infrastructure Projects: Thameslink Programme
22
Employers
Discretionary
Gainshare
Gainshare
Target
Cost
Saving
Total
Cost
TC + Fee
£31.8M
KRA Fee
Lump
Sum Fee
Milestone Fee
£5.0M
£15.0M
£25.0M
Limited grounds
for Target Cost
adjustment
No fee on Total
Cost above
Target Cost
£0.0M
6-Oct-16
/
Take Aways
Infrastructure Projects: Thameslink Programme
Commercial Model aligns NR & Costain to achieve
lowest cost delivery (business objective)
Creates the environment required to achieve lowest
cost delivery
6-Oct-16 23
Control Collaboration
Capacity Capability
• Deliver within agreed CP5 funding
• Supply chain performance
• Stable borrowing
• VfM
• Maintain a net cash balance at an appropriate level
• Supply chain performance
• Deliver shareholder value (adjusted profit before tax
and dividend per share pence)
Costain PLC Commercial Results IP Commercial Result
• Reputation
• Customer Satisfaction
• Advocacy
Joint Results
• VfM
/
Thameslink Staff Briefing 18th September 2015 24
 London Bridge Management Board –
Executive Level
 London Bridge Project Board
 Programme Manager – project controls
 Behavioural Specialist
 Supply Chain Integration
 Recognise strategic role of design
management
Leadership Review
/
Thameslink Staff Briefing 18th September 2015 25
 Construction Management team
 Stakeholder and Operational interface
manager
 GRIP 6-8 Design and Engineering Team
 Independent Project Controls Manager
 Strengthen NR Contract Administration
 Design Management Design team
Organisation Review
/
Thameslink Staff Briefing 18th September 2015 26
Behaviours Review
 Independent consultant behavioural review
across the project
 Senior management behaviours review
 Joint management behavioural workshop
 Project wide briefings
 Ongoing behavioural change support
/
Thameslink Staff Briefing 18th September 2015 27
Design Management
NR Design Programme Manager
MD level engagement within the design joint venture.
Design summit to agree plan for process
improvements and the determination of the overall
long term design strategy.
Control of amendment/revision of design has been
enhanced.
/
Thameslink Staff Briefing 18th September 2015 28Thameslink Staff Briefing 18th September 2015 28
Project Controls
 Independent Project Controls Manager
 Restructuring of reporting requirements
 Robust risk management
 Accountability for budget management process
 EWN process reinvigorated
 Change Impact Assessment
 Visualisation Room
/06.02.12
Thameslink - achievements and challenges
29
Where we are today
Areas Strengthened
 Safety - 5 million man hours
without major injuries
 Design management - 860/901 PDS
Requirements already evidenced
 Cost performance – Stable contract
value
 Schedule performance – All
milestones met
 KPI Performance embedded
 Behaviours – improved
 Stakeholders Relationships -
positive
Opportunities for improvement
 Independent project controls c
be more effective
 Change management could be
more efficient
 Commercial returns under pre
/06.02.12 30
 Risk profile dictates our options
 Commercial model is central to
collaboration
 Take collaboration seriously – good
intentions are not enough
/06.02.12 31
Risk profile changes during the
lifecycle of a project; therefore
the commercial model needs to
match this flux if effective
collaborative arrangement is to
be maintained.
This presentation was delivered
at an APM event
To find out more about
upcoming events please visit our
website www.apm.org.uk/events

More Related Content

What's hot

Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesJeremie Averous
 
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesaAconex
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasMircea Tomescu
 
Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Jeremie Averous
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014SHKLaw
 
How to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsHow to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsJeremie Averous
 
How Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectHow Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectJeremie Averous
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsJeremie Averous
 
Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Jeremie Averous
 
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo
 
Third Party Solar Financing
Third Party Solar FinancingThird Party Solar Financing
Third Party Solar FinancingSolarbabaGlobal
 
Project Control Basics
Project Control BasicsProject Control Basics
Project Control Basicsprojectcompany
 
Establishing a-pmo-in-the-nhs-15-03-26
Establishing a-pmo-in-the-nhs-15-03-26Establishing a-pmo-in-the-nhs-15-03-26
Establishing a-pmo-in-the-nhs-15-03-26Bestoutcome
 

What's hot (20)

Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
 
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
 
Project Delivery Method Selection Tool
Project Delivery Method Selection ToolProject Delivery Method Selection Tool
Project Delivery Method Selection Tool
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
 
Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 
How to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsHow to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex Projects
 
How Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectHow Governance Makes or Breaks a Project
How Governance Makes or Breaks a Project
 
Swwe branch event 14th july 2016
Swwe branch event 14th july 2016Swwe branch event 14th july 2016
Swwe branch event 14th july 2016
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Program management in the ICT sector
Program management in the ICT sectorProgram management in the ICT sector
Program management in the ICT sector
 
Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)
 
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
LI, GUANGYA
LI,  GUANGYALI,  GUANGYA
LI, GUANGYA
 
Third Party Solar Financing
Third Party Solar FinancingThird Party Solar Financing
Third Party Solar Financing
 
Project Control Basics
Project Control BasicsProject Control Basics
Project Control Basics
 
Establishing a-pmo-in-the-nhs-15-03-26
Establishing a-pmo-in-the-nhs-15-03-26Establishing a-pmo-in-the-nhs-15-03-26
Establishing a-pmo-in-the-nhs-15-03-26
 
Client cases by industry
Client cases by industryClient cases by industry
Client cases by industry
 

Viewers also liked

Perkembanganemosi 120602013421-phpapp01
Perkembanganemosi 120602013421-phpapp01Perkembanganemosi 120602013421-phpapp01
Perkembanganemosi 120602013421-phpapp01Serly Amalia
 
Exploring work-life balance (and how to improve it) - Sue Pritchard
Exploring work-life balance (and how to improve it) - Sue PritchardExploring work-life balance (and how to improve it) - Sue Pritchard
Exploring work-life balance (and how to improve it) - Sue PritchardAssociation for Project Management
 
Diversity in change projects - How to plan to minimise impact on people and r...
Diversity in change projects - How to plan to minimise impact on people and r...Diversity in change projects - How to plan to minimise impact on people and r...
Diversity in change projects - How to plan to minimise impact on people and r...Association for Project Management
 
Successful change - good culture and governance matter Conference - Melanie F...
Successful change - good culture and governance matter Conference - Melanie F...Successful change - good culture and governance matter Conference - Melanie F...
Successful change - good culture and governance matter Conference - Melanie F...Association for Project Management
 
Strategic Change Management in Large Organisations - Brian Martin
Strategic Change Management in Large Organisations - Brian MartinStrategic Change Management in Large Organisations - Brian Martin
Strategic Change Management in Large Organisations - Brian MartinAssociation for Project Management
 
Successful change - good culture and governance matter Conference - Ivor Benn...
Successful change - good culture and governance matter Conference - Ivor Benn...Successful change - good culture and governance matter Conference - Ivor Benn...
Successful change - good culture and governance matter Conference - Ivor Benn...Association for Project Management
 
4.1.3 properties of coals
4.1.3 properties of coals4.1.3 properties of coals
4.1.3 properties of coalsrajdeepjain
 
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Association for Project Management
 
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...Association for Project Management
 
The synergy between benefits management and change management, workshop 2, Ne...
The synergy between benefits management and change management, workshop 2, Ne...The synergy between benefits management and change management, workshop 2, Ne...
The synergy between benefits management and change management, workshop 2, Ne...Association for Project Management
 
PMO and Value Conference - Ruth Saunders, London, 25 October 2016
PMO and Value Conference - Ruth Saunders, London, 25 October 2016PMO and Value Conference - Ruth Saunders, London, 25 October 2016
PMO and Value Conference - Ruth Saunders, London, 25 October 2016Association for Project Management
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Association for Project Management
 
MATEMATIKA Operasi hitung bilangan bulat
MATEMATIKA Operasi hitung bilangan bulatMATEMATIKA Operasi hitung bilangan bulat
MATEMATIKA Operasi hitung bilangan bulatSerly Amalia
 
IPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWAN
IPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWANIPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWAN
IPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWANSerly Amalia
 
La révolution mobile & tablette : êtes-vous prêt ?
La révolution mobile & tablette : êtes-vous prêt ?La révolution mobile & tablette : êtes-vous prêt ?
La révolution mobile & tablette : êtes-vous prêt ?Net Design
 

