SlideShare a Scribd company logo
1 of 8
Download to read offline
1
Applying Earned Schedule
to Critical Path Analysis and More
Walt Lipke
Retired Deputy Chief
Software Division
Tinker Air Force Base
Abstract. Earned Schedule is a fairly new method for analyzing schedule performance;
it is a derived application of Earned Value Management (EVM) data. Created three
years ago, the method has propagated to several countries and been used for various
types of work spanning a large range of project sizes. During this period of infancy, a
misperception may have emerged that ES is only applicable to the total project and thus
is limited for schedule performance analysis. As has been shown in the article,
“Connecting Earned Value to the Schedule,” ES can be used for much more. It
facilitates the ability to identify constraints, impediments, and the possibility of rework at
the task level [1]. This information is very useful for management purposes, but it does
not provide performance indicators below the project level. This paper describes how
ES can be applied to sub-levels of the project. Using this capability, the project manager
can analyze schedule performance at virtually any level desired – control accounts,
work packages, and critical path activities.
During presentations about Earned Schedule (ES) I am sometimes asked, “Can
Earned Schedule be used to analyze the critical path?” My response is always,
“Certainly, simply treat the critical path as the project.” I notice then that the person
doesn’t say anything else, but has the look of someone who didn’t have his question
answered. This question is asked often enough …with the same result …that it is
apparent a more complete response is needed. Hopefully this paper will satisfy all those
who have voiced the question in the past, as well as those who are seeking a way to
use ES as a “drill-down” tool.
In this paper, it is assumed the reader has good understanding of Earned Value
Management (EVM) and that Earned Schedule is being used as one of the project
management tools. Although it is likely the reader has a working knowledge of ES, a
review of the concept, the time-based indicators and the forecasting calculation is
needed to establish a common foundation for the remainder of the paper.
Earned Schedule
The ES idea is simple: identify the time at which the amount of earned value (EV)
accrued should have been earned [2]. By determining this time, time-based indicators
can be formed to provide schedule variance and performance efficiency management
information.
2
Figure 1, Earned Schedule Concept, illustrates how the ES measure is obtained.
Projecting the cumulative EV onto the project management baseline (PMB), as shown
by the diagram, determines where planned value (PV) equals the EV accrued. This
intersection point identifies the time that amount of EV should have been earned in
accordance with the schedule. The vertical line from the point on the PMB to the time
axis determines the “earned” portion of the schedule. The duration from the beginning of
the project to the intersection of the time axis is the amount of earned schedule (ES).
With ES determined, time based indicators can be created. It is now possible to
compare where the project is time-wise with where it should be in accordance with the
PMB. “Actual time,” denoted AT, is the duration at which the EV accrued is recorded.
The time-based indicators are easily formulated from the two measures, ES and AT.
Schedule Variance becomes SV(t) = ES – AT, and Schedule Performance Index is
SPI(t) = ES / AT.
PV
EV
SPI =
AT
ES
SPI(t) =
$$
Time
PV
EV
Projection of EV
onto PV curve
7AT
PV(May)-PV(June)
PV(May)-EV
5ES
JuneofPortionMaythruJanES
=
+=
+=
J J JF M MA A S O N
PVEVSV −=
ATESSV(t) −=
Figure 1. Earned Schedule Concept
The graphic and the box in the lower right of figure 1 portray how ES is
calculated. While ES could be determined graphically as described previously, the
concept becomes much more useful when facilitated as a calculation. As observed from
the figure, all of the PV through May has been earned. However, only a portion of June
has been completed with respect to the baseline. Thus the duration of the completed
portion of the planned schedule is in excess of 5 months. The EV accrued appears at
3
the end of July, making actual time equal to 7 months. The method of calculation to
determine the portion of June to credit to ES is a linear interpolation. The amount of EV
extending past the cumulative PV for May divided by the incremental amount of PV
planned for June determines the fraction of the June schedule that has been earned.
The creation of ES and the derivative time-based schedule performance
efficiency, i.e. SPI(t), facilitates forecasting the duration of the project and its completion
date. Two formulas are presently in use; one is termed the “short form” and the other
the “long form.” The short form is IEAC(t) = PD / SPI(t), where IEAC(t) is the
Independent Estimate at Completion (time) and PD is the planned duration for the
project [3]. The long form is not needed in the subsequent discussion and,
consequently, is not stated.
Why the Question?
In the previous discussion of the concept, it is established that the determination
of ES requires the Project Management Baseline (PMB), and is a cumulative measure.
It is the cumulative “earned” portion of the schedule. The cumulative nature of ES is,
also, emphasized in the seminal paper, “Schedule is Different” [2]. And, the instructions
for using the ES calculator also stress that the complete PMB of the project must be
entered to expect correctly calculated results [4].
My conjecture is the emphasis of these statements could cause the
misunderstanding that the method is only applicable to the total project. With the
repeated overtures to use the project PMB along with the statements that ES is a
cumulative measure, it is a reasonable deduction.
However, ES is not limited to only the total project. It is much more applicable. I
intend to dispel the perception of the limitation and show how the ES method can be
applied at any level of interest within a project, including work packages, control
accounts, and critical path activities. In other words, the capability is available for “drill-
