SlideShare a Scribd company logo
1 of 39
© 2006 Prentice Hall, Inc.
6/18/20201
Welcome To Heartiest
Students
Dereje Jima
Construction Planning and Management
Department of Civil Engineering
ADDIS COLLEGE
Semester I
2017
6/18/20202
Stochastic Project Scheduling
Lecture
On
Stochastic Project Scheduling – Project Evaluation
and Review Technique
[PERT]
6/18/20203
Stochastic Project Scheduling [PERT]
Introduction
In some situations, estimating activity duration becomes
a difficult task due to ambiguity inherited in and the
risks associated with some work.
Thus, the duration of an activity is estimated as a
range of time values rather than being a single
value.
This section deals with the scheduling of the project
6/18/20204
Stochastic Project Scheduling
[PERT]
Scheduling with Uncertain Durations
Using the probabilistic distribution of activity
durations.
Duration of a particular activity is assumed to be a
random variable that is distributed in a particular fashion.
An activity duration might be assumed to be distributed
as a normal or a beta distributed random variable as
shown in figure below.
Stochastic Project Scheduling [PERT]
6/18/20205
Stochastic Project Scheduling
[PERT]
Figure shows the probability or chance of experiencing
a particular activity duration based on a probabilistic
distribution.
Stochastic Project Scheduling [PERT]
6/18/20206
Stochastic Project Scheduling
[PERT]
The beta distribution is often used to characterize
activity durations, since it can have an absolute
minimum and an absolute maximum of possible
duration times.
The normal distribution is a good approximation to the
beta distribution in the center of the distribution and
is easy to work with, so it is often used as an
approximation.
Stochastic Project Scheduling [PERT]
6/18/20207
Stochastic Project Scheduling
[PERT]
The most common formal approach to incorporate
uncertainty in the scheduling process is to apply the
critical path scheduling process and then analyze the
results from a probabilistic perspective.
This process is usually referred to as the Program
Evaluation and Review Technique [PERT] method.
The critical path [determined] is then used to analyze
the duration of the project incorporating the uncertainty
of the activity durations along the critical path.
Stochastic Project Scheduling [PERT]
6/18/20208
Stochastic Project Scheduling
[PERT]
The expected project duration is equal to the sum of
the expected durations of the activities along
the critical path.
Assuming that activity durations are independent
random variables, the variance or variation in the
duration of this critical path is calculated as the
sum of the variances along the critical path.
Stochastic Project Scheduling [PERT]
6/18/20209
Stochastic Project Scheduling
[PERT]
With the mean and variance of the identified critical
path known, the distribution of activity durations can also
be computed.
Stochastic Project Scheduling [PERT]
6/18/202010
Stochastic Project Scheduling
[PERT]
Program Evaluation and Review Technique
PERT introduces uncertainty into the estimates for
activity and project durations.
PERT is well suited for those situations where there is
either insufficient background information to specify
accurately time and cost or where project activities
require research and development.
Stochastic Project Scheduling [PERT]
6/18/202011
Stochastic Project Scheduling
[PERT]
AON diagramming can be easily used alternatively
AOA [original development approach].
The method is based on the well-known “central
limit theorem”.
Stochastic Project Scheduling [PERT]
6/18/202012
Stochastic Project Scheduling
[PERT]
The theorem states that:
… “Where a series of sequential independent activities
lie on the critical path of a network, the sum of the
individual activity durations will be distributed in
approximately normal fashion, regardless of the
distribution of the individual activities themselves….
… The mean of the distribution of the sum of the activity
durations will be the sum of the means of the individual
activities and its variance will be the sum of the
Stochastic Project Scheduling [PERT]
6/18/202013
Stochastic Project Scheduling
[PERT]
Primary assumptions of PERT can be summarized as
follows:
Any PERT path must have enough activities to make
central limit theorem valid.
The mean of the distribution of the path with the
greatest duration, from the initial node to a given
node, is given by the maximum mean of the duration
distribution of the paths entering the node.
PERT critical path is longer enough than any other path in
Stochastic Project Scheduling [PERT]
6/18/202014
Stochastic Project Scheduling [PERT]
Six Steps PERT & CPM
1. Define the project and prepare the work breakdown
structure
2. Develop relationships among the activities - decide
which activities must precede and which must follow
others
3. Draw the network connecting all of the activities
Stochastic Project Scheduling [PERT]
6/18/202015
Stochastic Project Scheduling [PERT]
Step Cont’d
4. Assign time and/or cost estimates to each activity
5. Compute the longest time path through the network –
this is called the critical path
6. Use the network to help plan, schedule, monitor, and
control the project
Stochastic Project Scheduling [PERT]
Questions PERT & CPM Can Answer
1. When will the entire project be completed?
2. What are the critical activities or tasks in the project?
3. Which are the noncritical activities?
4. What is the probability the project will be completed by
a specific date?
6/18/202016
Stochastic Project Scheduling
[PERT]
Stochastic Project Scheduling [PERT]
5. Is the project on schedule, behind schedule, or ahead
of schedule?
6. Is the money spent equal to, less than, or greater than
the budget?
7. Are there enough resources available to finish the
project on time?
8. If the project must be finished in a shorter time, what is
the way to accomplish this at least cost?6/18/202017
Stochastic Project Scheduling
[PERT]
Stochastic Project Scheduling [PERT]
6/18/202018
Stochastic Project Scheduling
[PERT]
Variability in Activity Times
CPM assumes we know a fixed time estimate for
