SlideShare a Scribd company logo
1 of 6
Download to read offline
Analysis of Power Transformer failure in
Transmission utilities
Shrikant S.Rajurkar
Superintending Engineer (Trans. O&M)
Maharashtra State Electricity Transmission Co Ltd (MSETCL)
Mumbai, India
e-mail address:ssrajurkar@gmail.com
Amit R. Kulkarni
Assistant Engineer (Trans. O&M)
Maharashtra State Electricity Transmission Co Ltd (MSETCL)
Mumbai, India
e-mail address: amk4.ind@gmail.com
Abstract—This paper focuses on failure of EHV transformers in
transmission utilities along with important reasons for failure of
the same in brief. This further covers case study of failure of
transformer in one of the region in the state of Maharashtra
along with remedial measures to be taken to avoid the same. It
also discusses in brief various activities needed to be taken in
order to effectively handle the issue of power transformer failure
Keywords-Transformer,transformer oil,oil insulation,
transformer winding, tranformer cores
I. INTRODUCTION
Today Indian economy is amongst the fastest growing
economy in the world despite of global financial meltdown. It
is expected that Indian economy shall continue to grow
approximately at the rate of 8-9 % in the years to come. India
is amongst the leading countries in the world to attract foreign
direct investment. India’s manufacturing sector, heavy
industries, various global service centres and booming high
tech software are all dependent on reliable power supply. This
underlines the principle that ‘No Power-No Business’. This
makes it utmost important that ‘Transformers’ the heart of
substation must function reliably 24x7.Ministry of Power’s
ambitious initiatives like Rajiv Gandhi Gramin Vidyutikaran
Yojana(RGGVY), Power to all by 2012 make it challenging
task to maintain reliability of supply. India faces major
challenge both today and in the future for the growth and
improvement in reliability of its electrical infrastructure
including that of transformer. Failures of critical transformer
assets not only impact industries, other consumer categories
affecting economy of the country but also have social and
political ramifications.
II. MSETCL INFRASTRUCTURE
MSETCL is the largest State Transmission Utility (STU)
in the country. MSETCL infrastructure is shown in Table I. It
Jayant G.Nandapurkar
Deputy Executive Engineer
Maharashtra State Electricity Transmission Co Ltd (MSETCL)
T&C Circle Nagpur
e-mail address: jgnandapurkar@gmail.com
is the only state utility operating and maintaining +/- 500kV,
1500MW Chandrapu-Padghe HVDC bipole transmission
system for large power haulage of the order of 1500 MW from
generation rich eastern part of the state to load rich western
part covering a distance of about 750 kms approximately.
MSETCL’s transmission system is capable of handling 18,500
MW of electric power. It has transmitted 97,189 MUs in the
year 2009-10.MSETCL has ambitious infrastructure
development plan of around 11,000 Cr rupees. MSETCL has
total EHV transformer population of around 1356 as on
31.03.2010. Out of those 318 numbers are ICTs contributing
to 31191 MVA capacity. There are 84 numbers of 400 kV
transformers and 234 numbers of 220 kV transformers. Apart
from this, MSETCL system also has 16 numbers of HVDC
converter transformers including two numbers of spare
converter transformers at each location.
TABLE I: MSETCL Infrastructure as on 31.03.2010.
VOLTAGE
LEVEL
EHV
SUBSTATION
TRANSFORMATION
CAPACITY
EHV
LINES
(CKT
KM)
500kV HVDC 2 3582 1504
400KV 21 13165 6562
220KV 149 31585 12356
132KV 246 19867 11064
110KV 33 2080 1698
100KV 35 2373 678
66KV 34 1139 3270
TOTAL 520 73791 37133
16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 180
Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
III. MSETCL TRANSFORMER FAILURE DETAILS IN
RECENT YEARS
Table I indicates that total transformation capacity in
MSETCL as on 31.03.2010 is 73,791 MVA. This emphasises
the fact that reliable operation of these transformers is of
utmost importance. To maintain reliability it is essential to
know reasons for failure of maintaining reliability and ways to
overcome the causes of failure. In order to assess failure of
transformers it is essential to know exactly the reasons behind
the failure. Following section gives methodology developed by
MSETCL based on practical experience to pinpoint the cause
of failure for EHV transformers. The risk of a transformer
failure is actually two-dimensional, the frequency of failure and
the severity of failure.Fig.1 gives details of transformer failure
in MSETCL during 2008-09, 09-10 (Upto June 2010)
Transformer failure in MSETCL during 08-09,09-
10 and upto June 10
21
21.5
22
22.5
23
23.5
24
24.5
0 to 5 5 to 15 15 to 25 above 25
Age of Transformer
Numberoftransformers
failed
Fig. 1.Agewise transformer failure details in MSETCL in recent past.
A. Analysis of transformer failure in Nagpur zone of
MSETCL
Nagpur zone has total of 72 EHV substations voltage
levelwise breakup for those is shown in fig.2.
Fig. 2.Details of EHV levelwise substations in Nagpur zone of MSETCL.
As MSETCL system is closely knit with MSEDCL system in
the state of Maharashtra,fig.3 shows how MSETCL system is
interfaced with MSEDCL system as far as transformer
distribution in Nagpur zone is concerned along with details of
number of EHV substations as per interfacing with voltage
level wise category.
There are total of 187 EHV transformers in Nagpur zone
153 of them are EHV transformers and 34 of them are ICTs
contributing to about 18% as shown in fig.4.
.
Fig. 3.Interface between MSETCL and MSEDCL system in Nagpur zone
Fig. 4.EHV transformer break up as ICTs and Non-ICTs in MSETCL system
in Nagpur zone
Transformer failure analysis in Nagpur zone covered under
this section considers duration from 2005-06 to 2008-09.There
were total of 27 transformer failures during this period. Fig.5
indicates details of number of transformer failures against year.
As MSETCL system has transformers of different MVA
capacities, for the purpose of analysis attempt was also made to
categorise MVA group wise transformer failure as shown in
fig.6.In this three categories of transformers namely
transformers having capacities 10 MVA andbelow,25 MVA
and above and 100 MVA and above are considered.
Fig. 5. Number of EHV transformer failures against year in MSETCL system
in Nagpur zone.
Breakup showing interfacing with Distribution Syatem
(Total 71 S/Ss)
5
15
20
31
0
5
10
15
20
25
30
35
40
Only EHV Level Only 33 KV Level Only 11 KV Level Both 33 & 11 KV
Level
Category
NoofEHVS/Ss
Yearwise T/F Failures (Total 27 Nos)
9
7
5
6
0
2
4
6
8
10
05-06 06-07 07-08 08-09
Year
NoofT/Ffailures
3
18
26 25
0
5
10
15
20
25
30
400 KV 220 KV 132 KV 66 KV
NoofS/Ss
Voltage Level in KV
Levelwise break-up of EHV S/Ss (Total 71 Nos)
16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 181
Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
Fig. 6. MVA groupwise transformer failures in MSETCL system in Nagpur
zone.
It is well known fact that fault level at substation also has
impact on proper functioning of transformers, so analytics is
also developed to categorise transformers in high, medium and
low fault level groups as shown in fig.7.
[7].
IV. USING THE TEMPLATE
Fig. 7. Fault level wise transformer failures in MSETCL system in Nagpur
zone.
There can be variety of reasons for failure of transformers,
some of the important ones are listed below
i)Insulation failure
ii)Design and Manufacturing default