down” schedule analysis by applying the ES method to the project EVM data.
What’s the Trick?
To broaden the applicability of ES to detailed schedule performance analysis is
not difficult. All that is required is to view the subject of the analysis as if it is the total
project. This response is very similar to my answer, earlier in the paper, to the question
concerning applying ES to analyze the critical path. It should be. But, just as it was for
the persons who posed the question during my presentations, the answer is incomplete.
Thus, the question becomes, “How do I make a portion of a project appear like a total
project?”
To answer this question, let us view Table 1, Project Plan and Performance
Measures by Task. The table depicts the time-phased plan, earned value (EV), and
actual costs (AC) for each of ten tasks comprising the notional project. The time-phased
plan, the performance baseline, is created from the planned value (PV) amounts. All
amounts are in units of cost and are periodic, not to be understood as cumulative. The
diamond symbol indicates the initiation of the task. At project completion, the sum of the
periodic EV amounts for each task equals the sum of its PV quantities.
To construct the PMB, first sum the periodic PV amounts across all tasks by
performance period (PP). Then, finalize the PMB by creating the cumulative quantities
4
by PP. This is accomplished by adding, successively, the periodic PV determined from
the summing across tasks. For example, add the total periodic PV in period two to
period one to obtain the cumulative PV for period two; then for period three add its
periodic PV to the cumulative PV for period two. This process is repeated through
period ten. The resultant cumulative values for periods one through ten is the PMB. This
is the project performance baseline from which ES for the total project is determined.
Project Data
••• Performance Period •••
Task Nr Measure 0 1 2 3 4 5 6 7 8 9 10 11 12
PV ♦ 5 5 5
1 EV ♦ 4 5 6
AC ♦ 5 5 7
PV ♦ 10
2 EV ♦ 7 3
AC ♦ 10 5
PV ♦ 10 10 10
3 EV ♦ 8 13 9
AC ♦ 10 15 10
PV ♦ 5 5
4 EV ♦ 3 4 3
AC ♦ 5 5 5
PV ♦ 5 5 5
5 EV ♦ 5 3 5 2
AC ♦ 5 5 5 2
PV ♦ 5 5
6 EV ♦ 6 4
AC ♦ 5 5
PV ♦ 10 10 10 10 10
7 EV ♦ 8 9 7 13 8 5
AC ♦ 10 10 10 15 10 5
PV ♦ 5 10 5
8 EV ♦ 12 8
AC ♦ 15 12
PV ♦ 5 5 5
9 EV ♦ 4 5 3 3
AC ♦ 5 6 5 3
PV ♦ 5 5
10 EV ♦ 10
AC ♦ 14
Table 1. Project Plan and Performance Measures by Task
5
To analyze tasks (work packages), control accounts or critical path a
performance baseline must be created specific to the analysis area; i.e., if a cost
account is to be analyzed, its comprising tasks must be segregated and grouped. Then
the process for creating the project PMB is applied to this set of tasks to create a PMB
for the cost account, PMBa. Having PMBa allows ES to be calculated specifically for the
cost account. In turn, the determination of ES facilitates the calculations of SPI(t) and
IEAC(t) for the specific evaluation of cost account performance.
Critical Path Example
With the methods in place, the process for applying ES to critical path analysis
can be described. As discussed in the previous section of the paper, segregate and
group the critical path tasks, and create a PMB representing them, PMBc. For this
example, the critical path for the notional project includes tasks one, four, eight, and ten
(1-4-8-10). Table 2, Performance Baselines and Earned Value Measures, aggregates
the data for both the total project and the critical path.
••• Performance Period •••
Measure 0 1 2 3 4 5 6 7 8 9 10 11 12
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PVper 0 5 5 35 30 40 30 20 5 10 5 0 0
PVcum 0 5 10 45 75 115 145 165 170 180 185 185 185
Total 0 0 0 0 0 0 0 0 0 0 0 0 0
Project EVper 0 0 4 16 43 27 18 31 16 9 15 3 3
EVcum 0 0 4 20 63 90 108 139 155 164 179 182 185
0 0 0 0 0 0 0 0 0 0 0 0 0
ACper 0 0 5 20 52 35 20 37 22 10 20 5 3
ACcum 0 0 5 25 77 112 132 169 191 201 221 226 229
0 0 0 0 0 0 0 0 0 0 0 0 0 0
PVper 0 5 5 5 5 5 5 10 5 5 5 0 0
PVcum 0 5 10 15 20 25 30 40 45 50 55 55 55
Critical 0 0 0 0 0 0 0 0 0 0 0 0 0
Path EVper 0 0 4 8 10 3 0 12 8 0 10 0 0
1-4-8-10 EVcum 0 0 4 12 22 25 25 37 45 45 55 55 55
0 0 0 0 0 0 0 0 0 0 0 0 0
ACper 0 0 5 10 12 5 0 15 12 0 14 0 0
ACcum 0 0 5 15 27 32 32 47 59 59 73 73 73
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Table 2. Performance Baselines and Earned Value Measures
The project management baselines for the total project (PMB) and critical path
(PMBc) are their respective PVcum rows. The PVper rows represent the summation of
the planned values of the representative tasks for the specific performance period. As
described previously, the PVcum is obtained from the PVper values. For example the
calculation for PVcum for period three of the total project is determined by adding PVper
for period three to PVcum of period two: PVcum(3) = PVcum(2) + PVper(3). Using the
values from the Table 2, the calculation can be performed: PVcum(3) = 10 + 35 = 45.
The remainder of Table 2 contains the performance data, earned value (EV) and
actual costs (AC), for the total project and for the specific critical path tasks. The
accumulation of this information allows analysis and prediction to occur for both the total
project and the critical path.
6
The EVM performance indicators and duration forecasts calculated from the
Table 2 data are aggregated in Table 3, Performance Indicators and Duration
Forecasts. The “p” and “c” appended to the indicators shown in the table indicate period
and cumulative, respectively.
From Table 2 it can be determined that the project is planned to complete in 10
time periods, but actually completes in 12. Similarly, Table 2 indicates the tasks on the
critical path completed at the planned time, 10 periods. For comparison purposes both
SPI and SPI(t) indicators are shown in Table 3. The familiar behavior of the two
indicators is seen for the critical path and total project. The values for SPI(t) compare
favorably to those for SPI for the critical path which completes as planned. However for
the total project, the values for the two indicators are significantly different. The
corresponding values for SPI(t)c and SPIc noticeably begin departing in period eight,
and conclude as expected for late finishing projects; at project completion, SPI(t)c is a
valid number (0.8333) truly depicting the actual schedule performance efficiency, while
