SlideShare a Scribd company logo
1 of 38
© ValueMetric Consultants LLC (2016)
Ayman El-Ghazzawi
BSc MSc FRICS
American University in Cairo
Architectural Engineering Programme
11 October 2016
© ValueMetric Consultants LLC (2016) 2
Introduction – terminology
Benchmarking
Cost Planning
Building Economics
Conclusion
Q&A
3
Introduction
© ValueMetric Consultants LLC (2016) 4
 Cost is a significant, if not essential part of a project  decides if the
scheme is viable….. No Money  No Project
 QS is responsible for all matters financial and commercial on a
construction project
 Triangle of Duties on a Project:
COST
QUALITY TIME
Quantity
Surveyor
Project
Manager
Architect
(Designer)
© ValueMetric Consultants LLC (2016) 5
US Approach to Cost Management UK Approach to Cost Management
Traditionally called a “Cost Estimator”
Previously called a Quantity Surveyor, now
more common to call Cost Manager
Approach is led by Programme Led by Design Stages (e.g. RIBA)
Use of cost-loaded programmes Use of Bills of Quantities to package works
Method of Measurement: CSI Masterformat Method of Measurement: POMI, NRM
Professional association: AACE Professional association: RICS
Combine Cost & Time  Project Controls Separate Cost & Time: QS and PM
© ValueMetric Consultants LLC (2016) 6
Provides an early, approximate vision of construction costs
Helps in setting a project’s budget
Used to commercially manage the pre-contract design
Concept  Schematic  Detailed Design
Provides an early warning of scope creep, monitors changes
Can assist with setting sale prices
Informs the financial P&L of a developer company
Captures entire development costs  helps form package
BOQs
© ValueMetric Consultants LLC (2016) 7
Term Definition
Cost actual price to be paid
Value
how much it is desired, price of what it’s
worth
Feasibility Estimate
Establishes the overall viability of the project,
return on investment
Order of Magnitude
Estimate
Reflects a particular design stage, e.g.
concept, schematic, detailed
Cost Plan
Reflects a particular design stage, e.g.
concept, schematic, detailed
© ValueMetric Consultants LLC (2016) 8
Term Definition
Cost Model
Cost-led, does not reflect a particular design,
allows for varying elements
Cost Analysis
Estimates the cost of construction of
particular elements or portion of the works
Cost Report
Tracks the overall project costs monthly,
monitors commercial performance
9
Benchmarking and Order
of Cost Estimates (OCE)
© ValueMetric Consultants LLC (2016) 10
Highest level of cost estimating, lowest accuracy
Usually based on functional units or built-up area
Examples of functional units:
› Hospitals EGP / bed
› Hotels EGP / key
› Schools EGP / student
› Residential EGP / m2 (or per habitable room)
› Office Buildings EGP / gross lettable area
© ValueMetric Consultants LLC (2016) 11
OCE: Order of Cost Estimate – most preliminary cost plan
Must find out:
› Type of building to be built (e.g. hotel)
› Expected number of functional units (e.g. nr of keys)
› When it is expected to be built (e.g. two years from now)
› Outline specification level (e.g. high/med/low quality, 4*, 5*)
› Location where it is to be built
© ValueMetric Consultants LLC (2016) 12
Source:
Spon’s Architects’and
Builders’ Price Book 2009
© ValueMetric Consultants LLC (2016) 13
Begin with a high level benchmark estimate by function
Adjust your estimate by:
› Geographical variation
› Inflation indices
Multiply by number of functional units
Add contingency, VAT, etc.
Emphasise that Tolerance / accuracy is low
Use an estimating resource – your own project database or
price book
© ValueMetric Consultants LLC (2016) 14
Source: Spon’s Architects’and Builders’ Price Book (2009)
© ValueMetric Consultants LLC (2016) 15
© ValueMetric Consultants LLC (2016) 16
© ValueMetric Consultants LLC (2016) 17
18
Cost Planning
© ValueMetric Consultants LLC (2016) 19
A document that details costs, usually developed from a
preliminary benchmark estimate, based on elemental or
functional units that reflects the Design Team’s intentions
Follows the project’s design stages, e.g. RIBA Work Stages
Sets a plan to spend costs, helps with purchasing and cost
control
As cost plan develops, accuracy is improved:
LE/function  LE/m2  Detailed LE costs based on qtys
© ValueMetric Consultants LLC (2016) 20
RIBA Work
Stage
Work Stage Description
A Appraisal / Feasibility
B Strategic Briefing
C Outline Proposals
D Detailed Proposals
E Final Proposals
F Production Information
G Tender Documentation
H Tender Action
J Mobilisation
K Construction  Practical Completion
L After Practical Completion
© ValueMetric Consultants LLC (2016) 21
COST PLANNING STAGES
Concept
30%
Schematic
60%
Detailed
90%
COST PLAN
Confirm Budget, Cost
Limits
COST PLAN
Set Cost Targets on
Schematic
COST PLAN
Set Cost Targets on
Detailed
SET
BUDGET
Proceed
to Tender
BOQ
Remedial Action: Value
Engineering
Pro-activeChangeControl
© ValueMetric Consultants LLC (2016) 22
Similar to OCE, but on an elemental level
Uses previous projects from a database, or pricing book
such as Spons
Adjust elements to suit the project being priced
› E.g. EGP/m2 will differ whether it is steel or concrete frame
Ensure it is a like-for-like benchmark comparison:
› Use same area types (BUA, NIA, etc.)
› Exclude sub-structure, earth work, external works
› Preliminaries (indirect costs), taxes and the like
© ValueMetric Consultants LLC (2016) 23
OCE or preliminary cost plan ± 25% to 30% tolerance
› EGP / functional unit
Concept Cost Plan ± 15% to 25% tolerance
› EGP / m2, based on floor areas
Schematic Cost Plan ± 10% to 15% tolerance
› EGP / m2, based on floor areas, with some systems allowed for
based on evolving design (e.g. district cooling v split units)
Detailed Cost Plan ± 5% to 10% tolerance
› EGP / m2, based on quantities and unit rates
© ValueMetric Consultants LLC (2016) 24
© ValueMetric Consultants LLC (2016) 25
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
EGP/m2
Electrical Engineering Works
Mechanical Engineering Works
Conveying Systems
Special Construction
Furnishings
Equipment
Specialties
Finishes
Doors and Windows
Thermal and Moisture Protection
Wood and Plastics
Metal Works
Masonry
Concrete Works
Site Construction
General Requirements
26
Building Economics
© ValueMetric Consultants LLC (2016) 27