iii)Oil contamination
iv)Overloading
v)Fire or Explosion
vi)Line surges
vii)Lightening
viii)Moisture ingress
Apart from this Aging, poor O&M practices, loose
connection, poor repairs etc can also result in failure of
transformers.Fig.8 shows transformer failure classification
based on cause of fault.
Fig. 8. Fault cause wise transformer failures in MSETCL system in Nagpur
As major responsibility of transmission utilities is to carry
bulk power from generating stations and bringing it to load
centres thus transmission utilities work in proximity with
distribution network. This may result many times into
transformers interfacing distribution network experiencing
more number of faults for longer duration further resulting
into failure of EHV transformers. This is indicated by fig.9
and fig.10.These figures indicate that EHV transformers of
132 /11kV and 66/11kV which are in close proximity with
distribution system have more number of failures compared to
other categories.Fig.9 indicates that out of 27 number of EHV
transformers in Nagpur zone 10 number of transformers are
132/11kV and other 10 are 66/11kV transformers contributing
to approximately 62% of the total transformer failures in the
zone.
Fig. 9. Voltage ratio wise transformer failures in MSETCL system in Nagpur
zone.
Fig. 10. Voltage ratio wise transformer failure rate in MSETCL system in
Nagpur zone.
B. Failure of HVDC Converter transformer
The converter transformer are single phase three winding
units of 298.6 MVA capacity each and having line winding of
3/400 kV and Delta and Star connected valve windings of
3211211− kV voltage rating respectively. Out of total of
16 numbers of transformers,8 numbers are supplied by BHEL-
India and 8 numbers by ABB Sweden. After bipolar operation
for a few months, failures of converter transformers at
Chandrapur and Padghe started from June 2001.Nine
transformers have failed, out of Nine transformers four
MVA Groupwise T/F Failures
12
14
1
0
2
4
6
8
10
12
14
16
<=10 <=25 100+
MVA Group
NoofT/FFailures
Falut Level wise Break-up of T/F Failures
16
6
5
0
2
4
6
8
10
12
14
16
18
High Medium Low
Category of Fault Level
NoofFailures
Fault cause wise breakup No of T/F Failures
9
2
3
4
9
0
2
4
6
8
10
12
Ageing Lightning Mfg defect Repair defect OG Fdr Flt
Fault Category
NoofT/FFailures
Voltage Ratiowise T/F Failures
1
4
10
2
10
0
2
4
6
8
10
12
220/132 132/33 132/11 66/33 66/11
Ratio in KV
NoofT/Ffailures
Voltage Ratio wise Failure Rate
15
50
24
13
49
1 4
10
2
10
6.67 8.00
41.67
15.38
20.41
0
10
20
30
40
50
60
Population 15 50 24 13 49
No of Failures 1 4 10 2 10
Faulure Rate 6.67 8.00 41.67 15.38 20.41
220/132 132/33 132/11 66/33 66/11
16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 182
Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
numbers are from BHEL-India and five numbers are from
ABB Sweden. Out of these, failed transformers one
transformer each of BHEL and ABB make which has failed,
was repaired earlier. In all the cases, transformers connected to
star winding have failed [1].
The failure was analysed considering the following:
• Frequent and high amplitude transients.
• Failure occurred in normal operation, however no
direct cause for breakdown was identified.
• Turn to turn breakdown in star winding.
• No breakdown paths to earth in the transformer.
C. Detail investigation of converter transformer failure in
MSETCL
In process to carry out detail investigation of failure of
converter transformer the design was scrutinised with design
tools.The voltage transient behaviour of the winding was
evaluated by using both calculations and measurements. The
strength of the insulation against repetitive transients was also
verified and concluded that no design deficiency is causing the
breakdowns.
i) Copper Sulphide Deposits
Inspection of the winding when disassembled turn by turn
showed that at some locations there was a shiny deposits on
spacers and conductor insulation. These deposits were
identified as Copper Sulphide (CU2 S).
ii)Influence on Dielectric Strength
The electric conductivity of CU2 S is significantly higher than
the conductivity of paper and oil. This means that the
presence of CU2 S may change the electric field distribution.
The series of tests were performed on both CU2 S
contaminated material and unaffected materials. The result of
these tests shows that:
• Partial Discharge (PD) initiation voltage and the
breakdown voltage of the CU2 S coated material are
significantly reduced as compared to the uncoated
material.
• Uncoated and unaffected insulation has the same
strength as brand new insulation.
iii)Impact of Transients
CU2 S lowers the PD- initiation level Depositions of copper
sulphide on the winding alone are not sufficient to create a
short circuit or partial discharge between two turns. For
either of these two happens the insulation has to be further
degraded by frequent repetitive transients. Such transients
may occur in HVDC applications, since HVDC transformer is
exposed to a commutation process when the current is
transferred from one phase to another. A rapid increase in the
terminal voltage during this process results in fast transients
in the winding which locally stress the insulation.
The converter normally operates at the firing angle (α) of 15°
but α = 90° operation during line faults though rare, cause
very high stresses on the turn –to turn insulations. This
operation occurs during line faults.
iv) Reasons for formation of Copper Sulphide ( CU2 S)
Formation of CU2 S is a very interesting phenomenon. The
transformer oil is basically highly refined mineral oil and
consists of mainly mixture of hydro-carbons and some other
compounds, containing Oxygen, Nitrogen and Sulphur .Most
of the compounds containing sulphur can react with copper
under extreme conditions and form copper sulphide deposits.
After investigation M/s ABB arrived at final conclusion as
follows:
Aggressive oil produces copper sulphide
Copper Sulphide weakens the insulation
Transients arising due to α =90° operation or transients
from continuous higher MVAR operation are sufficient to
initiate partial discharges. Repetitive transients further
degrade the insulation.
A partial discharge in sufficiently degraded insulation, will
not extinguish.
When the insulation is sufficiently degraded, PD will
continue at normal service voltage levels.
A partial discharge leads to a turn to turn fault and
Transformer breakdown.
Finally the detailed investigations revealed that the
series failure of HVDC transformer occurred mainly due to
insulating oil problem. M/sABB after studying the problem
suggested to use passivated oil for new or repaired unit and to
add passivator in the oil of in service converter transformer.
After taking remedial measures no converter transformer
failure is observed. These measures have resulted into
enhancing the availability of HVDC system. Currently HVDC
system availability is as per the standards decided by MERC.
IV. MEASURES TAKEN FOR REDUCTION OF
TRANSFORMER FAILURES IN MSETCL
A. Measurement of Capacitance and Tanδ
Capacitance and Tanδ measurement of bushings gives an
indication of the quality of insulation in the bushing[2]. In
MSETCL practice is followed to replace the bushing if value
of Tanδ is found to be greater than 0.007.If the trend in
variation of Capacitance and Tanδ values monitored is
16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 183
Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
