SlideShare a Scribd company logo
1 of 6
Download to read offline
Submitted to Agile Development, June 25–28, 2003 Salt Lake City, Utah
1
Making Agile Development Work in a Government Contracting Environment
Measuring velocity with Earned Value
Glen B. Alleman and Michael Henderson
CH2M HILL
Golden, Colorado
glen.alleman@rfets.gov
michael.henderson@rfets.gov
Ray Seggelke
Envision Technology Partners
Lakewood, Colorado
raymond.seggelke@rfets.gov
Abstract: Before any of the current “agile” development
methods, Earned Value Management provided informa-
tion for planning and controlling complex projects by
measuring how much “value” was produced for a given
cost in a period of time. One shortcoming of an agile
development method is its inability to forecast the future
cost and schedule of the project beyond the use of “yes-
terdays weather” metrics. These agile methods assume
the delivered value, “velocity” in the case of XP, is com-
pared with the estimated value – this is a simple compari-
son between budget and actual cost resulting in a Cost
Variance. No Schedule Variance process is directly
available in XP. Earned Value Analysis provides a means
of predicting future schedule and cost variances through
three measurements – budgeted cost for work scheduled,
actual cost for work performed, and budgeted cost for
work performed (earned value). This paper describes
the use of Earned Value in conjunction with Agile De-
velopment on a mission-critical, high-security, govern-
ment project.
1. INTRODUCTION
Measuring progress to plan is important no matter what
the business domain or software development method.
Extreme Programming, SCRUM, DSDM, FDD, Crystal,
etc. provide techniques for capturing requirements, esti-
mating effort, developing high quality software, reporting
progress to plan, and delivering value to the customer.
[1] The effectiveness of any specific agile method in
current business environments is not the topic of this
paper. The topic is the introduction of agile methods into
high–ceremony government contracting environments
that use Earned Value Management Systems as their
performance reporting and management.
In a government subcontractor software development
environment formal “artifacts” are needed for many
reasons, not the least of which is compliance with the
contract. [4] Earned Value Management Systems
(EVMS) are the means of complying with a “progress–
to–plan” reporting requirements. The desire to use agile
software development methods while still maintaining
compliance with contract reporting needs may appear to
be a conflict, but it is not. The two approaches provide
similar solutions to measuring progress. These include:
Earned Value Agile Development
A Big Picture View of the
Project.
Continuous production of
useable software.
Accurate Estimate at Com-
pletion.
Prediciton of the next itera-
tion’s effort.
End-to-end value tracking. Iteration to iteration tracking
Figure 1 – Basic Earned Value versus Agile Processes
The remainder of this paper describes our experiences
with embedded Extreme Programming practices in a
high–ceremony Earned Value software development
environment.
§ 2 Describes a brief overview of Earned Value
§ 3 Describes the realities of writing software in a
government contracting environment.
§ 4 Positions Earned Value Management in the con-
text of agile development
§ 5 Summarizes the steps needed and restates the
context of XP in an EVMS process.
2. A QUICK TOUR OF EARNED VALUE
Earned value provides a balance of technical (perform-
ance), cost (resources), and schedule (time) measures for
complex software projects, unlike traditional cost and
schedule only techniques.
Earned Value is a project management technique that
provides “leading” performance indicators that allow
project managers to identify and control project problems
before they become insurmountable. Traditional project
management techniques compare planned expenditures
with actual expenditures, which is equivalent to “driving
in the rear view mirror.” Earned Value adds a third meas-
ure – the actual work accomplishment as a result of the
expenditure. Measuring the actual work accomplished
provides greater insight into potential project risks.
2
risks. Figure 2 describes a “simple” view of these met-
rics and their relationships.
Figure 2 – Earned Value is One Slide
Like any good methodology a set of terms unique to that
method are needed. These Earned Value terms include:
! Budgeted Cost for Work Scheduled (BCWS) – this is
the Plan and represents the total budgeted cost. It an-
swers the question how much do we plan to spend?
! Budgeted Cost for Work Performed (BCWP) – this is
the Performance or Earned Value and is the cost
originally budgeted to accomplish the work that has
been completed. It answers the question how much
work has actually been completed?
! Actual Cost for Work Performed (ACWP) – this is
the Cost of the Performance or the Investment and
is the actual cost to accomplish all the work that was
performed. It answers the question how much did we
actually spend to deliver the Earned Value?
! Cost Variance – is the difference between planned
cost and actual cost. CV= ACWP–BCWS.
! Schedule Variance – is the difference between the
invested cost and the returned value. SV=BCWP–
ACWP.
! Cost and Schedule Performance Indices – are the
normalized performance indices. CPI=BCWP /
ACWP, SPI=BCWP / BCWS
! Estimate at Completion and Estimate to Completion –
are calculated values that are estimates of the total
cost and cost to complete.
EAC=Cost to Date + Estimated Cost of Remaining
Work.
The essence of EVMS … is that at some level of detail
appropriate for the degree of technical, schedule, and
cost risk or uncertainly associated with the program, a
target value … is established. — Paul Solomon [6]
3. REALITIES OF A GOVERNMENT PROJECT
3.1 What’s The Problem Here?
In the traditional government contracting environment a