© ValueMetric Consultants LLC (2016) 28
For the following two projects,
A and B, calculate:
1. Floor Area
2. Perimeter length
3. Wall Area
4. Wall-to-floor ratio
© ValueMetric Consultants LLC (2016) 29
For the following two projects,
A and B, calculate:
1. Floor Area
2. Perimeter length
3. Wall Area
4. Wall-to-floor ratio
© ValueMetric Consultants LLC (2016) 30
 Efficiency comes form plan shapes that are square (or circle)
 Consider whether it is better internal division (e.g. triangular plan)
 Less efficient shapes require more structure
 Consider a better enclosing wall to area ratio
 Core and circulation affected by choice of plan shape
 Short assessment
© ValueMetric Consultants LLC (2016) 31
For the following three Plan Shapes A, B and C, calculate:
1. Floor Area 3. Wall Area
2. Perimeter length 4. Wall-to-floor ratio
© ValueMetric Consultants LLC (2016) 32
For the following three Plan Shapes A, B and C, calculate:
1. Floor Area 3. Wall Area
2. Perimeter length 4. Wall-to-floor ratio
© ValueMetric Consultants LLC (2016) 33

© ValueMetric Consultants LLC (2016) 34

© ValueMetric Consultants LLC (2016) 35
 Tall structures are more costly – step
changes in height mean it is not a
uniform relationship of height to cost
 Storey heights can be cost sensitive
 VT costs to be considered
 More engineering costs for FP,
services performance
 Wider and more circulation space
needed
 Temporary works, lifting, etc. more
expensive
 Wind load will affect structural design
© ValueMetric Consultants LLC (2016) 36
 Building arrangement affects the
cost of construction
 Consider:
› Sharing elements between buildings
› Cost and of constructing
› Ability to construct: Buildability
 For the four arrangements shown,
1. Which is most desirable?
2. Which is most efficient?
3. Which has least “buildability”?
37
Conclusion
© ValueMetric Consultants LLC (2016) 38
Benchmarking is important to compare projects
› Expect differences and variation – explain them
› Separate abnormals (sub-structure, external works, infra, etc.)
Cost Plans are approximate, and not accurate by nature
Accuracy improves as design develops (± % tolerance
reduces)
Building shape, size and arrangement all affect costs 
understand how these affect your cost plan
Look at other efficiency parameters (net : gross area)

