SlideShare a Scribd company logo
1 of 41
Welcome to
Our
presentation
Ahsanullah university of science and technology
Department of civil engineering
CE 200
Details of Construction
Presented By:-
Group 03
Salma Afia Mim (16.02.03.015)
Mehedi Hassan Shuvo (16.02.03.016)
Abir Mahmud (16.01.03.052)
Visited Sites
Malibagh,Hazipara,DIT Road.
Tejgaon Industrial Area,Roads and
Highways Department.
MAT FOUNDATION
What is Mat Foundation ?
It is a type of shallow foundation(depth≤width).
Generally used in heavy industrial plant,official and commercial
buildings and sometimes in residential buildings where
basement is needed.
Mat foundation is a large,thick,usually reinforced concrete mat
which transfers load from a number of columns, or walls to the
underlying rock or soil. Also known as Raft Foundation.
When Mat Foundation is required ?
Where differential settlement is suspected.
If foundation area covers 50-60% of the total plot area.
It is required where soils have low bearing capacity and have to
support heavy structural loads.
When the expenses of deep foundation is higher than mat
foundation.
Procedure Flow Chart
Centering &
Leveling
Polythene
& CC Layer
Leveling of
Soil
Vibrating
Placing
Reinforcement
Concreting
Leveling
Shoring
Soil Excavation
Shuttering &
Bracing
Placing CC
Block
Soil Test
Details Construction Process of Mat Foundation
Step 01- Soil Test
 Bearing capacity of soil;
 Soil classification;
 Ground water level;
 Moisture content;
 Appropriation & depth of Mat.
Step 02- Centering & Leveling
 To provide an accurate network of height.
 To get the accurate position of excavation.
Figure:- Centering & Leveling
Step 03- Shoring
 Support the load of the surrounding structures during construction.
 Prevents the surrounding soil from breaking during construction.
 Prevents the collapsing of the existing structure.
 Protects from vibration.
 Can be of three types: Concrete pile shore, Steel pile shore, Timber
shore.
Figure:- Timber Shoring.
Figure:- Steel pile shoring. Figure:- Shore Pile.
TIE BEAM
 Tie beam is constructed mainly to join the piles of border line.
Figure:- Tie Beam.
KING POST
 The vertical member to support the bracing and struts is called king
post.
 Generally hollow steel piles are used as king post.
 After the end of the construction, the king posts are removed and the
vacuum space in the basement slab is filled in with rich concrete.
King Post
Step 04- Soil Excavation
 Partial and full excavation is required before further construction.
 The soil was not excavated fully at once rather it was done step wise for
depth basis bracing.
 Excavation can be done in two ways:- ⅰ) Manually, ⅱ) By using machine.
Figure:- Machine Excavation.
Step 05- Providing strutting
& Bracing
 Generally made of steel sheet.
 In order to support the shore piles bracing are provided.
 The horizontal members placed in between the bracings are the struts.
 Its requirement depends on the depth of the foundation.
Bracing
Strut
Step 06- Compaction & Leveling
of Soil
 After excavation, soil compaction is needed to obtain a
uniform surface for the placement of BFS and other layers.
Figure:- Soil Leveling
Step 07- Provide Polythene,
BFS & CC Layer
 First one layer of BFS is placed over the area.
 After that, CC layer of 2”-3” thickness is provided.
 After that, polythene is placed as damp proof course (DPC).
 After that, another cc layer is provided.
 Bricks should be placed alternately so that there remains no weak
position on the layer and the friction is developed evenly.
 Polythene sheets are used as damp proofing membrane as polythene is
impermeable to water.
 Finally a theodolite is used to check the degree of leveling.
Figure:- BFS. Figure:- Provide polythene.
Figure:- CC Layer & a theodolite
Step 08- Placing CC Block
 CC blocks are placed beneath bottom layer reinforcement to maintain
3” clear cover.
CC Block
Step 09- Placing Reinforcement
Placing of
Bottom mesh
Column rod
placement
Chair placement
over bottom
mesh
Upper mesh
placement
Placing of Bottom mesh
 At first some reinforcements are placed at regular intervals along the
short distance of the site.
 Then a few more rods are placed on them along the long distance.
 At the junctions, the rods are tied with G.I. (galvanized iron) wires.
Figure:- Bottom mesh
Column rod placement
Figure:- Column rods
 In bottom mesh extra bars are placed beneath the positions of column
rods.
 Then the reinforcements of the columns are erected and tied.
Chair placement over bottom mesh
 There is a special type of bar used in between the top and bottom layer
reinforcement of mat foundation called the chair.
 The chairs are placed to provide support to the upper layer
reinforcement.
 Distance between two chair was 4’.
Figure:- A Chair
Figure:-Placing of chairs and
checking their alignment.
Upper mesh placement
 After that the top layer reinforcements are placed according to the
design.
 In the top layer, extra bars are provided in between the columns to resist
the punching shear.
Figure:- Upper mesh.
Important Factors
Reinforcement Selection
60~72.5 Graded
12 mm ~25 mm
Rod cutter
Rod bending
Hook right angled
(90° or 135° )
Tie bar
Formwork or Shuttering
 Shuttering or formwork is a sort of temporary construction provide for
laying concrete to required shape.
 Steel plate, Wooden plate is used for shuttering purpose.
Figure:- Formwork.
Step 10- Concreting
 Concreting is the process of pouring concrete in the reinforcement mesh.
 Casting was done in layers.
 The ratio of cement: sand: aggregate was 1:2:4
 Water: Cement ratio was 0.45.
Figure:- Concreting.
Step 11- Vibrating
 Concreting and vibrating both are does simultaneously.
 By using vibrating machine this work is done.
 Vibrating is necessary to distribute the concrete uniformly and to remove
the void.
Figure:- Vibrating.
Step 12- Leveling
 After casting the whole mat area levelling is essential to be ensured that
the thickness of the mash slab is same all over the area.
Figure:- Leveling.
Step 13- Curing
 Curing is the process of keeping the set concrete continuously damp for
some days in order to enable the concrete gain more strength.
 It is very important to continue curing for 28 days so that hydration is
completed and the concrete is hardened properly.
Figure:- Curing.
Advantages and Disadvantages
Advantages
 Where differential settlement needs to be reduced.
 Can cope up with poor soil condition.
 It gives greater space which is needed for basement.
 Loads are spread over greater area.
Disadvantages
 Shore protection is needed.
 Cost is high.
 As the raft thickness is high, heat may trap inside.
 Water may seep inside the basement.
 While constructing, water level may rise that might cause the lose of
contact with the soil.
Some special observations
 Hanger: This is a small ‘U’ shaped reinforcement provided in the slab of
the mat while casting. This is used to support the rods that keep the
column reinforcements erect.
Figure:- Hanger
 Sewerage pipes: Provision for passing of sewerage pipes may be
present on the raft slab.
Figure:- Sewerage pipes provided on mat foundation.
Some special observations
Figure:- Failure of shuttering wall.
Some special observations
 Failure of shuttering wall: On the site we observed that after heavy
rainfall, shuttering wall collapsed due to pressure of water. The shuttering
wall was built again and necessary provisions were made so that in
future such type of failure did not occur.
Figure:- Bracing.
Some special observations
 Bracing: Bracing to keep the column or retaining wall reinforcement
align.
Figure:- Retaining Wall.
Some special observations
Retaining Wall:
 RCC wall is constructed around the mat foundation.
 It is constructed to resist the lateral load of soil.
Completed Mat Foundation
MAT FOUNDATION
Mat foundation