linear development process is common, usually based on
high–ceremony work artifacts embedded in a CMMi
compliant process. In many aspects these linear processes
are valuable, since care and concern is needed when
mission critical systems are developed. In nearly all cases
the “project controls” for these projects are based on
Earned Value measurements using the metrics shown in
Figure 2.
When agility is introduced to the development process
there is no real alternative for formally reporting pro-
gress–to–plan. The process of transforming a legacy
environment to an agile development environment can
take many paths. We took specific steps to not undo what
had been put in place in the past, while at the same time
moving forward. This includes:
! XP–like practices for software development [1]
–
these include most, but not all, of the XP practices
See Figure 3.
! Balanced Scorecard – focuses the IT organization on
strategies, objectives, and initiatives. This provides
the “reason” for many of the development projects
and process improvements. BSC starts at the top of
the organization and moves down, so top manage-
ment commitment is gained early in any improve-
ment process.
! Project Portfolio Management – assembles collec-
tions of projects into a portfolio for decision making
purposes.
! Team based delivery for all products and services –
breaks the mold on the legacy “command and con-
trol” management style and replaces it with self–
directed teams.
No matter what “work processes” are put in place, the
contractual reporting of “progress–to–plan,” must be
maintained. Reporting “velocity” to the Department of
Energy was not an option when we started to introduce
XP to the development process. Contract progress pay-
ments are based on “earned value” for the accounting
period and therefore are considered our “rice bowl,”
something you simply do not mess with.
3.2 OUR SOFTWARE DEVELOPMENT CHALLENGE
Most of the information and experience with earned
value is centered on large programs with systems and
1
We use the term XP–like to state that some of the XP prac-
tices aren’t in place. This also avoids explaining to the purist
what practices we use or don’t use.
3
organizations in place explicitly to support project man-
agement and earned value. Our development is small
compared to this environment. We have approximately
100 professional and technical support personnel that
provide software development, infrastructure deployment
and support, customer service, and program manage-
ment. We currently hold a CMM Level 3 certification
and are seeking CMMi Level 4. We would not be con-
sidered a “modern” development shop, since most of the
work is done in Oracle forms, PeopleSoft’s People-
Ware™ and other “low tech” tools.
Our mission is to provide applications and infrastructure
to an $11B de-construction project of critical national
importance. Rocky Flats Environmental Technology Site
is the first Department of Energy (DOE) nuclear weapons
production site to close on time on budget. Closure
means all the nuclear materials used in production and
their associated wastes will be removed from the 6,800–
acre site, restoring it to its natural pristine high plains
habitat. Our customer, Kaiser–Hill LLC, has a fixed
price, fixed duration contract with DOE for the closure.
Kaiser–Hill, DOE and our firm, CH2M HILL all live in
the earned value mentality.
Introducing agile development processes into this envi-
ronment is a challenge. Not because of the processes
themselves, but because of the financial reporting, CMM
compliance, and operational security requirements of the
contract.
XP is our method of choice and Figure 3 summarizes the
elements of XP currently in use in our project. Scrum is
also a choice, but most of the “agile” developers and
management have XP experience.
XP Practice Our Implementation
Planning Game Biweekly planning sessions.
Small Releases Biweekly iteration releases with full
integration with Configuration Man-
agement and IV&V.
Metaphor Not used.
Simple Design Forced on the team by the “time
boxed” iteration process.
Refactoring Not a major impact as yet.
Testing Unit tests, integration tests, IV&V
testing.
Pair Program-
ming
Not usually allowed because of code
access security requirements. Some
PP within small groups.
Collective Own-
ership
Not usually allowed because of code
access security.
Continuous Inte-
gration
Heavy investment in tools, but some
progress for daily builds.
40 Hour Week Mandated by our contract.
On–site Cus-
tomer
Customer Service Managers (CRMs)
with detailed process knowledge.
Coding Stan-
dards
Inherited from CMMI processes.
Figure 3 – XP Practices Deployed in a Government
Environment
4. EVMS AND THE AGILE FRAMEWORK
Not everything that can be counted
counts, and not everything that
counts can be counted. – Albert Ein-
stein
Most software development methods, including Agile
Methods, have a mechanism to measure progress to plan.
But comparing actual cost with planned costs is simply
measuring the “level of effort” consumed over a time
period. This measurement does not describe the “value”
delivered by the invested effort.
The critical aspect of Earned Value Analysis is the de-
termination of “value” delivered (BCWP) in exchange
for hours or dollars invested (ACWP) for software pro-
jects. This earned value is the basis for determining the
cost and schedule performance for a task or project.
4.1 EVMS DEVELOPMENT VALUE MEASUREMENT
All of the methods described above depend either on a
binary event or some subjective assessment of the pro-
gress that has been made during the reporting period.
Both approaches fail the integrity test for software pro-
ject management. This test asks the question – how do we
know that the software will behave as specified? If it does
behave as specified, then the development phase is com-
plete. If not, then rework is needed. In the typical EVMS
the budget for the task are used to accrue the value rather