More Related Content

What's hot

Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contractshiva prakash
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor温 庄壁
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Construction financial management
Construction financial managementConstruction financial management
Construction financial managementYibeltal Alamirew
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDFIDHAMUKI
 

What's hot (20)

Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Taking off qs
Taking off qsTaking off qs
Taking off qs
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Construction contract
Construction contract Construction contract
Construction contract
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Construction financial management
Construction financial managementConstruction financial management
Construction financial management
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 

Similar to Quantity Surveying & Cost Planning

07 It Application01 Intro
07 It Application01 Intro07 It Application01 Intro
07 It Application01 IntroFazie70
 
Rethink cost estimation with core processes that drive 5D BIM
Rethink cost estimation with core processes that drive 5D  BIM Rethink cost estimation with core processes that drive 5D  BIM
Rethink cost estimation with core processes that drive 5D BIM BIMEngus1
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project managementJohn Constance
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Dataconstructingexcellence
 
'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management' 'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management' Alan Martin Redmond, PhD
 
043 integrating risk management
043 integrating risk management043 integrating risk management
043 integrating risk managementdrdej19
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...IAEME Publication
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsiaemedu
 
Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01David Eagle
 
Life Cycle Costing for BREEAM 2011 requirements
Life Cycle Costing for BREEAM 2011 requirementsLife Cycle Costing for BREEAM 2011 requirements
Life Cycle Costing for BREEAM 2011 requirementsanthonywaterman
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET Journal
 
Successful change - good culture and governance matter Conference - Boris Luc...
Successful change - good culture and governance matter Conference - Boris Luc...Successful change - good culture and governance matter Conference - Boris Luc...
Successful change - good culture and governance matter Conference - Boris Luc...Association for Project Management
 
BIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and ProcedureBIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and Procedureanhc5l77 actp84nya
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 
Money and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation ChainMoney and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation ChainIES VE
 

Similar to Quantity Surveying & Cost Planning (20)

07 It Application01 Intro
07 It Application01 Intro07 It Application01 Intro
07 It Application01 Intro
 
BIM DAY 2016-BIM Execution Plan(English Edition)
BIM DAY 2016-BIM Execution Plan(English Edition)BIM DAY 2016-BIM Execution Plan(English Edition)
BIM DAY 2016-BIM Execution Plan(English Edition)
 
ARQvision keynote
ARQvision keynoteARQvision keynote
ARQvision keynote
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
Rethink cost estimation with core processes that drive 5D BIM
Rethink cost estimation with core processes that drive 5D  BIM Rethink cost estimation with core processes that drive 5D  BIM
Rethink cost estimation with core processes that drive 5D BIM
 
Leaflet Green Building
Leaflet Green BuildingLeaflet Green Building
Leaflet Green Building
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
 
'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management' 'Applying System Science and System Thinking Techniques to BIM Management'
'Applying System Science and System Thinking Techniques to BIM Management'
 
043 Integrating Risk Management
043 Integrating Risk Management043 Integrating Risk Management
043 Integrating Risk Management
 
043 integrating risk management
043 integrating risk management043 integrating risk management
043 integrating risk management
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
 
Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01
 
Life Cycle Costing for BREEAM 2011 requirements
Life Cycle Costing for BREEAM 2011 requirementsLife Cycle Costing for BREEAM 2011 requirements
Life Cycle Costing for BREEAM 2011 requirements
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
Successful change - good culture and governance matter Conference - Boris Luc...
Successful change - good culture and governance matter Conference - Boris Luc...Successful change - good culture and governance matter Conference - Boris Luc...
Successful change - good culture and governance matter Conference - Boris Luc...
 
BIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and ProcedureBIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and Procedure
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Money and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation ChainMoney and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation Chain
 

More from Galala University

Architecture and Architects in Egypt b
Architecture and Architects in Egypt bArchitecture and Architects in Egypt b
Architecture and Architects in Egypt bGalala University
 
Architecture and Architects in Egypt a
Architecture and Architects in Egypt aArchitecture and Architects in Egypt a
Architecture and Architects in Egypt aGalala University
 
Impact of Climate and Environment Changes on the Sustainability of the Coasta...
Impact of Climate and Environment Changes on the Sustainability of the Coasta...Impact of Climate and Environment Changes on the Sustainability of the Coasta...
Impact of Climate and Environment Changes on the Sustainability of the Coasta...Galala University
 
Sustainability of Tourism Development in the city of Ain-Sukhna, Egypt
Sustainability of Tourism Development in the city of Ain-Sukhna, EgyptSustainability of Tourism Development in the city of Ain-Sukhna, Egypt
Sustainability of Tourism Development in the city of Ain-Sukhna, EgyptGalala University
 
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...Galala University
 
Typologies of Urban Development in Sukhna-Zaafarana Area.pdf
Typologies of Urban Development in Sukhna-Zaafarana Area.pdfTypologies of Urban Development in Sukhna-Zaafarana Area.pdf
Typologies of Urban Development in Sukhna-Zaafarana Area.pdfGalala University
 
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...Galala University
 
Arc341 building 3 spring 2019 lecture 5 - surface active - chapter 4
Arc341 building 3 spring 2019   lecture 5 - surface active - chapter 4Arc341 building 3 spring 2019   lecture 5 - surface active - chapter 4
Arc341 building 3 spring 2019 lecture 5 - surface active - chapter 4Galala University
 
Arc341 building 3 spring 2019 lecture 4 - section active - chapter 3
Arc341 building 3 spring 2019   lecture 4 - section active - chapter 3Arc341 building 3 spring 2019   lecture 4 - section active - chapter 3
Arc341 building 3 spring 2019 lecture 4 - section active - chapter 3Galala University
 
Arc341 building 3 spring 2019 lecture 3 - vector-active - chapter 2
Arc341 building 3 spring 2019   lecture 3 - vector-active - chapter 2Arc341 building 3 spring 2019   lecture 3 - vector-active - chapter 2
Arc341 building 3 spring 2019 lecture 3 - vector-active - chapter 2Galala University
 
Arc341 building 3 spring 2019 lecture 2 - basics - chapter 0
Arc341 building 3 spring 2019   lecture 2 - basics - chapter 0Arc341 building 3 spring 2019   lecture 2 - basics - chapter 0
Arc341 building 3 spring 2019 lecture 2 - basics - chapter 0Galala University
 
Arc341 building 3 spring 2019 lecture 1 - introduction to structures
Arc341 building 3 spring 2019   lecture 1 - introduction to structuresArc341 building 3 spring 2019   lecture 1 - introduction to structures
Arc341 building 3 spring 2019 lecture 1 - introduction to structuresGalala University
 
Fue theory 4 2018 lecture 5 - the formulation and analysis of architectural...
Fue theory 4 2018   lecture 5 - the formulation and analysis of architectural...Fue theory 4 2018   lecture 5 - the formulation and analysis of architectural...
Fue theory 4 2018 lecture 5 - the formulation and analysis of architectural...Galala University
 
Fue theory 4 2018 lecture 4 - the formulation and analysis of architectural...
Fue theory 4 2018   lecture 4 - the formulation and analysis of architectural...Fue theory 4 2018   lecture 4 - the formulation and analysis of architectural...
Fue theory 4 2018 lecture 4 - the formulation and analysis of architectural...Galala University
 
Fue theory 4 2018 lecture 3 - architectural timeline
Fue theory 4 2018   lecture 3 - architectural timelineFue theory 4 2018   lecture 3 - architectural timeline
Fue theory 4 2018 lecture 3 - architectural timelineGalala University
 
Fue theory 4 2018 lecture 2 - history of theory
Fue theory 4 2018   lecture 2 - history of theoryFue theory 4 2018   lecture 2 - history of theory
Fue theory 4 2018 lecture 2 - history of theoryGalala University
 