More Related Content

What's hot

Lecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soilLecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soilhusseinhadi2
 
detailed specification for cement concrete
detailed specification for cement concretedetailed specification for cement concrete
detailed specification for cement concretevivek gami
 
MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction Tahey Bin Mainur
 
Reinforced Earth Wall RE wall
Reinforced Earth Wall RE wallReinforced Earth Wall RE wall
Reinforced Earth Wall RE wallAmir nazir paray
 
Goetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedGoetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedIrfan Malik
 
Presentation on Mat Foundation
Presentation on Mat FoundationPresentation on Mat Foundation
Presentation on Mat FoundationTanvir Alam Khan
 
Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of SoilPirpasha Ujede
 
Raft foundations
Raft foundationsRaft foundations
Raft foundationshatim ahmed
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesSravan Muguda
 
retaining walls ( word )
retaining walls ( word )retaining walls ( word )
retaining walls ( word )hussein96o
 

What's hot (20)

Lecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soilLecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soil
 
detailed specification for cement concrete
detailed specification for cement concretedetailed specification for cement concrete
detailed specification for cement concrete
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction
 
Reinforced Earth Wall RE wall
Reinforced Earth Wall RE wallReinforced Earth Wall RE wall
Reinforced Earth Wall RE wall
 
Goetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedGoetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signed
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Presentation on Mat Foundation
Presentation on Mat FoundationPresentation on Mat Foundation
Presentation on Mat Foundation
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of Soil
 
