SlideShare a Scribd company logo
1 of 10
Download to read offline
Ebara Engineering Review No. 2512016-4
─  ─11
ability because it must operate in more severe condi-
tions such as partial load operation and increased fre-
quency of start and stop actions.
2. History
2.1 BFPs for conventional thermal power plants
Since BFPs are used to feed high-temperature/pres-
sure water to boilers, their history is closely related
with the improvement toward higher boiler capacities
and higher temperatures and pressures.
 Boilers and other equipment for commercial thermal
power generation have been improved to achieve higher
per-unit capacities with the objective of reducing the
percentage of equipment costs (for advantages of scale)
as well as to achieve higher steam temperatures and
pressures for higher thermal efficiency1)
.
 Looking at the history of boilers in Japan, the maximum
unit capacity was 66 MW in 1955, which increased to
325 MW in 1965 and to 600 MW in 1969. In 1974, a
boiler with a capacity of 1000 MW was brought into
operation. Boilers in Japan thus have been undergoing
rapid increases in capacity. After 1980, boilers with a
unit capacity of more than 600 MW went mainstream,
Abstract
In a thermal power plant, the boiler feed pump (BFP) is one of the critical auxiliary machines that are equivalent to the heart
of the plant. In pace with the increases in the capacity of equipment for thermal power generation, improvements to adapt to
higher temperatures and pressures, and changes in operation method, BFPs have been improving and advancing. This paper
explains how BFPs have been upsized and made compatible to higher pressures; main specifications of BFPs; structures and
materials of typical BFPs for conventional supercritical thermal power plants and for combined-cycle thermal power plants;
characteristics of the shaft seal and bearing; technological development for higher capacities and performance; actual develop-
ment and delivery of 100% capacity BFPs; improvements to the structure design for increasing the stress resistance of BFPs
so that they can adapt to more severe conditions in the operation of thermal power plants associated with the spread of renew-
able energy; and examples of efforts to streamline the BFP design for manufacturing cost reduction and space saving.
Keywords:	Feed water pump, High pressure, Efficiency, Super critical thermal power, Combined cycle thermal power, Reliability,
Specific speed, Shaft strength, Bearing, Double casing
1. Introduction
This paper outlines the history and structural and
technical characteristics of boiler feed pumps (hereafter
referred to as BFP), which are high-pressure pumps
mainly used for thermal power generation.
 In a thermal power plant, the BFP is one of the criti-
cal auxiliary machines that are equivalent to the heart
of the plant. In thermal power generation, high-pres-
sure steam is used to drive a turbine, which in turn ro-
tates the generator directly connected to the turbine to
generate power. The steam is produced by feeding hot
water to the boiler from the BFP. This means that an
unexpected stop of the BFP completely stops power
generation and therefore the BFP requires a very high
level of reliability. In recent years, with the populariza-
tion of renewable energy, thermal power generation re-
quires load adjustment for a stable power generation
system as well as operation under severe conditions
such as rapid changes in load. The BFP is also required
to provide even higher levels of capabilities and reli-
[Commentary]
Boiler Feed Pump (BFP)
Shigeru YOSHIKAWA*
*	 Fluid Machinery  Systems Company
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─12
followed by many units with a capacity of more than
1000 MW built after 1990.
 Looking at the steam conditions, Japan’s first boiler
with a steam pressure of 16.6 MPa (at the inlet of the
turbine) was fabricated in 1959. In 1967, Japan’s first
supercritical constant-pressure boiler was brought into
operation for higher generation efficiency. Boilers sub-
sequently underwent rapid increases in supercritical
pressure, resulting in a situation where 82% of the
power generating units built in 1974 were of a super-
critical type1)
.
 When used in combination with a supercritical-pres-
sure boiler with a unit capacity of more than 1000 MW,
the BFP is required to deliver a very high level of per-
formance such as a flow rate of approximately 1700 t/h,
a discharge pressure of approximately 30 MPa, and a
shaft power of approximately 20000 kW. To achieve
this high pressure, the BFP is required to achieve a
high rotation speed of 5000 to 6000 min-1
. At that time,
it was common to combine two 50% capacity BFPs
driven by steam turbines (T-BFPs) and one BFP driven
by a motor with a speed-increasing gear (M-BFP) as a
backup and for start-up purposes. Figure 1 shows the
relationship between the increases in boiler pressure
and BFP discharge pressure2)
.
 Note that EBARA supplied BFPs for both of Japan’s
first supercritical and ultra-supercritical (USC) power
generating units. EBARA also delivered Japan’s first
BFP for a 1000 MW power generating unit.
 In the 1980s, many nuclear power plants were built,
which started to act as base-load power plants. Under
the circumstances, in commercial thermal power gen-
eration, many units that were compatible with middle-
load operation started to be used, with supercritical
variable-pressure once-through boilers, capable of main-
taining high efficiency even in the middle-load area, go-
ing mainstream. This situation required variable-speed
motor drives, leading to the introduction of motor
drives with a built-in speed increasing gear and a fluid
coupling.
 Efforts to increase the thermal efficiency continued.
In 1989, a 700 MW, USC plant was brought into opera-
tion with a main steam pressure of 31.1 MPa and a
main steam temperature of 566 °C.
 Table 1 shows the specifications of the BFPs used in
this plant2)
.
2.2 BFPs for combined-cycle thermal power plants
In parallel with the movement to improve the systems
for the conventional thermal power generation toward
higher capacities, temperatures, and pressures, com-
bined-cycle power generation went into actual use in the
middle 1980s, a thermal power generation system that
achieves higher efficiency by combining two cycles: a
gas-turbine combustion cycle and a steam-turbine cycle
that uses the exhaust heat from the former cycle. With
continuous technological development for cooling turbine
blades and making them heat resistant, the gas-turbine
combustion temperature has increased, resulting in fur-
ther improvement in power generation efficiency. State-
of-the-art combined-cycle plants (with a gas turbine that
uses a temperature of higher than 1 600 °C) have
achieved a sending-end efficiency of as high as 60%. In
recent years, many combined-cycle thermal power
plants have been constructed because they use, as a fuel
Feed pump
discharge pressure
PressureMPa
Boiler
pressure
Approx.38 MPa
45
40
35
30
25
20
15
10
5
0
31 MPa
Approx.30 MPa
Approx.20 MPa
17 MPa
25 MPa
Ultra-supercritical (USC)
19891967
Supercritical
Fig. 1 Boiler pressure and BFP discharge pressure
Table 1 BFP specifications for 700 MW USC thermal power plant
Purpose Main feed water
Start-up and
backup
Capacity t/h 1200 730
Discharge pressure MPa 38.05 37.26
Rotation speed min-1
6000 6300
Water temperature ℃ 188.4 184.1
Drive Steam turbine
Motor drive (with
a fluid coupling)
Output kW 17500 12000
Number of units 2 1
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─13
for gas turbines, LNG−a fuel that emits less carbon
dioxide−and therefore impose less environmental load.
These plants require BFPs that feed water to heat
recovery steam generators (HRSG).
3. Structures of BFPs
3.1 BFPs for conventional thermal power plants3)
(1) Casing structure
BFPs used in supercritical and USC plants are required
to provide a high discharge pressure of 30 to 35 MPa
with a feed-water temperature of as high as 180 °C or
higher. These plants use double casing barrel-type
multi-stage pumps designed to be adaptable to high-
pressure and -temperature specifications. These pumps
have a forged cylindrical outer barrel with a high rigid-
ity that contains a single-piece structure consisting of
an internal casing and a rotor, with one end of the outer
barrel fastened to a discharge cover with bolts. They
are designed according to the technical standard for
thermal power generation or a similar public standard
so that the thicknesses of the outer barrel, discharge
cover, and discharge nozzle, and the size and number
of cover fastening bolts will provide sufficient strengths
against the design pressure (maximum allowable working
pressure).
 The outer barrel is a simple thick cylinder that is not
affected by high pressures or changes in pressure. The
barrel is fastened to the discharge cover with bolts
with a spiral gasket inserted between them to prevent
leakage of water. The fastening bolts are controlled with
a hydraulic wrench, bolt heater, or bolt tensioner so that
it will constantly provide appropriate fastening force.
 By providing a middle extraction flange on the dis-
charge cover side or the suction side as appropriate, in-
termediate pressure can be taken out so that it can be
used for applications such as coolant spraying to the
reheater.
(2) Internal structure
The structures of the internal casing, impeller, and other
hydraulic components are divided into two groups: one
group uses a combination of a axially split casing, back
to back arrangement impeller, and a volute type and
the other group uses a combination of a ring section
casing, straight through impeller, and a diffuser type.
The latter group requires a balance disk or a similar
component for balancing the axial thrust.
(3) Material
The outer barrel and discharge cover, which are pres-
sure-containing components, are made of forged carbon
steel, and the gasket surface and high velocity sections
are overlaid with austenitic stainless steel to prevent
erosion. The internal casing and impeller are made of
13Cr or 13Cr-4Ni martensitic cast stainless steel.
(4) Shaft seal and bearing
Most commercial thermal power generation plants in
Japan used non-contact throttle bushes or floating
rings, which are not likely to wear under high-speed
and -pressure conditions and are suitable to continuous
operation. In recent years, overseas plants in particular
use mechanical seals in many cases. As for the bear-
ings, a forced lubricating type is used.
 Figure 2 shows the structure of a typical BFP for
conventional thermal power plants.
3.2 BFPs for combined-cycle plants3)
(1) Casing structure
BFPs for combined-cycle thermal power plants feed
water to the heat recovery steam generator. They are
required to provide a discharge pressure of 15 to 20
MPa and a feed-water temperature of approximately
150 °C, which are substantially low compared to super-
critical thermal power plants. For this reason, single
