SlideShare a Scribd company logo
1 of 29
A
Presentation
on
Practical Training
taken at
DURATION: 23/05/2016 to 23/07/2016
SUBMITTED BY :
1. TEJPRAKASH KUMAWAT
Final Year B.Tech (Civil)
SUBMITTED TO :
DEPARTMENT OF CIVIL
ENGG.
DEPARTMENT OF CIVIL ENGINEERING
GOVT ENGINEERING COLLEGE
BANSWARA
HIGH FLOOD LEVEL BRIDGE ACROSS
MAHI RIVER
Details Of The Project:
Site location:- HFL Bridge across Mahi river, Pipalkhut , Pratapgarh
abutment type:- Conterfront Type.
Bearing:- POT/ PTEF Bearing.
Girder:- Precast PSC Girder.
Handrail:- Steel Hand rail with welded mesh.
Reinforcement:– HYSD Bar ( 8 mm To 32 mm).
About the project:- Construction of HFL bridge across Mahi river at Chain age 118+363 at pipalkhut on Pratapgarh padi road
(National highway NH-113).
Construction Company:- Dilip Buildcon Ltd. , Bhopal
Project In charge:- Mr. P.K. Mishra
Project Engg.:- Mr. Ramesh Babu
Expect Cost:- Rs. 12 cr after dismantling.
Date of Initiate:- 26 –Apr-2014
Date of Completion:- 24-Oct- 2016
Bridge length- 360 m
span- 12 (12×30) m
CONTENT
1. EXCAVATION WORK FOR RAFT
2. RAFT OF ABUTMENT AND PIER
3. PIER
4. PIER CAP
5. ABUTMENT
6. PEDESTAL
7. PLACE FOR JACK
8. GIRDER LAUNCHING
9. SLAB
EXCAVATION WORK FOR RAFT
• A RAFT FOUNDATION IS A TYPE OF FOUNDATION THAT SPREADS THE LOAD
FROM A BUILDING OR STRUCTURE OVER A LARGE AREA.
• RAFT FOUNDATIONS ARE ALSO USED TO REDUCE THE SETTLEMENT OF
STRUCTURES LOCATED ABOVE HIGHLY COMPRESSIBLE DEPOSITS.
• RAFT ARE USUALLY AT SOME DEPTH IN THE GROUND ,A LARGE VOLUME OF
EXCAVATION MAY BE REQUIRED.
Fig: excavation work for foundation
RAFT OF ABUTMENT AND PIER
• LEVEL THE GROUND
• PCC OF M15 GRADE CONCRETE
• PLACE THE REINFORCEMENT AS PER DRAWING
• COVER =75MM.
• HEIGHT = 1.1 M
Fig: Reinforcement details of raft
PIER
• MULTI-SPAN BRIDGES REQUIRE PIERS TO SUPPORT THE ENDS OF SPANS BETWEEN
ABUTMENTS
• TRANSFER LOAD OF SLAB,GIRDER,PIERCAP TO RAFT
Fig: pier
Fig: details: of pier
PIERCAP
THE UPPER OR BEARING PART OF THE PIER, USUALLY MADE OF CONCRETE OR
HARD STONE; DESIGNED TO DISTRIBUTE CONCENTRATED LOADS EVENLY OVER
THE AREA OF PIER.
 THE WIDTH OF PIER CAP DEPENDS UPON THE WIDTH OF CARRIAGEWAY, ITS SIZE
DEPENDS UPON THE LIVE LOAD AND DEAD LOAD BRIDGE CAPACITY
GRADE OF CONCRETE M35
QUANTITY OF CONCRETE 35.567 M3
ABUTMENT
ABUTMENT CONSIST OF THREE PARTS
MAIN WALL
COUNTER FRONT WALL
RIDING RETAINING WALL
Fig: abutment
PEDESTAL
• USED TO TRANSFER LOAD FROM BEARING TO PIERCAP
• GRADE OF CONCRETE USED M35
PLACE FOR JACK
• THE LOCATION OF JACK AND TEMPORARY BEARING FOR LIFTING OF THE
SUPERSTRUCTURE TO REPLACE BEARING ETC. THIS IS SHOWN BY SYMBOL
• THE TWO LAYRS OF MESH REINFORCEMENT ONE AT 20 MM FROM TOP AND THE
OTHER AT 100 MM FROM TOP OF PEDESTAL AND PIERCAP EACH CONSISTING OF
8 MM BARS AT 75 MM IN BOTH DIRECTIONS SHALL BE PROVIDED DIRECTLY
UNDER THE BEARING/JACK AND TEMPORARY BEARING
+
LAUNCHING OF GIRDERS
 SITE PREPARATION
 BASIC PLANNING
 PLACING OF GIRDER ON EXCEL PULLER OF CAPACITY 125 T
 TRANSPORT TO THE LOCATION
 LIFTING THE GIRDER BY USING THE CRANE CAPACITY OF 250 T
 FIXING THE POT/ PTEF BEARING IN GIRDER
 PLACING OF GIRDER IN PROPER LOCATION WITH PROPER SAFETY & SUPPOR
FIXING THE POT/ PTEF BEARING IN GIRDER
METHODOLOGY OF CAST IN SITU SLAB
1. Reinforcement & Concreting of End & Middle
Diaphram
2. Fixing of shuttering
3. Placing reinforcement as per drawing &
specification
4. Pouring of concrete M40 as per approved mixed
design
inforcement & Concreting of End & Middle Diaphram
FIXING OF SHUTTERING
PLACING REINFORCEMENT AS PER DRAWING
& SPECIFICATION
POURING OF CONCRETE M40 AS PER APPROVED MIXED
DESIGN
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION

