Boris Lucic
Keeping collaborative delivery arrangements in focus and of course... a case of LBSR
Successful change - good culture and governance matter
APM Governance Specific Interest Group Conference
London, 06 Oct 2016
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
Keeping Collaborative Delivery Arrangements on Track
1. /06.02.12 1
Keeping collaborative delivery
arrangements in focus and on course
…a case of LBSR
Boris Lucic EMBA CEng MICE RPP
Programme Engineering Manager
London Bridge Station Redevelopment
2. /06.02.12 2
“The reality is that true collaboration
is difficult. It requires subordinating
individual goals to collective
achievement.”
Have you ever been
accused of not being
collaborative?
3. /6-Oct-16 3
This story is based on true events…
Strategy
Development
Strategy
Execution
Project
Review and
Interventions
Where we are
today
4. /06.02.12
Thameslink - achievements and challenges
4
Transformational Change
Scale
Complexity
People
Communication
London Bridge Station
5. /06.02.12
Thameslink - achievements and challenges
5
Super critical milestones
Operational requirements take
precedent
Cumulative complexity
Constrained site
Limited resources and supply chain
pool
Constraints
7. /06.02.12 7
Strategy in 2008
Early Works Contractor
Main Works Delivery Contractor
Detailed Design and Build
Early Contractor Involvement
Early Sub-contractor Involvement
Target Cost
Co-located organisation
One project identity-common brand
Minimise man ‘man-marking’
Collaborative, non-confrontational style
Risk approach to quality assurance
Multiple detailed design control points
Co-ordination and stakeholder management
Common IT platforms
Common document management system
One Schedule, one system
ORGANISATION & BEHAVIOURS SYSTEMS
PROCESSES PROCUREMENT
16. /6-Oct-16 16
UNDER
ASSESSMENT OF
COMPLEXITY
POORLY DEFINED
REFERENCE
DESIGN, TOO
SHORT TIME FOR
DETAILED DESIGN
COMPLEXITY
POOR
EFFICIENCY
Pressure to
Design to
Budget
Poorly defined
Reference
Design or late
design decisions
triggers cost
growth
The complexity
of Major Projects
is often
intangible and
not estimated
Optimum bias
about
completion dates
leads to minimal
estimate of
Prolongation
CostGrowth
Time constraints impacts Procurement & Construction quality inc
Temporary Services & Finishes
ESTIMATING DETAILED DESIGN CONSTRUCTION PROLONGATION FOR COMPLETION &
QUALITY
Optimism Bias
Political Pressure
Design & Construction
Overlap
Fixed
Milestones
Hand
Back
Drivers of tension in a constrained commercial
model
17. /Date 00.00.00 Create your footer by changing copy in the Header and Footer section 17
18. /Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18
Team Behaviours
No conflict
Commitment to project schedule delivery
More compromise than collaboration
Lack of challenge
Reporting with insufficient clarity to support
effective management decisions
Light touch governance
21. /08.06.15 21
RISKLow High
Existing Incentivised
Target Cost
Guaranteed
Maximum Price
Commercial Model
• No threat to balance
sheet
• Driving defensive
behaviours
• Upward pressure on
target cost
• Threat to balance
sheet
• Limited negotiating
leverage
• Potential increase in
cost or fee due to risk
transfer
22. /
25% / 75%
60% / 40%
50% / 50%
40% / 60%
£31.8M
Target Cost £0.0M
New Incentivisation Model
Infrastructure Projects: Thameslink Programme
22
Employers
Discretionary
Gainshare
Gainshare
Target
Cost
Saving
Total
Cost
TC + Fee
£31.8M
KRA Fee
Lump
Sum Fee
Milestone Fee
£5.0M
£15.0M
£25.0M
Limited grounds
for Target Cost
adjustment
No fee on Total
Cost above
Target Cost
£0.0M
6-Oct-16
23. /
Take Aways
Infrastructure Projects: Thameslink Programme
Commercial Model aligns NR & Costain to achieve
lowest cost delivery (business objective)
Creates the environment required to achieve lowest
cost delivery
6-Oct-16 23
Control Collaboration
Capacity Capability
• Deliver within agreed CP5 funding
• Supply chain performance
• Stable borrowing
• VfM
• Maintain a net cash balance at an appropriate level
• Supply chain performance
• Deliver shareholder value (adjusted profit before tax
and dividend per share pence)
Costain PLC Commercial Results IP Commercial Result
• Reputation
• Customer Satisfaction
• Advocacy
Joint Results
• VfM
24. /
Thameslink Staff Briefing 18th September 2015 24
London Bridge Management Board –
Executive Level
London Bridge Project Board
Programme Manager – project controls
Behavioural Specialist
Supply Chain Integration
Recognise strategic role of design
management
Leadership Review
25. /
Thameslink Staff Briefing 18th September 2015 25
Construction Management team
Stakeholder and Operational interface
manager
GRIP 6-8 Design and Engineering Team
Independent Project Controls Manager
Strengthen NR Contract Administration
Design Management Design team
Organisation Review
26. /
Thameslink Staff Briefing 18th September 2015 26
Behaviours Review
Independent consultant behavioural review
across the project
Senior management behaviours review
Joint management behavioural workshop
Project wide briefings
Ongoing behavioural change support
27. /
Thameslink Staff Briefing 18th September 2015 27
Design Management
NR Design Programme Manager
MD level engagement within the design joint venture.
Design summit to agree plan for process
improvements and the determination of the overall
long term design strategy.
Control of amendment/revision of design has been
enhanced.
28. /
Thameslink Staff Briefing 18th September 2015 28Thameslink Staff Briefing 18th September 2015 28
Project Controls
Independent Project Controls Manager
Restructuring of reporting requirements
Robust risk management
Accountability for budget management process
EWN process reinvigorated
Change Impact Assessment
Visualisation Room
29. /06.02.12
Thameslink - achievements and challenges
29
Where we are today
Areas Strengthened
Safety - 5 million man hours
without major injuries
Design management - 860/901 PDS
Requirements already evidenced
Cost performance – Stable contract
value
Schedule performance – All
milestones met
KPI Performance embedded
Behaviours – improved
Stakeholders Relationships -
positive
Opportunities for improvement
Independent project controls c
be more effective
Change management could be
more efficient
Commercial returns under pre
30. /06.02.12 30
Risk profile dictates our options
Commercial model is central to
collaboration
Take collaboration seriously – good
intentions are not enough
31. /06.02.12 31
Risk profile changes during the
lifecycle of a project; therefore
the commercial model needs to
match this flux if effective
collaborative arrangement is to
be maintained.
32. This presentation was delivered
at an APM event
To find out more about
upcoming events please visit our
website www.apm.org.uk/events