each activity and there is no variability in activity
times
PERT uses a probability distribution for activity
times to allow for variability
Stochastic Project Scheduling [PERT]
6/18/202019
Stochastic Project Scheduling
[PERT]
Variability in Activity Times: Three time
estimates are required
Optimistic time (a): Estimate of the minimum time
required for an activity if exceptionally good luck is
experienced. If everything goes according to
plan.
Most–likely or modal time (m) [Most
realistic/probable estimate]: Time required if the
activity is repeated a number of times under
Stochastic Project Scheduling [PERT]
6/18/202020
Stochastic Project Scheduling
[PERT]
Pessimistic time (b) [Assuming very
unfavorable conditions]: Estimate of the maximum
time required if unusually bad luck is experienced.
Stochastic Project Scheduling [PERT]
6/18/202021
Stochastic Project Scheduling
[PERT]
These three time estimates become the framework on
which the probability distribution curve for the
activity is erected.
Many authors argue that beta distribution is mostly
fit construction activities.
The three times are thought to be easier for
managers to estimate subjectively.
Stochastic Project Scheduling [PERT]
6/18/202022
Stochastic Project Scheduling
[PERT]
Using the three times estimates, the expected mean
time (te) is derived using equation below.
Then, te is used as the best available time
approximation for the activity in question.
The standard deviation (σ) is given by equation below,
The variance (ν) can be determined as ν = σ2.
Stochastic Project Scheduling [PERT]
6/18/202023
Stochastic Project Scheduling
[PERT]
Estimate follows beta distribution
Standard Deviation
Expected time:
Variance of times:
t = (a + 4m +
b)/6
v = [(b – a)/6]2
Stochastic Project Scheduling [PERT]
6/18/202024
Stochastic Project Scheduling
[PERT]
By adopting activity expected mean time, the critical
path calculations proceed as CPM.
Associated with each duration in PERT, however,
is its standard deviation or its variance.
The project duration is determined by summing up the
activity expected mean time along the critical path
and thus will be an expected mean duration.
Stochastic Project Scheduling [PERT]
6/18/202025
Stochastic Project Scheduling
[PERT]
Since the activities on the critical path are
independent of each other, central limit theory gives
the variance of the project duration as the sum of
the individual variances of these critical path
activities.
Stochastic Project Scheduling [PERT]
6/18/202026
Stochastic Project Scheduling
[PERT]
Once the expected mean time for project duration
(TX) and its standard deviation (σX) are determined,
it is possible to calculate the chance of meeting
specific project duration (TS).
Then normal probability tables are used to
determine such chance using Equation below.
Stochastic Project Scheduling [PERT]
6/18/202027
Stochastic Project Scheduling
[PERT]
The procedure for hand probability computations using
PERT can be summarized in the following steps:
1. Make the usual forward and backward pass
computations based on a single estimate (mean) for
each activity.
2. Obtain estimates for a, m, and b for only critical
activities. If necessary, adjust the length of the critical
path as dictated by the new te values based on a, m,
and b.
Stochastic Project Scheduling [PERT]
6/18/202028
Stochastic Project Scheduling
[PERT]
3. Compute the variance for event x (νX) by
summing the variances for the critical activities
leading to event x.
4. Compute Z and find the corresponding normal
probability.
Stochastic Project Scheduling [PERT]
6/18/202029
Stochastic Project Scheduling
[PERT]
Estimate follows beta distribution
Expected time:
Variance of times:
t = (a + 4m + b)/6
v = [(b − a)/6]2
Probability
of 1 in 100
of > b
occurring
Probability
of 1 in 100
of
< a
occurring
Probability
Optimistic
Time (a)
Most Likely
Time (m)
Pessimistic
Time (b)
Activity
Time
Stochastic Project Scheduling [PERT]
6/18/202030
Stochastic Project Scheduling
[PERT]
Most Expected
Optimistic Likely Pessimistic Time Variance
Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2
A 1 2 3 2 .11
B 2 3 4 3 .11
C 1 2 3 2 .11
D 2 4 6 4 .44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 .11
Computing Variance
Stochastic Project Scheduling [PERT]
6/18/202031
Stochastic Project Scheduling
[PERT]
Project variance is computed by summing the
variances of critical activities
s2 = Project variance
= (variances of activities
on critical path)
p
Probability of Project Completion
Stochastic Project Scheduling [PERT]
6/18/202032
Stochastic Project Scheduling
[PERT]
Project variance
s2 = .11 + .11 + 1.00 + 1.78 + .11 = 3.11
Project standard deviation
sp = Project variance
= 3.11 = 1.76 weeks
p
Stochastic Project Scheduling [PERT]
6/18/202033
Stochastic Project Scheduling
[PERT]
Standard deviation = 1.76 weeks
15 Weeks
(Expected Completion Time)
Stochastic Project Scheduling [PERT]
6/18/202034
Stochastic Project Scheduling
[PERT]
What is the probability this project can be completed
on or before the 16 week deadline?
Z = – /sp
= (16 wks – 15 wks)/1.76
= 0.57
due expected date
date of completion
Where Z is the number of
standard deviations the due
date lies from the mean
Stochastic Project Scheduling [PERT]
6/18/202035
Stochastic Project Scheduling
[PERT]
Z= − /sp
= (16 wks − 15 wks)/1.76
= 0.57
due expected date
date of completion
Where Z is the number of
standard deviations the due
date lies from the mean
.00 .01 .07 .08
.1 .50000 .50399 .52790 .53188
.2 .53983 .54380 .56749 .57142
.5 .69146 .69497 .71566 .71904
.6 .72575 .72907 .74857 .75175
From Appendix I
Stochastic Project Scheduling [PERT]
6/18/202036
Stochastic Project Scheduling
[PERT]
Time
Probability
(T ≤ 16 weeks)
is 71.57%
0.57 Standard deviations
15 16
Weeks Weeks
Stochastic Project Scheduling [PERT]
6/18/202037
Stochastic Project Scheduling
[PERT]
Probability
of 0.01
Z
From Appendix I
Probability
of 0.99
2.33
Standard
deviations0 2.33
Determining Project Completion Time
Stochastic Project Scheduling [PERT]
6/18/202038
6/18/202039
Stochastic Project Scheduling
[PERT]
Stochastic Project Scheduling
[PERT]