SPIc illogically equals 1.0.
••• Performance Period •••
Indicator 0 1 2 3 4 5 6 7 8 9 10 11 12
CPIp xxx xxx 0.8000 0.8000 0.8269 0.7714 0.9000 0.8378 0.7273 0.9000 0.7500 0.6000 1.0000
CPIc xxx xxx 0.8000 0.8000 0.8182 0.8036 0.8182 0.8225 0.8115 0.8159 0.8100 0.8053 0.8079
Total SPI(t)p xxx 0.0000 0.8000 1.4857 1.3143 0.7750 0.4500 0.9750 0.7000 0.4500 1.9500 0.5000 0.6000
Project SPI(t)c xxx 0.0000 0.4000 0.7619 0.9000 0.8750 0.8042 0.8286 0.8125 0.7722 0.8900 0.8545 0.8333
SPIp xxx 0.0000 0.8000 0.4571 1.4333 0.6750 0.6000 1.5500 3.2000 0.9000 3.0000 xxx xxx
SPIc xxx 0.0000 0.4000 0.4444 0.8400 0.7826 0.7448 0.8424 0.9118 0.9111 0.9676 0.9838 1.0000
IEAC(t) xxx xxx 25.00 13.13 11.11 11.43 12.44 12.07 12.31 12.95 11.24 11.70 12.00
CPIp xxx xxx 0.8000 0.8000 0.8333 0.6000 xxx 0.8000 0.6667 xxx 0.7143
CPIc xxx xxx 0.8000 0.8000 0.8148 0.7813 0.7813 0.7872 0.7627 0.7627 0.7534
Critical Path SPI(t)p xxx 0.0000 0.8000 1.6000 2.0000 0.6000 0.0000 1.7000 1.3000 0.0000 2.0000
1-4-8-10 SPI(t)c xxx 0.0000 0.4000 0.8000 1.1000 1.0000 0.8333 0.9571 1.0000 0.8889 1.0000
SPIp xxx 0.0000 0.8000 1.6000 2.0000 0.6000 0.0000 1.2000 1.6000 0.0000 2.0000
SPIc xxx 0.0000 0.4000 0.8000 1.1000 1.0000 0.8333 0.9250 1.0000 0.9000 1.0000
IEAC(t) xxx xxx 25.00 12.50 9.09 10.00 12.00 10.45 10.00 11.25 10.00 xxx xxx
Table 3. Performance Indicators and Duration Forecasts
By inspection of Table 2, it is obvious the critical path changed during project
execution. Knowing this begs the question, “Does the simultaneous application of ES to
both the critical path and total project provide advance warning of this condition?” If the
answer is “Yes,” then applying ES has been shown to yield analysis advantages to
project managers.
One significant implication of a response of “Yes” is detailed schedule
performance information can be obtained solely from the EVM data …without the
laborious bottom-up analysis performed by skilled schedulers.
Another point is detailed schedule analysis takes time and considerable effort by
sometimes several people, oftentimes becoming a distraction to those performing
project work. For any size, but especially for larger projects, performing a detailed
schedule analysis involving several subcontractors in the time-frame the ES schedule
forecasting calculations can be made is virtually impossible.
7
The time advantage offered by IEAC(t) does not mean to imply that detailed
bottom-up schedule analysis should never be performed. Certainly, just as the final cost
estimate obtained from IEAC is not relied on solely at critical points without a detailed
cost analysis, a bottom-up schedule estimation should be performed for confirmation of
the ES forecast.
By reviewing and comparing the IEAC(t) numbers for the total project and critical
path we can answer the question posed a few paragraphs earlier. The answer is “Yes,”
it can be observed that the critical path is likely to have changed. From examining Table
3 it is seen very early, beginning with period 3, that the forecast duration for the total
project is always greater than the forecast for the critical path. It is reasonably clear that
the critical path changed early in the project execution from tasks 1-4-8-10. From this
example, it may be said that ES can provide advance warning that the critical path has
changed.
Without going into the detail, the project duration forecasting method from ES
can further be used to identify the longest duration path; i.e., the changed critical path.
By forecasting duration for each task and inserting the forecasts into the network
structure of the schedule, the actual critical path can be determined as well as
conditions for float. With some technical ingenuity, this analysis could be completely
automated.
Summary
The Earned Schedule analysis method is demonstrated in this paper to be
applicable to more than the total project. Segregating and grouping EVM data for a
specific portion of the project is the technique by which ES is made applicable to the
total project and any sub-level desired. Specifically, the technique is shown to be
capable of analyzing the schedule performance for the critical path. By employing the
same techniques to analyze critical path, schedule performance by individual tasks can
be evaluated, which then allows identification of the longest duration path for the project
(actual critical path) along with schedule float.
References
1. Lipke, Walt. “Connecting Earned Value to the Schedule,” CrossTalk, June 2005:
On-line (http://www.stsc.hill.af.mil/crosstalk/2005/06/0506Lipke.html).
2. Lipke, Walt. “Schedule is Different,” The Measurable News, March 2003: 10-15.
3. Henderson, Kym. “Further Developments in Earned Schedule,” The Measurable
News, Spring 2004: 15-22.
4. http://www.earnedschedule.com/Calculator.shtml
About the Author
Walt Lipke recently retired as the deputy chief of the Software Division at the Oklahoma
City Air Logistics Center. The division employs approximately 600 people, primarily
electronics engineers. He has over 35 years of experience in the development,
maintenance, and management of software for automated testing of avionics and jet
8
engines as well as automation of industrial processes. During his tenure, the division
achieved several software process improvement milestones:
• 1993 - first Air Force activity to achieve Level 2 of the Software Engineering
Institute’s Capability Maturity Model® (CMM®)
• 1996 - first software activity in federal service to achieve CMM® Level 4 distinction
• 1998 – division achieved ISO 9001/TickIT registration
• 1999 - division received the SEI/IEEE Award for Software Process Achievement
Mr. Lipke has published several articles and presented at conferences, internationally,
on the benefits of software process improvement and the application of earned value
management and statistical methods to software projects. He is the creator of the
technique Earned Schedule (Copyright © 2003 Lipke), which extracts schedule
information from earned value data. Mr. Lipke is a graduate of the USA DoD course for
Program Managers. He is a professional engineer with a master’s degree in physics,
and is a member of the physics honor society, ΣΠΣ. Lipke achieved distinguished
academic honors with the selection to ΦΚΦ.

