Concept of Operations
Air routes Sectorisation
and Capacity
Developing the scope of work for ATM Master Plan Implementation


Technical workshop 12th of
   July 2012
Background
• ATM Master Plan is an excellent a start but lacked a
  strategic policy level concept of operations.
• ATM Master Plan recommended a series of short term
  activities including airspace management and demand
  and capacity management activities
• The Master Plan was subject to review by DGCA and
  AP/AP2 – facilitated by consultants from IndII and
  recommended priority activities including;
   Development of an Operational Concept
    Document
   Airspace redesign

                                                         2
Background (continued)

• Other issues include;
₋   Forecast traffic movements and how these are
    determined
₋   Airspace capacity simulation and modeling and the
    software used
₋   The workload and capacity issues apparent in some
    parts of the system
₋   Changes to technology including communication,
    navigation and surveillance s (CNS) systems
₋   Accommodating our customers requirements for the
    use of PBN and satellite based routes and procedures.

                                                        3
What we are doing here today
• This is the first part of IMPLEMENTATION of some of the ATM
  Master Plan recommendations regarding Airspace
  Management.
• Purpose – Develop a scope of work for ATM Master plan
  implementation.
  – Review information at an strategic level regarding airspace
    management planning documentation.
  – The information should cover air routes, sectorisation and capacity
    and demand.
  – Today we will review
     o Current status
     o Issues, risks and constraints
     o Any plans that are in place or underway
  – This will assist us in developing a scope of works for a new project to
     o Review and or modify air routes
     o Revise airspace management and
     o Provide an overall Concept of Operations to supplement the ATM MP

                                                                           4
Introducing the Team
• Peter Atkins
• Bruce Robinson
• Novaro Martodihardjo
• John McCarthy
And the MOT and IndII team with us today




                                           5
Review of Agenda
• Presentation by each of the attendees. Three slides to
  address airspace management status, plans and issues.
• Discussion regarding the work required in terms of
  CONOPS, airspace re-organisation and demand and
  capacity.
• Summary and agreement of action items by consultant(s)




                                                      6
Outcomes for Today
          Airspace Management
• We need your understanding of;
   What is the status of air routes and the
    associated airspace management including
    airspace management, airroutes, ATC, and
    capacity – WHAT IS THE PROBLEM?
   What plans do you have in place to address any
    issues, forecast increase in movements, risks
    or changes to procedures and technology.
    WHAT DO YOU THINK WE SHOULD DO ABOUT
    IT.
   Who is responsible for any of those plans and
    what is the timeframe. WHEN DOES IT NEED
    TO BE DONE
                                                7
Outcomes for Today
          Concept of Operation
• We need your understanding of;
   Apart from the ATM Master plan, what
    other plans are being used for strategic
    guidance – for example the “blueprint”
    plans.
   What other corporate, strategic or business
    plans are expected to be provided in the
    next 12 months.
   Who is responsible for any of those plans
    and what is the timeframe.

                                              8

More Related Content

Similar to Workshop2 sectorisation v1

UK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme managementUK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme management
Association for Project Management
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfAYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdf
rinkumandaljis
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
Ahmed Rami Elsherif, PMP, ITBMC
 
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
p6academy
 
Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8
Hari Krishna Shrestha
 
Presentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptxPresentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptx
AbdulrahmanAfabafal
 
Outage planning
Outage planningOutage planning
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Cissp Week 24
Cissp Week 24Cissp Week 24
Cissp Week 24
jemtallon
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
EqraBaig
 
PERT
PERTPERT
PmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalPmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit Payal
AMIT PAYAL
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM Projects
ARC Advisory Group
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project management
sdbhosale860
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
Peter White
 
Introduction to ict project management
Introduction to ict project managementIntroduction to ict project management
Introduction to ict project management
manproy
 
OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009
Ian van Vuuren
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
Michael Pink
 
MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)
Jonathan Coleman
 
document-part- (10).doc
document-part- (10).docdocument-part- (10).doc
document-part- (10).doc
PawanNegi39
 

Similar to Workshop2 sectorisation v1 (20)

UK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme managementUK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme management
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfAYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdf
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
 
Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8
 
Presentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptxPresentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptx
 
Outage planning
Outage planningOutage planning
Outage planning
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Cissp Week 24
Cissp Week 24Cissp Week 24
Cissp Week 24
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
PERT
PERTPERT
PERT
 
PmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalPmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit Payal
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM Projects
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project management
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
 
Introduction to ict project management
Introduction to ict project managementIntroduction to ict project management
Introduction to ict project management
 
OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009OC3 STRATEGIC CONVERSATION FEB 2009
OC3 STRATEGIC CONVERSATION FEB 2009
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)MIS: Business Process Modeling (BPMN)
MIS: Business Process Modeling (BPMN)
 
document-part- (10).doc
document-part- (10).docdocument-part- (10).doc
document-part- (10).doc
 

More from Indonesia Infrastructure Initiative

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
Indonesia Infrastructure Initiative
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
Indonesia Infrastructure Initiative
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
Indonesia Infrastructure Initiative
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesia Infrastructure Initiative
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
Indonesia Infrastructure Initiative
 