More Related Content

What's hot

Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
Road Construction
Road ConstructionRoad Construction
Road ConstructionDanish Mohd
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTSatyam Anand
 
Training report - RCC Bridge
Training report - RCC BridgeTraining report - RCC Bridge
Training report - RCC BridgePRASUNMANI
 
Bridge components
Bridge componentsBridge components
Bridge componentsAratiSavant
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTSsrinivas cnu
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadampradip dangar
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 

What's hot (20)

Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 
Casting yard
Casting yardCasting yard
Casting yard
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Training report - RCC Bridge
Training report - RCC BridgeTraining report - RCC Bridge
Training report - RCC Bridge
 
Bridge components
Bridge componentsBridge components
Bridge components
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Box culverts
Box culvertsBox culverts
Box culverts
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
 
river training work
river training workriver training work
river training work
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
Introduction to bridges
Introduction to bridgesIntroduction to bridges
Introduction to bridges
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 

Viewers also liked

Viewers also liked (20)

High bridge trail final
High bridge trail finalHigh bridge trail final
High bridge trail final
 
Presentation2
Presentation2Presentation2
Presentation2
 
seminar II Presentation
seminar II Presentationseminar II Presentation
seminar II Presentation
 
Ppt final
Ppt finalPpt final
Ppt final
 
Bamboo drip irrigation pipes design
Bamboo drip irrigation pipes designBamboo drip irrigation pipes design
Bamboo drip irrigation pipes design
 
Clean and green India
Clean and green IndiaClean and green India
Clean and green India
 
Drip irrigation and fertigation
Drip irrigation and fertigationDrip irrigation and fertigation
Drip irrigation and fertigation
 
ppt
pptppt
ppt
 
Rural roads-india
Rural roads-indiaRural roads-india
Rural roads-india
 
Rural Road Safety
Rural Road SafetyRural Road Safety
Rural Road Safety
 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasan
 
Types of Bridge Superstructures
Types of Bridge SuperstructuresTypes of Bridge Superstructures
Types of Bridge Superstructures
 
Advance technology’s
Advance technology’sAdvance technology’s
Advance technology’s
 
Solar road pavement
Solar road pavement Solar road pavement
Solar road pavement
 
railway
railwayrailway
railway
 
Canals ppt
Canals pptCanals ppt
Canals ppt
 
final year Project (civil)
final year Project (civil)final year Project (civil)
final year Project (civil)
 
Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 

Similar to HIGH FLOOD LEVEL BRIDGE CONSTRUCTION

Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Summer traning report
Summer traning reportSummer traning report
Summer traning reportAmit Raj
 
Summer traning report BRPNNL by Amit Raj 14CE10005
Summer traning report BRPNNL by Amit Raj 14CE10005Summer traning report BRPNNL by Amit Raj 14CE10005
Summer traning report BRPNNL by Amit Raj 14CE10005Amit Raj
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...IEI GSC
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
 
Internship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam ConstructionInternship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam ConstructionKhaliqur Rahman
 
A project report on nagpur metro rail corporation
A project report on nagpur metro rail corporationA project report on nagpur metro rail corporation
A project report on nagpur metro rail corporationNikhil Kumar
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...Prem Prakash Kumar
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentationATUL SHUKLA
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD hitendra pendam
 

Similar to HIGH FLOOD LEVEL BRIDGE CONSTRUCTION (20)

Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
Metroppt
MetropptMetroppt
Metroppt
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
 
Summer traning report BRPNNL by Amit Raj 14CE10005
Summer traning report BRPNNL by Amit Raj 14CE10005Summer traning report BRPNNL by Amit Raj 14CE10005
Summer traning report BRPNNL by Amit Raj 14CE10005
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...
 
Internship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam ConstructionInternship Report on Bridge Construction & Dam Construction
Internship Report on Bridge Construction & Dam Construction
 
A project report on nagpur metro rail corporation
A project report on nagpur metro rail corporationA project report on nagpur metro rail corporation
A project report on nagpur metro rail corporation
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 