observed to be abnormal decision of replacing of bushing is
taken. The same technique is used to know healthiness of
ground and interwinding insulation of transformer.MSETCL
has a practice of yearly monitoring of Capacitance and Tanδ
measurement.
B. Provision of High set relay for EHV transformers
High set relays are provided on distribution side feeders to
avoid unwarranted trippings/failure of transformers. For a
closeup fault on distribution feeder, the high set relays are
expected to operate to clear the fault and avoid the reflection
of the same on transformer. The high set relays being
instantaneous helps to isolate the faulty feeder
quickly.MSETCL has provided high set relays on distribution
side feeders emanating from EHV substations and this has
helped to reduce the incidents of transformer tripping/failure
due to distribution related faults.
C. Independent operation of EHV transformers
Based on the failure analysis of transformers, it is noticed that
the failures of EHV transformers feeding the distribution
network are more than that of ICTs. After detailed analysis
and studies it has been decided to operate the EHV
transformers in independent mode rather than parallel
operation as far as possible where the load can be managed.
This has helped in reducing inadvertent trippings and failure
of transformers also to some extent.
D. Dissolved gas analysis(DGA)
Dissolved Gas Analysis (DGA) is one of the most widely
used diagnostic tools for detecting and evaluating faults in
electrical equipment. However the interpretation of DGA
results is often complex and should always be done with care,
involving experienced insulation maintenance
personnel.(Ref:IEC 60599:1999).This technique is mainly
useful for the transformers filled with mineral insulating oil
and insulated with cellulosic paper or press-board-based solid
insulation. This process mainly involves steps
i)Knowing reasons for generation of gases:
Fault gases are produced by degradation of the transformer oil
and other insulating materials such as cellulose. In the
presence of an active fault, the rate of oil and cellulose
degradation is significantly increased, and the types of
degradation products formed will vary with the nature and
severity of the fault.
ii)Interpretation of dissolved gas analysis
Interpretation of dissolved gas analysis is generally done based
on standards like IS. 10593:1992, IEC 60599:1999,
ASTMD3612.Apart from this it is also important to see
Whether the measured values are well above the sensitivity of
the analytical methods and equipment and to check whether
gas concentration is high enough to consider for further
investigation.
Inputs on following historical information is vital in carrying
out the DGA interpretation.
1) How old Is the transformer?
2) Did a bushing fail at some point?
3) Did the transformer fail at some time?
4) Is the unit heavily loaded as of today or in past?
5) Has the transformer been repaired after a failure?
6) Has the DGA tests been performed in past?
7) Have the fault gases risen suddenly?
8) Has the oil been degassed?
The method in IS 10593:1992 was based on IEC Pub 599:
1978, which has since been modified as IEC 60599.MSETCL
has a practice of taking yearly DGA and based on DGA results
appropriate action to safeguard the transformer is taken.
Portable DGA kit procured by MSETCL works on photo
acoustic principle has capable of detecting concentration of 8
fault gases alongwith the moisture content. MSETCL has also
provided online DGA monitoring equipment on experimental
basis on some of the units.
Apart from above DC resistance measurement and
determination of Polarization Index (PI) corresponding to 60s.
and 600 s, SFRA etc. are the other maintenance practices
followed at MSETCL in order to minimise transformer failure
rate. MSETCL follows the practice of recording SFRA during
testing at factory before despatch of the transformers and
confirming healthiness of transformer by recording SFRA at
site before commissioning of the transformer.
Further MSETCL has taken a policy decision to provide
Nitrogen injection type fire protection system for all
transformers of rating 100 MVA and above to prevent the
transformers from catching fire during failure incident.
It is observed that with above mentioned measures taken by
MSETCL number of instances of EHV transformer failure
could be controlled, further helping in improvement in the
reliability of supply.
V. CONCLUSIONS
This paper discusses in short, some of the important reasons
for the power transformer failure alongwith methodology to
classify transformer failures depending on various factors.
Based on the data it can be said that many times transformers
interfacing distribution network experience more number of
faults for longer duration further resulting into failure of EHV
transformers. This paper also discussed some of the preventive
methods in brief to minimise the rate of transformer failure.
16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 184
Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
ACKNOWLEDGMENT
Authors are thankful to management of MSETCL for
permitting them to submit the paper and for their
encouragement throughout the process.
REFERENCES
[1] P.R.Gange,S.A.Jaolikar,S.SRajurkar,R.S.Parulkar“Operational
experiences of Chandrapur-Padghe HVDC bipole project” CIGRE
International conference on HVDC Applications,Bangalore,2005.
[2] G.N.Mathur and R. S.Chadha. Sneddon, “EHV substation equipment
maintenance”,publication No.24,Central Board of Irrigation and Power
New Delhi 2005,pp. 71–75.
BIOGRAPHIES
Rajurkar S.S. He graduated from Nagpur University in the year 1982.He also
obtained M.Tech. (Electrical) degree from Nagpur University in the year
1984.He joined Maharashtra State Electricity Board (MSEB) in the year 1984
and working in Maharashtra State Electricity Transmission Company Ltd
(MSETCL) after restructuring of erstwhile MSEB. He is associated with
400kV and HVDC system planning, Operation and maintenance work for the
same. He is presently working in Transmission O&M department at
Corporate Office of MSETCL in Mumbai. His special fields of interest
include power system protection, power system stability, HVDC applications.
Jayant G. Nandapurkar He received his B.E. (Electrical) from Govt.
College of Engineering, Aurangabad in 1979 He has special interest in Power
System protection, Short circuit studies, Load Flow Studies, Power System
Harmonics. Worked as Testing & Commissioning engineer with erstwhile
Maharashtra State Electricity Board (MSEB).Member of expert study group
on protection issues of MSETCL.He is member of expert group formed for
review of relay settings of the protection equipment of MSETCL.Presently
working as Dy. Executive Engineer under Testing & Communication Circle
Nagpur with Maharashtra State Electricity Transmission Co. Ltd. (MSETCL.
Amit Kulkarni He graduated from Shivaji University Kolhapur in the year
1999. He also obtained M.E. (Power System) from Pune University in 2004
and worked in project on power system stability at Electrical Engineering
Department at IIT Bombay. He joined Maharashtra State Electricity
Transmission Company Ltd (MSETCL) in 2006.He is presently working in
the Corporate Office of MSETCL in Mumbai. His special fields of interest
include power system stability, power system operation and control, power
system protection and FACTS.
16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 185
Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.