case, ring section-type, multi-stage pumps are used in
most combined-cycle plants. However, they absolutely
require technologies for analyzing and evaluating ther-
mal stress and deformation because they are required
to adapt to quick plant starts and abrupt changes in
feed-water temperature. The basic structure of a ring
section-type casing consists of a suction casing, dis-
charge casing, inter stage casing, and intermediate ex-
traction casing, which are fastened with casing bolts,
with the joints between the casings sealed with metal
touch based on the fastening contact pressure of the
bolts. Depending on the results of thermal deformation
analysis, an O-ring is fitted as appropriate to completely
prevent leakage of feed water even during thermal
transient.
(2) Internal structure
Heat recovery steam generators for combined-cycle
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─14
plants are often structured with three stages (high-,
middle-, and low-pressure drums), and designed to ex-
tract intermediate-pressure feed water from the inter-
mediate stage of the BFP to feed it to the middle-pres-
sure drum. In other words, one unit of BFP can feed
middle- and high-pressure water. Total amount of the
middle- and high-pressure feed water are sucked from
the suction casing. After the amount of the water to be
fed to the middle-pressure drum is extracted from the
extraction stage, only the amount of the water to be
fed to the high-pressure drum is pressurized. For this
reason, the specific speeds (Ns) of impeller and diffuser
for the stage before the extraction are often different
from those after the extraction.
 In combined-cycle plants, ring section-type diffuser
pumps are used. They have all impellers arranged in
one direction and therefore require a thrust balancing
component. Balancing components are available in two
types: balance-disk and balance-drum types. Water
leaked from the balancing component is normally re-
turned to the suction side. When the pressure decreases
in the balancing component, the water temperature
rises. When the saturated vapor pressure of water with
the temperature rise taken into account is higher than
the suction pressure, the water may flush out and re-
turns to the pump inlet. If this is the case, the pump
does not operate soundly. If this happens, the balancing
piping is connected to the deaerator.
 Pumps structured to use double suction impeller at
only the first stage are often used because this struc-
ture can reduce the required NPSH by halving the suc-
tion flow because of the double suction.
(3) Material
The suction, discharge, and extraction casings, which
are pressure-containing components, are made of 13Cr-
4Ni cast stainless steel and the inter stage casing of
13Cr-4Ni stainless steel.
(4) Shaft seal and bearing
For the shaft sealing device, a mechanical seal with
almost no leakage is used because the pressure and
peripheral speed conditions are slightly less severe than
those for BFPs for supercritical plants. For the bearing,
though a forced lubricating type is used, a self-lubricat-
ing type can also be safely used in some cases as will
be described later since the peripheral-speed conditions
are less severe than those in conventional supercritical
thermal power plants. Figure 3 shows the structure of
a typical BFP for combined-cycle thermal power plants.
4. Upsizing and sophistication of BFPs
With the growth of equipment for thermal power gen-
eration in capacity and pressure, BFPs have been
upsized and become sophisticated. Among the pumps
used in a thermal power plant, the BFP uses the most
power because it must produce high pressures re-
quired by the boiler. This means that the improve-
Discharge nozzle Temperature
detection seat Suction ïŹ‚ange
Forced lubricating
bearing (radial)
Throttle bush
Balance return ïŹ‚angeNozzle for draining
and warmingMiddle extraction ïŹ‚ange
for spraying to reheater
Throttle bush
Forced lubricating
bearing (thrust)
Discharge cover
Outer
barrel
Fig. 2 Double casing barrel type BFP for supercritical thermal power plants
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─15
ment in BFP efficiency is a critical challenge that
must be solved to reduce the environmental load. The
impeller used in a BFP is a centrifugal pump with a
specific speed (Ns) of approximately 120 to 250 (m3
/
min, m, min-1
). Generally, the pump efficiency is higher
when the specific speed is higher within this range or
the flow rate is higher if the specific speed is the
same. In a normal case, two BFPs each with a 50%
capacity are used as the main feed pumps. If one BFP
can provide a 100% capacity, it improves the efficiency
through the increase in capacity and enhancement in
specific speed as well as helps save space and re-
sources4)
. In Japan, EBARA has experience in designing,
fabricating, and delivering main feed pumps with a
specification of 100% capacity per unit for 500 MW
and 600 MW supercritical thermal power plants and
these pumps are successfully operating. In some coun-
tries and areas, a system based on a single main feed
pump with a 100% capacity is in actual use in 1000 MW
plants. Recently, EBARA also manufactured and
delivered a large BFP that satisfied this requirement.
Figure 4 shows actually shipped BFP and followings
are the outlined specifications of this BFP.
 Capacity of 3200 t/h×total pump head of 3800 m×
shaft power of 37700 kW×rotation speed of 5000 min-1
 Specific speed of approximately 250 (m3
/min, m, min-1
)
 In general, higher capacities and higher specific
speeds increase the pump efficiency. The shaft power
increases with the increase in capacity; accordingly, if
the rotation speed is the same as that of a 50% capacity
BFP, the main shaft has larger torque and is thus required
to have a large diameter, compared to conventional
BFPs, to maintain the required strength. If the
rotational speed and pump head remain the same, the
diameter of the impeller also remains unchanged. This
means the main shaft with an increased diameter
interferes with the flow passage of the impeller meridian
plane. Under the circumstances, to achieve high efficiency,
we determined the optimal hydraulic shape including
the volute−which reduces the flow velocity of the water
from the impeller, and converts it into static pressure
−and the cross over passages between the stages. To
this end, we made full use of CFDnote
including analysis
of unsteady flows.
 We also determined, through analysis of the main
shaft strength, the optimal diameter that minimizes the
Fig. 4 100% capacity BFP for 1000 MW supercritical thermal
	 power plants
16-72 01/251
Intermediate
volute
Middle-pressure drum
feed-water ïŹ‚ange
High-pressure drum
feed-water ïŹ‚ange
Discharge casing
Suction casing
Suction ïŹ‚ange
Casing bolt
Bearing (thrust)Bearing (radial)
Mechanical seal
Mechanical seal
Balancing component
Fig. 3 Structure of a BFP for combined cycle thermal power plants
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─16
increase in shaft diameter from that of the 50% capacity
BFP (existing conventional design). For a system based
on a 100% capacity BFP, only one unit is used and if it
should unexpectedly stop, the power generation capacity
is totally lost. For this reason, needless to say, we
designed the main shaft so that each part of the shaft
would maintain a sufficient strength.
Note: Computational fluid dynamics
 Table 2 compares the performance of BFPs delivered
to power plants of typical sizes and with typical out-
puts. The BFP shaft power consumes 3.5 to 4% of plant
output; this ratio can be reduced through the increase
in efficiency to be achieved by increases in capacity.
For 500 MW plants, we successfully reduced the ratio
to the rated plant output by approximately 0.5 point by
using one 100% capacity BFP. Even if the output is the
same, however, the water temperature (density), capac-
ity, and total pressure are different from plant to plant
and therefore it is not generally practical to make com-
parisons according to only the shaft power ratio. Look-
ing at the efficiency, for the 500 MW plants, while the
system based on two units exhibited an efficiency of
82%, the system based on a single unit achieved an
86% efficiency, resulting in a 4-point improvement as
described earlier4)
.
5. Improvement in BFP stress resistance
Recent years have seen increased introductions of re-
newable energies such as solar and wind power. Re-
newable energy is expected to continue to spread as
one of the measures against global warming because it
does not use fossil fuel and therefore emits no carbon
dioxide when used for power generation. However, the
power output based on solar and wind power signifi-
cantly depends on the meteorological conditions such
as the weather and wind conditions, resulting in the
drawback that it is difficult to stably operate electric
power systems based on renewable energy. In order
to cope with this issue, thermal power plants are
increasingly required to provide more flexible power
system operation with a higher level of supply-and-de-
mand adjustment capability. Specifically, they are re-
quired to improve the load change rate, minimize the
minimum load factor, and shorten the start-up time.
 In association with the supply-and-demand adjust-
ment capability added to thermal power plants, BFPs
are required to operate in more severe conditions such
as increased frequency of start and stop actions, changes
in feed water temperature, and increased frequency of
low flow operation. To address these requirements,
efforts have been made to improve the stress resis-
tance (robustness) of BFPs by reviewing the structure,
materials, and design. Figure 5 shows an example of a
BFP structure that has incorporated the structural and
design considerations to adapt to the operational re-
quirements above. Table 3 shows specific items that
must be improved and phenomena that must be ad-
dressed along with possible causes of them (some of
the measures in the Table 3 are not always against the
more severe operating conditions but have been intro-
duced as part of the efforts to improve the general
functional reliability of BFPs5)
).
6. Streamlining of BFPs
As described earlier, BFPs are the heart of the main
piping system in thermal power systems and therefore
required to provide high levels of functionality and reli-
ability. On the other hand, it is also important to supply
power at as low a price as possible, in developing coun-
tries in particular, where the demand for power is
pressing and therefore the construction of many new
thermal power plants is planned. For this reason, pump
suppliers are also required to cooperate to simplify the
equipment for power generation plants and make
efforts to reduce the costs for such equipment as one of
the challenges that they must address. Here are some
of the efforts to streamline BFPs.
Table 2 Specifications of typical BFPs
Rated
plant
output
Capacity
Total
pressure
Rotation