than the expected business value associated with the
task’s completion. [2]
4.1.1 Technical Performance Measurement
One approach to measuring value is to employ “Techni-
cal Performance Measurement.” This approach is used on
many engineering and development projects in defense
systems. [5] Technical Performance Measurement is the
plan for expected technical achievement. The actual
progress of the project is compared using periodic meas-
urements or tests. The difference between the planned
progress and the actual progress represents a technical
variance. Technical Performance Measurement is an
accepted Earned Value process for assigning value to
BCWP. [5]
4.1.2 Testable Requirements
Within Earned Value’s Technical Performance Meas-
urement our approach to measuring the “value” of a
software component (BCWP) is the use of testable re-
quirements as a completion criteria and a linearly ad-
justed monetary value for the component as a percent of
4
BCWS. [7, 8] A testable requirement can be decomposed
to a collection of precise, unambiguous, and indivisible
set of low–level requirements. These criteria are only met
if it is possible to write a test case that would validate
whether the requirement has or has not been imple-
mented correctly. This is the source of the term “testable
requirement.”
Testable requirements provide several benefits for an
EVMS based development method, including:
! An overarching technical performance measure for
identifying progress to plan.
! The support of the contract measurement goals of a
Performance Based Contract.
! A uniform metric from the software conception phase
through system acceptance
! “Success oriented” metrics rather than “effort ori-
ented.”
! Integration of schedule and technical cost objectives
in a single performance based metric.
A testable requirement can be described in terms of:
! The state of the system and the data elements that are
inputs (e.g., customer number, product number)
! The condition or action associated with the require-
ment (e.g., the user enters data, the order is validated,
the check amount is deducted)
! The expected or specified result described in terms of
data elements (e.g., customer number must be 8 digit
numeric, product quantity must be greater than zero).
4.2 AGILE DEVELOPMENT VALUE MEASUREMENTS
In our use of EVMS, we took the approach of booking
0% or 100% of a task as BCWP and making the task
durations sufficiently small. With this simple guideline,
something then happens to the EVMS “value generating”
approach – it looks similar, in many respects, to an Agile
software development process. With this fine–grained
task breakdown process, all the EVMS principles are still
in place, but the behavior of the management system has
many of the attributes of an agile process.
There are still gaps to be closed, but the two paradigms
are now closer together than one would first imagine. In
an XP environment “velocity” is the measure of the ef-
fort invested to produce software. The deployment of EV
always starts with a chart of the EV components. Like
the chart in the previous page, but now the XP compo-
nents are integrated.
BCWS – from Work Authorization, linear spread or manual by period
ACWP – from ETS (time cards)
BCWP – from “testable requirements”
Start Month 1 Month 2 Month 3 Month 4 End
Week 1 Week 4.3Week 4Week 3Week 2
Month 5
BCWS – Linear distribution from WA budget
BCWS – User defined over duration of the WA
ACWP from ETS
BCWP from “testable requirements”
Iteration Iteration Iteration
Stories = BCWS
Tasks = BCWS in more detail
Assignments = ACWP
Velocity = BCWP
Testable Requirements = 0%/100% BCWP
Figure 4 – replacing Velocity with earned value
For each iteration, BCWS and ACWP are acquired from
the time card system. BCWP is defined through Stories,
Tasks, and Testable Requirements. The testable Re-
quirements are verified using Unit and Functional tests.
From the point of view of EVMS these processes are
“normal,” with the exception of the “fine grained” deliv-
erables. From the point of view of XP these processes are
also “normal.”
An earned value management system is not a reporting
system, contract administration, cost analysis, account-
ing, or a contractor's task management system. It is a
measure of the value of physical progress in a project and
as such adds additional effort to the work of managing a
project. Beyond the additional effort of an EVMS, care
must be taken to avoid hindering the project team’s abil-
ity to use its organic management systems.
With the Earned Value and Agile methods now outlined,
let’s look at the similarities of each as ask why can’t
Agile methods be used in an EVMS environment?
EVMS Methods Agile Methods
Define the scope of work. Scope defined in stories
and tasks. Scope captured
with 5 by 7 cards and held
in a 3–ring binder by the
project manager.
Develop an integrated
bottom–up estimate for
performing the scope of
work.
Using stories, tasks, “ve-
locity” estimates for com-
pletion and estimates at
completion can be created.
Assign resources for each
task in the plan.
Resources assigned during
the bi–weekly planning
session.
5
Measure the performance
of these resources against
the plan.
Use earned value as de-
fined in EIA–748.
Measure the cost effi-
ciency against the cost
plan.
Use earned value as de-
fined in EIA–748.
Forecast the final cost
based on the current
performance.
Use earned value as de-
fined in EIA–748.
Manage the remaining
work.
Use stories and tasks in the
planning sessions.
Mange changes to the
baseline.
Use stories and tasks in the
planning session.
Table 1 – Comparison between EVMS and Agile
Management
This table shows that many of the agile and EVMS proc-
esses share the same goal. It is likely though that each
community has little understanding of the other’s frame-
work and motivations.
4.3 Three Success Factors of Final Project Results
The success of using Earned Value Management to man-
