• Purpose
• What is AutoDISE
• Layout
• Overlay
• Division Main Example
• Inventory
• Consumers
• Power Analysis
• Practical Exercise
• Closing/Questions
3. UNCLASSIFIED
UNCLASSIFIED
References:
• AutoDISE Website (https://www.autodise.net/)
• AutoDISE Software Version 7.0.4.3
• Army Operational Energy Management Electrical Power
Production and Distribution Whitepaper (01 April 2015)
4. UNCLASSIFIED
UNCLASSIFIED
• Provide a capabilities overview of the AutoDISE software
to show Construction Engineering Technicians the value
added by the software to future basecamp planning
operations.N+48hrs.
• ETL 1110-3-506 – Information brief on how to Provide BEB
Commander the capability of constructing a tactical airstrip
(05-CO-5142) for a UAS at N+48hrs.
• Aviation Complex Planning and Design Criteria for Unmanned
Aircraft Systems (UAS)
• UFC 3-260-1 - Airfield and Heliport Planning and Design
• UFC 3-260-3 - Airfield Pavement Evaluation
• TM 3-34.41 – Construction Estimating
• Army Training Network
• Operations Center
5. UNCLASSIFIED
UNCLASSIFIED
• What is AutoDISE
• Is a model and simulation program that helps
design/develop/correct:
• Power
• Water
• Wastewater
• Network (IT)
• HVAC
• Can be used to show layout and help design future
expansions/changes
• Show cable lengths (voltage drop)
• Fuel consumption of generator sets
• Camp layouts
• Space constraints can be addressed before building starts
• Can model future plans to see what impacts the changes will
have on the power grid
• Can show 3-D walk through simulation(Future capability)
15. UNCLASSIFIED
UNCLASSIFIED
• OPEN AUTODISE ON DESKTOP
• FILE TAB (NEW)
• OPEN TOOLBOX ON LEFT SIDE
• USE DRASH-MX TO BUILD TOC ADDING EQUIPMENT
INSIDE
• USE ANY POWER SOURCES (TQG’S, AMMPS,
RENEWABLES)
• Recommendation
WORK FROM SHELTERS BACK TO POWER SOURCE
16. UNCLASSIFIED
UNCLASSIFIED
.93 GPH .93 GPH
1.08 GPH
1.86 GPH x $3.00 Gallon = $5.58 per
hour x 24 hours = $133.92
1.08 GPH x $3.00 Gallon = $3.24 per
hour x 24 hours = $77.76
$56.16 per day saved and $20,498.40
per year saved. Cost is also saved in
maintenance due to less required
overall and maintenance due to
wetstacking.