speed
Shaft
power
Efficiency
Number
of unit
Power
ratio
MW t/h MPa min−1
kW % Unit %
500 890 29.67 5500 9999 82 2 4.00
500 1630 30.1 5500 17747 86 1 3.55
600 1000 30.1 5500 11157 83.5 2 3.72
600 1860 33.2 5000 22589 85.3 1 3.76
700 1120 30.6 5500 12711.7 85 2 3.63
1000 1650 30.5 5500 18393.3 86 2 3.68
1050 1700 31.2 6000 19279.5 85.5 2 3.67
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─17
6.1 Discontinuance of booster pumps
With a rotation speed of as high as 5000 to 6000 min-1
,
BFPs for supercritical thermal power plants require a
high required NPSH (NPSHR). With an increase in
power generation capacity, the flow rate of the BFP in-
creases, which requires an even higher NPSHR. The
NPSH available (NPSHA) of a BFP, which is deter-
mined by the height of the deaerator installed, is nor-
mally approximately 20 to 25 m. For this reason,
through the cross over piping, a booster pump is nor-
mally installed upstream of the BFP to ensure the
NPSH required for the BFP.
 Under the circumstances, M-BFPs for start-up pur-
poses used in some plants are actually designed to in-
clude an impeller equipped with an inducer in the first
stage to lower the NPSHR for elimination of the need
to use a booster pump and cross over piping. This
design helps reduce plant construction costs by saving
space and resources. Figure 6 shows the structure of a
BFP with an inducer4)
.
①
⑱
â‘„
â‘€
②④
⑩
⑹
⑧
⑩
Fig. 5 BFP structure that has incorporated measures for increasing the robustness
Table 3 Measures for increasing the robustness of BFPs
No Degradation Causes Measures for increasing the robustness
①
Wall thickness reduction of
discharge nozzle
Erosion caused by high velocity and/or uneven
flow
Overlaying austenitic stainless steel onto the
inner surface
②
Erosion of high-differential-pressure
part of the inner volute
Degraded seal performance of metal touch seal or
self-compressed gasket associated with increased
frequencies of start and stop actions
Using an auxiliary O-ring in combination
⑱ Incipient cavitation
Increased duration of low flow operation
associated with the adoption of DSS, etc.
Replacing the first stage impeller with new
one designed for low flow regarding with inlet
configuration
④
Cracks at the portion to which
auxiliary piping is attached
Impact of pulsation caused by increased duration
of low flow operation
Modifying the nozzle stub so that it will be a
more rigid structure
â‘€ Vibration caused by misalignment
Changes in nozzle load associated with increased
frequencies of start and stop actions
Installing an stabilizing device
â‘„ Increased bearing vibration
Impact of pulsation caused by increased duration
of low flow operation
Using a full circular bearing housing
⑩ Damaged bearing metal
Wire-wool damage of 13Cr steel shaft caused by
foreign particles in lube oil
Overlaying carbon steel to the main shaft
journal
⑧
Occurring of abruptly changing
vibration
Torque locking caused by poor sliding of the
gear-coupling tooth surface
Upgrading to a flexible disk coupling
⑹
Fretting corrosion on the fitting
portion of the thrust disk
Decreased torque of the shaft-end nut. Loosened
fixed disk caused by secular distortion of the disk
contact surface
Using a shaft-end nut of a locking sleeve type
Using a long hub type thrust disk
⑩
Degraded mechanical seal for inter
stage bleed off
No maintenance for a long time because it is
installed on the suction cover and not required
when the inner-volute rotor disassembly
Discontinuing the use of the bleed off pipe
and the mechanical seal as the structure for
extraction from the discharge cover
The above number is the part that shows the number of the in Fig. 5.
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─18
6.2 Full-cartridge, ring section, double casing
BFPs
The BFPs shown in Figs. 2, 6, and Figure 7 are structured
with a horizontally split internal casing (inner volute).
As Fig. 7 shows, a BFP with this structure allows you
to take out the shaft and impeller as a rotor assembled
as one unit if the upper half of the inner volute is
disassembled. Since this facilitates inspection in power
plants, this design has been adopted in many power plants
inside and outside Japan. It also has the drawback,
however, that the design requires a high manufacturing
cost because the inner volute has a complicated structure
made of cast steel. On the other hand, the structure
with a ring section-type internal casing (inner case)
offers the cost-related advantages that it does not require
an inner volute, which is costly, and that when compared
under the same performance (pressure), it allows you
to slightly reduce the diameter of the internal casing,
resulting in a smaller diameter of the outer barrel. This
structure has the drawback, however, that it is difficult
to inspect on site because inspection of the rotor requires
you to vertically place the inner casing and rotor and
then take out the inner case, guide vane, and impeller on a
stage-by-stage basis. On the other hand, a full-cartridge
structure allows you to take out, as one unit, all components,
including the inner casing, rotor, outer-barrel cover,
bearing, and shaft seal, except the outer barrel. This allows
you to return the full-cartridge component to the factory
for inspection, eliminating the need for on-site inspection.
EBARA has experience in manufacturing and delivering
a 100% capacity, ring section, double casing BFP for
350 MW supercritical plants (equivalent to the 50% ca-
pacity BFP for 700 MW supercritical plants). Figure 8
shows a full-cartridge, ring section, double casing
BFP in assembled and dissembled states.
6.3 Self-lubricating bearing
Involving high rotation speed and high output, BFPs
use a forced lubricating bearing. The lube oil unit (LO)
requires arrangement of a main oil pump (MOP) and
an auxiliary oil pump (AOP) for start-up and backup
purposes. Normal oil supply pressure is between 0.08
and 0.12 MPa. When the oil pressure has decreased (to
0.05 MPa) during operation, the pressure switch or
transmitter installed in the lubricant feed piping issues
an alarm and, at the same time, automatically activates
the auxiliary oil pump. When the oil pressure has
further decreased (to 0.03 MPa), it stops the BFP for
protecting the bearing and ensuring safety. The lube
oil unit is provided with an oil reservoir for containing
lubricant, oil-pressure regulating valve, oil cooler,
switching twin filter, and other equipment. A normal
oil reservoir requires a capacity three or more times
the flow rate of the oil pump. The required instruments
include devices for monitoring the differential filter
Inducer
Back to balance piping
Flow to balance the piping
Middle extraction
DischargeDischarge
SuctionSuction
Fig. 6 BFP with an inducer
Fig. 7 Disassembled inner volute and the rotor to be taken out
16-72 02/251
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─19
pressure, oil level of the oil reservoir, and oil temperature.
Since the unit equipped with these devices and
instruments make up a large percentage in terms of
foot print and manufacturing cost, it is significant to
streamline the lubrication system (Figure 9).
 Whether the bearing requires forced lubrication or
self-lubrication depends on the peripheral speed at the
radial bearing and the type of the thrust bearing. Con-
sidering the fact that BFPs for supercritical thermal
power plants provides a high rotation speed of more
than 5000 min-1
with high shaft power, they will probably
continue to require forced lubrication. Lubricant is fed
from the turbine if the BFP is driven by a turbine or
from the fluid coupling if the BFP is driven by a motor
with a fluid coupling, meaning that the lubricating
method of the pump bearing does not affect the
manufacturing cost or installation space.
 On the other hand, a typical BFP for combined-cycle
plants is directly driven by a 2P motor and provides an
output of approximately 2000 to 2500 kW, which is low
compared with BFPs for supercritical thermal power
plants. Equipped with no turbine or fluid coupling, this
BFP requires a separately installed lube oil unit. The
BFP, if equipped with a self-lubricating bearing, can
streamline the power generation system by reducing
the floor space for installation. While the current BFPs
use a forced lubricating bearing based on the existing
selection criteria, we think that it is possible to broaden
the self-lubricating bearings to a wider range of appli-
cations by improving the self-lubricating mechanism
and bearing cooling structure (Figure 10).
a) Assembled  b) Disassembled
Fig. 8 Full-cartridge, sectional-type BFP
Motor
Suction Discharge
Pump
Oil supply unit
Oil tank
Cooler
Auxiliary
oil pump
1780
1400
6700
Fig. 9 Boiler feed pump outline drawing (with oil supply unit)
Boiler Feed Pump (BFP)
Ebara Engineering Review No. 2512016-4
─  ─20
7. Conclusion
This paper outlines the history and characteristics of
boiler feed pumps (BFPs) used for commercial thermal
power generation along with technical improvements
to them. In pace with the increases in the capacity of
equipment for commercial thermal power generation,
improvements to adapt to higher temperatures and
pressures, and changes in operation method, BFPs
have been improving and advancing. We believe that,
in making efforts to meet the increasing demand for
power and to reduce the environmental load, thermal
power generation will play an increasingly important
role. It is expected that in Japan, the load-adjusting
operation will be more flexible through combined use
of renewable energy, and in oil-producing countries
more technologies will be introduced, for example, of
controlling carbon dioxide emissions based on carbon
capture and storage (CCS). It is required that while
responding to the changes in the market environment,
we should make further efforts to develop technologies
for further increasing the efficiency and reliability of
BFPs and reduce their manufacturing costs.
References
1)	 Boiler Outline 1“Trend of boilers for power generation and
the technological development for them”from Course 32
(2005 version) by Thermal and Nuclear Power Engineering
Society (issued in June 2006 by Thermal and Nuclear Power
Engineering Society).
2)	 “III Boiler feed pumps”from the lecture on pumps and pip-
ing/valves from the introductory course about thermal and
nuclear power generation (No.595, Vol.57, April 2006 issue
from Thermal and Nuclear Power Engineering Society).
3)	 Thermal engineering handbook 8−pumps (revised 2015 ver-
sion from Thermal and Nuclear Power Engineering Society).
4)	 Yoshikawa,“Sophistication of boiler feed pumps,”Turboma-
chinery November 2008 issue.
5)	 “2-3. Pumps”from the lecture on Preventive maintenance
and remaining life assessment of power generation equip-
ment from Course 27 by Thermal and Nuclear Power
Engineering Society (issued in June 2001 by Thermal and
Nuclear Power Engineering Society).
Radial
bearingMain shaft Thrust bearing
Fig. 10 Self-lubricating bearing