More Related Content

What's hot

Enhancement of power quality using microprocessor based shunt active power fi...
Enhancement of power quality using microprocessor based shunt active power fi...Enhancement of power quality using microprocessor based shunt active power fi...
Enhancement of power quality using microprocessor based shunt active power fi...IJECEIAES
 
Efficacy of Facts in Power Oscillation Damping and Renewable Integration
Efficacy of Facts in Power Oscillation Damping and Renewable IntegrationEfficacy of Facts in Power Oscillation Damping and Renewable Integration
Efficacy of Facts in Power Oscillation Damping and Renewable IntegrationIOSRJEEE
 
ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...
ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...
ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...IAEME Publication
 
IRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieW
IRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieWIRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieW
IRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieWIRJET Journal
 
Modified Single Stage AC-AC Converter
Modified Single Stage AC-AC ConverterModified Single Stage AC-AC Converter
Modified Single Stage AC-AC ConverterIAES-IJPEDS
 
SHE Control for PV System Connected to the Grid
SHE Control for PV System Connected to the GridSHE Control for PV System Connected to the Grid
SHE Control for PV System Connected to the GridTELKOMNIKA JOURNAL
 
Power Quality Improvement by SRF Based Control using D-STATCOM
Power Quality Improvement by  SRF Based Control using D-STATCOMPower Quality Improvement by  SRF Based Control using D-STATCOM
Power Quality Improvement by SRF Based Control using D-STATCOMIRJET Journal
 
IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...
IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...
IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...IRJET Journal
 
Minimization of Power Loss in Distribution System using SVC and STATCOM
Minimization of Power Loss in Distribution System using SVC and STATCOMMinimization of Power Loss in Distribution System using SVC and STATCOM
Minimization of Power Loss in Distribution System using SVC and STATCOMIRJET Journal
 
Ann based voltage stability margin assessment
Ann based voltage stability margin assessmentAnn based voltage stability margin assessment
Ann based voltage stability margin assessmentNaganathan G Sesaiyan
 
IRJET - Improvement of Power Factor and Efficiency of Three Phase Inducti...
IRJET -  	  Improvement of Power Factor and Efficiency of Three Phase Inducti...IRJET -  	  Improvement of Power Factor and Efficiency of Three Phase Inducti...
IRJET - Improvement of Power Factor and Efficiency of Three Phase Inducti...IRJET Journal
 
Online voltage stability margin assessment
Online voltage stability margin assessmentOnline voltage stability margin assessment
Online voltage stability margin assessmentNaganathan G Sesaiyan
 
Single Phase Matrix Converter for Input Power Factor Improvement
Single Phase Matrix Converter for Input Power Factor ImprovementSingle Phase Matrix Converter for Input Power Factor Improvement
Single Phase Matrix Converter for Input Power Factor Improvementiosrjce
 

What's hot (20)

Enhancement of power quality using microprocessor based shunt active power fi...
Enhancement of power quality using microprocessor based shunt active power fi...Enhancement of power quality using microprocessor based shunt active power fi...
Enhancement of power quality using microprocessor based shunt active power fi...
 
Az044319323
Az044319323Az044319323
Az044319323
 
Efficacy of Facts in Power Oscillation Damping and Renewable Integration
Efficacy of Facts in Power Oscillation Damping and Renewable IntegrationEfficacy of Facts in Power Oscillation Damping and Renewable Integration
Efficacy of Facts in Power Oscillation Damping and Renewable Integration
 
ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...
ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...
ANALYSIS OF VARIOUS COMPENSATION DEVICES FOR POWER QUALITY IMPROVEMENT IN WIN...
 
D010223139
D010223139D010223139
D010223139
 
Multi-machine transient stability by using static synchronous series compensator
Multi-machine transient stability by using static synchronous series compensatorMulti-machine transient stability by using static synchronous series compensator
Multi-machine transient stability by using static synchronous series compensator
 
IRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieW
IRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieWIRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieW
IRJET- Enhancement of Power Flow Capability in Power System using UPFC- A RevieW
 
Modified Single Stage AC-AC Converter
Modified Single Stage AC-AC ConverterModified Single Stage AC-AC Converter
Modified Single Stage AC-AC Converter
 
40220140505010
4022014050501040220140505010
40220140505010
 
SHE Control for PV System Connected to the Grid
SHE Control for PV System Connected to the GridSHE Control for PV System Connected to the Grid
SHE Control for PV System Connected to the Grid
 
Power Quality Improvement by SRF Based Control using D-STATCOM
Power Quality Improvement by  SRF Based Control using D-STATCOMPower Quality Improvement by  SRF Based Control using D-STATCOM
Power Quality Improvement by SRF Based Control using D-STATCOM
 
IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...
IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...
IRJET - Comparison of Different Third Harmonic Injected PWM Strategies for 5-...
 
Implementation of the conventional seven-level single-phase symmetrical casca...
Implementation of the conventional seven-level single-phase symmetrical casca...Implementation of the conventional seven-level single-phase symmetrical casca...
Implementation of the conventional seven-level single-phase symmetrical casca...
 
Minimization of Power Loss in Distribution System using SVC and STATCOM
Minimization of Power Loss in Distribution System using SVC and STATCOMMinimization of Power Loss in Distribution System using SVC and STATCOM
Minimization of Power Loss in Distribution System using SVC and STATCOM
 
Asymmetric hybrid multilevel inverter with reduced harmonic using hybrid modu...
Asymmetric hybrid multilevel inverter with reduced harmonic using hybrid modu...Asymmetric hybrid multilevel inverter with reduced harmonic using hybrid modu...
Asymmetric hybrid multilevel inverter with reduced harmonic using hybrid modu...
 
Ann based voltage stability margin assessment
Ann based voltage stability margin assessmentAnn based voltage stability margin assessment
Ann based voltage stability margin assessment
 
D1072535
D1072535D1072535
D1072535
 
IRJET - Improvement of Power Factor and Efficiency of Three Phase Inducti...
IRJET -  	  Improvement of Power Factor and Efficiency of Three Phase Inducti...IRJET -  	  Improvement of Power Factor and Efficiency of Three Phase Inducti...
IRJET - Improvement of Power Factor and Efficiency of Three Phase Inducti...
 