HIGH FLOOD LEVEL BRIDGE CONSTRUCTION

  • 1. A Presentation on Practical Training taken at DURATION: 23/05/2016 to 23/07/2016 SUBMITTED BY : 1. TEJPRAKASH KUMAWAT Final Year B.Tech (Civil) SUBMITTED TO : DEPARTMENT OF CIVIL ENGG. DEPARTMENT OF CIVIL ENGINEERING GOVT ENGINEERING COLLEGE BANSWARA HIGH FLOOD LEVEL BRIDGE ACROSS MAHI RIVER
  • 2. Details Of The Project: Site location:- HFL Bridge across Mahi river, Pipalkhut , Pratapgarh abutment type:- Conterfront Type. Bearing:- POT/ PTEF Bearing. Girder:- Precast PSC Girder. Handrail:- Steel Hand rail with welded mesh. Reinforcement:– HYSD Bar ( 8 mm To 32 mm). About the project:- Construction of HFL bridge across Mahi river at Chain age 118+363 at pipalkhut on Pratapgarh padi road (National highway NH-113). Construction Company:- Dilip Buildcon Ltd. , Bhopal Project In charge:- Mr. P.K. Mishra Project Engg.:- Mr. Ramesh Babu Expect Cost:- Rs. 12 cr after dismantling. Date of Initiate:- 26 –Apr-2014 Date of Completion:- 24-Oct- 2016 Bridge length- 360 m span- 12 (12×30) m
  • 3. CONTENT 1. EXCAVATION WORK FOR RAFT 2. RAFT OF ABUTMENT AND PIER 3. PIER 4. PIER CAP 5. ABUTMENT 6. PEDESTAL 7. PLACE FOR JACK 8. GIRDER LAUNCHING 9. SLAB
  • 4. EXCAVATION WORK FOR RAFT • A RAFT FOUNDATION IS A TYPE OF FOUNDATION THAT SPREADS THE LOAD FROM A BUILDING OR STRUCTURE OVER A LARGE AREA. • RAFT FOUNDATIONS ARE ALSO USED TO REDUCE THE SETTLEMENT OF STRUCTURES LOCATED ABOVE HIGHLY COMPRESSIBLE DEPOSITS. • RAFT ARE USUALLY AT SOME DEPTH IN THE GROUND ,A LARGE VOLUME OF EXCAVATION MAY BE REQUIRED.
  • 5. Fig: excavation work for foundation
  • 6. RAFT OF ABUTMENT AND PIER • LEVEL THE GROUND • PCC OF M15 GRADE CONCRETE • PLACE THE REINFORCEMENT AS PER DRAWING • COVER =75MM. • HEIGHT = 1.1 M
  • 8.
  • 9. PIER • MULTI-SPAN BRIDGES REQUIRE PIERS TO SUPPORT THE ENDS OF SPANS BETWEEN ABUTMENTS • TRANSFER LOAD OF SLAB,GIRDER,PIERCAP TO RAFT Fig: pier
  • 11. PIERCAP THE UPPER OR BEARING PART OF THE PIER, USUALLY MADE OF CONCRETE OR HARD STONE; DESIGNED TO DISTRIBUTE CONCENTRATED LOADS EVENLY OVER THE AREA OF PIER.  THE WIDTH OF PIER CAP DEPENDS UPON THE WIDTH OF CARRIAGEWAY, ITS SIZE DEPENDS UPON THE LIVE LOAD AND DEAD LOAD BRIDGE CAPACITY GRADE OF CONCRETE M35 QUANTITY OF CONCRETE 35.567 M3
  • 12.
  • 13. ABUTMENT ABUTMENT CONSIST OF THREE PARTS MAIN WALL COUNTER FRONT WALL RIDING RETAINING WALL
  • 15. PEDESTAL • USED TO TRANSFER LOAD FROM BEARING TO PIERCAP • GRADE OF CONCRETE USED M35
  • 16. PLACE FOR JACK • THE LOCATION OF JACK AND TEMPORARY BEARING FOR LIFTING OF THE SUPERSTRUCTURE TO REPLACE BEARING ETC. THIS IS SHOWN BY SYMBOL • THE TWO LAYRS OF MESH REINFORCEMENT ONE AT 20 MM FROM TOP AND THE OTHER AT 100 MM FROM TOP OF PEDESTAL AND PIERCAP EACH CONSISTING OF 8 MM BARS AT 75 MM IN BOTH DIRECTIONS SHALL BE PROVIDED DIRECTLY UNDER THE BEARING/JACK AND TEMPORARY BEARING +
  • 17.
  • 18. LAUNCHING OF GIRDERS  SITE PREPARATION  BASIC PLANNING  PLACING OF GIRDER ON EXCEL PULLER OF CAPACITY 125 T  TRANSPORT TO THE LOCATION  LIFTING THE GIRDER BY USING THE CRANE CAPACITY OF 250 T  FIXING THE POT/ PTEF BEARING IN GIRDER  PLACING OF GIRDER IN PROPER LOCATION WITH PROPER SAFETY & SUPPOR
  • 19.
  • 20.
  • 21. FIXING THE POT/ PTEF BEARING IN GIRDER
  • 22.
  • 23. METHODOLOGY OF CAST IN SITU SLAB 1. Reinforcement & Concreting of End & Middle Diaphram 2. Fixing of shuttering 3. Placing reinforcement as per drawing & specification 4. Pouring of concrete M40 as per approved mixed design
  • 24. inforcement & Concreting of End & Middle Diaphram
  • 26. PLACING REINFORCEMENT AS PER DRAWING & SPECIFICATION
  • 27. POURING OF CONCRETE M40 AS PER APPROVED MIXED DESIGN