More Related Content

What's hot

Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
TURBINE FUNDAMENTAL
TURBINE FUNDAMENTALTURBINE FUNDAMENTAL
TURBINE FUNDAMENTALAgniva Firewall
 
Boiler Presentation
Boiler PresentationBoiler Presentation
Boiler Presentationanshsmartstud
 
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositTurbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositProject Sales Corp
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operationNitin Patel
 
Steam turbine
Steam turbineSteam turbine
Steam turbineNathan
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Manohar Tatwawadi
 
Power plant performance_efficiency
Power plant performance_efficiencyPower plant performance_efficiency
Power plant performance_efficiencyKeyur Patel
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its typesSanila Khalid
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines BasicsPrasad Vejendla
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 
Gas turbine power plant
Gas turbine power plantGas turbine power plant
Gas turbine power plantRipuranjan Singh
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINESAI SHARATH GAMPA
 
Heat balance diagram
Heat balance diagramHeat balance diagram
Heat balance diagramJITENDRA BHATIA
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineManohar Tatwawadi
 

What's hot (20)

STEAM TURBINE BASIC
STEAM TURBINE BASIC STEAM TURBINE BASIC
STEAM TURBINE BASIC
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
TURBINE FUNDAMENTAL
TURBINE FUNDAMENTALTURBINE FUNDAMENTAL
TURBINE FUNDAMENTAL
 
Boiler Presentation
Boiler PresentationBoiler Presentation
Boiler Presentation
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositTurbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Cooling water (CW) system
Cooling water (CW) system Cooling water (CW) system
Cooling water (CW) system
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
 
Power plant performance_efficiency
Power plant performance_efficiencyPower plant performance_efficiency
Power plant performance_efficiency
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Gas turbine power plant
Gas turbine power plantGas turbine power plant
Gas turbine power plant
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
Heat balance diagram
Heat balance diagramHeat balance diagram
Heat balance diagram
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 

Similar to BFP History, Design and Advancements

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
Improved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad MollaImproved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad MollaRazin Sazzad Molla
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantAbhishek Kumar
 
07 ii-gas combined-cycle
07 ii-gas combined-cycle07 ii-gas combined-cycle
07 ii-gas combined-cycleIIT Kanpur
 
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFULIN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFULHafiz M .Hamid
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccppDurgSingh
 
To Improve Thermal Efficiency of 27mw Coal Fired Power Plant
To Improve Thermal Efficiency of 27mw Coal Fired Power PlantTo Improve Thermal Efficiency of 27mw Coal Fired Power Plant
To Improve Thermal Efficiency of 27mw Coal Fired Power PlantIJMER
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1Prashant kumar
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesjyotishmathi college
 
steam power plant
steam power plantsteam power plant
steam power plantOmar Qasim
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.Ankit Kumar
 
Ind lab.pptx
Ind lab.pptxInd lab.pptx
Ind lab.pptxAsta86
 
Thermal Efficiency of Combined Cycle Power Plant
Thermal Efficiency of Combined Cycle Power PlantThermal Efficiency of Combined Cycle Power Plant
Thermal Efficiency of Combined Cycle Power PlantDr. Amarjeet Singh
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02arvind singh rathore
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )HaseebAhmadChughtai
 
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)HaseebAhmadChughtai
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantShikhar Sodhani
 