More Related Content

What's hot

“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and Technique“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and TechniquePantho Sarker
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)AnkitaKadam20
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review TechniqueSimonRobertson
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2ahsanrabbani
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3ahsanrabbani
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handoutZenawi Mehari
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project SchedulingIzah Asmadi
 
An Alternate Approach to Cost and Schedule Integration
An Alternate Approach to Cost and Schedule IntegrationAn Alternate Approach to Cost and Schedule Integration
An Alternate Approach to Cost and Schedule IntegrationAcumen
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsChethanMp7
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 

What's hot (20)

“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and Technique“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and Technique
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
 
PERT
PERTPERT
PERT
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project Scheduling
 
An Alternate Approach to Cost and Schedule Integration
An Alternate Approach to Cost and Schedule IntegrationAn Alternate Approach to Cost and Schedule Integration
An Alternate Approach to Cost and Schedule Integration
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 

Viewers also liked

Generate a Content Strategy to Create Rabid Fans and Buyers
Generate a Content Strategy to Create Rabid Fans and BuyersGenerate a Content Strategy to Create Rabid Fans and Buyers
Generate a Content Strategy to Create Rabid Fans and BuyersAffiliate Summit
 
8%a7لفيل من كتاب المصباح عن حفص
8%a7لفيل من كتاب المصباح عن حفص8%a7لفيل من كتاب المصباح عن حفص
8%a7لفيل من كتاب المصباح عن حفصسمير بسيوني
 
메가888 호게임 ★〓♥♥♥♥〓★『【MSK822. COM 】』 ★〓♥♥♥♥〓★메가888 호게임
메가888 호게임 ★〓♥♥♥♥〓★『【MSK822.  COM 】』  ★〓♥♥♥♥〓★메가888 호게임메가888 호게임 ★〓♥♥♥♥〓★『【MSK822.  COM 】』  ★〓♥♥♥♥〓★메가888 호게임
메가888 호게임 ★〓♥♥♥♥〓★『【MSK822. COM 】』 ★〓♥♥♥♥〓★메가888 호게임rhengsadface01
 
История космонавтики леонова 8а
История космонавтики леонова 8аИстория космонавтики леонова 8а
История космонавтики леонова 8аjuliana-zh
 
89711046...2003
89711046...200389711046...2003
89711046...2003KHCHOTEL
 
8d5eb957b9390c513b4e073deb50027f 2
8d5eb957b9390c513b4e073deb50027f 28d5eb957b9390c513b4e073deb50027f 2
8d5eb957b9390c513b4e073deb50027f 2Chanamon Monjai
 
Обращение в редакцию #885 05.11.2014 г. в 01:08
Обращение в редакцию  #885 05.11.2014 г. в 01:08Обращение в редакцию  #885 05.11.2014 г. в 01:08
Обращение в редакцию #885 05.11.2014 г. в 01:08Opennewspaper
 
Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.
Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.
Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.diana diana
 
8 consejos para emprendedores
8 consejos para emprendedores8 consejos para emprendedores
8 consejos para emprendedoresCARLOS RODRIGUEZ
 

Viewers also liked (20)

8 Bands
8 Bands8 Bands
8 Bands
 
Generate a Content Strategy to Create Rabid Fans and Buyers
Generate a Content Strategy to Create Rabid Fans and BuyersGenerate a Content Strategy to Create Rabid Fans and Buyers
Generate a Content Strategy to Create Rabid Fans and Buyers
 
блог 8в
блог 8вблог 8в
блог 8в
 
8%a7لفيل من كتاب المصباح عن حفص
8%a7لفيل من كتاب المصباح عن حفص8%a7لفيل من كتاب المصباح عن حفص
8%a7لفيل من كتاب المصباح عن حفص
 
메가888 호게임 ★〓♥♥♥♥〓★『【MSK822. COM 】』 ★〓♥♥♥♥〓★메가888 호게임
메가888 호게임 ★〓♥♥♥♥〓★『【MSK822.  COM 】』  ★〓♥♥♥♥〓★메가888 호게임메가888 호게임 ★〓♥♥♥♥〓★『【MSK822.  COM 】』  ★〓♥♥♥♥〓★메가888 호게임
메가888 호게임 ★〓♥♥♥♥〓★『【MSK822. COM 】』 ★〓♥♥♥♥〓★메가888 호게임
 