More Related Content

What's hot

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysistheijes
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET Journal
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt341741357
 
8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-moreatifaizan
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project kaishwarya3
 
ROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTY
ROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTYROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTY
ROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTYijseajournal
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 

What's hot (18)

PROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERTPROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERT
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
PERT
PERTPERT
PERT
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
ROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTY
ROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTYROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTY
ROBUST OPTIMIZATION FOR RCPSP UNDER UNCERTAINTY
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 

Similar to PERT

Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing AlgorithmIOSR Journals
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET Journal
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applicationsAmrit Mty
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Chandra Shekar Immani
 
NET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxNET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxpaulkinyua6
 
A partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfA partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfrozakashif85
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptRajnikantPatel45
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartMathew Varghese V
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 

Similar to PERT (20)

PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
NET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxNET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptx
 
A partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfA partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdf
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 

More from Dereje Jima

Manage Quality Customer Service1.pdf
Manage Quality Customer Service1.pdfManage Quality Customer Service1.pdf
Manage Quality Customer Service1.pdfDereje Jima
 
Arrange building applications and approvals.pdf
Arrange building applications and approvals.pdfArrange building applications and approvals.pdf
Arrange building applications and approvals.pdfDereje Jima
 
Administer Legal Obligations of Construction Contract.docx
Administer Legal Obligations of Construction Contract.docxAdminister Legal Obligations of Construction Contract.docx
Administer Legal Obligations of Construction Contract.docxDereje Jima
 