Design of superheater for 210 MW thermal powerplant final
Design of superheater for 210 MW thermal powerplant finalDesign of superheater for 210 MW thermal powerplant final
Design of superheater for 210 MW thermal powerplant finalKundan Chakraborty
 
Report on improved efficiency of gas turbine final
Report on improved efficiency of gas turbine finalReport on improved efficiency of gas turbine final
Report on improved efficiency of gas turbine finalRazin Sazzad Molla
 

Similar to BFP History, Design and Advancements (20)

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Improved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad MollaImproved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad Molla
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
 
07 ii-gas combined-cycle
07 ii-gas combined-cycle07 ii-gas combined-cycle
07 ii-gas combined-cycle
 
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFULIN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFUL
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
To Improve Thermal Efficiency of 27mw Coal Fired Power Plant
To Improve Thermal Efficiency of 27mw Coal Fired Power PlantTo Improve Thermal Efficiency of 27mw Coal Fired Power Plant
To Improve Thermal Efficiency of 27mw Coal Fired Power Plant
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliaries
 
steam power plant
steam power plantsteam power plant
steam power plant
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
 
Ind lab.pptx
Ind lab.pptxInd lab.pptx
Ind lab.pptx
 
Thermal Efficiency of Combined Cycle Power Plant
Thermal Efficiency of Combined Cycle Power PlantThermal Efficiency of Combined Cycle Power Plant
Thermal Efficiency of Combined Cycle Power Plant
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
 
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Design of superheater for 210 MW thermal powerplant final
Design of superheater for 210 MW thermal powerplant finalDesign of superheater for 210 MW thermal powerplant final
Design of superheater for 210 MW thermal powerplant final
 
Report on improved efficiency of gas turbine final
Report on improved efficiency of gas turbine finalReport on improved efficiency of gas turbine final
Report on improved efficiency of gas turbine final
 

More from Udhayakumar Venkataraman

Sugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdfSugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdfUdhayakumar Venkataraman
 
Sintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docxSintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docxUdhayakumar Venkataraman
 
Performance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptxPerformance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptxUdhayakumar Venkataraman
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaUdhayakumar Venkataraman
 
Maintenance strategy forf power plant
Maintenance strategy forf power plantMaintenance strategy forf power plant
Maintenance strategy forf power plantUdhayakumar Venkataraman
 
Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Udhayakumar Venkataraman
 
Efficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsEfficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsUdhayakumar Venkataraman
 
Efficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsEfficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsUdhayakumar Venkataraman
 

More from Udhayakumar Venkataraman (20)

Sugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdfSugar Industrial Boiler tube failure.pdf
Sugar Industrial Boiler tube failure.pdf
 
How do you use PID in PLC.docx
How do you use PID in PLC.docxHow do you use PID in PLC.docx
How do you use PID in PLC.docx
 
Sintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docxSintering process of Iron Ore General.docx
Sintering process of Iron Ore General.docx
 
IA & SA Compressed Air system.docx
IA & SA Compressed Air system.docxIA & SA Compressed Air system.docx
IA & SA Compressed Air system.docx
 
Performance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptxPerformance Paramters of Coal Fired TPS in General for our team.pptx
Performance Paramters of Coal Fired TPS in General for our team.pptx
 
Turbine design need of the hour
Turbine design need of the hourTurbine design need of the hour
Turbine design need of the hour
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performa
 
Fgd general norms
Fgd general normsFgd general norms
Fgd general norms
 
Condenser vacuum discussion
Condenser vacuum discussionCondenser vacuum discussion
Condenser vacuum discussion
 
Condenser vacuum discussion
Condenser vacuum discussionCondenser vacuum discussion
Condenser vacuum discussion
 
By abb motor e book
By abb motor  e bookBy abb motor  e book
By abb motor e book
 
Maintenance strategy forf power plant
Maintenance strategy forf power plantMaintenance strategy forf power plant
Maintenance strategy forf power plant
 
Bearing over greasing failures ]
Bearing over greasing failures ]Bearing over greasing failures ]
Bearing over greasing failures ]
 
Bearings type and selection
Bearings type and selectionBearings type and selection
Bearings type and selection
 
Seals of turbine and improvement
Seals of turbine and improvementSeals of turbine and improvement
Seals of turbine and improvement
 
Soot blowing and advantages
Soot blowing and advantagesSoot blowing and advantages
Soot blowing and advantages
 
Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2
 
Efficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsEfficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuators
 
Boiler optimization journey
Boiler optimization journeyBoiler optimization journey
Boiler optimization journey
 
Efficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuatorsEfficiency by controlling modulation of actuators
Efficiency by controlling modulation of actuators
 

Recently uploaded

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube ExchangerAnamika Sarkar
 

Recently uploaded (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Study on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ï»żTube Exchanger
 