8. b.n. agosto 2014
8. b.n. agosto 20148. b.n. agosto 2014
8. b.n. agosto 2014
 
8 4 etica 2
8 4 etica 28 4 etica 2
8 4 etica 2
 
89 276-1-pb
89 276-1-pb89 276-1-pb
89 276-1-pb
 
История космонавтики леонова 8а
История космонавтики леонова 8аИстория космонавтики леонова 8а
История космонавтики леонова 8а
 
89711046...2003
89711046...200389711046...2003
89711046...2003
 
89_lehenengo galdera.doc
89_lehenengo galdera.doc89_lehenengo galdera.doc
89_lehenengo galdera.doc
 
8d5eb957b9390c513b4e073deb50027f 2
8d5eb957b9390c513b4e073deb50027f 28d5eb957b9390c513b4e073deb50027f 2
8d5eb957b9390c513b4e073deb50027f 2
 
8e 3período
8e 3período8e 3período
8e 3período
 
Обращение в редакцию #885 05.11.2014 г. в 01:08
Обращение в редакцию  #885 05.11.2014 г. в 01:08Обращение в редакцию  #885 05.11.2014 г. в 01:08
Обращение в редакцию #885 05.11.2014 г. в 01:08
 
8. crear eventos
8. crear eventos8. crear eventos
8. crear eventos
 
8. aprender en la vida
8.  aprender en la vida8.  aprender en la vida
8. aprender en la vida
 
Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.
Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.
Проект обучающегося 8 класса на тему: Смежные и вертикальные углы.
 
8 consejos para emprendedores
8 consejos para emprendedores8 consejos para emprendedores
8 consejos para emprendedores
 
892 moraes
892 moraes892 moraes
892 moraes
 
Zagara's Market Circular
Zagara's Market CircularZagara's Market Circular
Zagara's Market Circular
 

Similar to 8 applying-es-to-critical-path-and-more

Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...IJERA Editor
 
Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...
Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...
Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...Daphne Smith
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
One of My published papers on EVM
One of My published papers on EVMOne of My published papers on EVM
One of My published papers on EVMqosatimio
 
Available online at www.sciencedirect.comInternational Jou.docx
Available online at www.sciencedirect.comInternational Jou.docxAvailable online at www.sciencedirect.comInternational Jou.docx
Available online at www.sciencedirect.comInternational Jou.docxrock73
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxkhenry4
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTIAEME Publication
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performanceGlen Alleman
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Lecture Capture Summary (LCS) #11. Chapter Title Containin.docx
Lecture Capture Summary (LCS) #11. Chapter Title Containin.docxLecture Capture Summary (LCS) #11. Chapter Title Containin.docx
Lecture Capture Summary (LCS) #11. Chapter Title Containin.docxjesssueann
 

Similar to 8 applying-es-to-critical-path-and-more (20)

Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...
Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...
Applying Statistical Forecasting Of Project Duration To Earned Schedule-Longe...
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
One of My published papers on EVM
One of My published papers on EVMOne of My published papers on EVM
One of My published papers on EVM
 
Available online at www.sciencedirect.comInternational Jou.docx
Available online at www.sciencedirect.comInternational Jou.docxAvailable online at www.sciencedirect.comInternational Jou.docx
Available online at www.sciencedirect.comInternational Jou.docx
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned Effort Analysis
Earned Effort AnalysisEarned Effort Analysis
Earned Effort Analysis
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performance
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Lecture Capture Summary (LCS) #11. Chapter Title Containin.docx
Lecture Capture Summary (LCS) #11. Chapter Title Containin.docxLecture Capture Summary (LCS) #11. Chapter Title Containin.docx
Lecture Capture Summary (LCS) #11. Chapter Title Containin.docx
 

Recently uploaded

Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFOrient Homes
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
A.I. Bot Summit 3 Opening Keynote - Perry Belcher
A.I. Bot Summit 3 Opening Keynote - Perry BelcherA.I. Bot Summit 3 Opening Keynote - Perry Belcher
A.I. Bot Summit 3 Opening Keynote - Perry BelcherPerry Belcher
 

Recently uploaded (20)

Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
A.I. Bot Summit 3 Opening Keynote - Perry Belcher
A.I. Bot Summit 3 Opening Keynote - Perry BelcherA.I. Bot Summit 3 Opening Keynote - Perry Belcher
A.I. Bot Summit 3 Opening Keynote - Perry Belcher
 