Development of multimodal transport in north java corridor
Development of multimodal transport in north java corridorDevelopment of multimodal transport in north java corridor
Development of multimodal transport in north java corridor
Indonesia Infrastructure Initiative
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
Indonesia Infrastructure Initiative
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
Indonesia Infrastructure Initiative
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
Indonesia Infrastructure Initiative
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
Indonesia Infrastructure Initiative
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
Indonesia Infrastructure Initiative
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
Indonesia Infrastructure Initiative
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
Indonesia Infrastructure Initiative
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
Indonesia Infrastructure Initiative
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 me
Ws3 meWs3 me
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
Indonesia Infrastructure Initiative
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
Indonesia Infrastructure Initiative
 
Ws2 introduction
Ws2 introductionWs2 introduction
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
Indonesia Infrastructure Initiative
 

More from Indonesia Infrastructure Initiative (20)

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
 
Development of multimodal transport in north java corridor
Development of multimodal transport in north java corridorDevelopment of multimodal transport in north java corridor
Development of multimodal transport in north java corridor
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 presentation
 
Ws3 me
Ws3 meWs3 me
Ws3 me
 
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
 
Ws2 introduction
Ws2 introductionWs2 introduction
Ws2 introduction
 
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
 

Recently uploaded

Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
obriengroupinc04
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Niswey
 
Enhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: IntroductionEnhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: Introduction
Cor Verdouw
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
PennapaKeavsiri
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium PresentationKirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani case
 
deft. 2024 pricing guide for onboarding
deft.  2024 pricing guide for onboardingdeft.  2024 pricing guide for onboarding
deft. 2024 pricing guide for onboarding
hello960827
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
Cambridge Product Management Network
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Stone Art Hub
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
advik4387
 
Efficient PHP Development Solutions for Dynamic Web Applications
Efficient PHP Development Solutions for Dynamic Web ApplicationsEfficient PHP Development Solutions for Dynamic Web Applications
Efficient PHP Development Solutions for Dynamic Web Applications
Harwinder Singh
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
JoeYangGreatMachiner
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
IPLTech Electric
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
Ksquare Energy Pvt. Ltd.
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip
 

Recently uploaded (20)

Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
 
Enhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: IntroductionEnhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: Introduction
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium PresentationKirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
 
deft. 2024 pricing guide for onboarding
deft.  2024 pricing guide for onboardingdeft.  2024 pricing guide for onboarding
deft. 2024 pricing guide for onboarding
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
 
Efficient PHP Development Solutions for Dynamic Web Applications
Efficient PHP Development Solutions for Dynamic Web ApplicationsEfficient PHP Development Solutions for Dynamic Web Applications
Efficient PHP Development Solutions for Dynamic Web Applications
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
 

Workshop2 sectorisation v1

  • 1. Concept of Operations Air routes Sectorisation and Capacity Developing the scope of work for ATM Master Plan Implementation Technical workshop 12th of July 2012
  • 2. Background • ATM Master Plan is an excellent a start but lacked a strategic policy level concept of operations. • ATM Master Plan recommended a series of short term activities including airspace management and demand and capacity management activities • The Master Plan was subject to review by DGCA and AP/AP2 – facilitated by consultants from IndII and recommended priority activities including;  Development of an Operational Concept Document  Airspace redesign 2
  • 3. Background (continued) • Other issues include; ₋ Forecast traffic movements and how these are determined ₋ Airspace capacity simulation and modeling and the software used ₋ The workload and capacity issues apparent in some parts of the system ₋ Changes to technology including communication, navigation and surveillance s (CNS) systems ₋ Accommodating our customers requirements for the use of PBN and satellite based routes and procedures. 3
  • 4. What we are doing here today • This is the first part of IMPLEMENTATION of some of the ATM Master Plan recommendations regarding Airspace Management. • Purpose – Develop a scope of work for ATM Master plan implementation. – Review information at an strategic level regarding airspace management planning documentation. – The information should cover air routes, sectorisation and capacity and demand. – Today we will review o Current status o Issues, risks and constraints o Any plans that are in place or underway – This will assist us in developing a scope of works for a new project to o Review and or modify air routes o Revise airspace management and o Provide an overall Concept of Operations to supplement the ATM MP 4
  • 5. Introducing the Team • Peter Atkins • Bruce Robinson • Novaro Martodihardjo • John McCarthy And the MOT and IndII team with us today 5
  • 6. Review of Agenda • Presentation by each of the attendees. Three slides to address airspace management status, plans and issues. • Discussion regarding the work required in terms of CONOPS, airspace re-organisation and demand and capacity. • Summary and agreement of action items by consultant(s) 6
  • 7. Outcomes for Today Airspace Management • We need your understanding of;  What is the status of air routes and the associated airspace management including airspace management, airroutes, ATC, and capacity – WHAT IS THE PROBLEM?  What plans do you have in place to address any issues, forecast increase in movements, risks or changes to procedures and technology. WHAT DO YOU THINK WE SHOULD DO ABOUT IT.  Who is responsible for any of those plans and what is the timeframe. WHEN DOES IT NEED TO BE DONE 7
  • 8. Outcomes for Today Concept of Operation • We need your understanding of;  Apart from the ATM Master plan, what other plans are being used for strategic guidance – for example the “blueprint” plans.  What other corporate, strategic or business plans are expected to be provided in the next 12 months.  Who is responsible for any of those plans and what is the timeframe. 8