BFP History, Design and Advancements

  • 1. Ebara Engineering Review No. 2512016-4 ─  ─11 ability because it must operate in more severe condi- tions such as partial load operation and increased fre- quency of start and stop actions. 2. History 2.1 BFPs for conventional thermal power plants Since BFPs are used to feed high-temperature/pres- sure water to boilers, their history is closely related with the improvement toward higher boiler capacities and higher temperatures and pressures.  Boilers and other equipment for commercial thermal power generation have been improved to achieve higher per-unit capacities with the objective of reducing the percentage of equipment costs (for advantages of scale) as well as to achieve higher steam temperatures and pressures for higher thermal efficiency1) .  Looking at the history of boilers in Japan, the maximum unit capacity was 66 MW in 1955, which increased to 325 MW in 1965 and to 600 MW in 1969. In 1974, a boiler with a capacity of 1000 MW was brought into operation. Boilers in Japan thus have been undergoing rapid increases in capacity. After 1980, boilers with a unit capacity of more than 600 MW went mainstream, Abstract In a thermal power plant, the boiler feed pump (BFP) is one of the critical auxiliary machines that are equivalent to the heart of the plant. In pace with the increases in the capacity of equipment for thermal power generation, improvements to adapt to higher temperatures and pressures, and changes in operation method, BFPs have been improving and advancing. This paper explains how BFPs have been upsized and made compatible to higher pressures; main specifications of BFPs; structures and materials of typical BFPs for conventional supercritical thermal power plants and for combined-cycle thermal power plants; characteristics of the shaft seal and bearing; technological development for higher capacities and performance; actual develop- ment and delivery of 100% capacity BFPs; improvements to the structure design for increasing the stress resistance of BFPs so that they can adapt to more severe conditions in the operation of thermal power plants associated with the spread of renew- able energy; and examples of efforts to streamline the BFP design for manufacturing cost reduction and space saving. Keywords: Feed water pump, High pressure, Efficiency, Super critical thermal power, Combined cycle thermal power, Reliability, Specific speed, Shaft strength, Bearing, Double casing 1. Introduction This paper outlines the history and structural and technical characteristics of boiler feed pumps (hereafter referred to as BFP), which are high-pressure pumps mainly used for thermal power generation.  In a thermal power plant, the BFP is one of the criti- cal auxiliary machines that are equivalent to the heart of the plant. In thermal power generation, high-pres- sure steam is used to drive a turbine, which in turn ro- tates the generator directly connected to the turbine to generate power. The steam is produced by feeding hot water to the boiler from the BFP. This means that an unexpected stop of the BFP completely stops power generation and therefore the BFP requires a very high level of reliability. In recent years, with the populariza- tion of renewable energy, thermal power generation re- quires load adjustment for a stable power generation system as well as operation under severe conditions such as rapid changes in load. The BFP is also required to provide even higher levels of capabilities and reli- [Commentary] Boiler Feed Pump (BFP) Shigeru YOSHIKAWA* * Fluid Machinery Systems Company
  • 2. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─12 followed by many units with a capacity of more than 1000 MW built after 1990.  Looking at the steam conditions, Japan’s first boiler with a steam pressure of 16.6 MPa (at the inlet of the turbine) was fabricated in 1959. In 1967, Japan’s first supercritical constant-pressure boiler was brought into operation for higher generation efficiency. Boilers sub- sequently underwent rapid increases in supercritical pressure, resulting in a situation where 82% of the power generating units built in 1974 were of a super- critical type1) .  When used in combination with a supercritical-pres- sure boiler with a unit capacity of more than 1000 MW, the BFP is required to deliver a very high level of per- formance such as a flow rate of approximately 1700 t/h, a discharge pressure of approximately 30 MPa, and a shaft power of approximately 20000 kW. To achieve this high pressure, the BFP is required to achieve a high rotation speed of 5000 to 6000 min-1 . At that time, it was common to combine two 50% capacity BFPs driven by steam turbines (T-BFPs) and one BFP driven by a motor with a speed-increasing gear (M-BFP) as a backup and for start-up purposes. Figure 1 shows the relationship between the increases in boiler pressure and BFP discharge pressure2) .  Note that EBARA supplied BFPs for both of Japan’s first supercritical and ultra-supercritical (USC) power generating units. EBARA also delivered Japan’s first BFP for a 1000 MW power generating unit.  In the 1980s, many nuclear power plants were built, which started to act as base-load power plants. Under the circumstances, in commercial thermal power gen- eration, many units that were compatible with middle- load operation started to be used, with supercritical variable-pressure once-through boilers, capable of main- taining high efficiency even in the middle-load area, go- ing mainstream. This situation required variable-speed motor drives, leading to the introduction of motor drives with a built-in speed increasing gear and a fluid coupling.  Efforts to increase the thermal efficiency continued. In 1989, a 700 MW, USC plant was brought into opera- tion with a main steam pressure of 31.1 MPa and a main steam temperature of 566 °C.  Table 1 shows the specifications of the BFPs used in this plant2) . 2.2 BFPs for combined-cycle thermal power plants In parallel with the movement to improve the systems for the conventional thermal power generation toward higher capacities, temperatures, and pressures, com- bined-cycle power generation went into actual use in the middle 1980s, a thermal power generation system that achieves higher efficiency by combining two cycles: a gas-turbine combustion cycle and a steam-turbine cycle that uses the exhaust heat from the former cycle. With continuous technological development for cooling turbine blades and making them heat resistant, the gas-turbine combustion temperature has increased, resulting in fur- ther improvement in power generation efficiency. State- of-the-art combined-cycle plants (with a gas turbine that uses a temperature of higher than 1 600 °C) have achieved a sending-end efficiency of as high as 60%. In recent years, many combined-cycle thermal power plants have been constructed because they use, as a fuel Feed pump discharge pressure PressureMPa Boiler pressure Approx.38 MPa 45 40 35 30 25 20 15 10 5 0 31 MPa Approx.30 MPa Approx.20 MPa 17 MPa 25 MPa Ultra-supercritical (USC) 19891967 Supercritical Fig. 1 Boiler pressure and BFP discharge pressure Table 1 BFP specifications for 700 MW USC thermal power plant Purpose Main feed water Start-up and backup Capacity t/h 1200 730 Discharge pressure MPa 38.05 37.26 Rotation speed min-1 6000 6300 Water temperature ℃ 188.4 184.1 Drive Steam turbine Motor drive (with a fluid coupling) Output kW 17500 12000 Number of units 2 1
  • 3. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─13 for gas turbines, LNG−a fuel that emits less carbon dioxide−and therefore impose less environmental load. These plants require BFPs that feed water to heat recovery steam generators (HRSG). 3. Structures of BFPs 3.1 BFPs for conventional thermal power plants3) (1) Casing structure BFPs used in supercritical and USC plants are required to provide a high discharge pressure of 30 to 35 MPa with a feed-water temperature of as high as 180 °C or higher. These plants use double casing barrel-type multi-stage pumps designed to be adaptable to high- pressure and -temperature specifications. These pumps have a forged cylindrical outer barrel with a high rigid- ity that contains a single-piece structure consisting of an internal casing and a rotor, with one end of the outer barrel fastened to a discharge cover with bolts. They are designed according to the technical standard for thermal power generation or a similar public standard so that the thicknesses of the outer barrel, discharge cover, and discharge nozzle, and the size and number of cover fastening bolts will provide sufficient strengths against the design pressure (maximum allowable working pressure).  The outer barrel is a simple thick cylinder that is not affected by high pressures or changes in pressure. The barrel is fastened to the discharge cover with bolts with a spiral gasket inserted between them to prevent leakage of water. The fastening bolts are controlled with a hydraulic wrench, bolt heater, or bolt tensioner so that it will constantly provide appropriate fastening force.  By providing a middle extraction flange on the dis- charge cover side or the suction side as appropriate, in- termediate pressure can be taken out so that it can be used for applications such as coolant spraying to the reheater. (2) Internal structure The structures of the internal casing, impeller, and other hydraulic components are divided into two groups: one group uses a combination of a axially split casing, back to back arrangement impeller, and a volute type and the other group uses a combination of a ring section casing, straight through impeller, and a diffuser type. The latter group requires a balance disk or a similar component for balancing the axial thrust. (3) Material The outer barrel and discharge cover, which are pres- sure-containing components, are made of forged carbon steel, and the gasket surface and high velocity sections are overlaid with austenitic stainless steel to prevent erosion. The internal casing and impeller are made of 13Cr or 13Cr-4Ni martensitic cast stainless steel. (4) Shaft seal and bearing Most commercial thermal power generation plants in Japan used non-contact throttle bushes or floating rings, which are not likely to wear under high-speed and -pressure conditions and are suitable to continuous operation. In recent years, overseas plants in particular use mechanical seals in many cases. As for the bear- ings, a forced lubricating type is used.  Figure 2 shows the structure of a typical BFP for conventional thermal power plants. 3.2 BFPs for combined-cycle plants3) (1) Casing structure BFPs for combined-cycle thermal power plants feed water to the heat recovery steam generator. They are required to provide a discharge pressure of 15 to 20 MPa and a feed-water temperature of approximately 150 °C, which are substantially low compared to super- critical thermal power plants. For this reason, single case, ring section-type, multi-stage pumps are used in most combined-cycle plants. However, they absolutely require technologies for analyzing and evaluating ther- mal stress and deformation because they are required to adapt to quick plant starts and abrupt changes in feed-water temperature. The basic structure of a ring section-type casing consists of a suction casing, dis- charge casing, inter stage casing, and intermediate ex- traction casing, which are fastened with casing bolts, with the joints between the casings sealed with metal touch based on the fastening contact pressure of the bolts. Depending on the results of thermal deformation analysis, an O-ring is fitted as appropriate to completely prevent leakage of feed water even during thermal transient. (2) Internal structure Heat recovery steam generators for combined-cycle