Viewers also liked (20)

Closing the gap - women in the professions - Peter Cheese
Closing the gap - women in the professions - Peter CheeseClosing the gap - women in the professions - Peter Cheese
Closing the gap - women in the professions - Peter Cheese
 
Perkembanganemosi 120602013421-phpapp01
Perkembanganemosi 120602013421-phpapp01Perkembanganemosi 120602013421-phpapp01
Perkembanganemosi 120602013421-phpapp01
 
It takes two to tango pbk (nd) 160916
It takes two to tango pbk (nd) 160916It takes two to tango pbk (nd) 160916
It takes two to tango pbk (nd) 160916
 
Exploring work-life balance (and how to improve it) - Sue Pritchard
Exploring work-life balance (and how to improve it) - Sue PritchardExploring work-life balance (and how to improve it) - Sue Pritchard
Exploring work-life balance (and how to improve it) - Sue Pritchard
 
Diversity in change projects - How to plan to minimise impact on people and r...
Diversity in change projects - How to plan to minimise impact on people and r...Diversity in change projects - How to plan to minimise impact on people and r...
Diversity in change projects - How to plan to minimise impact on people and r...
 
Successful change - good culture and governance matter Conference - Melanie F...
Successful change - good culture and governance matter Conference - Melanie F...Successful change - good culture and governance matter Conference - Melanie F...
Successful change - good culture and governance matter Conference - Melanie F...
 
Strategic Change Management in Large Organisations - Brian Martin
Strategic Change Management in Large Organisations - Brian MartinStrategic Change Management in Large Organisations - Brian Martin
Strategic Change Management in Large Organisations - Brian Martin
 
Successful change - good culture and governance matter Conference - Ivor Benn...
Successful change - good culture and governance matter Conference - Ivor Benn...Successful change - good culture and governance matter Conference - Ivor Benn...
Successful change - good culture and governance matter Conference - Ivor Benn...
 
How far away is innovation in design and delivery
How far away is innovation in design and delivery How far away is innovation in design and delivery
How far away is innovation in design and delivery
 
4.1.3 properties of coals
4.1.3 properties of coals4.1.3 properties of coals
4.1.3 properties of coals
 
How to successfully deliver business change
How to successfully deliver business changeHow to successfully deliver business change
How to successfully deliver business change
 
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
 
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
 
The synergy between benefits management and change management, workshop 2, Ne...
The synergy between benefits management and change management, workshop 2, Ne...The synergy between benefits management and change management, workshop 2, Ne...
The synergy between benefits management and change management, workshop 2, Ne...
 
B1
B1B1
B1
 
PMO and Value Conference - Ruth Saunders, London, 25 October 2016
PMO and Value Conference - Ruth Saunders, London, 25 October 2016PMO and Value Conference - Ruth Saunders, London, 25 October 2016
PMO and Value Conference - Ruth Saunders, London, 25 October 2016
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
 
MATEMATIKA Operasi hitung bilangan bulat
MATEMATIKA Operasi hitung bilangan bulatMATEMATIKA Operasi hitung bilangan bulat
MATEMATIKA Operasi hitung bilangan bulat
 
IPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWAN
IPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWANIPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWAN
IPA DASAR - ALAT PERNAFASAN MANUSIA dan HEWAN
 
La révolution mobile & tablette : êtes-vous prêt ?
La révolution mobile & tablette : êtes-vous prêt ?La révolution mobile & tablette : êtes-vous prêt ?
La révolution mobile & tablette : êtes-vous prêt ?
 

Similar to Keeping Collaborative Delivery Arrangements on Track

The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...Association for Project Management
 
3rd_NDC_SL_Commercial_Strategy_Public
3rd_NDC_SL_Commercial_Strategy_Public3rd_NDC_SL_Commercial_Strategy_Public
3rd_NDC_SL_Commercial_Strategy_PublicRichard B. Petch
 
5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)
5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)
5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)JiWoon Yi
 
Surviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits ManagementSurviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits Managementcombera
 
Best Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit CrunchBest Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit Crunchrmoret
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015FBE Manchester
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project ValueLeanleaders.org
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project ValueLeanleaders.org
 