Fue theory 4 2018 lecture 1- introduction
Fue theory 4 2018   lecture 1- introductionFue theory 4 2018   lecture 1- introduction
Fue theory 4 2018 lecture 1- introductionGalala University
 
Fue theory 4 2018 lecture 6 - synthesis of the design concept- different te...
Fue theory 4 2018   lecture 6 - synthesis of the design concept- different te...Fue theory 4 2018   lecture 6 - synthesis of the design concept- different te...
Fue theory 4 2018 lecture 6 - synthesis of the design concept- different te...Galala University
 
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2Galala University
 
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1Arc 323 human studies in architecture fall 2018 lecture 8-topics 1
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1Galala University
 

More from Galala University (20)

Architecture and Architects in Egypt b
Architecture and Architects in Egypt bArchitecture and Architects in Egypt b
Architecture and Architects in Egypt b
 
Architecture and Architects in Egypt a
Architecture and Architects in Egypt aArchitecture and Architects in Egypt a
Architecture and Architects in Egypt a
 
Impact of Climate and Environment Changes on the Sustainability of the Coasta...
Impact of Climate and Environment Changes on the Sustainability of the Coasta...Impact of Climate and Environment Changes on the Sustainability of the Coasta...
Impact of Climate and Environment Changes on the Sustainability of the Coasta...
 
Sustainability of Tourism Development in the city of Ain-Sukhna, Egypt
Sustainability of Tourism Development in the city of Ain-Sukhna, EgyptSustainability of Tourism Development in the city of Ain-Sukhna, Egypt
Sustainability of Tourism Development in the city of Ain-Sukhna, Egypt
 
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
Sustainability of Tourism Development in Al Ain Al Sukhna, Egypt Yasser Mahgo...
 
Typologies of Urban Development in Sukhna-Zaafarana Area.pdf
Typologies of Urban Development in Sukhna-Zaafarana Area.pdfTypologies of Urban Development in Sukhna-Zaafarana Area.pdf
Typologies of Urban Development in Sukhna-Zaafarana Area.pdf
 
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
AI-Human Dialogue for Architectural Design Concept Generation presentation 26...
 
Arc341 building 3 spring 2019 lecture 5 - surface active - chapter 4
Arc341 building 3 spring 2019   lecture 5 - surface active - chapter 4Arc341 building 3 spring 2019   lecture 5 - surface active - chapter 4
Arc341 building 3 spring 2019 lecture 5 - surface active - chapter 4
 
Arc341 building 3 spring 2019 lecture 4 - section active - chapter 3
Arc341 building 3 spring 2019   lecture 4 - section active - chapter 3Arc341 building 3 spring 2019   lecture 4 - section active - chapter 3
Arc341 building 3 spring 2019 lecture 4 - section active - chapter 3
 
Arc341 building 3 spring 2019 lecture 3 - vector-active - chapter 2
Arc341 building 3 spring 2019   lecture 3 - vector-active - chapter 2Arc341 building 3 spring 2019   lecture 3 - vector-active - chapter 2
Arc341 building 3 spring 2019 lecture 3 - vector-active - chapter 2
 
Arc341 building 3 spring 2019 lecture 2 - basics - chapter 0
Arc341 building 3 spring 2019   lecture 2 - basics - chapter 0Arc341 building 3 spring 2019   lecture 2 - basics - chapter 0
Arc341 building 3 spring 2019 lecture 2 - basics - chapter 0
 
Arc341 building 3 spring 2019 lecture 1 - introduction to structures
Arc341 building 3 spring 2019   lecture 1 - introduction to structuresArc341 building 3 spring 2019   lecture 1 - introduction to structures
Arc341 building 3 spring 2019 lecture 1 - introduction to structures
 
Fue theory 4 2018 lecture 5 - the formulation and analysis of architectural...
Fue theory 4 2018   lecture 5 - the formulation and analysis of architectural...Fue theory 4 2018   lecture 5 - the formulation and analysis of architectural...
Fue theory 4 2018 lecture 5 - the formulation and analysis of architectural...
 
Fue theory 4 2018 lecture 4 - the formulation and analysis of architectural...
Fue theory 4 2018   lecture 4 - the formulation and analysis of architectural...Fue theory 4 2018   lecture 4 - the formulation and analysis of architectural...
Fue theory 4 2018 lecture 4 - the formulation and analysis of architectural...
 