Covariance and correlation(Dereje JIMA)
Covariance and correlation(Dereje JIMA)Covariance and correlation(Dereje JIMA)
Covariance and correlation(Dereje JIMA)Dereje Jima
 
system analysis and management techniques (Dereje jima)
system analysis and management techniques (Dereje jima)system analysis and management techniques (Dereje jima)
system analysis and management techniques (Dereje jima)Dereje Jima
 
Project planning
Project planning Project planning
Project planning Dereje Jima
 
Special concrete and advanced construction materials
Special concrete and advanced construction materialsSpecial concrete and advanced construction materials
Special concrete and advanced construction materialsDereje Jima
 
CONSTRUCTION STATISTICS pr by Dereje jima
CONSTRUCTION STATISTICS pr by Dereje jimaCONSTRUCTION STATISTICS pr by Dereje jima
CONSTRUCTION STATISTICS pr by Dereje jimaDereje Jima
 

More from Dereje Jima (8)

Manage Quality Customer Service1.pdf
Manage Quality Customer Service1.pdfManage Quality Customer Service1.pdf
Manage Quality Customer Service1.pdf
 
Arrange building applications and approvals.pdf
Arrange building applications and approvals.pdfArrange building applications and approvals.pdf
Arrange building applications and approvals.pdf
 
Administer Legal Obligations of Construction Contract.docx
Administer Legal Obligations of Construction Contract.docxAdminister Legal Obligations of Construction Contract.docx
Administer Legal Obligations of Construction Contract.docx
 
Covariance and correlation(Dereje JIMA)
Covariance and correlation(Dereje JIMA)Covariance and correlation(Dereje JIMA)
Covariance and correlation(Dereje JIMA)
 
system analysis and management techniques (Dereje jima)
system analysis and management techniques (Dereje jima)system analysis and management techniques (Dereje jima)
system analysis and management techniques (Dereje jima)
 
Project planning
Project planning Project planning
Project planning
 
Special concrete and advanced construction materials
Special concrete and advanced construction materialsSpecial concrete and advanced construction materials
Special concrete and advanced construction materials
 
CONSTRUCTION STATISTICS pr by Dereje jima
CONSTRUCTION STATISTICS pr by Dereje jimaCONSTRUCTION STATISTICS pr by Dereje jima
CONSTRUCTION STATISTICS pr by Dereje jima
 