Online voltage stability margin assessment
Online voltage stability margin assessmentOnline voltage stability margin assessment
Online voltage stability margin assessment
 
Single Phase Matrix Converter for Input Power Factor Improvement
Single Phase Matrix Converter for Input Power Factor ImprovementSingle Phase Matrix Converter for Input Power Factor Improvement
Single Phase Matrix Converter for Input Power Factor Improvement
 

Similar to Analysis of transformer failure sample papers 2

Understanding operation of shunt capacitors and oltc for transmission
Understanding operation of shunt capacitors and oltc for transmissionUnderstanding operation of shunt capacitors and oltc for transmission
Understanding operation of shunt capacitors and oltc for transmissionIAEME Publication
 
Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...
Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...
Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...IJPEDS-IAES
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...IAEME Publication
 
BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments Anuj Gupta
 
Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...
Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...
Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...IJECEIAES
 
Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...
Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...
Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...IJPEDS-IAES
 
Cost implication of Line Voltage variation on Three Phase Induction Motor ope...
Cost implication of Line Voltage variation on Three Phase Induction Motor ope...Cost implication of Line Voltage variation on Three Phase Induction Motor ope...
Cost implication of Line Voltage variation on Three Phase Induction Motor ope...TELKOMNIKA JOURNAL
 
TRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSS
TRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSSTRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSS
TRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSSIAEME Publication
 
Improvements the direct torque control performance for an induction machine u...
Improvements the direct torque control performance for an induction machine u...Improvements the direct torque control performance for an induction machine u...
Improvements the direct torque control performance for an induction machine u...IJECEIAES
 
The scheme of three level inverters based on svpwm overmodulation technique
The scheme of three level inverters based on svpwm overmodulation techniqueThe scheme of three level inverters based on svpwm overmodulation technique
The scheme of three level inverters based on svpwm overmodulation techniqueIAEME Publication
 
Application of single phase matrix converter topology to an uninterruptible p...
Application of single phase matrix converter topology to an uninterruptible p...Application of single phase matrix converter topology to an uninterruptible p...
Application of single phase matrix converter topology to an uninterruptible p...eSAT Publishing House
 
Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...
Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...
Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...IAES-IJPEDS
 
IRJET- Automatic EB DG Switiching Operation using PLC and HMI
IRJET-  	  Automatic EB DG Switiching Operation using PLC and HMIIRJET-  	  Automatic EB DG Switiching Operation using PLC and HMI
IRJET- Automatic EB DG Switiching Operation using PLC and HMIIRJET Journal
 
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space ApproachReliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space ApproachIJERA Editor
 

Similar to Analysis of transformer failure sample papers 2 (20)

Understanding operation of shunt capacitors and oltc for transmission
Understanding operation of shunt capacitors and oltc for transmissionUnderstanding operation of shunt capacitors and oltc for transmission
Understanding operation of shunt capacitors and oltc for transmission
 
Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...
Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...
Enhanced Torque Control and Reduced Switching Frequency in Direct Torque Cont...
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
 
BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments
 
Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...
Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...
Modulation Index Variation Effect on Harmonic Behavior of Fifteen Multilevel ...
 
Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...
Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...
Vector Control of Three-Phase Induction Motor with Two Stator Phases Open-Cir...
 
Cost implication of Line Voltage variation on Three Phase Induction Motor ope...
Cost implication of Line Voltage variation on Three Phase Induction Motor ope...Cost implication of Line Voltage variation on Three Phase Induction Motor ope...
Cost implication of Line Voltage variation on Three Phase Induction Motor ope...
 
Carrier Shifting Algorithms for the Mitigation of Circulating Current in Diod...
Carrier Shifting Algorithms for the Mitigation of Circulating Current in Diod...Carrier Shifting Algorithms for the Mitigation of Circulating Current in Diod...
Carrier Shifting Algorithms for the Mitigation of Circulating Current in Diod...
 
TRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSS
TRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSSTRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSS
TRANSIENT STABILITY ENHANCEMENT BY USING DSSC AND PSS
 
A review of direct torque control development in various multilevel inverter ...
A review of direct torque control development in various multilevel inverter ...A review of direct torque control development in various multilevel inverter ...
A review of direct torque control development in various multilevel inverter ...
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
Eo34861869
Eo34861869Eo34861869
Eo34861869
 
Improvements the direct torque control performance for an induction machine u...
Improvements the direct torque control performance for an induction machine u...Improvements the direct torque control performance for an induction machine u...
Improvements the direct torque control performance for an induction machine u...
 
40220140504010
4022014050401040220140504010
40220140504010
 
The scheme of three level inverters based on svpwm overmodulation technique
The scheme of three level inverters based on svpwm overmodulation techniqueThe scheme of three level inverters based on svpwm overmodulation technique
The scheme of three level inverters based on svpwm overmodulation technique
 
Application of single phase matrix converter topology to an uninterruptible p...
Application of single phase matrix converter topology to an uninterruptible p...Application of single phase matrix converter topology to an uninterruptible p...
Application of single phase matrix converter topology to an uninterruptible p...
 
Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...
Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...
Interleaved Boost Converter Fed with PV for Induction Motor/Agricultural Appl...
 
IRJET- Automatic EB DG Switiching Operation using PLC and HMI
IRJET-  	  Automatic EB DG Switiching Operation using PLC and HMIIRJET-  	  Automatic EB DG Switiching Operation using PLC and HMI
IRJET- Automatic EB DG Switiching Operation using PLC and HMI
 
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space ApproachReliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
 

More from Udhayakumar Venkataraman

Sintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docxSintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docxUdhayakumar Venkataraman
 
Performance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptxPerformance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptxUdhayakumar Venkataraman
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaUdhayakumar Venkataraman
 
Efficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsEfficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsUdhayakumar Venkataraman
 

More from Udhayakumar Venkataraman (20)

Sugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdfSugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdf
 
How do you use PID in PLC.docx
How do you use PID in PLC.docxHow do you use PID in PLC.docx
How do you use PID in PLC.docx
 
Sintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docxSintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docx
 
IA & SA Compressed Air system.docx
IA & SA Compressed Air system.docxIA & SA Compressed Air system.docx
IA & SA Compressed Air system.docx
 
Performance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptxPerformance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptx
 
Turbine design need of the hour
Turbine design need of the hourTurbine design need of the hour
Turbine design need of the hour
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performa
 
Fgd general norms
Fgd general normsFgd general norms
Fgd general norms
 
Condenser vacuum discussion
Condenser vacuum discussionCondenser vacuum discussion
Condenser vacuum discussion
 
Bfp aspetcs
Bfp aspetcsBfp aspetcs
Bfp aspetcs
 
Condenser vacuum discussion
Condenser vacuum discussionCondenser vacuum discussion
Condenser vacuum discussion
 
By abb motor e book
By abb motor  e bookBy abb motor  e book
By abb motor e book
 
Maintenance strategy forf power plant
Maintenance strategy forf power plantMaintenance strategy forf power plant
Maintenance strategy forf power plant
 
Bearing over greasing failures ]
Bearing over greasing failures ]Bearing over greasing failures ]
Bearing over greasing failures ]
 