8 applying-es-to-critical-path-and-more

  • 1. 1 Applying Earned Schedule to Critical Path Analysis and More Walt Lipke Retired Deputy Chief Software Division Tinker Air Force Base Abstract. Earned Schedule is a fairly new method for analyzing schedule performance; it is a derived application of Earned Value Management (EVM) data. Created three years ago, the method has propagated to several countries and been used for various types of work spanning a large range of project sizes. During this period of infancy, a misperception may have emerged that ES is only applicable to the total project and thus is limited for schedule performance analysis. As has been shown in the article, “Connecting Earned Value to the Schedule,” ES can be used for much more. It facilitates the ability to identify constraints, impediments, and the possibility of rework at the task level [1]. This information is very useful for management purposes, but it does not provide performance indicators below the project level. This paper describes how ES can be applied to sub-levels of the project. Using this capability, the project manager can analyze schedule performance at virtually any level desired – control accounts, work packages, and critical path activities. During presentations about Earned Schedule (ES) I am sometimes asked, “Can Earned Schedule be used to analyze the critical path?” My response is always, “Certainly, simply treat the critical path as the project.” I notice then that the person doesn’t say anything else, but has the look of someone who didn’t have his question answered. This question is asked often enough …with the same result …that it is apparent a more complete response is needed. Hopefully this paper will satisfy all those who have voiced the question in the past, as well as those who are seeking a way to use ES as a “drill-down” tool. In this paper, it is assumed the reader has good understanding of Earned Value Management (EVM) and that Earned Schedule is being used as one of the project management tools. Although it is likely the reader has a working knowledge of ES, a review of the concept, the time-based indicators and the forecasting calculation is needed to establish a common foundation for the remainder of the paper. Earned Schedule The ES idea is simple: identify the time at which the amount of earned value (EV) accrued should have been earned [2]. By determining this time, time-based indicators can be formed to provide schedule variance and performance efficiency management information.
  • 2. 2 Figure 1, Earned Schedule Concept, illustrates how the ES measure is obtained. Projecting the cumulative EV onto the project management baseline (PMB), as shown by the diagram, determines where planned value (PV) equals the EV accrued. This intersection point identifies the time that amount of EV should have been earned in accordance with the schedule. The vertical line from the point on the PMB to the time axis determines the “earned” portion of the schedule. The duration from the beginning of the project to the intersection of the time axis is the amount of earned schedule (ES). With ES determined, time based indicators can be created. It is now possible to compare where the project is time-wise with where it should be in accordance with the PMB. “Actual time,” denoted AT, is the duration at which the EV accrued is recorded. The time-based indicators are easily formulated from the two measures, ES and AT. Schedule Variance becomes SV(t) = ES – AT, and Schedule Performance Index is SPI(t) = ES / AT. PV EV SPI = AT ES SPI(t) = $$ Time PV EV Projection of EV onto PV curve 7AT PV(May)-PV(June) PV(May)-EV 5ES JuneofPortionMaythruJanES = += += J J JF M MA A S O N PVEVSV −= ATESSV(t) −= Figure 1. Earned Schedule Concept The graphic and the box in the lower right of figure 1 portray how ES is calculated. While ES could be determined graphically as described previously, the concept becomes much more useful when facilitated as a calculation. As observed from the figure, all of the PV through May has been earned. However, only a portion of June has been completed with respect to the baseline. Thus the duration of the completed portion of the planned schedule is in excess of 5 months. The EV accrued appears at
  • 3. 3 the end of July, making actual time equal to 7 months. The method of calculation to determine the portion of June to credit to ES is a linear interpolation. The amount of EV extending past the cumulative PV for May divided by the incremental amount of PV planned for June determines the fraction of the June schedule that has been earned. The creation of ES and the derivative time-based schedule performance efficiency, i.e. SPI(t), facilitates forecasting the duration of the project and its completion date. Two formulas are presently in use; one is termed the “short form” and the other the “long form.” The short form is IEAC(t) = PD / SPI(t), where IEAC(t) is the Independent Estimate at Completion (time) and PD is the planned duration for the project [3]. The long form is not needed in the subsequent discussion and, consequently, is not stated. Why the Question? In the previous discussion of the concept, it is established that the determination of ES requires the Project Management Baseline (PMB), and is a cumulative measure. It is the cumulative “earned” portion of the schedule. The cumulative nature of ES is, also, emphasized in the seminal paper, “Schedule is Different” [2]. And, the instructions for using the ES calculator also stress that the complete PMB of the project must be entered to expect correctly calculated results [4]. My conjecture is the emphasis of these statements could cause the misunderstanding that the method is only applicable to the total project. With the repeated overtures to use the project PMB along with the statements that ES is a cumulative measure, it is a reasonable deduction. However, ES is not limited to only the total project. It is much more applicable. I intend to dispel the perception of the limitation and show how the ES method can be applied at any level of interest within a project, including work packages, control accounts, and critical path activities. In other words, the capability is available for “drill- down” schedule analysis by applying the ES method