age software development projects is dependent on three
factors:
! The quality of the baseline. The establishment of a
measurable baseline for work to be performed is dif-
ficult in the traditional software development effort.
Agile project methods focus much of their effort on
defining and discovering the scope of work to be per-
formance in iteration. Both XP and SCRUM have
unique methods for capturing this scope of work.
! The actual performance against the approved base-
line. Once the plan has been approved and imple-
mented the second success factor comes into play –
the actual performance of the project activities.
! Management’s determination to influence the results
given the performance indices. This is the most criti-
cal success factor for any project management
method. Without a commitment from management to
take aggressive actions based on the performance in-
dicators to influence the outcome of the remaining
work the project will fail to meet its desired out-
comes.
Aggressive project management actions, if taken
early, can often alter the final projected outcome for
the project. [3]
5. CONCLUSION
Many would content that XP and government contracting
Earned Value measurements based software development
are like “gasoline and fire,” never to be mixed. It turns
out that Earned Value Management Systems are very
similar to XP’s velocity measurement. Using the activi-
ties in Table 1, an XP team can comply with EIA–748
planning, reporting, and cost/schedule management proc-
esses with ease.
We’ve created a development environment that performs
many of the XP practices while maintaining our reporting
deliverables for EIA–748 compliance. This involved:
! Replacing XP’s velocity with Earned Value metrics.
! Creating fine–grained measures of BCWP using
“testable requirements.”
! Establishing the BCWS baseline at the beginning of
each iteration.
! Capturing ACWP through a time keeping system.
! Computing Cost Variance, Schedule Variance from
the three base earned value metrics
! Computing Estimate at Completion (EAC) and Esti-
mate to Completion (ETC) from these base metrics as
well.
Much of the “noise” about agile development, especially
XP in the traditionalist environment, has to do with how
to position these processes in a larger context. We’ve
taken the approach that XP is for writing code, support-
ing the processes for writing code, and delivery code to
the customer base. There are many other activities
needed to fulfill the needs of a government contracting
business, or any other business context.
Figure 5 shows how XP is positioned in this context…
Figure 5 – Embedding XP in a Larger Context
In our environment we have embedded Extreme Pro-
gramming in a large context. This context includes:
! Solution Architecture analyzes the business situation
to accurately identify the core needs of the customer
as well as the constraints imposed by the business en-
vironment.
6
! Extreme Programming Delivery provides the mecha-
nisms to incrementally deliver value, address risks
early in the development cycle, engage in continuous
integration and test, and deploy the system to the cus-
tomer in an incremental manner.
! Delivery Management is the key to success in the
government contracting environment. Delivery Man-
agement provides:
! Schedule Management through the creation and
maintenance of the project schedule.
! Budget and Financial Management through the
creation and maintenance of the financial plan,
the approved invoices for subcontractors and non-
labor items, and the financial metrics. In our envi-
ronment these are earned value metrics.
! Scope Management through the creation and
maintenance of updated schedules, architecture
and system requirements.
! Change Control Dispositioning and Integration
manages change requests and the updated project
baseline.
6. REFERENCES
1. Abrahamsson, Pekka, Outi Salo, Jussi Ron-
kainen, and Juhani Warsta “Agile Software De-
velopment Methods: Review and Analysis,”
Proceeding of ESPOO 2002.
2. Boehm, Barry and Kevin Sullivan, “Software Eco-
nomics: A Roadmap,” Proceedings on the Future of
Software Engineering, Limerick Ireland, 2000.
3. Fleming, Quentin and Joel M. Koppelman, Earned
Value Project Management 2nd
Edition, Project
Management Institute, 2000.
4. Lett, Steve, “Earned Value Management for Self
Directed Software Teams,” Software Engineering
Process Group, Lockheed Martin.
5. Pisano, N. D., Commander, USN, “Technical Per-
formance Measurement, Earned Value, and Risk
Management: An Integrated Diagnostic Tool for
Program Management.”
6. Solomon, Paul J., “Practical Software Measurement,
Performance–Based Earned Value,” Crosstalk, Sep-
tember, 2002.
7. Wilson, P. B., “Testable Requirements – An Alter-
nate Sizing Measure,” The Journal of the Quality
Assurance Institute (October 1995):1
8. Wilson, P. B., “Sizing Software with Testable Re-
quirements,” Systems Development Management,
34–10–04, Auerbach Publications, 2000
Glen B. Alleman is Vice President, Program Management,
CH2M HILL. Prior to CH2M HILL, Glen was a member
of a consulting firm specializing in ERP systems architec-
ture and deployment.
Michael Henderson is Manager, Applications Develop-
ment, CH2M HILL. Prior to CH2M HILL Michael was a
Vice President of Development with Computer Associ-
ates.
Raymond Seggelke is Manager, Software Development
for Environmental Technology Partners, a subcontractor to
CH2M HILL. Prior to ETP, Ray was an engagement
manager for BoldTech a Denver based Extreme Pro-
gramming software development firm. Prior to Boldtech,
Ray managed software development at Raytheon for
TDRS.
CH2M HILL is a tier one contractor for the Rocky Flats
Environmental Technology Site, Golden Colorado.
Michael and Glen work in the Communications Group’s
Information and Network Services department of CH2M
HILL, providing applications and infrastructure support of
the closure of Rocky Flats on or before December 15th
,
2006.