Bearings type and selection
Bearings type and selectionBearings type and selection
Bearings type and selection
 
Seals of turbine and improvement
Seals of turbine and improvementSeals of turbine and improvement
Seals of turbine and improvement
 
Soot blowing and advantages
Soot blowing and advantagesSoot blowing and advantages
Soot blowing and advantages
 
Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2
 
Efficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsEfficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuators
 
Boiler optimization journey
Boiler optimization journeyBoiler optimization journey
Boiler optimization journey
 

Recently uploaded

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 

Recently uploaded (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 

Analysis of transformer failure sample papers 2

  • 1. Analysis of Power Transformer failure in Transmission utilities Shrikant S.Rajurkar Superintending Engineer (Trans. O&M) Maharashtra State Electricity Transmission Co Ltd (MSETCL) Mumbai, India e-mail address:ssrajurkar@gmail.com Amit R. Kulkarni Assistant Engineer (Trans. O&M) Maharashtra State Electricity Transmission Co Ltd (MSETCL) Mumbai, India e-mail address: amk4.ind@gmail.com Abstract—This paper focuses on failure of EHV transformers in transmission utilities along with important reasons for failure of the same in brief. This further covers case study of failure of transformer in one of the region in the state of Maharashtra along with remedial measures to be taken to avoid the same. It also discusses in brief various activities needed to be taken in order to effectively handle the issue of power transformer failure Keywords-Transformer,transformer oil,oil insulation, transformer winding, tranformer cores I. INTRODUCTION Today Indian economy is amongst the fastest growing economy in the world despite of global financial meltdown. It is expected that Indian economy shall continue to grow approximately at the rate of 8-9 % in the years to come. India is amongst the leading countries in the world to attract foreign direct investment. India’s manufacturing sector, heavy industries, various global service centres and booming high tech software are all dependent on reliable power supply. This underlines the principle that ‘No Power-No Business’. This makes it utmost important that ‘Transformers’ the heart of substation must function reliably 24x7.Ministry of Power’s ambitious initiatives like Rajiv Gandhi Gramin Vidyutikaran Yojana(RGGVY), Power to all by 2012 make it challenging task to maintain reliability of supply. India faces major challenge both today and in the future for the growth and improvement in reliability of its electrical infrastructure including that of transformer. Failures of critical transformer assets not only impact industries, other consumer categories affecting economy of the country but also have social and political ramifications. II. MSETCL INFRASTRUCTURE MSETCL is the largest State Transmission Utility (STU) in the country. MSETCL infrastructure is shown in Table I. It Jayant G.Nandapurkar Deputy Executive Engineer Maharashtra State Electricity Transmission Co Ltd (MSETCL) T&C Circle Nagpur e-mail address: jgnandapurkar@gmail.com is the only state utility operating and maintaining +/- 500kV, 1500MW Chandrapu-Padghe HVDC bipole transmission system for large power haulage of the order of 1500 MW from generation rich eastern part of the state to load rich western part covering a distance of about 750 kms approximately. MSETCL’s transmission system is capable of handling 18,500 MW of electric power. It has transmitted 97,189 MUs in the year 2009-10.MSETCL has ambitious infrastructure development plan of around 11,000 Cr rupees. MSETCL has total EHV transformer population of around 1356 as on 31.03.2010. Out of those 318 numbers are ICTs contributing to 31191 MVA capacity. There are 84 numbers of 400 kV transformers and 234 numbers of 220 kV transformers. Apart from this, MSETCL system also has 16 numbers of HVDC converter transformers including two numbers of spare converter transformers at each location. TABLE I: MSETCL Infrastructure as on 31.03.2010. VOLTAGE LEVEL EHV SUBSTATION TRANSFORMATION CAPACITY EHV LINES (CKT KM) 500kV HVDC 2 3582 1504 400KV 21 13165 6562 220KV 149 31585 12356 132KV 246 19867 11064 110KV 33 2080 1698 100KV 35 2373 678 66KV 34 1139 3270 TOTAL 520 73791 37133 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 180 Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
  • 2. III. MSETCL TRANSFORMER FAILURE DETAILS IN RECENT YEARS Table I indicates that total transformation capacity in MSETCL as on 31.03.2010 is 73,791 MVA. This emphasises the fact that reliable operation of these transformers is of utmost importance. To maintain reliability it is essential to know reasons for failure of maintaining reliability and ways to overcome the causes of failure. In order to assess failure of transformers it is essential to know exactly the reasons behind the failure. Following section gives methodology developed by MSETCL based on practical experience to pinpoint the cause of failure for EHV transformers. The risk of a transformer failure is actually two-dimensional, the frequency of failure and the severity of failure.Fig.1 gives details of transformer failure in MSETCL during 2008-09, 09-10 (Upto June 2010) Transformer failure in MSETCL during 08-09,09- 10 and upto June 10 21 21.5 22 22.5 23 23.5 24 24.5 0 to 5 5 to 15 15 to 25 above 25 Age of Transformer Numberoftransformers failed Fig. 1.Agewise transformer failure details in MSETCL in recent past. A. Analysis of transformer failure in Nagpur zone of MSETCL Nagpur zone has total of 72 EHV substations voltage levelwise breakup for those is shown in fig.2. Fig. 2.Details of EHV levelwise substations in Nagpur zone of MSETCL. As MSETCL system is closely knit with MSEDCL system in the state of Maharashtra,fig.3 shows how MSETCL system is interfaced with MSEDCL system as far as transformer distribution in Nagpur zone is concerned along with details of number of EHV substations as per interfacing with voltage level wise category. There are total of 187 EHV transformers in Nagpur zone 153 of them are EHV transformers and 34 of them are ICTs contributing to about 18% as shown in fig.4. . Fig. 3.Interface between MSETCL and MSEDCL system in Nagpur zone Fig. 4.EHV transformer break up as ICTs and Non-ICTs in MSETCL system in Nagpur zone Transformer failure analysis in Nagpur zone covered under this section considers duration from 2005-06 to 2008-09.There were total of 27 transformer failures during this period. Fig.5 indicates details of number of transformer failures against year. As MSETCL system has transformers of different MVA capacities, for the purpose of analysis attempt was also made to categorise MVA group wise transformer failure as shown in fig.6.In this three categories of transformers namely transformers having capacities 10 MVA andbelow,25 MVA and above and 100 MVA and above are considered. Fig. 5. Number of EHV transformer failures against year in MSETCL system in Nagpur zone. Breakup showing interfacing with Distribution Syatem (Total 71 S/Ss) 5 15 20 31 0 5 10 15 20 25 30 35 40 Only EHV Level Only 33 KV Level Only 11 KV Level Both 33 & 11 KV Level Category NoofEHVS/Ss Yearwise T/F Failures (Total 27 Nos) 9 7 5 6 0 2 4 6 8 10 05-06 06-07 07-08 08-09 Year NoofT/Ffailures 3 18 26 25 0 5 10 15 20 25 30 400 KV 220 KV 132 KV 66 KV NoofS/Ss Voltage Level in KV Levelwise break-up of EHV S/Ss (Total 71 Nos) 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 181 Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