Webinar Critical Chain Project Management - Marris Consulting - June 2020
Webinar Critical Chain Project Management  - Marris Consulting - June 2020Webinar Critical Chain Project Management  - Marris Consulting - June 2020
Webinar Critical Chain Project Management - Marris Consulting - June 2020MARRIS Consulting
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
ned-presentation-project-management.pdf
ned-presentation-project-management.pdfned-presentation-project-management.pdf
ned-presentation-project-management.pdfBENALI Idriss
 
S10 Organisations Software and Methodologies
S10 Organisations Software and MethodologiesS10 Organisations Software and Methodologies
S10 Organisations Software and MethodologiesRoland Berberich
 
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...Moustafa Ismail Abu Dief
 
david mason, low carbon construction - challenges, trends and technologies, l...
david mason, low carbon construction - challenges, trends and technologies, l...david mason, low carbon construction - challenges, trends and technologies, l...
david mason, low carbon construction - challenges, trends and technologies, l...The Future Economy Network
 
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018Wellingtone
 

Similar to Keeping Collaborative Delivery Arrangements on Track (20)

Jacques Deschamps master-class (TETRA PAK) — LeanForum 2019 (11/12/2019)
Jacques Deschamps master-class (TETRA PAK) — LeanForum 2019 (11/12/2019)Jacques Deschamps master-class (TETRA PAK) — LeanForum 2019 (11/12/2019)
Jacques Deschamps master-class (TETRA PAK) — LeanForum 2019 (11/12/2019)
 
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
 
3rd_NDC_SL_Commercial_Strategy_Public
3rd_NDC_SL_Commercial_Strategy_Public3rd_NDC_SL_Commercial_Strategy_Public
3rd_NDC_SL_Commercial_Strategy_Public
 
5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)
5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)
5 영국의 건설사업관리 발전방향 saleem akram 이사(ciob)
 
Surviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits ManagementSurviving The Credit Crunch Using Benefits Management
Surviving The Credit Crunch Using Benefits Management
 
Best Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit CrunchBest Practice Showcase Presentation Surviving The Credit Crunch
Best Practice Showcase Presentation Surviving The Credit Crunch
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015
 
FINLAY_A_KEITH_CV
FINLAY_A_KEITH_CVFINLAY_A_KEITH_CV
FINLAY_A_KEITH_CV
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project Value
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project Value
 
BBC - Better Business Cases - Foundation
BBC - Better Business Cases - FoundationBBC - Better Business Cases - Foundation
BBC - Better Business Cases - Foundation
 
Webinar Critical Chain Project Management - Marris Consulting - June 2020
Webinar Critical Chain Project Management  - Marris Consulting - June 2020Webinar Critical Chain Project Management  - Marris Consulting - June 2020
Webinar Critical Chain Project Management - Marris Consulting - June 2020
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
ned-presentation-project-management.pdf
ned-presentation-project-management.pdfned-presentation-project-management.pdf
ned-presentation-project-management.pdf
 
Alan Watt - APM Assurance SIG Conference 2018
Alan Watt - APM Assurance SIG Conference 2018Alan Watt - APM Assurance SIG Conference 2018
Alan Watt - APM Assurance SIG Conference 2018
 
S10 Organisations Software and Methodologies
S10 Organisations Software and MethodologiesS10 Organisations Software and Methodologies
S10 Organisations Software and Methodologies
 
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
 
david mason, low carbon construction - challenges, trends and technologies, l...
david mason, low carbon construction - challenges, trends and technologies, l...david mason, low carbon construction - challenges, trends and technologies, l...
david mason, low carbon construction - challenges, trends and technologies, l...
 
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
 
ABB - Sustainable Procurement by Philip Juneau at GIB Summit
ABB - Sustainable Procurement by Philip Juneau at GIB SummitABB - Sustainable Procurement by Philip Juneau at GIB Summit
ABB - Sustainable Procurement by Philip Juneau at GIB Summit
 

More from Association for Project Management

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakAssociation for Project Management
 

More from Association for Project Management (20)

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peak
 
Demystifying digital accessibility webinar
Demystifying digital accessibility webinarDemystifying digital accessibility webinar
Demystifying digital accessibility webinar
 

Recently uploaded

(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Investment analysis and portfolio management
Investment analysis and portfolio managementInvestment analysis and portfolio management
Investment analysis and portfolio managementJunaidKhan750825
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...lizamodels9
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCRsoniya singh
 