More Related Content

What's hot

From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersGlen Alleman
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essayGlen Alleman
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)Glen Alleman
 
Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Glen Alleman
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisGlen Alleman
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management GuidanceGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMGlen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darksideGlen Alleman
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)Glen Alleman
 
Risk adjusted engineering management
Risk adjusted engineering managementRisk adjusted engineering management
Risk adjusted engineering managementGlen Alleman
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineGlen Alleman
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project RiskGlen Alleman
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPKevin West
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?Glen Alleman
 

What's hot (20)

From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essay
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
 
Risk adjusted engineering management
Risk adjusted engineering managementRisk adjusted engineering management
Risk adjusted engineering management
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?
 

Similar to Making Agile Development work in Government Contracting

Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementGlen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Is project management worth the expense? How can you know?
Is project management worth the expense?  How can you know?Is project management worth the expense?  How can you know?
Is project management worth the expense? How can you know?Kolinger & Associates, LLC
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Project management
Project managementProject management
Project managementAhmed Said
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 

Similar to Making Agile Development work in Government Contracting (20)

Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Is project management worth the expense? How can you know?
Is project management worth the expense?  How can you know?Is project management worth the expense?  How can you know?
Is project management worth the expense? How can you know?
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Chap07
Chap07Chap07
Chap07
 
Project management
Project managementProject management
Project management
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
DPPM1
DPPM1DPPM1
DPPM1
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 

Recently uploaded

Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 

Recently uploaded (20)

Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 

Making Agile Development work in Government Contracting

  • 1. Submitted to Agile Development, June 25–28, 2003 Salt Lake City, Utah 1 Making Agile Development Work in a Government Contracting Environment Measuring velocity with Earned Value Glen B. Alleman and Michael Henderson CH2M HILL Golden, Colorado glen.alleman@rfets.gov michael.henderson@rfets.gov Ray Seggelke Envision Technology Partners Lakewood, Colorado raymond.seggelke@rfets.gov Abstract: Before any of the current “agile” development methods, Earned Value Management provided informa- tion for planning and controlling complex projects by measuring how much “value” was produced for a given cost in a period of time. One shortcoming of an agile development method is its inability to forecast the future cost and schedule of the project beyond the use of “yes- terdays weather” metrics. These agile methods assume the delivered value, “velocity” in the case of XP, is com- pared with the estimated value – this is a simple compari- son between budget and actual cost resulting in a Cost Variance. No Schedule Variance process is directly available in XP. Earned Value Analysis provides a means of predicting future schedule and cost variances through three measurements – budgeted cost for work scheduled, actual cost for work performed, and budgeted cost for work performed (earned value). This paper describes the use of Earned Value in conjunction with Agile De- velopment on a mission-critical, high-security, govern- ment project. 1. INTRODUCTION Measuring progress to plan is important no matter what the business domain or software development method. Extreme Programming, SCRUM, DSDM, FDD, Crystal, etc. provide techniques for capturing requirements, esti- mating effort, developing high quality software, reporting progress to plan, and delivering value to the customer. [1] The effectiveness of any specific agile method in current business environments is not the topic of this paper. The topic is the introduction of agile methods into high–ceremony government contracting environments that use Earned Value Management Systems as their performance reporting and management. In a government subcontractor software development environment formal “artifacts” are needed for many reasons, not the least of which is compliance with the contract. [4] Earned Value Management Systems (EVMS) are the means of complying with a “progress– to–plan” reporting requirements. The desire to use agile software development methods while still maintaining compliance with contract reporting needs may appear to be a conflict, but it is not. The two approaches provide similar solutions to measuring progress. These include: Earned Value Agile Development A Big Picture View of the Project. Continuous production of useable software. Accurate Estimate at Com- pletion. Prediciton of the next itera- tion’s effort. End-to-end value tracking. Iteration to iteration tracking Figure 1 – Basic Earned Value versus Agile Processes The remainder of this paper describes our experiences with embedded Extreme Programming practices in a high–ceremony Earned Value software development environment. § 2 Describes a brief overview of Earned Value § 3 Describes the realities of writing software in a government contracting environment. § 4 Positions Earned Value Management in the con- text of agile development § 5 Summarizes the steps needed and restates the context of XP in an EVMS process. 2. A QUICK TOUR OF EARNED VALUE Earned value provides a balance of technical (perform- ance), cost (resources), and schedule (time) measures for complex software projects, unlike traditional cost and schedule only techniques. Earned Value is a project management technique that provides “leading” performance indicators that allow project managers to identify and control project problems before they become insurmountable. Traditional project management techniques compare planned expenditures with actual expenditures, which is equivalent to “driving in the rear view mirror.” Earned Value adds a third meas- ure – the actual work accomplishment as a result of the expenditure. Measuring the actual work accomplished provides greater insight into potential project risks.
  • 2. 2 risks. Figure 2 describes a “simple” view of these met- rics and their relationships. Figure 2 – Earned Value is One Slide Like any good methodology a set of terms unique to that method are needed. These Earned Value terms include: ! Budgeted Cost for Work Scheduled (BCWS) – this is the Plan and represents the total budgeted cost. It an- swers the question how much do we plan to spend? ! Budgeted Cost for Work Performed (BCWP) – this is the Performance or Earned Value and is the cost originally budgeted to accomplish the work that has been completed. It answers the question how much work has actually been completed? ! Actual Cost for Work Performed (ACWP) – this is the Cost of the Performance or the Investment and is the actual cost to accomplish all the work that was performed. It answers the question how much did we actually spend to deliver the Earned Value? ! Cost Variance – is the difference between planned cost and actual cost. CV= ACWP–BCWS. ! Schedule Variance – is the difference between the invested cost and the returned value. SV=BCWP– ACWP. ! Cost and Schedule Performance Indices – are the normalized performance indices. CPI=BCWP / ACWP, SPI=BCWP / BCWS ! Estimate at Completion and Estimate to Completion – are calculated values that are estimates of the total cost and cost to complete. EAC=Cost to Date + Estimated Cost of Remaining Work. The essence of EVMS … is that at some level of detail appropriate for the degree of technical, schedule, and cost risk or uncertainly associated with the program, a target value … is established. — Paul Solomon [6] 3. REALITIES OF A GOVERNMENT PROJECT 3.1 What’s The Problem Here? In the traditional government contracting environment a linear development process is common, usually based on high–ceremony work artifacts embedded in a CMMi compliant process. In many aspects these linear processes are valuable, since care and concern is needed when mission critical systems are developed. In nearly all cases the “project controls” for these projects are based on Earned Value measurements using the metrics shown in Figure 2. When agility is introduced to the development process there is no real alternative for formally reporting pro- gress–to–plan. The process of transforming a legacy environment to an agile development environment can take many paths. We took specific steps to not undo what had been put in place in the past, while at the same time moving forward. This includes: ! XP–like practices for software development [1] – these include most, but not all, of the XP practices See Figure 3. ! Balanced Scorecard – focuses the IT organization on strategies, objectives, and initiatives. This provides the “reason” for many of the development projects and process improvements. BSC starts at the top of the organization and moves down, so top manage- ment commitment is gained early in any improve- ment process. ! Project Portfolio Management – assembles collec- tions of projects into a portfolio for decision making purposes. ! Team based delivery for all products and services – breaks the mold on the legacy “command and con- trol” management style and replaces it with self– directed teams. No matter what “work processes” are put in place, the contractual reporting of “progress–to–plan,” must be maintained. Reporting “velocity” to the Department of Energy was not an option when we started to introduce XP to the development process. Contract progress pay- ments are based on “earned value” for the accounting period and therefore are considered our “rice bowl,” something you simply do not mess with. 3.2 OUR SOFTWARE DEVELOPMENT CHALLENGE Most of the information and experience with earned value is centered on large programs with systems and 1 We use the term XP–like to state that some of the XP prac- tices aren’t in place. This also avoids explaining to the purist what practices we use or don’t use.