to the project EVM data. What’s the Trick? To broaden the applicability of ES to detailed schedule performance analysis is not difficult. All that is required is to view the subject of the analysis as if it is the total project. This response is very similar to my answer, earlier in the paper, to the question concerning applying ES to analyze the critical path. It should be. But, just as it was for the persons who posed the question during my presentations, the answer is incomplete. Thus, the question becomes, “How do I make a portion of a project appear like a total project?” To answer this question, let us view Table 1, Project Plan and Performance Measures by Task. The table depicts the time-phased plan, earned value (EV), and actual costs (AC) for each of ten tasks comprising the notional project. The time-phased plan, the performance baseline, is created from the planned value (PV) amounts. All amounts are in units of cost and are periodic, not to be understood as cumulative. The diamond symbol indicates the initiation of the task. At project completion, the sum of the periodic EV amounts for each task equals the sum of its PV quantities. To construct the PMB, first sum the periodic PV amounts across all tasks by performance period (PP). Then, finalize the PMB by creating the cumulative quantities
  • 4. 4 by PP. This is accomplished by adding, successively, the periodic PV determined from the summing across tasks. For example, add the total periodic PV in period two to period one to obtain the cumulative PV for period two; then for period three add its periodic PV to the cumulative PV for period two. This process is repeated through period ten. The resultant cumulative values for periods one through ten is the PMB. This is the project performance baseline from which ES for the total project is determined. Project Data ••• Performance Period ••• Task Nr Measure 0 1 2 3 4 5 6 7 8 9 10 11 12 PV ♦ 5 5 5 1 EV ♦ 4 5 6 AC ♦ 5 5 7 PV ♦ 10 2 EV ♦ 7 3 AC ♦ 10 5 PV ♦ 10 10 10 3 EV ♦ 8 13 9 AC ♦ 10 15 10 PV ♦ 5 5 4 EV ♦ 3 4 3 AC ♦ 5 5 5 PV ♦ 5 5 5 5 EV ♦ 5 3 5 2 AC ♦ 5 5 5 2 PV ♦ 5 5 6 EV ♦ 6 4 AC ♦ 5 5 PV ♦ 10 10 10 10 10 7 EV ♦ 8 9 7 13 8 5 AC ♦ 10 10 10 15 10 5 PV ♦ 5 10 5 8 EV ♦ 12 8 AC ♦ 15 12 PV ♦ 5 5 5 9 EV ♦ 4 5 3 3 AC ♦ 5 6 5 3 PV ♦ 5 5 10 EV ♦ 10 AC ♦ 14 Table 1. Project Plan and Performance Measures by Task
  • 5. 5 To analyze tasks (work packages), control accounts or critical path a performance baseline must be created specific to the analysis area; i.e., if a cost account is to be analyzed, its comprising tasks must be segregated and grouped. Then the process for creating the project PMB is applied to this set of tasks to create a PMB for the cost account, PMBa. Having PMBa allows ES to be calculated specifically for the cost account. In turn, the determination of ES facilitates the calculations of SPI(t) and IEAC(t) for the specific evaluation of cost account performance. Critical Path Example With the methods in place, the process for applying ES to critical path analysis can be described. As discussed in the previous section of the paper, segregate and group the critical path tasks, and create a PMB representing them, PMBc. For this example, the critical path for the notional project includes tasks one, four, eight, and ten (1-4-8-10). Table 2, Performance Baselines and Earned Value Measures, aggregates the data for both the total project and the critical path. ••• Performance Period ••• Measure 0 1 2 3 4 5 6 7 8 9 10 11 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 PVper 0 5 5 35 30 40 30 20 5 10 5 0 0 PVcum 0 5 10 45 75 115 145 165 170 180 185 185 185 Total 0 0 0 0 0 0 0 0 0 0 0 0 0 Project EVper 0 0 4 16 43 27 18 31 16 9 15 3 3 EVcum 0 0 4 20 63 90 108 139 155 164 179 182 185 0 0 0 0 0 0 0 0 0 0 0 0 0 ACper 0 0 5 20 52 35 20 37 22 10 20 5 3 ACcum 0 0 5 25 77 112 132 169 191 201 221 226 229 0 0 0 0 0 0 0 0 0 0 0 0 0 0 PVper 0 5 5 5 5 5 5 10 5 5 5 0 0 PVcum 0 5 10 15 20 25 30 40 45 50 55 55 55 Critical 0 0 0 0 0 0 0 0 0 0 0 0 0 Path EVper 0 0 4 8 10 3 0 12 8 0 10 0 0 1-4-8-10 EVcum 0 0 4 12 22 25 25 37 45 45 55 55 55 0 0 0 0 0 0 0 0 0 0 0 0 0 ACper 0 0 5 10 12 5 0 15 12 0 14 0 0 ACcum 0 0 5 15 27 32 32 47 59 59 73 73 73 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Table 2. Performance Baselines and Earned Value Measures The project management baselines for the total project (PMB) and critical path (PMBc) are their respective PVcum rows. The PVper rows represent the summation of the planned values of the representative tasks for the specific performance period. As described previously, the PVcum is obtained from the PVper values. For example the calculation for PVcum for period three of the total project is determined by adding PVper for period three to PVcum of period two: PVcum(3) = PVcum(2) + PVper(3). Using the values from the Table 2, the calculation can be performed: PVcum(3) = 10 + 35 = 45. The remainder of Table 2 contains the performance data, earned value (EV) and actual costs (AC), for the total project and for the specific critical path tasks. The accumulation of this information allows analysis and prediction to occur for both the total project and the critical path.
  • 6. 6 The EVM performance indicators and duration forecasts calculated from the Table 2 data are aggregated in Table 3, Performance Indicators and Duration Forecasts. The “p” and “c” appended to the indicators shown in the table indicate period and cumulative, respectively. From Table 2 it can be determined that the project is planned to complete in 10 time periods, but actually completes in 12. Similarly, Table 2 indicates the tasks on the critical path completed at the planned time, 10 periods. For comparison purposes both SPI and SPI(t) indicators are shown in Table 3. The familiar behavior of the two indicators is seen for the critical path and total project. The values for SPI(t) compare favorably to those for SPI for the critical path which completes as planned. However for the total project, the values for the two indicators are significantly different. The corresponding values for SPI(t)c and SPIc noticeably begin departing in period eight, and conclude as expected for late finishing projects; at project completion, SPI(t)c is a valid number (0.8333) truly depicting the actual