Recently uploaded (20)

(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Investment analysis and portfolio management
Investment analysis and portfolio managementInvestment analysis and portfolio management
Investment analysis and portfolio management
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
 

Keeping Collaborative Delivery Arrangements on Track

  • 1. /06.02.12 1 Keeping collaborative delivery arrangements in focus and on course …a case of LBSR Boris Lucic EMBA CEng MICE RPP Programme Engineering Manager London Bridge Station Redevelopment
  • 2. /06.02.12 2 “The reality is that true collaboration is difficult. It requires subordinating individual goals to collective achievement.” Have you ever been accused of not being collaborative?
  • 3. /6-Oct-16 3 This story is based on true events… Strategy Development Strategy Execution Project Review and Interventions Where we are today
  • 4. /06.02.12 Thameslink - achievements and challenges 4  Transformational Change  Scale  Complexity  People  Communication London Bridge Station
  • 5. /06.02.12 Thameslink - achievements and challenges 5  Super critical milestones  Operational requirements take precedent  Cumulative complexity  Constrained site  Limited resources and supply chain pool Constraints
  • 6. /06.02.12 6 Success Criteria Safety Schedule Performance Cost Performance Quality Stakeholder Impact Operational Performance
  • 7. /06.02.12 7 Strategy in 2008  Early Works Contractor  Main Works Delivery Contractor  Detailed Design and Build  Early Contractor Involvement  Early Sub-contractor Involvement  Target Cost  Co-located organisation  One project identity-common brand  Minimise man ‘man-marking’  Collaborative, non-confrontational style  Risk approach to quality assurance  Multiple detailed design control points  Co-ordination and stakeholder management  Common IT platforms  Common document management system  One Schedule, one system ORGANISATION & BEHAVIOURS SYSTEMS PROCESSES PROCUREMENT
  • 9. /06.02.12 9 2011 2012 2013 2014 2015 2016 2017 2018 GRIP 4 ( OUTLINE DESIGN) GRIP 5 (DETAILED DESIGN) GRIP 6 – 8 (CONSTRUCTION - HANDBACK) Feb 2012 Main Works Contract Signature Target Cost Agreed Mar. Stage 1 Completion Early Works Contractor Sept.. Stage 1a Completion Jan. Stage 1 b Completion May. Stage CC Completion Jan. Stage2 Completion July. Stage 2A (2A#) Completion Apr.. Stage 3 Completion Sept. Stage 4 Compl. Strategy Execution
  • 10. /06.02.12 10 Commercial Model 60% / 40% £100.0M £0.0M Variable Fee Gainshare Target Cost Saving Total Cost TC + Fee £100.0M £40.0M
  • 11. /Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11
  • 12. / Everything with people in mind 6-Oct-16 12
  • 14. /06.02.12 14 2011 2012 2013 2014 2015 2016 2017 2018 GRIP 4 ( OUTLINE DESIGN) GRIP 5 (DETAILED DESIGN) GRIP 6 – 8 (CONSTRUCTION - HANDBACK) Feb 2012 Contract Signature Supplemental Agreeement Project Review and Restructuring Mar. Stage 1 Completion Enabling Works Contract Sept.. Stage 1a Completion Jan. Stage 1 b Completion May. Stage CC Completion Jan. Stage2 Completion July. Stage 2A (2A#) Completion Apr.. Stage 3 Completion Sept. Stage 4 Compl. Schedule Performance
  • 15. /06.02.12 15 Commercial Performance 60% / 40% £100.0M £0.0M Variable Fee Gainshare Target Cost Saving Total Cost TC + Fee £100.0M £40.0M
  • 16. /6-Oct-16 16 UNDER ASSESSMENT OF COMPLEXITY POORLY DEFINED REFERENCE DESIGN, TOO SHORT TIME FOR DETAILED DESIGN COMPLEXITY POOR EFFICIENCY Pressure to Design to Budget Poorly defined Reference Design or late design decisions triggers cost growth The complexity of Major Projects is often intangible and not estimated Optimum bias about completion dates leads to minimal estimate of Prolongation CostGrowth Time constraints impacts Procurement & Construction quality inc Temporary Services & Finishes ESTIMATING DETAILED DESIGN CONSTRUCTION PROLONGATION FOR COMPLETION & QUALITY Optimism Bias Political Pressure Design & Construction Overlap Fixed Milestones Hand Back Drivers of tension in a constrained commercial model
  • 17. /Date 00.00.00 Create your footer by changing copy in the Header and Footer section 17