Fue theory 4 2018 lecture 3 - architectural timeline
Fue theory 4 2018   lecture 3 - architectural timelineFue theory 4 2018   lecture 3 - architectural timeline
Fue theory 4 2018 lecture 3 - architectural timeline
 
Fue theory 4 2018 lecture 2 - history of theory
Fue theory 4 2018   lecture 2 - history of theoryFue theory 4 2018   lecture 2 - history of theory
Fue theory 4 2018 lecture 2 - history of theory
 
Fue theory 4 2018 lecture 1- introduction
Fue theory 4 2018   lecture 1- introductionFue theory 4 2018   lecture 1- introduction
Fue theory 4 2018 lecture 1- introduction
 
Fue theory 4 2018 lecture 6 - synthesis of the design concept- different te...
Fue theory 4 2018   lecture 6 - synthesis of the design concept- different te...Fue theory 4 2018   lecture 6 - synthesis of the design concept- different te...
Fue theory 4 2018 lecture 6 - synthesis of the design concept- different te...
 
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
Arc 323 human studies in architecture fall 2018 lecture 9-topics 2
 
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1Arc 323 human studies in architecture fall 2018 lecture 8-topics 1
Arc 323 human studies in architecture fall 2018 lecture 8-topics 1
 

Recently uploaded

In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in RiyadhIn Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadhahmedjiabur940
 
Spring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers ParisSpring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers ParisPeclers Paris
 
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...samsungultra782445
 
Edward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky
 
Essential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideEssential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideDesign Studio UI UX
 
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
Spring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers ParisSpring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers ParisPeclers Paris
 
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制eqaqen
 
TRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptxTRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptxtrose8
 
Resume all my skills and educations and achievement
Resume all my skills and educations and  achievement Resume all my skills and educations and  achievement
Resume all my skills and educations and achievement 210303105569
 
NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...Amil baba
 
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...samsungultra782445
 
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样awasv46j
 
一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证
一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证
一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证khuurq8kz
 
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证wpkuukw
 
Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证eqaqen
 
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证eeanqy
 
Morgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity DesignMorgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity Design1508 A/S
 
422368378-Laos-Architecture.pdfmmmmkkkkmmm
422368378-Laos-Architecture.pdfmmmmkkkkmmm422368378-Laos-Architecture.pdfmmmmkkkkmmm
422368378-Laos-Architecture.pdfmmmmkkkkmmmKarenNares2
 

Recently uploaded (20)

In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in RiyadhIn Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
 
Spring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers ParisSpring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers Paris
 
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Jeddah +966572737505 <> buy cytotec <> unwanted kit Saudi A...
 
Edward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to Printing
 
Essential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideEssential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive Guide
 
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
 
Spring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers ParisSpring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers Paris
 
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
定(购)莫纳什大学毕业证(Monash毕业证)成绩单学位证专业定制
 
TRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptxTRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptx
 
Resume all my skills and educations and achievement
Resume all my skills and educations and  achievement Resume all my skills and educations and  achievement
Resume all my skills and educations and achievement
 
NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
NO1 Top Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
 
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
 
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
 
一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证
一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证
一比一原版澳洲堪培拉大学毕业证(UC毕业证书)毕业证成绩单留信认证
 
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
 
Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Semarang ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
 
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
怎样办理伦敦国王学院毕业证(KCL毕业证书)成绩单留信认证
 
Morgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity DesignMorgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity Design
 
422368378-Laos-Architecture.pdfmmmmkkkkmmm
422368378-Laos-Architecture.pdfmmmmkkkkmmm422368378-Laos-Architecture.pdfmmmmkkkkmmm
422368378-Laos-Architecture.pdfmmmmkkkkmmm
 