  • 3. 3 organizations in place explicitly to support project man- agement and earned value. Our development is small compared to this environment. We have approximately 100 professional and technical support personnel that provide software development, infrastructure deployment and support, customer service, and program manage- ment. We currently hold a CMM Level 3 certification and are seeking CMMi Level 4. We would not be con- sidered a “modern” development shop, since most of the work is done in Oracle forms, PeopleSoft’s People- Ware™ and other “low tech” tools. Our mission is to provide applications and infrastructure to an $11B de-construction project of critical national importance. Rocky Flats Environmental Technology Site is the first Department of Energy (DOE) nuclear weapons production site to close on time on budget. Closure means all the nuclear materials used in production and their associated wastes will be removed from the 6,800– acre site, restoring it to its natural pristine high plains habitat. Our customer, Kaiser–Hill LLC, has a fixed price, fixed duration contract with DOE for the closure. Kaiser–Hill, DOE and our firm, CH2M HILL all live in the earned value mentality. Introducing agile development processes into this envi- ronment is a challenge. Not because of the processes themselves, but because of the financial reporting, CMM compliance, and operational security requirements of the contract. XP is our method of choice and Figure 3 summarizes the elements of XP currently in use in our project. Scrum is also a choice, but most of the “agile” developers and management have XP experience. XP Practice Our Implementation Planning Game Biweekly planning sessions. Small Releases Biweekly iteration releases with full integration with Configuration Man- agement and IV&V. Metaphor Not used. Simple Design Forced on the team by the “time boxed” iteration process. Refactoring Not a major impact as yet. Testing Unit tests, integration tests, IV&V testing. Pair Program- ming Not usually allowed because of code access security requirements. Some PP within small groups. Collective Own- ership Not usually allowed because of code access security. Continuous Inte- gration Heavy investment in tools, but some progress for daily builds. 40 Hour Week Mandated by our contract. On–site Cus- tomer Customer Service Managers (CRMs) with detailed process knowledge. Coding Stan- dards Inherited from CMMI processes. Figure 3 – XP Practices Deployed in a Government Environment 4. EVMS AND THE AGILE FRAMEWORK Not everything that can be counted counts, and not everything that counts can be counted. – Albert Ein- stein Most software development methods, including Agile Methods, have a mechanism to measure progress to plan. But comparing actual cost with planned costs is simply measuring the “level of effort” consumed over a time period. This measurement does not describe the “value” delivered by the invested effort. The critical aspect of Earned Value Analysis is the de- termination of “value” delivered (BCWP) in exchange for hours or dollars invested (ACWP) for software pro- jects. This earned value is the basis for determining the cost and schedule performance for a task or project. 4.1 EVMS DEVELOPMENT VALUE MEASUREMENT All of the methods described above depend either on a binary event or some subjective assessment of the pro- gress that has been made during the reporting period. Both approaches fail the integrity test for software pro- ject management. This test asks the question – how do we know that the software will behave as specified? If it does behave as specified, then the development phase is com- plete. If not, then rework is needed. In the typical EVMS the budget for the task are used to accrue the value rather than the expected business value associated with the task’s completion. [2] 4.1.1 Technical Performance Measurement One approach to measuring value is to employ “Techni- cal Performance Measurement.” This approach is used on many engineering and development projects in defense systems. [5] Technical Performance Measurement is the plan for expected technical achievement. The actual progress of the project is compared using periodic meas- urements or tests. The difference between the planned progress and the actual progress represents a technical variance. Technical Performance Measurement is an accepted Earned Value process for assigning value to BCWP. [5] 4.1.2 Testable Requirements Within Earned Value’s Technical Performance Meas- urement our approach to measuring the “value” of a software component (BCWP) is the use of testable re- quirements as a completion criteria and a linearly ad- justed monetary value for the component as a percent of
  • 4. 4 BCWS. [7, 8] A testable requirement can be decomposed to a collection of precise, unambiguous, and indivisible set of low–level requirements. These criteria are only met if it is possible to write a test case that would validate whether the requirement has or has not been imple- mented correctly. This is the source of the term “testable requirement.” Testable requirements provide several benefits for an EVMS based development method, including: ! An overarching technical performance measure for identifying progress to plan. ! The support of the contract measurement goals of a Performance Based Contract. ! A uniform metric from the software conception phase through system acceptance ! “Success oriented” metrics rather than “effort ori- ented.” ! Integration of schedule and technical cost objectives in a single performance based metric. A testable requirement can be described in terms of: ! The state of the system and the data elements that are inputs (e.g., customer number, product number) ! The condition or action associated with the require- ment (e.g., the user enters data, the order is validated, the check amount is deducted) ! The expected or specified result described in terms of data elements (e.g., customer number must be 8 digit numeric, product quantity must be greater than zero). 4.2 AGILE DEVELOPMENT VALUE MEASUREMENTS In our use of EVMS, we took the approach of booking 0% or 100% of a task as BCWP and making the task durations sufficiently small. With this simple guideline, something then happens to the EVMS “value generating” approach – it looks similar, in many respects, to an Agile software development process. With this fine–grained task breakdown process, all the EVMS principles are still in place, but the behavior of the management system has many of the attributes of an agile process. There are still gaps to be closed, but the two paradigms are now closer together than one would first imagine. In an XP environment “velocity” is the measure of the ef- fort invested to produce software. The deployment of EV always starts with a chart of the EV components. Like the chart in the previous page, but now the XP compo- nents are integrated. BCWS – from Work Authorization, linear spread or manual by period ACWP – from ETS (time cards) BCWP – from “testable requirements” Start Month 1 Month 2 Month 3 Month 4 End Week 1 Week 4.3Week 4Week 3Week 2 Month 5 BCWS – Linear distribution from WA budget BCWS – User defined over duration of the WA ACWP from ETS BCWP from “testable requirements” Iteration Iteration Iteration Stories = BCWS Tasks = BCWS in more detail Assignments = ACWP Velocity = BCWP Testable Requirements = 0%/100% BCWP Figure 4 – replacing Velocity with earned value For each iteration, BCWS and ACWP are acquired from the time card system. BCWP is defined through Stories, Tasks, and Testable Requirements. The testable Re- quirements are verified using Unit and Functional tests. From the point of view of EVMS these