  • 4. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─14 plants are often structured with three stages (high-, middle-, and low-pressure drums), and designed to ex- tract intermediate-pressure feed water from the inter- mediate stage of the BFP to feed it to the middle-pres- sure drum. In other words, one unit of BFP can feed middle- and high-pressure water. Total amount of the middle- and high-pressure feed water are sucked from the suction casing. After the amount of the water to be fed to the middle-pressure drum is extracted from the extraction stage, only the amount of the water to be fed to the high-pressure drum is pressurized. For this reason, the specific speeds (Ns) of impeller and diffuser for the stage before the extraction are often different from those after the extraction.  In combined-cycle plants, ring section-type diffuser pumps are used. They have all impellers arranged in one direction and therefore require a thrust balancing component. Balancing components are available in two types: balance-disk and balance-drum types. Water leaked from the balancing component is normally re- turned to the suction side. When the pressure decreases in the balancing component, the water temperature rises. When the saturated vapor pressure of water with the temperature rise taken into account is higher than the suction pressure, the water may flush out and re- turns to the pump inlet. If this is the case, the pump does not operate soundly. If this happens, the balancing piping is connected to the deaerator.  Pumps structured to use double suction impeller at only the first stage are often used because this struc- ture can reduce the required NPSH by halving the suc- tion flow because of the double suction. (3) Material The suction, discharge, and extraction casings, which are pressure-containing components, are made of 13Cr- 4Ni cast stainless steel and the inter stage casing of 13Cr-4Ni stainless steel. (4) Shaft seal and bearing For the shaft sealing device, a mechanical seal with almost no leakage is used because the pressure and peripheral speed conditions are slightly less severe than those for BFPs for supercritical plants. For the bearing, though a forced lubricating type is used, a self-lubricat- ing type can also be safely used in some cases as will be described later since the peripheral-speed conditions are less severe than those in conventional supercritical thermal power plants. Figure 3 shows the structure of a typical BFP for combined-cycle thermal power plants. 4. Upsizing and sophistication of BFPs With the growth of equipment for thermal power gen- eration in capacity and pressure, BFPs have been upsized and become sophisticated. Among the pumps used in a thermal power plant, the BFP uses the most power because it must produce high pressures re- quired by the boiler. This means that the improve- Discharge nozzle Temperature detection seat Suction ïŹ‚ange Forced lubricating bearing (radial) Throttle bush Balance return ïŹ‚angeNozzle for draining and warmingMiddle extraction ïŹ‚ange for spraying to reheater Throttle bush Forced lubricating bearing (thrust) Discharge cover Outer barrel Fig. 2 Double casing barrel type BFP for supercritical thermal power plants
  • 5. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─15 ment in BFP efficiency is a critical challenge that must be solved to reduce the environmental load. The impeller used in a BFP is a centrifugal pump with a specific speed (Ns) of approximately 120 to 250 (m3 / min, m, min-1 ). Generally, the pump efficiency is higher when the specific speed is higher within this range or the flow rate is higher if the specific speed is the same. In a normal case, two BFPs each with a 50% capacity are used as the main feed pumps. If one BFP can provide a 100% capacity, it improves the efficiency through the increase in capacity and enhancement in specific speed as well as helps save space and re- sources4) . In Japan, EBARA has experience in designing, fabricating, and delivering main feed pumps with a specification of 100% capacity per unit for 500 MW and 600 MW supercritical thermal power plants and these pumps are successfully operating. In some coun- tries and areas, a system based on a single main feed pump with a 100% capacity is in actual use in 1000 MW plants. Recently, EBARA also manufactured and delivered a large BFP that satisfied this requirement. Figure 4 shows actually shipped BFP and followings are the outlined specifications of this BFP.  Capacity of 3200 t/h×total pump head of 3800 m× shaft power of 37700 kW×rotation speed of 5000 min-1  Specific speed of approximately 250 (m3 /min, m, min-1 )  In general, higher capacities and higher specific speeds increase the pump efficiency. The shaft power increases with the increase in capacity; accordingly, if the rotation speed is the same as that of a 50% capacity BFP, the main shaft has larger torque and is thus required to have a large diameter, compared to conventional BFPs, to maintain the required strength. If the rotational speed and pump head remain the same, the diameter of the impeller also remains unchanged. This means the main shaft with an increased diameter interferes with the flow passage of the impeller meridian plane. Under the circumstances, to achieve high efficiency, we determined the optimal hydraulic shape including the volute−which reduces the flow velocity of the water from the impeller, and converts it into static pressure −and the cross over passages between the stages. To this end, we made full use of CFDnote including analysis of unsteady flows.  We also determined, through analysis of the main shaft strength, the optimal diameter that minimizes the Fig. 4 100% capacity BFP for 1000 MW supercritical thermal power plants 16-72 01/251 Intermediate volute Middle-pressure drum feed-water ïŹ‚ange High-pressure drum feed-water ïŹ‚ange Discharge casing Suction casing Suction ïŹ‚ange Casing bolt Bearing (thrust)Bearing (radial) Mechanical seal Mechanical seal Balancing component Fig. 3 Structure of a BFP for combined cycle thermal power plants
  • 6. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─16 increase in shaft diameter from that of the 50% capacity BFP (existing conventional design). For a system based on a 100% capacity BFP, only one unit is used and if it should unexpectedly stop, the power generation capacity is totally lost. For this reason, needless to say, we designed the main shaft so that each part of the shaft would maintain a sufficient strength. Note: Computational fluid dynamics  Table 2 compares the performance of BFPs delivered to power plants of typical sizes and with typical out- puts. The BFP shaft power consumes 3.5 to 4% of plant output; this ratio can be reduced through the increase in efficiency to be achieved by increases in capacity. For 500 MW plants, we successfully reduced the ratio to the rated plant output by approximately 0.5 point by using one 100% capacity BFP. Even if the output is the same, however, the water temperature (density), capac- ity, and total pressure are different from plant to plant and therefore it is not generally practical to make com- parisons according to only the shaft power ratio. Look- ing at the efficiency, for the 500 MW plants, while the system based on two units exhibited an efficiency of 82%, the system based on a single unit achieved an 86% efficiency, resulting in a 4-point improvement as described earlier4) . 5. Improvement in BFP stress resistance Recent years have seen increased introductions of re- newable energies such as solar and wind power. Re- newable energy is expected to continue to spread as one of the measures against global warming because it does not use fossil fuel and therefore emits no carbon dioxide when used for power generation. However, the power output based on solar and wind power signifi- cantly depends on the meteorological conditions such as the weather and wind conditions, resulting in the drawback that it is difficult to stably operate electric power systems based on renewable energy. In order to cope with this issue, thermal power plants are increasingly required to provide more flexible power system operation with a higher level of supply-and-de- mand adjustment capability. Specifically, they are re- quired to improve the load change rate, minimize the minimum load factor, and shorten the start-up time.  In association with the supply-and-demand adjust- ment capability added to thermal power plants, BFPs are required to operate in more severe conditions such as increased frequency of start and stop actions, changes in feed water temperature, and increased frequency of low flow operation. To address these requirements, efforts have been made to improve the stress resis- tance (robustness) of BFPs by reviewing the structure, materials, and design. Figure 5 shows an example of a BFP structure that has incorporated the structural and design considerations to adapt to the operational re- quirements above. Table 3 shows specific items that must be improved and phenomena that must be ad- dressed along with possible causes of them (some of the measures in the Table 3 are not always against the more severe operating conditions but have been intro- duced as part of the efforts to improve the general functional reliability of BFPs5) ). 6. Streamlining of BFPs As described earlier, BFPs are the heart of the main piping system in thermal power systems and therefore required to provide high levels of functionality and reli- ability. On the other hand, it is also important to supply power at as low a price as possible, in developing coun- tries in particular, where the demand for power is pressing and therefore the construction of many new thermal power plants is planned. For this reason, pump suppliers are also required to cooperate to simplify the equipment for power generation plants and make efforts to reduce the costs for such equipment as one of the challenges that they must address. Here are some of the efforts to streamline BFPs. Table 2 Specifications of typical BFPs Rated plant output Capacity Total pressure Rotation speed Shaft power Efficiency Number of unit Power ratio MW t/h MPa min−1 kW % Unit % 500 890 29.67 5500 9999 82 2 4.00 500 1630 30.1 5500 17747 86 1 3.55 600 1000 30.1 5500 11157 83.5 2 3.72 600 1860 33.2 5000 22589 85.3 1 3.76 700 1120 30.6 5500 12711.7 85 2 3.63 1000 1650 30.5 5500 18393.3 86 2 3.68 1050 1700 31.2 6000 19279.5 85.5 2 3.67
