Walden Center - Naples, FL
Another project showing the best results of the merging of Preconstruction, Estimating and Field execution and how
these pieces working together can produce great results.
This project was a competitive bid design-build project where the preconstruction team had to come up with the
elevation, sample floor plan and a GMP budget.
I was the team lead on the design as well as the conceptual estimator and preconstruction manager. We set about
developing a winning estimate from which we finalized our elevation, and schematic floor plans.
We then used all of the team’s skills to specify each of the components for the project, the number or lights what
styles, the type of cooling systems, sizes and all of the finishes. Everything was specified and detailed in our
presentation calming the client’s worries regarding change-orders or delays. We coupled all of this with a very
aggressive schedule.
Happily we won the award of the project. However this is only half the story the best part came after we signed the
contract.
Our owner always spoke about their desire to build two buildings on this site but felt that they just could not afford to
do this at the time. During the buy-out we inserted into our bid documents the request for the savings if we did two
projects, with the second project being released within 90 days of award. Armed with this information for savings we
surprised the owner and they awarded us a change-order to start immediately on the “second” phase.
Finally due to ground water we lined the pond using bentonite slurry vs. the traditional rubberized liner approach.
This simple change allowed us to line the pond in-the-wet saving both time and money.

More Related Content

What's hot

Project Charter Completed
Project Charter CompletedProject Charter Completed
Project Charter CompletedDonny Olson
 
Sample-Construction-Business-Proposal
Sample-Construction-Business-ProposalSample-Construction-Business-Proposal
Sample-Construction-Business-ProposalJennifer Riggins
 
Aqeel Ahmed se (2)
Aqeel Ahmed se (2)Aqeel Ahmed se (2)
Aqeel Ahmed se (2)aqeel ahmed
 
CNG station construction project report.
CNG station construction project report.CNG station construction project report.
CNG station construction project report.Hagi Sahib
 
Designing with glass to achieve estidama pearl ratings
Designing with glass to achieve estidama pearl ratingsDesigning with glass to achieve estidama pearl ratings
Designing with glass to achieve estidama pearl ratingsReshma Philip
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentationKunal Gudwani
 
News Letter Vol1
News Letter Vol1News Letter Vol1
News Letter Vol1Jorge Aldea
 
Inspection Engineer Taufeeque cv
Inspection Engineer Taufeeque cvInspection Engineer Taufeeque cv
Inspection Engineer Taufeeque cvTAUFEEQUE AHMAD
 
House Revamp Proposal PowerPoint Presentation Slides
House Revamp Proposal PowerPoint Presentation SlidesHouse Revamp Proposal PowerPoint Presentation Slides
House Revamp Proposal PowerPoint Presentation SlidesSlideTeam
 
James Beam resume1
James Beam resume1James Beam resume1
James Beam resume1James Beam
 

What's hot (19)

Project Charter Completed
Project Charter CompletedProject Charter Completed
Project Charter Completed
 
waseem cv
waseem cvwaseem cv
waseem cv
 
CV Abdul Gaffer.docx revised (3)
CV Abdul Gaffer.docx revised (3)CV Abdul Gaffer.docx revised (3)
CV Abdul Gaffer.docx revised (3)
 
Sample-Construction-Business-Proposal
Sample-Construction-Business-ProposalSample-Construction-Business-Proposal
Sample-Construction-Business-Proposal
 
Aqeel Ahmed se (2)
Aqeel Ahmed se (2)Aqeel Ahmed se (2)
Aqeel Ahmed se (2)
 
CNG station construction project report.
CNG station construction project report.CNG station construction project report.
CNG station construction project report.
 
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
 
MY RESUME (1)
MY RESUME (1)MY RESUME (1)
MY RESUME (1)
 
Designing with glass to achieve estidama pearl ratings
Designing with glass to achieve estidama pearl ratingsDesigning with glass to achieve estidama pearl ratings
Designing with glass to achieve estidama pearl ratings
 
Edd resume march 2019
Edd resume march 2019Edd resume march 2019
Edd resume march 2019
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
Resume_Brandon Schissel
Resume_Brandon SchisselResume_Brandon Schissel
Resume_Brandon Schissel
 
James River Project Update for the James River Partnership XVII
James River Project Update for the James River Partnership XVIIJames River Project Update for the James River Partnership XVII
James River Project Update for the James River Partnership XVII
 
Summary
SummarySummary
Summary
 
News Letter Vol1
News Letter Vol1News Letter Vol1
News Letter Vol1
 
Prashant_Kharche new
Prashant_Kharche new Prashant_Kharche new
Prashant_Kharche new
 
Inspection Engineer Taufeeque cv
Inspection Engineer Taufeeque cvInspection Engineer Taufeeque cv
Inspection Engineer Taufeeque cv
 
House Revamp Proposal PowerPoint Presentation Slides
House Revamp Proposal PowerPoint Presentation SlidesHouse Revamp Proposal PowerPoint Presentation Slides
House Revamp Proposal PowerPoint Presentation Slides
 