Recently uploaded

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

PERT

  • 1. © 2006 Prentice Hall, Inc. 6/18/20201 Welcome To Heartiest Students Dereje Jima Construction Planning and Management Department of Civil Engineering ADDIS COLLEGE Semester I 2017
  • 2. 6/18/20202 Stochastic Project Scheduling Lecture On Stochastic Project Scheduling – Project Evaluation and Review Technique [PERT]
  • 3. 6/18/20203 Stochastic Project Scheduling [PERT] Introduction In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. Thus, the duration of an activity is estimated as a range of time values rather than being a single value. This section deals with the scheduling of the project
  • 4. 6/18/20204 Stochastic Project Scheduling [PERT] Scheduling with Uncertain Durations Using the probabilistic distribution of activity durations. Duration of a particular activity is assumed to be a random variable that is distributed in a particular fashion. An activity duration might be assumed to be distributed as a normal or a beta distributed random variable as shown in figure below. Stochastic Project Scheduling [PERT]
  • 5. 6/18/20205 Stochastic Project Scheduling [PERT] Figure shows the probability or chance of experiencing a particular activity duration based on a probabilistic distribution. Stochastic Project Scheduling [PERT]
  • 6. 6/18/20206 Stochastic Project Scheduling [PERT] The beta distribution is often used to characterize activity durations, since it can have an absolute minimum and an absolute maximum of possible duration times. The normal distribution is a good approximation to the beta distribution in the center of the distribution and is easy to work with, so it is often used as an approximation. Stochastic Project Scheduling [PERT]
  • 7. 6/18/20207 Stochastic Project Scheduling [PERT] The most common formal approach to incorporate uncertainty in the scheduling process is to apply the critical path scheduling process and then analyze the results from a probabilistic perspective. This process is usually referred to as the Program Evaluation and Review Technique [PERT] method. The critical path [determined] is then used to analyze the duration of the project incorporating the uncertainty of the activity durations along the critical path. Stochastic Project Scheduling [PERT]
  • 8. 6/18/20208 Stochastic Project Scheduling [PERT] The expected project duration is equal to the sum of the expected durations of the activities along the critical path. Assuming that activity durations are independent random variables, the variance or variation in the duration of this critical path is calculated as the sum of the variances along the critical path. Stochastic Project Scheduling [PERT]
  • 9. 6/18/20209 Stochastic Project Scheduling [PERT] With the mean and variance of the identified critical path known, the distribution of activity durations can also be computed. Stochastic Project Scheduling [PERT]
  • 10. 6/18/202010 Stochastic Project Scheduling [PERT] Program Evaluation and Review Technique PERT introduces uncertainty into the estimates for activity and project durations. PERT is well suited for those situations where there is either insufficient background information to specify accurately time and cost or where project activities require research and development. Stochastic Project Scheduling [PERT]
  • 11. 6/18/202011 Stochastic Project Scheduling [PERT] AON diagramming can be easily used alternatively AOA [original development approach]. The method is based on the well-known “central limit theorem”. Stochastic Project Scheduling [PERT]
  • 12. 6/18/202012 Stochastic Project Scheduling [PERT] The theorem states that: … “Where a series of sequential independent activities lie on the critical path of a network, the sum of the individual activity durations will be distributed in approximately normal fashion, regardless of the distribution of the individual activities themselves…. … The mean of the distribution of the sum of the activity durations will be the sum of the means of the individual activities and its variance will be the sum of the Stochastic Project Scheduling [PERT]
  • 13. 6/18/202013 Stochastic Project Scheduling [PERT] Primary assumptions of PERT can be summarized as follows: Any PERT path must have enough activities to make central limit theorem valid. The mean of the distribution of the path with the greatest duration, from the initial node to a given node, is given by the maximum mean of the duration distribution of the paths entering the node. PERT critical path is longer enough than any other path in Stochastic Project Scheduling [PERT]
  • 14. 6/18/202014 Stochastic Project Scheduling [PERT] Six Steps PERT & CPM 1. Define the project and prepare the work breakdown structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities Stochastic Project Scheduling [PERT]
  • 15. 6/18/202015 Stochastic Project Scheduling [PERT] Step Cont’d 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network – this is called the critical path 6. Use the network to help plan, schedule, monitor, and control the project Stochastic Project Scheduling [PERT]
  • 16. Questions PERT & CPM Can Answer 1. When will the entire project be completed? 2. What are the critical activities or tasks in the project? 3. Which are the noncritical activities? 4. What is the probability the project will be completed by a specific date? 6/18/202016 Stochastic Project Scheduling [PERT] Stochastic Project Scheduling [PERT]
  • 17. 5. Is the project on schedule, behind schedule, or ahead of schedule? 6. Is the money spent equal to, less than, or greater than the budget? 7. Are there enough resources available to finish the project on time? 8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost?6/18/202017 Stochastic Project Scheduling [PERT] Stochastic Project Scheduling [PERT]
  • 18. 6/18/202018 Stochastic Project Scheduling [PERT] Variability in Activity Times CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a probability distribution for activity times to allow for variability Stochastic Project Scheduling [PERT]