  • 3. Fig. 6. MVA groupwise transformer failures in MSETCL system in Nagpur zone. It is well known fact that fault level at substation also has impact on proper functioning of transformers, so analytics is also developed to categorise transformers in high, medium and low fault level groups as shown in fig.7. [7]. IV. USING THE TEMPLATE Fig. 7. Fault level wise transformer failures in MSETCL system in Nagpur zone. There can be variety of reasons for failure of transformers, some of the important ones are listed below i)Insulation failure ii)Design and Manufacturing default iii)Oil contamination iv)Overloading v)Fire or Explosion vi)Line surges vii)Lightening viii)Moisture ingress Apart from this Aging, poor O&M practices, loose connection, poor repairs etc can also result in failure of transformers.Fig.8 shows transformer failure classification based on cause of fault. Fig. 8. Fault cause wise transformer failures in MSETCL system in Nagpur As major responsibility of transmission utilities is to carry bulk power from generating stations and bringing it to load centres thus transmission utilities work in proximity with distribution network. This may result many times into transformers interfacing distribution network experiencing more number of faults for longer duration further resulting into failure of EHV transformers. This is indicated by fig.9 and fig.10.These figures indicate that EHV transformers of 132 /11kV and 66/11kV which are in close proximity with distribution system have more number of failures compared to other categories.Fig.9 indicates that out of 27 number of EHV transformers in Nagpur zone 10 number of transformers are 132/11kV and other 10 are 66/11kV transformers contributing to approximately 62% of the total transformer failures in the zone. Fig. 9. Voltage ratio wise transformer failures in MSETCL system in Nagpur zone. Fig. 10. Voltage ratio wise transformer failure rate in MSETCL system in Nagpur zone. B. Failure of HVDC Converter transformer The converter transformer are single phase three winding units of 298.6 MVA capacity each and having line winding of 3/400 kV and Delta and Star connected valve windings of 3211211− kV voltage rating respectively. Out of total of 16 numbers of transformers,8 numbers are supplied by BHEL- India and 8 numbers by ABB Sweden. After bipolar operation for a few months, failures of converter transformers at Chandrapur and Padghe started from June 2001.Nine transformers have failed, out of Nine transformers four MVA Groupwise T/F Failures 12 14 1 0 2 4 6 8 10 12 14 16 <=10 <=25 100+ MVA Group NoofT/FFailures Falut Level wise Break-up of T/F Failures 16 6 5 0 2 4 6 8 10 12 14 16 18 High Medium Low Category of Fault Level NoofFailures Fault cause wise breakup No of T/F Failures 9 2 3 4 9 0 2 4 6 8 10 12 Ageing Lightning Mfg defect Repair defect OG Fdr Flt Fault Category NoofT/FFailures Voltage Ratiowise T/F Failures 1 4 10 2 10 0 2 4 6 8 10 12 220/132 132/33 132/11 66/33 66/11 Ratio in KV NoofT/Ffailures Voltage Ratio wise Failure Rate 15 50 24 13 49 1 4 10 2 10 6.67 8.00 41.67 15.38 20.41 0 10 20 30 40 50 60 Population 15 50 24 13 49 No of Failures 1 4 10 2 10 Faulure Rate 6.67 8.00 41.67 15.38 20.41 220/132 132/33 132/11 66/33 66/11 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 182 Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
  • 4. numbers are from BHEL-India and five numbers are from ABB Sweden. Out of these, failed transformers one transformer each of BHEL and ABB make which has failed, was repaired earlier. In all the cases, transformers connected to star winding have failed [1]. The failure was analysed considering the following: • Frequent and high amplitude transients. • Failure occurred in normal operation, however no direct cause for breakdown was identified. • Turn to turn breakdown in star winding. • No breakdown paths to earth in the transformer. C. Detail investigation of converter transformer failure in MSETCL In process to carry out detail investigation of failure of converter transformer the design was scrutinised with design tools.The voltage transient behaviour of the winding was evaluated by using both calculations and measurements. The strength of the insulation against repetitive transients was also verified and concluded that no design deficiency is causing the breakdowns. i) Copper Sulphide Deposits Inspection of the winding when disassembled turn by turn showed that at some locations there was a shiny deposits on spacers and conductor insulation. These deposits were identified as Copper Sulphide (CU2 S). ii)Influence on Dielectric Strength The electric conductivity of CU2 S is significantly higher than the conductivity of paper and oil. This means that the presence of CU2 S may change the electric field distribution. The series of tests were performed on both CU2 S contaminated material and unaffected materials. The result of these tests shows that: • Partial Discharge (PD) initiation voltage and the breakdown voltage of the CU2 S coated material are significantly reduced as compared to the uncoated material. • Uncoated and unaffected insulation has the same strength as brand new insulation. iii)Impact of Transients CU2 S lowers the PD- initiation level Depositions of copper sulphide on the winding alone are not sufficient to create a short circuit or partial discharge between two turns. For either of these two happens the insulation has to be further degraded by frequent repetitive transients. Such transients may occur in HVDC applications, since HVDC transformer is exposed to a commutation process when the current is transferred from one phase to another. A rapid increase in the terminal voltage during this process results in fast transients in the winding which locally stress the insulation. The converter normally operates at the firing angle (α) of 15° but α = 90° operation during line faults though rare, cause very high stresses on the turn –to turn insulations. This operation occurs during line faults. iv) Reasons for formation of Copper Sulphide ( CU2 S) Formation of CU2 S is a very interesting phenomenon. The transformer oil is basically highly refined mineral oil and consists of mainly mixture of hydro-carbons and some other compounds, containing Oxygen, Nitrogen and Sulphur .Most of the compounds containing sulphur can react with copper under extreme conditions and form copper sulphide deposits. After investigation M/s ABB arrived at final conclusion as follows: Aggressive oil produces copper sulphide Copper Sulphide weakens the insulation Transients arising due to α =90° operation or transients from continuous higher MVAR operation are sufficient to initiate partial discharges. Repetitive transients further degrade the insulation. A partial discharge in sufficiently degraded insulation, will not extinguish. When the insulation is sufficiently degraded, PD will continue at normal service voltage levels. A partial discharge leads to a turn to turn fault and Transformer breakdown. Finally the detailed investigations revealed that the series failure of HVDC transformer occurred mainly due to insulating oil problem. M/sABB after studying the problem suggested to use passivated oil for new or repaired unit and to add passivator in the oil of in service converter transformer. After taking remedial measures no converter transformer failure is observed. These measures have resulted into enhancing the availability of HVDC system. Currently HVDC system availability is as per the standards decided by MERC. IV. MEASURES TAKEN FOR REDUCTION OF TRANSFORMER FAILURES IN MSETCL A. Measurement of Capacitance and Tanδ Capacitance and Tanδ measurement of bushings gives an indication of the quality of insulation in the bushing[2]. In MSETCL practice is followed to replace the bushing if value of Tanδ is found to be greater than 0.007.If the trend in variation of Capacitance and Tanδ values monitored is 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 183 Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