Piles, Piers and Caissons
Piles, Piers and CaissonsPiles, Piers and Caissons
Piles, Piers and Caissons
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
retaining walls ( word )
retaining walls ( word )retaining walls ( word )
retaining walls ( word )
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 

Similar to Mat foundation

Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabDivineGraceFernando
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Transmission tower
Transmission towerTransmission tower
Transmission towerKiran Hadiya
 
Presentation on Mat Foundation
Presentation on Mat FoundationPresentation on Mat Foundation
Presentation on Mat FoundationSaif Ahmed
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdfShrutiGarg261479
 
INTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxINTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxHumnaTolina
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Ppt supersstructure
Ppt supersstructurePpt supersstructure
Ppt supersstructureShrafatBalti
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES Saleh Ahmed
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelIRJET Journal
 

Similar to Mat foundation (20)

Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Combined Footing
Combined FootingCombined Footing
Combined Footing
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slab
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
KUY Limeng,e20190482(I4GCI-B)_4.pdf
KUY Limeng,e20190482(I4GCI-B)_4.pdfKUY Limeng,e20190482(I4GCI-B)_4.pdf
KUY Limeng,e20190482(I4GCI-B)_4.pdf
 
Transmission tower
Transmission towerTransmission tower
Transmission tower
 
Presentation on Mat Foundation
Presentation on Mat FoundationPresentation on Mat Foundation
Presentation on Mat Foundation
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf
 
INTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxINTERNSHIP PPT.pptx
INTERNSHIP PPT.pptx
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Ppt supersstructure
Ppt supersstructurePpt supersstructure
Ppt supersstructure
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 

Recently uploaded

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 

Recently uploaded (20)