James Beam resume1
James Beam resume1James Beam resume1
James Beam resume1
 

Viewers also liked

Good_Sams - Revised 050716
Good_Sams - Revised 050716Good_Sams - Revised 050716
Good_Sams - Revised 050716David Peterson
 
Film Marketing – Homework Project
Film Marketing – Homework ProjectFilm Marketing – Homework Project
Film Marketing – Homework ProjectTerri-Ann Macro
 
La ley 100 de 1993 de colombia. scrubbed
La ley 100 de 1993 de colombia. scrubbedLa ley 100 de 1993 de colombia. scrubbed
La ley 100 de 1993 de colombia. scrubbedHarold Estupiñan
 
The Glenn Building - Revised_ 051011
The Glenn Building - Revised_ 051011The Glenn Building - Revised_ 051011
The Glenn Building - Revised_ 051011David Peterson
 
órganos de gobierno
órganos de gobierno órganos de gobierno
órganos de gobierno lananiojeda
 
TM half pg HORIZ 2015_CHI
TM half pg HORIZ 2015_CHITM half pg HORIZ 2015_CHI
TM half pg HORIZ 2015_CHITara Pink
 
Introduction to JavaScript Programming
Introduction to JavaScript ProgrammingIntroduction to JavaScript Programming
Introduction to JavaScript ProgrammingRaveendra R
 
Histologia nervioso
Histologia nerviosoHistologia nervioso
Histologia nerviosoAsis Nasseri
 
5 Winter Care Tips for Your Orchid
5 Winter Care Tips for Your Orchid5 Winter Care Tips for Your Orchid
5 Winter Care Tips for Your OrchidJustAddIceOrchids
 
Just Add Ice Orchids - Consumer Report 2012
Just Add Ice Orchids - Consumer Report 2012Just Add Ice Orchids - Consumer Report 2012
Just Add Ice Orchids - Consumer Report 2012JustAddIceOrchids
 
perencanaan pembangunan nasional
perencanaan pembangunan nasionalperencanaan pembangunan nasional
perencanaan pembangunan nasionalCucu Sya'diah
 
10 Ways to Keep Your Orchid Healthy
10 Ways to Keep Your Orchid Healthy10 Ways to Keep Your Orchid Healthy
10 Ways to Keep Your Orchid HealthyJustAddIceOrchids
 
Perencanaan pembangunan dan penganggaran apbd
Perencanaan pembangunan dan penganggaran apbdPerencanaan pembangunan dan penganggaran apbd
Perencanaan pembangunan dan penganggaran apbdQiu El Fahmi
 
Repaso imágenes histológicas de tejido nervioso
Repaso imágenes histológicas de tejido nerviosoRepaso imágenes histológicas de tejido nervioso
Repaso imágenes histológicas de tejido nerviosoAnahi Chavarria
 

Viewers also liked (17)

Good_Sams - Revised 050716
Good_Sams - Revised 050716Good_Sams - Revised 050716
Good_Sams - Revised 050716
 
Film Marketing – Homework Project
Film Marketing – Homework ProjectFilm Marketing – Homework Project
Film Marketing – Homework Project
 
La ley 100 de 1993 de colombia. scrubbed
La ley 100 de 1993 de colombia. scrubbedLa ley 100 de 1993 de colombia. scrubbed
La ley 100 de 1993 de colombia. scrubbed
 
The Glenn Building - Revised_ 051011
The Glenn Building - Revised_ 051011The Glenn Building - Revised_ 051011
The Glenn Building - Revised_ 051011
 
órganos de gobierno
órganos de gobierno órganos de gobierno
órganos de gobierno
 
TM half pg HORIZ 2015_CHI
TM half pg HORIZ 2015_CHITM half pg HORIZ 2015_CHI
TM half pg HORIZ 2015_CHI
 
Introduction to JavaScript Programming
Introduction to JavaScript ProgrammingIntroduction to JavaScript Programming
Introduction to JavaScript Programming
 
Histologia nervioso
Histologia nerviosoHistologia nervioso
Histologia nervioso
 
5 Winter Care Tips for Your Orchid
5 Winter Care Tips for Your Orchid5 Winter Care Tips for Your Orchid
5 Winter Care Tips for Your Orchid
 
Just Add Ice Orchids - Consumer Report 2012
Just Add Ice Orchids - Consumer Report 2012Just Add Ice Orchids - Consumer Report 2012
Just Add Ice Orchids - Consumer Report 2012
 
perencanaan pembangunan nasional
perencanaan pembangunan nasionalperencanaan pembangunan nasional
perencanaan pembangunan nasional
 
10 Ways to Keep Your Orchid Healthy
10 Ways to Keep Your Orchid Healthy10 Ways to Keep Your Orchid Healthy
10 Ways to Keep Your Orchid Healthy
 
