This document provides details on the construction of a mat foundation. It describes the key steps including shoring, soil excavation, reinforcement placement, concrete casting, and curing. Advantages of mat foundations include reducing differential settlement and providing a stable base for poor soil conditions or where a basement is needed. Disadvantages include higher costs than other foundation types and potential issues with heat and water. The document appears to be a student presentation summarizing their site visit observations of mat foundation construction procedures.
1. CE 200
DETAILS OF CONSTRUCTION
PRESENTATION ON MAT FOUNDATION
Submitted By:-
Group-02, Section-B1, 2nd
Year, 2nd
Semester,
Department Of Civil Engineering
2. Towhidur Rahman Tasin ID NO.16-02-03-088
Faria Sultana ID NO.16-02-03-085
Ashik Azad Nibir ID NO.16-02-03-086
Ashiqur Rahman Prottoy ID NO.16-02-03-087
Soumik Paul ID NO.16-02-03-089
Contributed By
5. A continuous, thick, concrete slab foundation heavily
reinforced with steel supporting an entire structure.
It is a type of shallow foundation (depth ≤ width).
All the columns are connected to an large RCC slab
and the slab has direct contact with the soil.
Mainly constructed at a depth of 1-20 feet from
ground level.
Mat Foundation
6. When foundation area cover 50% -60% of the total plot area
because of large column loads.
The soil is soft with a low bearing capacity.
When the expenses of deep foundation is higher then raft
foundation.
When basement is needed
Reasons For Mat Foundation
9. Shoring is commonly used when installing the foundation.
Shoring support the surrounding loads until the underground
levels of the building are constructed.
Used to prevent the side soil from collapsing.
Can be of 3 types:
i. Concrete Pile shore
ii. Timber Pile Shore
iii. Steel Pile shore
Shoring
11. o After Shoring the soil is
excavated.
o The soil wasn’t excavated
fully at once rather it was
done step wise for depth
basis bracing.
Soil Excavation
12. o A horizontal support for the boundary
shores during excavation and foundation.
o Depends on the depth of foundation.
o Also known as horizontal shores.
o Ties and Struts are placed.
o Further excavation was done if needed.
Strutting & Bracing
14. For Leveling the soil, spade or
other tools are used.
Soil is dressed with sand.
Sand is compacted by hammer.
Leveling & Compaction
15. First one layer of brick flat
soaling is placed over the
area.
Provide Polythene, BFS & CC Layer
After that Cement concrete
layer of 3” thickness is
provided.
After that Polythene is placed
as damp proof course.
16. CC blocks of Circular/Cubic
shape of about 3” height are
placed on the CC layer.
Blocks are provided to
maintain clear cover at the
bottom.
CC Block Placing
17. A batch of horizontal reinforcement
placing;
Another batch of reinforcement
placement to complete the bottom
mesh;
Column rod placement;
Vertical rod (chair) placement over
bottom mesh to hold the upper mesh;
Upper mesh placement.
Reinforcement Placement
19. Important Factors
Reinforcement Selection 12mm ~ 25mm
60 ~ 72.5 Graded
Chair Height 2 feet
Heavy steel wire used for joining the reinforcement
Spacing between two Vertical & Horizontal
reinforcement bar are 6 “
20. Retaining Wall
• It’s one kind of wall constructed
around the mat foundation.
• It is constructed to resist the
lateral load of soil.
21. The process of pouring concrete
in the reinforcement mesh.
Start from one end.
Casting was done in layers.
Casting
22. • Casting and Compacting
was done simultaneously.
• Vibrator machine was
used for compacting
Compaction
23. After casting the concrete,
the upper surface was
leveled.
Levelers were used for
this process.
Leveling
24. Curing is done for 28 days.
Water is sprayed on the
surface for curing.
Making water pond on the
surface.
Curing
25. Advantages:
• Reduces differential settlement.
• Ideal for poor ground condition.
• Provides more space.
• Provides basement.
Disadvantages:
• Cost is high as shore protection is needed.
• As the slab has greater thickness, heat may trap inside during hydration
reaction.
• During construction water level may rise that might cause the lose of
contact with the soil.
Advantages & Disadvantages Of Mat Foundation
26. The whole Mat foundation wasn’t done at once
This presentation is based on the observations on Mat
foundation in various sites & meeting with concerned
engineers & workers.
The purpose of this presentation was to gather some
practical experience on Mat foundation.
During the making of this presentation, we also practically
experienced other major & minor parts of a construction.
Casting was done at night to reduce time wastage.
Conclusion