schedule performance efficiency, while SPIc illogically equals 1.0. ••• Performance Period ••• Indicator 0 1 2 3 4 5 6 7 8 9 10 11 12 CPIp xxx xxx 0.8000 0.8000 0.8269 0.7714 0.9000 0.8378 0.7273 0.9000 0.7500 0.6000 1.0000 CPIc xxx xxx 0.8000 0.8000 0.8182 0.8036 0.8182 0.8225 0.8115 0.8159 0.8100 0.8053 0.8079 Total SPI(t)p xxx 0.0000 0.8000 1.4857 1.3143 0.7750 0.4500 0.9750 0.7000 0.4500 1.9500 0.5000 0.6000 Project SPI(t)c xxx 0.0000 0.4000 0.7619 0.9000 0.8750 0.8042 0.8286 0.8125 0.7722 0.8900 0.8545 0.8333 SPIp xxx 0.0000 0.8000 0.4571 1.4333 0.6750 0.6000 1.5500 3.2000 0.9000 3.0000 xxx xxx SPIc xxx 0.0000 0.4000 0.4444 0.8400 0.7826 0.7448 0.8424 0.9118 0.9111 0.9676 0.9838 1.0000 IEAC(t) xxx xxx 25.00 13.13 11.11 11.43 12.44 12.07 12.31 12.95 11.24 11.70 12.00 CPIp xxx xxx 0.8000 0.8000 0.8333 0.6000 xxx 0.8000 0.6667 xxx 0.7143 CPIc xxx xxx 0.8000 0.8000 0.8148 0.7813 0.7813 0.7872 0.7627 0.7627 0.7534 Critical Path SPI(t)p xxx 0.0000 0.8000 1.6000 2.0000 0.6000 0.0000 1.7000 1.3000 0.0000 2.0000 1-4-8-10 SPI(t)c xxx 0.0000 0.4000 0.8000 1.1000 1.0000 0.8333 0.9571 1.0000 0.8889 1.0000 SPIp xxx 0.0000 0.8000 1.6000 2.0000 0.6000 0.0000 1.2000 1.6000 0.0000 2.0000 SPIc xxx 0.0000 0.4000 0.8000 1.1000 1.0000 0.8333 0.9250 1.0000 0.9000 1.0000 IEAC(t) xxx xxx 25.00 12.50 9.09 10.00 12.00 10.45 10.00 11.25 10.00 xxx xxx Table 3. Performance Indicators and Duration Forecasts By inspection of Table 2, it is obvious the critical path changed during project execution. Knowing this begs the question, “Does the simultaneous application of ES to both the critical path and total project provide advance warning of this condition?” If the answer is “Yes,” then applying ES has been shown to yield analysis advantages to project managers. One significant implication of a response of “Yes” is detailed schedule performance information can be obtained solely from the EVM data …without the laborious bottom-up analysis performed by skilled schedulers. Another point is detailed schedule analysis takes time and considerable effort by sometimes several people, oftentimes becoming a distraction to those performing project work. For any size, but especially for larger projects, performing a detailed schedule analysis involving several subcontractors in the time-frame the ES schedule forecasting calculations can be made is virtually impossible.
  • 7. 7 The time advantage offered by IEAC(t) does not mean to imply that detailed bottom-up schedule analysis should never be performed. Certainly, just as the final cost estimate obtained from IEAC is not relied on solely at critical points without a detailed cost analysis, a bottom-up schedule estimation should be performed for confirmation of the ES forecast. By reviewing and comparing the IEAC(t) numbers for the total project and critical path we can answer the question posed a few paragraphs earlier. The answer is “Yes,” it can be observed that the critical path is likely to have changed. From examining Table 3 it is seen very early, beginning with period 3, that the forecast duration for the total project is always greater than the forecast for the critical path. It is reasonably clear that the critical path changed early in the project execution from tasks 1-4-8-10. From this example, it may be said that ES can provide advance warning that the critical path has changed. Without going into the detail, the project duration forecasting method from ES can further be used to identify the longest duration path; i.e., the changed critical path. By forecasting duration for each task and inserting the forecasts into the network structure of the schedule, the actual critical path can be determined as well as conditions for float. With some technical ingenuity, this analysis could be completely automated. Summary The Earned Schedule analysis method is demonstrated in this paper to be applicable to more than the total project. Segregating and grouping EVM data for a specific portion of the project is the technique by which ES is made applicable to the total project and any sub-level desired. Specifically, the technique is shown to be capable of analyzing the schedule performance for the critical path. By employing the same techniques to analyze critical path, schedule performance by individual tasks can be evaluated, which then allows identification of the longest duration path for the project (actual critical path) along with schedule float. References 1. Lipke, Walt. “Connecting Earned Value to the Schedule,” CrossTalk, June 2005: On-line (http://www.stsc.hill.af.mil/crosstalk/2005/06/0506Lipke.html). 2. Lipke, Walt. “Schedule is Different,” The Measurable News, March 2003: 10-15. 3. Henderson, Kym. “Further Developments in Earned Schedule,” The Measurable News, Spring 2004: 15-22. 4. http://www.earnedschedule.com/Calculator.shtml About the Author Walt Lipke recently retired as the deputy chief of the Software Division at the Oklahoma City Air Logistics Center. The division employs approximately 600 people, primarily electronics engineers. He has over 35 years of experience in the development, maintenance, and management of software for automated testing of avionics and jet
  • 8. 8 engines as well as automation of industrial processes. During his tenure, the division achieved several software process improvement milestones: • 1993 - first Air Force activity to achieve Level 2 of the Software Engineering Institute’s Capability Maturity Model® (CMM®) • 1996 - first software activity in federal service to achieve CMM® Level 4 distinction • 1998 – division achieved ISO 9001/TickIT registration • 1999 - division received the SEI/IEEE Award for Software Process Achievement Mr. Lipke has published several articles and presented at conferences, internationally, on the benefits of software process improvement and the application of earned value management and statistical methods to software projects. He is the creator of the technique Earned Schedule (Copyright © 2003 Lipke), which extracts schedule information from earned value data. Mr. Lipke is a graduate of the USA DoD course for Program Managers. He is a professional engineer with a master’s degree in physics, and is a member of the physics honor society, ΣΠΣ. Lipke achieved distinguished academic honors with the selection to ΦΚΦ.