  • 7. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─17 6.1 Discontinuance of booster pumps With a rotation speed of as high as 5000 to 6000 min-1 , BFPs for supercritical thermal power plants require a high required NPSH (NPSHR). With an increase in power generation capacity, the flow rate of the BFP in- creases, which requires an even higher NPSHR. The NPSH available (NPSHA) of a BFP, which is deter- mined by the height of the deaerator installed, is nor- mally approximately 20 to 25 m. For this reason, through the cross over piping, a booster pump is nor- mally installed upstream of the BFP to ensure the NPSH required for the BFP.  Under the circumstances, M-BFPs for start-up pur- poses used in some plants are actually designed to in- clude an impeller equipped with an inducer in the first stage to lower the NPSHR for elimination of the need to use a booster pump and cross over piping. This design helps reduce plant construction costs by saving space and resources. Figure 6 shows the structure of a BFP with an inducer4) . ① ⑱ â‘„ â‘€ ②④ ⑩ ⑹ ⑧ ⑩ Fig. 5 BFP structure that has incorporated measures for increasing the robustness Table 3 Measures for increasing the robustness of BFPs No Degradation Causes Measures for increasing the robustness ① Wall thickness reduction of discharge nozzle Erosion caused by high velocity and/or uneven flow Overlaying austenitic stainless steel onto the inner surface ② Erosion of high-differential-pressure part of the inner volute Degraded seal performance of metal touch seal or self-compressed gasket associated with increased frequencies of start and stop actions Using an auxiliary O-ring in combination ⑱ Incipient cavitation Increased duration of low flow operation associated with the adoption of DSS, etc. Replacing the first stage impeller with new one designed for low flow regarding with inlet configuration ④ Cracks at the portion to which auxiliary piping is attached Impact of pulsation caused by increased duration of low flow operation Modifying the nozzle stub so that it will be a more rigid structure â‘€ Vibration caused by misalignment Changes in nozzle load associated with increased frequencies of start and stop actions Installing an stabilizing device â‘„ Increased bearing vibration Impact of pulsation caused by increased duration of low flow operation Using a full circular bearing housing ⑩ Damaged bearing metal Wire-wool damage of 13Cr steel shaft caused by foreign particles in lube oil Overlaying carbon steel to the main shaft journal ⑧ Occurring of abruptly changing vibration Torque locking caused by poor sliding of the gear-coupling tooth surface Upgrading to a flexible disk coupling ⑹ Fretting corrosion on the fitting portion of the thrust disk Decreased torque of the shaft-end nut. Loosened fixed disk caused by secular distortion of the disk contact surface Using a shaft-end nut of a locking sleeve type Using a long hub type thrust disk ⑩ Degraded mechanical seal for inter stage bleed off No maintenance for a long time because it is installed on the suction cover and not required when the inner-volute rotor disassembly Discontinuing the use of the bleed off pipe and the mechanical seal as the structure for extraction from the discharge cover The above number is the part that shows the number of the in Fig. 5.
  • 8. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─18 6.2 Full-cartridge, ring section, double casing BFPs The BFPs shown in Figs. 2, 6, and Figure 7 are structured with a horizontally split internal casing (inner volute). As Fig. 7 shows, a BFP with this structure allows you to take out the shaft and impeller as a rotor assembled as one unit if the upper half of the inner volute is disassembled. Since this facilitates inspection in power plants, this design has been adopted in many power plants inside and outside Japan. It also has the drawback, however, that the design requires a high manufacturing cost because the inner volute has a complicated structure made of cast steel. On the other hand, the structure with a ring section-type internal casing (inner case) offers the cost-related advantages that it does not require an inner volute, which is costly, and that when compared under the same performance (pressure), it allows you to slightly reduce the diameter of the internal casing, resulting in a smaller diameter of the outer barrel. This structure has the drawback, however, that it is difficult to inspect on site because inspection of the rotor requires you to vertically place the inner casing and rotor and then take out the inner case, guide vane, and impeller on a stage-by-stage basis. On the other hand, a full-cartridge structure allows you to take out, as one unit, all components, including the inner casing, rotor, outer-barrel cover, bearing, and shaft seal, except the outer barrel. This allows you to return the full-cartridge component to the factory for inspection, eliminating the need for on-site inspection. EBARA has experience in manufacturing and delivering a 100% capacity, ring section, double casing BFP for 350 MW supercritical plants (equivalent to the 50% ca- pacity BFP for 700 MW supercritical plants). Figure 8 shows a full-cartridge, ring section, double casing BFP in assembled and dissembled states. 6.3 Self-lubricating bearing Involving high rotation speed and high output, BFPs use a forced lubricating bearing. The lube oil unit (LO) requires arrangement of a main oil pump (MOP) and an auxiliary oil pump (AOP) for start-up and backup purposes. Normal oil supply pressure is between 0.08 and 0.12 MPa. When the oil pressure has decreased (to 0.05 MPa) during operation, the pressure switch or transmitter installed in the lubricant feed piping issues an alarm and, at the same time, automatically activates the auxiliary oil pump. When the oil pressure has further decreased (to 0.03 MPa), it stops the BFP for protecting the bearing and ensuring safety. The lube oil unit is provided with an oil reservoir for containing lubricant, oil-pressure regulating valve, oil cooler, switching twin filter, and other equipment. A normal oil reservoir requires a capacity three or more times the flow rate of the oil pump. The required instruments include devices for monitoring the differential filter Inducer Back to balance piping Flow to balance the piping Middle extraction DischargeDischarge SuctionSuction Fig. 6 BFP with an inducer Fig. 7 Disassembled inner volute and the rotor to be taken out 16-72 02/251
  • 9. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─19 pressure, oil level of the oil reservoir, and oil temperature. Since the unit equipped with these devices and instruments make up a large percentage in terms of foot print and manufacturing cost, it is significant to streamline the lubrication system (Figure 9).  Whether the bearing requires forced lubrication or self-lubrication depends on the peripheral speed at the radial bearing and the type of the thrust bearing. Con- sidering the fact that BFPs for supercritical thermal power plants provides a high rotation speed of more than 5000 min-1 with high shaft power, they will probably continue to require forced lubrication. Lubricant is fed from the turbine if the BFP is driven by a turbine or from the fluid coupling if the BFP is driven by a motor with a fluid coupling, meaning that the lubricating method of the pump bearing does not affect the manufacturing cost or installation space.  On the other hand, a typical BFP for combined-cycle plants is directly driven by a 2P motor and provides an output of approximately 2000 to 2500 kW, which is low compared with BFPs for supercritical thermal power plants. Equipped with no turbine or fluid coupling, this BFP requires a separately installed lube oil unit. The BFP, if equipped with a self-lubricating bearing, can streamline the power generation system by reducing the floor space for installation. While the current BFPs use a forced lubricating bearing based on the existing selection criteria, we think that it is possible to broaden the self-lubricating bearings to a wider range of appli- cations by improving the self-lubricating mechanism and bearing cooling structure (Figure 10). a) Assembled  b) Disassembled Fig. 8 Full-cartridge, sectional-type BFP Motor Suction Discharge Pump Oil supply unit Oil tank Cooler Auxiliary oil pump 1780 1400 6700 Fig. 9 Boiler feed pump outline drawing (with oil supply unit)
  • 10. Boiler Feed Pump (BFP) Ebara Engineering Review No. 2512016-4 ─  ─20 7. Conclusion This paper outlines the history and characteristics of boiler feed pumps (BFPs) used for commercial thermal power generation along with technical improvements to them. In pace with the increases in the capacity of equipment for commercial thermal power generation, improvements to adapt to higher temperatures and pressures, and changes in operation method, BFPs have been improving and advancing. We believe that, in making efforts to meet the increasing demand for power and to reduce the environmental load, thermal power generation will play an increasingly important role. It is expected that in Japan, the load-adjusting operation will be more flexible through combined use of renewable energy, and in oil-producing countries more technologies will be introduced, for example, of controlling carbon dioxide emissions based on carbon capture and storage (CCS). It is required that while responding to the changes in the market environment, we should make further efforts to develop technologies for further increasing the efficiency and reliability of BFPs and reduce their manufacturing costs. References 1) Boiler Outline 1“Trend of boilers for power generation and the technological development for them”from Course 32 (2005 version) by Thermal and Nuclear Power Engineering Society (issued in June 2006 by Thermal and Nuclear Power Engineering Society). 2) “III Boiler feed pumps”from the lecture on pumps and pip- ing/valves from the introductory course about thermal and nuclear power generation (No.595, Vol.57, April 2006 issue from Thermal and Nuclear Power Engineering Society). 3) Thermal engineering handbook 8−pumps (revised 2015 ver- sion from Thermal and Nuclear Power Engineering Society). 4) Yoshikawa,“Sophistication of boiler feed pumps,”Turboma- chinery November 2008 issue. 5) “2-3. Pumps”from the lecture on Preventive maintenance and remaining life assessment of power generation equip- ment from Course 27 by Thermal and Nuclear Power Engineering Society (issued in June 2001 by Thermal and Nuclear Power Engineering Society). Radial bearingMain shaft Thrust bearing Fig. 10 Self-lubricating bearing