  • 5. observed to be abnormal decision of replacing of bushing is taken. The same technique is used to know healthiness of ground and interwinding insulation of transformer.MSETCL has a practice of yearly monitoring of Capacitance and Tanδ measurement. B. Provision of High set relay for EHV transformers High set relays are provided on distribution side feeders to avoid unwarranted trippings/failure of transformers. For a closeup fault on distribution feeder, the high set relays are expected to operate to clear the fault and avoid the reflection of the same on transformer. The high set relays being instantaneous helps to isolate the faulty feeder quickly.MSETCL has provided high set relays on distribution side feeders emanating from EHV substations and this has helped to reduce the incidents of transformer tripping/failure due to distribution related faults. C. Independent operation of EHV transformers Based on the failure analysis of transformers, it is noticed that the failures of EHV transformers feeding the distribution network are more than that of ICTs. After detailed analysis and studies it has been decided to operate the EHV transformers in independent mode rather than parallel operation as far as possible where the load can be managed. This has helped in reducing inadvertent trippings and failure of transformers also to some extent. D. Dissolved gas analysis(DGA) Dissolved Gas Analysis (DGA) is one of the most widely used diagnostic tools for detecting and evaluating faults in electrical equipment. However the interpretation of DGA results is often complex and should always be done with care, involving experienced insulation maintenance personnel.(Ref:IEC 60599:1999).This technique is mainly useful for the transformers filled with mineral insulating oil and insulated with cellulosic paper or press-board-based solid insulation. This process mainly involves steps i)Knowing reasons for generation of gases: Fault gases are produced by degradation of the transformer oil and other insulating materials such as cellulose. In the presence of an active fault, the rate of oil and cellulose degradation is significantly increased, and the types of degradation products formed will vary with the nature and severity of the fault. ii)Interpretation of dissolved gas analysis Interpretation of dissolved gas analysis is generally done based on standards like IS. 10593:1992, IEC 60599:1999, ASTMD3612.Apart from this it is also important to see Whether the measured values are well above the sensitivity of the analytical methods and equipment and to check whether gas concentration is high enough to consider for further investigation. Inputs on following historical information is vital in carrying out the DGA interpretation. 1) How old Is the transformer? 2) Did a bushing fail at some point? 3) Did the transformer fail at some time? 4) Is the unit heavily loaded as of today or in past? 5) Has the transformer been repaired after a failure? 6) Has the DGA tests been performed in past? 7) Have the fault gases risen suddenly? 8) Has the oil been degassed? The method in IS 10593:1992 was based on IEC Pub 599: 1978, which has since been modified as IEC 60599.MSETCL has a practice of taking yearly DGA and based on DGA results appropriate action to safeguard the transformer is taken. Portable DGA kit procured by MSETCL works on photo acoustic principle has capable of detecting concentration of 8 fault gases alongwith the moisture content. MSETCL has also provided online DGA monitoring equipment on experimental basis on some of the units. Apart from above DC resistance measurement and determination of Polarization Index (PI) corresponding to 60s. and 600 s, SFRA etc. are the other maintenance practices followed at MSETCL in order to minimise transformer failure rate. MSETCL follows the practice of recording SFRA during testing at factory before despatch of the transformers and confirming healthiness of transformer by recording SFRA at site before commissioning of the transformer. Further MSETCL has taken a policy decision to provide Nitrogen injection type fire protection system for all transformers of rating 100 MVA and above to prevent the transformers from catching fire during failure incident. It is observed that with above mentioned measures taken by MSETCL number of instances of EHV transformer failure could be controlled, further helping in improvement in the reliability of supply. V. CONCLUSIONS This paper discusses in short, some of the important reasons for the power transformer failure alongwith methodology to classify transformer failures depending on various factors. Based on the data it can be said that many times transformers interfacing distribution network experience more number of faults for longer duration further resulting into failure of EHV transformers. This paper also discussed some of the preventive methods in brief to minimise the rate of transformer failure. 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 184 Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.
  • 6. ACKNOWLEDGMENT Authors are thankful to management of MSETCL for permitting them to submit the paper and for their encouragement throughout the process. REFERENCES [1] P.R.Gange,S.A.Jaolikar,S.SRajurkar,R.S.Parulkar“Operational experiences of Chandrapur-Padghe HVDC bipole project” CIGRE International conference on HVDC Applications,Bangalore,2005. [2] G.N.Mathur and R. S.Chadha. Sneddon, “EHV substation equipment maintenance”,publication No.24,Central Board of Irrigation and Power New Delhi 2005,pp. 71–75. BIOGRAPHIES Rajurkar S.S. He graduated from Nagpur University in the year 1982.He also obtained M.Tech. (Electrical) degree from Nagpur University in the year 1984.He joined Maharashtra State Electricity Board (MSEB) in the year 1984 and working in Maharashtra State Electricity Transmission Company Ltd (MSETCL) after restructuring of erstwhile MSEB. He is associated with 400kV and HVDC system planning, Operation and maintenance work for the same. He is presently working in Transmission O&M department at Corporate Office of MSETCL in Mumbai. His special fields of interest include power system protection, power system stability, HVDC applications. Jayant G. Nandapurkar He received his B.E. (Electrical) from Govt. College of Engineering, Aurangabad in 1979 He has special interest in Power System protection, Short circuit studies, Load Flow Studies, Power System Harmonics. Worked as Testing & Commissioning engineer with erstwhile Maharashtra State Electricity Board (MSEB).Member of expert study group on protection issues of MSETCL.He is member of expert group formed for review of relay settings of the protection equipment of MSETCL.Presently working as Dy. Executive Engineer under Testing & Communication Circle Nagpur with Maharashtra State Electricity Transmission Co. Ltd. (MSETCL. Amit Kulkarni He graduated from Shivaji University Kolhapur in the year 1999. He also obtained M.E. (Power System) from Pune University in 2004 and worked in project on power system stability at Electrical Engineering Department at IIT Bombay. He joined Maharashtra State Electricity Transmission Company Ltd (MSETCL) in 2006.He is presently working in the Corporate Office of MSETCL in Mumbai. His special fields of interest include power system stability, power system operation and control, power system protection and FACTS. 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 185 Department of Electrical Engineering, Univ. College of Engg., Osmania University, Hyderabad, A.P, INDIA.