  • 18. /Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18 Team Behaviours  No conflict  Commitment to project schedule delivery  More compromise than collaboration  Lack of challenge  Reporting with insufficient clarity to support effective management decisions  Light touch governance
  • 19. / What it means to collaborate? 6-Oct-16 19
  • 21. /08.06.15 21 RISKLow High Existing Incentivised Target Cost Guaranteed Maximum Price Commercial Model • No threat to balance sheet • Driving defensive behaviours • Upward pressure on target cost • Threat to balance sheet • Limited negotiating leverage • Potential increase in cost or fee due to risk transfer
  • 22. / 25% / 75% 60% / 40% 50% / 50% 40% / 60% £31.8M Target Cost £0.0M New Incentivisation Model Infrastructure Projects: Thameslink Programme 22 Employers Discretionary Gainshare Gainshare Target Cost Saving Total Cost TC + Fee £31.8M KRA Fee Lump Sum Fee Milestone Fee £5.0M £15.0M £25.0M Limited grounds for Target Cost adjustment No fee on Total Cost above Target Cost £0.0M 6-Oct-16
  • 23. / Take Aways Infrastructure Projects: Thameslink Programme Commercial Model aligns NR & Costain to achieve lowest cost delivery (business objective) Creates the environment required to achieve lowest cost delivery 6-Oct-16 23 Control Collaboration Capacity Capability • Deliver within agreed CP5 funding • Supply chain performance • Stable borrowing • VfM • Maintain a net cash balance at an appropriate level • Supply chain performance • Deliver shareholder value (adjusted profit before tax and dividend per share pence) Costain PLC Commercial Results IP Commercial Result • Reputation • Customer Satisfaction • Advocacy Joint Results • VfM
  • 24. / Thameslink Staff Briefing 18th September 2015 24  London Bridge Management Board – Executive Level  London Bridge Project Board  Programme Manager – project controls  Behavioural Specialist  Supply Chain Integration  Recognise strategic role of design management Leadership Review
  • 25. / Thameslink Staff Briefing 18th September 2015 25  Construction Management team  Stakeholder and Operational interface manager  GRIP 6-8 Design and Engineering Team  Independent Project Controls Manager  Strengthen NR Contract Administration  Design Management Design team Organisation Review
  • 26. / Thameslink Staff Briefing 18th September 2015 26 Behaviours Review  Independent consultant behavioural review across the project  Senior management behaviours review  Joint management behavioural workshop  Project wide briefings  Ongoing behavioural change support
  • 27. / Thameslink Staff Briefing 18th September 2015 27 Design Management NR Design Programme Manager MD level engagement within the design joint venture. Design summit to agree plan for process improvements and the determination of the overall long term design strategy. Control of amendment/revision of design has been enhanced.
  • 28. / Thameslink Staff Briefing 18th September 2015 28Thameslink Staff Briefing 18th September 2015 28 Project Controls  Independent Project Controls Manager  Restructuring of reporting requirements  Robust risk management  Accountability for budget management process  EWN process reinvigorated  Change Impact Assessment  Visualisation Room
  • 29. /06.02.12 Thameslink - achievements and challenges 29 Where we are today Areas Strengthened  Safety - 5 million man hours without major injuries  Design management - 860/901 PDS Requirements already evidenced  Cost performance – Stable contract value  Schedule performance – All milestones met  KPI Performance embedded  Behaviours – improved  Stakeholders Relationships - positive Opportunities for improvement  Independent project controls c be more effective  Change management could be more efficient  Commercial returns under pre
  • 30. /06.02.12 30  Risk profile dictates our options  Commercial model is central to collaboration  Take collaboration seriously – good intentions are not enough
  • 31. /06.02.12 31 Risk profile changes during the lifecycle of a project; therefore the commercial model needs to match this flux if effective collaborative arrangement is to be maintained.
  • 32. This presentation was delivered at an APM event To find out more about upcoming events please visit our website www.apm.org.uk/events