Quantity Surveying & Cost Planning

  • 1. © ValueMetric Consultants LLC (2016) Ayman El-Ghazzawi BSc MSc FRICS American University in Cairo Architectural Engineering Programme 11 October 2016
  • 2. © ValueMetric Consultants LLC (2016) 2 Introduction – terminology Benchmarking Cost Planning Building Economics Conclusion Q&A
  • 4. © ValueMetric Consultants LLC (2016) 4  Cost is a significant, if not essential part of a project  decides if the scheme is viable….. No Money  No Project  QS is responsible for all matters financial and commercial on a construction project  Triangle of Duties on a Project: COST QUALITY TIME Quantity Surveyor Project Manager Architect (Designer)
  • 5. © ValueMetric Consultants LLC (2016) 5 US Approach to Cost Management UK Approach to Cost Management Traditionally called a “Cost Estimator” Previously called a Quantity Surveyor, now more common to call Cost Manager Approach is led by Programme Led by Design Stages (e.g. RIBA) Use of cost-loaded programmes Use of Bills of Quantities to package works Method of Measurement: CSI Masterformat Method of Measurement: POMI, NRM Professional association: AACE Professional association: RICS Combine Cost & Time  Project Controls Separate Cost & Time: QS and PM
  • 6. © ValueMetric Consultants LLC (2016) 6 Provides an early, approximate vision of construction costs Helps in setting a project’s budget Used to commercially manage the pre-contract design Concept  Schematic  Detailed Design Provides an early warning of scope creep, monitors changes Can assist with setting sale prices Informs the financial P&L of a developer company Captures entire development costs  helps form package BOQs
  • 7. © ValueMetric Consultants LLC (2016) 7 Term Definition Cost actual price to be paid Value how much it is desired, price of what it’s worth Feasibility Estimate Establishes the overall viability of the project, return on investment Order of Magnitude Estimate Reflects a particular design stage, e.g. concept, schematic, detailed Cost Plan Reflects a particular design stage, e.g. concept, schematic, detailed
  • 8. © ValueMetric Consultants LLC (2016) 8 Term Definition Cost Model Cost-led, does not reflect a particular design, allows for varying elements Cost Analysis Estimates the cost of construction of particular elements or portion of the works Cost Report Tracks the overall project costs monthly, monitors commercial performance
  • 9. 9 Benchmarking and Order of Cost Estimates (OCE)
  • 10. © ValueMetric Consultants LLC (2016) 10 Highest level of cost estimating, lowest accuracy Usually based on functional units or built-up area Examples of functional units: › Hospitals EGP / bed › Hotels EGP / key › Schools EGP / student › Residential EGP / m2 (or per habitable room) › Office Buildings EGP / gross lettable area
  • 11. © ValueMetric Consultants LLC (2016) 11 OCE: Order of Cost Estimate – most preliminary cost plan Must find out: › Type of building to be built (e.g. hotel) › Expected number of functional units (e.g. nr of keys) › When it is expected to be built (e.g. two years from now) › Outline specification level (e.g. high/med/low quality, 4*, 5*) › Location where it is to be built
  • 12. © ValueMetric Consultants LLC (2016) 12 Source: Spon’s Architects’and Builders’ Price Book 2009
  • 13. © ValueMetric Consultants LLC (2016) 13 Begin with a high level benchmark estimate by function Adjust your estimate by: › Geographical variation › Inflation indices Multiply by number of functional units Add contingency, VAT, etc. Emphasise that Tolerance / accuracy is low Use an estimating resource – your own project database or price book
  • 14. © ValueMetric Consultants LLC (2016) 14 Source: Spon’s Architects’and Builders’ Price Book (2009)
  • 15. © ValueMetric Consultants LLC (2016) 15
  • 16. © ValueMetric Consultants LLC (2016) 16
  • 17. © ValueMetric Consultants LLC (2016) 17
  • 19. © ValueMetric Consultants LLC (2016) 19 A document that details costs, usually developed from a preliminary benchmark estimate, based on elemental or functional units that reflects the Design Team’s intentions Follows the project’s design stages, e.g. RIBA Work Stages Sets a plan to spend costs, helps with purchasing and cost control As cost plan develops, accuracy is improved: LE/function  LE/m2  Detailed LE costs based on qtys