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 

Mat foundation

  • 2. Ahsanullah university of science and technology Department of civil engineering CE 200 Details of Construction Presented By:- Group 03 Salma Afia Mim (16.02.03.015) Mehedi Hassan Shuvo (16.02.03.016) Abir Mahmud (16.01.03.052)
  • 3. Visited Sites Malibagh,Hazipara,DIT Road. Tejgaon Industrial Area,Roads and Highways Department.
  • 5. What is Mat Foundation ? It is a type of shallow foundation(depth≤width). Generally used in heavy industrial plant,official and commercial buildings and sometimes in residential buildings where basement is needed. Mat foundation is a large,thick,usually reinforced concrete mat which transfers load from a number of columns, or walls to the underlying rock or soil. Also known as Raft Foundation.
  • 6. When Mat Foundation is required ? Where differential settlement is suspected. If foundation area covers 50-60% of the total plot area. It is required where soils have low bearing capacity and have to support heavy structural loads. When the expenses of deep foundation is higher than mat foundation.
  • 7. Procedure Flow Chart Centering & Leveling Polythene & CC Layer Leveling of Soil Vibrating Placing Reinforcement Concreting Leveling Shoring Soil Excavation Shuttering & Bracing Placing CC Block Soil Test
  • 8. Details Construction Process of Mat Foundation
  • 9. Step 01- Soil Test  Bearing capacity of soil;  Soil classification;  Ground water level;  Moisture content;  Appropriation & depth of Mat.
  • 10. Step 02- Centering & Leveling  To provide an accurate network of height.  To get the accurate position of excavation. Figure:- Centering & Leveling
  • 11. Step 03- Shoring  Support the load of the surrounding structures during construction.  Prevents the surrounding soil from breaking during construction.  Prevents the collapsing of the existing structure.  Protects from vibration.  Can be of three types: Concrete pile shore, Steel pile shore, Timber shore. Figure:- Timber Shoring.
  • 12. Figure:- Steel pile shoring. Figure:- Shore Pile.
  • 13. TIE BEAM  Tie beam is constructed mainly to join the piles of border line. Figure:- Tie Beam.
  • 14. KING POST  The vertical member to support the bracing and struts is called king post.  Generally hollow steel piles are used as king post.  After the end of the construction, the king posts are removed and the vacuum space in the basement slab is filled in with rich concrete. King Post
  • 15. Step 04- Soil Excavation  Partial and full excavation is required before further construction.  The soil was not excavated fully at once rather it was done step wise for depth basis bracing.  Excavation can be done in two ways:- ⅰ) Manually, ⅱ) By using machine. Figure:- Machine Excavation.
  • 16. Step 05- Providing strutting & Bracing  Generally made of steel sheet.  In order to support the shore piles bracing are provided.  The horizontal members placed in between the bracings are the struts.  Its requirement depends on the depth of the foundation. Bracing Strut
  • 17. Step 06- Compaction & Leveling of Soil  After excavation, soil compaction is needed to obtain a uniform surface for the placement of BFS and other layers. Figure:- Soil Leveling
  • 18. Step 07- Provide Polythene, BFS & CC Layer  First one layer of BFS is placed over the area.  After that, CC layer of 2”-3” thickness is provided.  After that, polythene is placed as damp proof course (DPC).  After that, another cc layer is provided.  Bricks should be placed alternately so that there remains no weak position on the layer and the friction is developed evenly.  Polythene sheets are used as damp proofing membrane as polythene is impermeable to water.  Finally a theodolite is used to check the degree of leveling.
  • 19. Figure:- BFS. Figure:- Provide polythene.
  • 20. Figure:- CC Layer & a theodolite
  • 21. Step 08- Placing CC Block  CC blocks are placed beneath bottom layer reinforcement to maintain 3” clear cover. CC Block
  • 22. Step 09- Placing Reinforcement Placing of Bottom mesh Column rod placement Chair placement over bottom mesh Upper mesh placement
  • 23. Placing of Bottom mesh  At first some reinforcements are placed at regular intervals along the short distance of the site.  Then a few more rods are placed on them along the long distance.  At the junctions, the rods are tied with G.I. (galvanized iron) wires. Figure:- Bottom mesh
  • 24. Column rod placement Figure:- Column rods  In bottom mesh extra bars are placed beneath the positions of column rods.  Then the reinforcements of the columns are erected and tied.
  • 25. Chair placement over bottom mesh  There is a special type of bar used in between the top and bottom layer reinforcement of mat foundation called the chair.  The chairs are placed to provide support to the upper layer reinforcement.  Distance between two chair was 4’. Figure:- A Chair Figure:-Placing of chairs and checking their alignment.
  • 26. Upper mesh placement  After that the top layer reinforcements are placed according to the design.  In the top layer, extra bars are provided in between the columns to resist the punching shear. Figure:- Upper mesh.
  • 27. Important Factors Reinforcement Selection 60~72.5 Graded 12 mm ~25 mm Rod cutter Rod bending Hook right angled (90° or 135° ) Tie bar
  • 28. Formwork or Shuttering  Shuttering or formwork is a sort of temporary construction provide for laying concrete to required shape.  Steel plate, Wooden plate is used for shuttering purpose. Figure:- Formwork.
  • 29. Step 10- Concreting  Concreting is the process of pouring concrete in the reinforcement mesh.  Casting was done in layers.  The ratio of cement: sand: aggregate was 1:2:4  Water: Cement ratio was 0.45. Figure:- Concreting.
  • 30. Step 11- Vibrating  Concreting and vibrating both are does simultaneously.  By using vibrating machine this work is done.  Vibrating is necessary to distribute the concrete uniformly and to remove the void. Figure:- Vibrating.
  • 31. Step 12- Leveling  After casting the whole mat area levelling is essential to be ensured that the thickness of the mash slab is same all over the area. Figure:- Leveling.
  • 32. Step 13- Curing  Curing is the process of keeping the set concrete continuously damp for some days in order to enable the concrete gain more strength.  It is very important to continue curing for 28 days so that hydration is completed and the concrete is hardened properly. Figure:- Curing.
  • 33. Advantages and Disadvantages Advantages  Where differential settlement needs to be reduced.  Can cope up with poor soil condition.  It gives greater space which is needed for basement.  Loads are spread over greater area. Disadvantages  Shore protection is needed.  Cost is high.  As the raft thickness is high, heat may trap inside.  Water may seep inside the basement.  While constructing, water level may rise that might cause the lose of contact with the soil.
  • 34. Some special observations  Hanger: This is a small ‘U’ shaped reinforcement provided in the slab of the mat while casting. This is used to support the rods that keep the column reinforcements erect. Figure:- Hanger
  • 35.  Sewerage pipes: Provision for passing of sewerage pipes may be present on the raft slab. Figure:- Sewerage pipes provided on mat foundation. Some special observations
  • 36. Figure:- Failure of shuttering wall. Some special observations  Failure of shuttering wall: On the site we observed that after heavy rainfall, shuttering wall collapsed due to pressure of water. The shuttering wall was built again and necessary provisions were made so that in future such type of failure did not occur.
  • 37. Figure:- Bracing. Some special observations  Bracing: Bracing to keep the column or retaining wall reinforcement align.
  • 38. Figure:- Retaining Wall. Some special observations Retaining Wall:  RCC wall is constructed around the mat foundation.  It is constructed to resist the lateral load of soil.