processes are “normal,” with the exception of the “fine grained” deliv- erables. From the point of view of XP these processes are also “normal.” An earned value management system is not a reporting system, contract administration, cost analysis, account- ing, or a contractor's task management system. It is a measure of the value of physical progress in a project and as such adds additional effort to the work of managing a project. Beyond the additional effort of an EVMS, care must be taken to avoid hindering the project team’s abil- ity to use its organic management systems. With the Earned Value and Agile methods now outlined, let’s look at the similarities of each as ask why can’t Agile methods be used in an EVMS environment? EVMS Methods Agile Methods Define the scope of work. Scope defined in stories and tasks. Scope captured with 5 by 7 cards and held in a 3–ring binder by the project manager. Develop an integrated bottom–up estimate for performing the scope of work. Using stories, tasks, “ve- locity” estimates for com- pletion and estimates at completion can be created. Assign resources for each task in the plan. Resources assigned during the bi–weekly planning session.
  • 5. 5 Measure the performance of these resources against the plan. Use earned value as de- fined in EIA–748. Measure the cost effi- ciency against the cost plan. Use earned value as de- fined in EIA–748. Forecast the final cost based on the current performance. Use earned value as de- fined in EIA–748. Manage the remaining work. Use stories and tasks in the planning sessions. Mange changes to the baseline. Use stories and tasks in the planning session. Table 1 – Comparison between EVMS and Agile Management This table shows that many of the agile and EVMS proc- esses share the same goal. It is likely though that each community has little understanding of the other’s frame- work and motivations. 4.3 Three Success Factors of Final Project Results The success of using Earned Value Management to man- age software development projects is dependent on three factors: ! The quality of the baseline. The establishment of a measurable baseline for work to be performed is dif- ficult in the traditional software development effort. Agile project methods focus much of their effort on defining and discovering the scope of work to be per- formance in iteration. Both XP and SCRUM have unique methods for capturing this scope of work. ! The actual performance against the approved base- line. Once the plan has been approved and imple- mented the second success factor comes into play – the actual performance of the project activities. ! Management’s determination to influence the results given the performance indices. This is the most criti- cal success factor for any project management method. Without a commitment from management to take aggressive actions based on the performance in- dicators to influence the outcome of the remaining work the project will fail to meet its desired out- comes. Aggressive project management actions, if taken early, can often alter the final projected outcome for the project. [3] 5. CONCLUSION Many would content that XP and government contracting Earned Value measurements based software development are like “gasoline and fire,” never to be mixed. It turns out that Earned Value Management Systems are very similar to XP’s velocity measurement. Using the activi- ties in Table 1, an XP team can comply with EIA–748 planning, reporting, and cost/schedule management proc- esses with ease. We’ve created a development environment that performs many of the XP practices while maintaining our reporting deliverables for EIA–748 compliance. This involved: ! Replacing XP’s velocity with Earned Value metrics. ! Creating fine–grained measures of BCWP using “testable requirements.” ! Establishing the BCWS baseline at the beginning of each iteration. ! Capturing ACWP through a time keeping system. ! Computing Cost Variance, Schedule Variance from the three base earned value metrics ! Computing Estimate at Completion (EAC) and Esti- mate to Completion (ETC) from these base metrics as well. Much of the “noise” about agile development, especially XP in the traditionalist environment, has to do with how to position these processes in a larger context. We’ve taken the approach that XP is for writing code, support- ing the processes for writing code, and delivery code to the customer base. There are many other activities needed to fulfill the needs of a government contracting business, or any other business context. Figure 5 shows how XP is positioned in this context… Figure 5 – Embedding XP in a Larger Context In our environment we have embedded Extreme Pro- gramming in a large context. This context includes: ! Solution Architecture analyzes the business situation to accurately identify the core needs of the customer as well as the constraints imposed by the business en- vironment.
  • 6. 6 ! Extreme Programming Delivery provides the mecha- nisms to incrementally deliver value, address risks early in the development cycle, engage in continuous integration and test, and deploy the system to the cus- tomer in an incremental manner. ! Delivery Management is the key to success in the government contracting environment. Delivery Man- agement provides: ! Schedule Management through the creation and maintenance of the project schedule. ! Budget and Financial Management through the creation and maintenance of the financial plan, the approved invoices for subcontractors and non- labor items, and the financial metrics. In our envi- ronment these are earned value metrics. ! Scope Management through the creation and maintenance of updated schedules, architecture and system requirements. ! Change Control Dispositioning and Integration manages change requests and the updated project baseline. 6. REFERENCES 1. Abrahamsson, Pekka, Outi Salo, Jussi Ron- kainen, and Juhani Warsta “Agile Software De- velopment Methods: Review and Analysis,” Proceeding of ESPOO 2002. 2. Boehm, Barry and Kevin Sullivan, “Software Eco- nomics: A Roadmap,” Proceedings on the Future of Software Engineering, Limerick Ireland, 2000. 3. Fleming, Quentin and Joel M. Koppelman, Earned Value Project Management 2nd Edition, Project Management Institute, 2000. 4. Lett, Steve, “Earned Value Management for Self Directed Software Teams,” Software Engineering Process Group, Lockheed Martin. 5. Pisano, N. D., Commander, USN, “Technical Per- formance Measurement, Earned Value, and Risk Management: An Integrated Diagnostic Tool for Program Management.” 6. Solomon, Paul J., “Practical Software Measurement, Performance–Based Earned Value,” Crosstalk, Sep- tember, 2002. 7. Wilson, P. B., “Testable Requirements – An Alter- nate Sizing Measure,” The Journal of the Quality Assurance Institute (October 1995):1 8. Wilson, P. B., “Sizing Software with Testable Re- quirements,” Systems Development Management, 34–10–04, Auerbach Publications, 2000 Glen B. Alleman is Vice President, Program Management, CH2M HILL. Prior to CH2M HILL, Glen was a member of a consulting firm specializing in ERP systems architec- ture and deployment. Michael Henderson is Manager, Applications Develop- ment, CH2M HILL. Prior to CH2M HILL Michael was a Vice President of Development with Computer Associ- ates. Raymond Seggelke is Manager, Software Development for Environmental Technology Partners, a subcontractor to CH2M HILL. Prior to ETP, Ray was an engagement manager for BoldTech a Denver based Extreme Pro- gramming software development firm. Prior to Boldtech, Ray managed software development at Raytheon for TDRS. CH2M HILL is a tier one contractor for the Rocky Flats Environmental Technology Site, Golden Colorado. Michael and Glen work in the Communications Group’s Information and Network Services department of CH2M HILL, providing applications and infrastructure support of the closure of Rocky Flats on or before December 15th , 2006.