  • 20. © ValueMetric Consultants LLC (2016) 20 RIBA Work Stage Work Stage Description A Appraisal / Feasibility B Strategic Briefing C Outline Proposals D Detailed Proposals E Final Proposals F Production Information G Tender Documentation H Tender Action J Mobilisation K Construction  Practical Completion L After Practical Completion
  • 21. © ValueMetric Consultants LLC (2016) 21 COST PLANNING STAGES Concept 30% Schematic 60% Detailed 90% COST PLAN Confirm Budget, Cost Limits COST PLAN Set Cost Targets on Schematic COST PLAN Set Cost Targets on Detailed SET BUDGET Proceed to Tender BOQ Remedial Action: Value Engineering Pro-activeChangeControl
  • 22. © ValueMetric Consultants LLC (2016) 22 Similar to OCE, but on an elemental level Uses previous projects from a database, or pricing book such as Spons Adjust elements to suit the project being priced › E.g. EGP/m2 will differ whether it is steel or concrete frame Ensure it is a like-for-like benchmark comparison: › Use same area types (BUA, NIA, etc.) › Exclude sub-structure, earth work, external works › Preliminaries (indirect costs), taxes and the like
  • 23. © ValueMetric Consultants LLC (2016) 23 OCE or preliminary cost plan ± 25% to 30% tolerance › EGP / functional unit Concept Cost Plan ± 15% to 25% tolerance › EGP / m2, based on floor areas Schematic Cost Plan ± 10% to 15% tolerance › EGP / m2, based on floor areas, with some systems allowed for based on evolving design (e.g. district cooling v split units) Detailed Cost Plan ± 5% to 10% tolerance › EGP / m2, based on quantities and unit rates
  • 24. © ValueMetric Consultants LLC (2016) 24
  • 25. © ValueMetric Consultants LLC (2016) 25 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 EGP/m2 Electrical Engineering Works Mechanical Engineering Works Conveying Systems Special Construction Furnishings Equipment Specialties Finishes Doors and Windows Thermal and Moisture Protection Wood and Plastics Metal Works Masonry Concrete Works Site Construction General Requirements
  • 27. © ValueMetric Consultants LLC (2016) 27 
  • 28. © ValueMetric Consultants LLC (2016) 28 For the following two projects, A and B, calculate: 1. Floor Area 2. Perimeter length 3. Wall Area 4. Wall-to-floor ratio
  • 29. © ValueMetric Consultants LLC (2016) 29 For the following two projects, A and B, calculate: 1. Floor Area 2. Perimeter length 3. Wall Area 4. Wall-to-floor ratio
  • 30. © ValueMetric Consultants LLC (2016) 30  Efficiency comes form plan shapes that are square (or circle)  Consider whether it is better internal division (e.g. triangular plan)  Less efficient shapes require more structure  Consider a better enclosing wall to area ratio  Core and circulation affected by choice of plan shape  Short assessment
  • 31. © ValueMetric Consultants LLC (2016) 31 For the following three Plan Shapes A, B and C, calculate: 1. Floor Area 3. Wall Area 2. Perimeter length 4. Wall-to-floor ratio
  • 32. © ValueMetric Consultants LLC (2016) 32 For the following three Plan Shapes A, B and C, calculate: 1. Floor Area 3. Wall Area 2. Perimeter length 4. Wall-to-floor ratio
  • 33. © ValueMetric Consultants LLC (2016) 33 
  • 34. © ValueMetric Consultants LLC (2016) 34 
  • 35. © ValueMetric Consultants LLC (2016) 35  Tall structures are more costly – step changes in height mean it is not a uniform relationship of height to cost  Storey heights can be cost sensitive  VT costs to be considered  More engineering costs for FP, services performance  Wider and more circulation space needed  Temporary works, lifting, etc. more expensive  Wind load will affect structural design
  • 36. © ValueMetric Consultants LLC (2016) 36  Building arrangement affects the cost of construction  Consider: › Sharing elements between buildings › Cost and of constructing › Ability to construct: Buildability  For the four arrangements shown, 1. Which is most desirable? 2. Which is most efficient? 3. Which has least “buildability”?
  • 38. © ValueMetric Consultants LLC (2016) 38 Benchmarking is important to compare projects › Expect differences and variation – explain them › Separate abnormals (sub-structure, external works, infra, etc.) Cost Plans are approximate, and not accurate by nature Accuracy improves as design develops (± % tolerance reduces) Building shape, size and arrangement all affect costs  understand how these affect your cost plan Look at other efficiency parameters (net : gross area)