  • 19. 6/18/202019 Stochastic Project Scheduling [PERT] Variability in Activity Times: Three time estimates are required Optimistic time (a): Estimate of the minimum time required for an activity if exceptionally good luck is experienced. If everything goes according to plan. Most–likely or modal time (m) [Most realistic/probable estimate]: Time required if the activity is repeated a number of times under Stochastic Project Scheduling [PERT]
  • 20. 6/18/202020 Stochastic Project Scheduling [PERT] Pessimistic time (b) [Assuming very unfavorable conditions]: Estimate of the maximum time required if unusually bad luck is experienced. Stochastic Project Scheduling [PERT]
  • 21. 6/18/202021 Stochastic Project Scheduling [PERT] These three time estimates become the framework on which the probability distribution curve for the activity is erected. Many authors argue that beta distribution is mostly fit construction activities. The three times are thought to be easier for managers to estimate subjectively. Stochastic Project Scheduling [PERT]
  • 22. 6/18/202022 Stochastic Project Scheduling [PERT] Using the three times estimates, the expected mean time (te) is derived using equation below. Then, te is used as the best available time approximation for the activity in question. The standard deviation (σ) is given by equation below, The variance (ν) can be determined as ν = σ2. Stochastic Project Scheduling [PERT]
  • 23. 6/18/202023 Stochastic Project Scheduling [PERT] Estimate follows beta distribution Standard Deviation Expected time: Variance of times: t = (a + 4m + b)/6 v = [(b – a)/6]2 Stochastic Project Scheduling [PERT]
  • 24. 6/18/202024 Stochastic Project Scheduling [PERT] By adopting activity expected mean time, the critical path calculations proceed as CPM. Associated with each duration in PERT, however, is its standard deviation or its variance. The project duration is determined by summing up the activity expected mean time along the critical path and thus will be an expected mean duration. Stochastic Project Scheduling [PERT]
  • 25. 6/18/202025 Stochastic Project Scheduling [PERT] Since the activities on the critical path are independent of each other, central limit theory gives the variance of the project duration as the sum of the individual variances of these critical path activities. Stochastic Project Scheduling [PERT]
  • 26. 6/18/202026 Stochastic Project Scheduling [PERT] Once the expected mean time for project duration (TX) and its standard deviation (σX) are determined, it is possible to calculate the chance of meeting specific project duration (TS). Then normal probability tables are used to determine such chance using Equation below. Stochastic Project Scheduling [PERT]
  • 27. 6/18/202027 Stochastic Project Scheduling [PERT] The procedure for hand probability computations using PERT can be summarized in the following steps: 1. Make the usual forward and backward pass computations based on a single estimate (mean) for each activity. 2. Obtain estimates for a, m, and b for only critical activities. If necessary, adjust the length of the critical path as dictated by the new te values based on a, m, and b. Stochastic Project Scheduling [PERT]
  • 28. 6/18/202028 Stochastic Project Scheduling [PERT] 3. Compute the variance for event x (νX) by summing the variances for the critical activities leading to event x. 4. Compute Z and find the corresponding normal probability. Stochastic Project Scheduling [PERT]
  • 29. 6/18/202029 Stochastic Project Scheduling [PERT] Estimate follows beta distribution Expected time: Variance of times: t = (a + 4m + b)/6 v = [(b − a)/6]2 Probability of 1 in 100 of > b occurring Probability of 1 in 100 of < a occurring Probability Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) Activity Time Stochastic Project Scheduling [PERT]
  • 30. 6/18/202030 Stochastic Project Scheduling [PERT] Most Expected Optimistic Likely Pessimistic Time Variance Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2 A 1 2 3 2 .11 B 2 3 4 3 .11 C 1 2 3 2 .11 D 2 4 6 4 .44 E 1 4 7 4 1.00 F 1 2 9 3 1.78 G 3 4 11 5 1.78 H 1 2 3 2 .11 Computing Variance Stochastic Project Scheduling [PERT]
  • 31. 6/18/202031 Stochastic Project Scheduling [PERT] Project variance is computed by summing the variances of critical activities s2 = Project variance = (variances of activities on critical path) p Probability of Project Completion Stochastic Project Scheduling [PERT]
  • 32. 6/18/202032 Stochastic Project Scheduling [PERT] Project variance s2 = .11 + .11 + 1.00 + 1.78 + .11 = 3.11 Project standard deviation sp = Project variance = 3.11 = 1.76 weeks p Stochastic Project Scheduling [PERT]
  • 33. 6/18/202033 Stochastic Project Scheduling [PERT] Standard deviation = 1.76 weeks 15 Weeks (Expected Completion Time) Stochastic Project Scheduling [PERT]
  • 34. 6/18/202034 Stochastic Project Scheduling [PERT] What is the probability this project can be completed on or before the 16 week deadline? Z = – /sp = (16 wks – 15 wks)/1.76 = 0.57 due expected date date of completion Where Z is the number of standard deviations the due date lies from the mean Stochastic Project Scheduling [PERT]
  • 35. 6/18/202035 Stochastic Project Scheduling [PERT] Z= − /sp = (16 wks − 15 wks)/1.76 = 0.57 due expected date date of completion Where Z is the number of standard deviations the due date lies from the mean .00 .01 .07 .08 .1 .50000 .50399 .52790 .53188 .2 .53983 .54380 .56749 .57142 .5 .69146 .69497 .71566 .71904 .6 .72575 .72907 .74857 .75175 From Appendix I Stochastic Project Scheduling [PERT]
  • 36. 6/18/202036 Stochastic Project Scheduling [PERT] Time Probability (T ≤ 16 weeks) is 71.57% 0.57 Standard deviations 15 16 Weeks Weeks Stochastic Project Scheduling [PERT]
  • 37. 6/18/202037 Stochastic Project Scheduling [PERT] Probability of 0.01 Z From Appendix I Probability of 0.99 2.33 Standard deviations0 2.33 Determining Project Completion Time Stochastic Project Scheduling [PERT]