Examen fisico
Examen fisicoExamen fisico
Examen fisico
 
Studio Perencanaa - Proposal teknis
Studio Perencanaa - Proposal teknisStudio Perencanaa - Proposal teknis
Studio Perencanaa - Proposal teknis
 
Perencanaan pembangunan dan penganggaran apbd
Perencanaan pembangunan dan penganggaran apbdPerencanaan pembangunan dan penganggaran apbd
Perencanaan pembangunan dan penganggaran apbd
 
Tejidosfundamentales
TejidosfundamentalesTejidosfundamentales
Tejidosfundamentales
 
Repaso imágenes histológicas de tejido nervioso
Repaso imágenes histológicas de tejido nerviosoRepaso imágenes histológicas de tejido nervioso
Repaso imágenes histológicas de tejido nervioso
 

Similar to Walden Center-Revised 050716

DESIGN & BUILD OPINION PIECE
DESIGN & BUILD OPINION PIECEDESIGN & BUILD OPINION PIECE
DESIGN & BUILD OPINION PIECEWill Bennett
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectAllen Green
 
J hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dpJ hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dpJonathan Hay
 
Best of CET Designer Awards - Best Success Story
Best of CET Designer Awards - Best Success StoryBest of CET Designer Awards - Best Success Story
Best of CET Designer Awards - Best Success StoryConfigura
 
J hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dpJ hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dpJonathan Hay
 
J hay resume final res 2014 v dp
J hay resume final res 2014 v dpJ hay resume final res 2014 v dp
J hay resume final res 2014 v dpJonathan Hay
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdcAvi Grigorescu
 
Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014William Crenshaw
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)kevin breiter
 
Contractor Services Proposal PowerPoint Presentation Slides
Contractor Services Proposal PowerPoint Presentation SlidesContractor Services Proposal PowerPoint Presentation Slides
Contractor Services Proposal PowerPoint Presentation SlidesSlideTeam
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash PoolPick_Everard
 
Modular high school, a better way to build
Modular high school, a better way to buildModular high school, a better way to build
Modular high school, a better way to buildModular Solutions, ltd
 
Beach house construction desktop 02 29
Beach house construction desktop 02 29Beach house construction desktop 02 29
Beach house construction desktop 02 29sheylaobm
 
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | GordianGordian
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Dbright Pamphlet
Dbright PamphletDbright Pamphlet
Dbright Pamphletjcornwell
 

Similar to Walden Center-Revised 050716 (20)

DESIGN & BUILD OPINION PIECE
DESIGN & BUILD OPINION PIECEDESIGN & BUILD OPINION PIECE
DESIGN & BUILD OPINION PIECE
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final Project
 
PMN0516 GID LeBard
PMN0516 GID LeBardPMN0516 GID LeBard
PMN0516 GID LeBard
 
J hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dpJ hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dp
 
Best of CET Designer Awards - Best Success Story
Best of CET Designer Awards - Best Success StoryBest of CET Designer Awards - Best Success Story
Best of CET Designer Awards - Best Success Story
 
J hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dpJ hay resume final com pm 2016 v dp
J hay resume final com pm 2016 v dp
 
J hay resume final res 2014 v dp
J hay resume final res 2014 v dpJ hay resume final res 2014 v dp
J hay resume final res 2014 v dp
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc
 
General Contractor Miami
General Contractor MiamiGeneral Contractor Miami
General Contractor Miami
 
Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)
 
Contractor Services Proposal PowerPoint Presentation Slides
Contractor Services Proposal PowerPoint Presentation SlidesContractor Services Proposal PowerPoint Presentation Slides
Contractor Services Proposal PowerPoint Presentation Slides
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash Pool
 
Rushden Splash Pool
Rushden Splash PoolRushden Splash Pool
Rushden Splash Pool
 
Modular high school, a better way to build
Modular high school, a better way to buildModular high school, a better way to build
Modular high school, a better way to build
 
Beach house construction desktop 02 29
Beach house construction desktop 02 29Beach house construction desktop 02 29
Beach house construction desktop 02 29
 
DSSCondoppt
DSSCondopptDSSCondoppt
DSSCondoppt
 
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
2016 Harry H. Mellon Awards in Job Order Contracting | Gordian
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Dbright Pamphlet
Dbright PamphletDbright Pamphlet
Dbright Pamphlet
 

Walden Center-Revised 050716

  • 1. Walden Center - Naples, FL Another project showing the best results of the merging of Preconstruction, Estimating and Field execution and how these pieces working together can produce great results. This project was a competitive bid design-build project where the preconstruction team had to come up with the elevation, sample floor plan and a GMP budget. I was the team lead on the design as well as the conceptual estimator and preconstruction manager. We set about developing a winning estimate from which we finalized our elevation, and schematic floor plans. We then used all of the team’s skills to specify each of the components for the project, the number or lights what styles, the type of cooling systems, sizes and all of the finishes. Everything was specified and detailed in our presentation calming the client’s worries regarding change-orders or delays. We coupled all of this with a very aggressive schedule. Happily we won the award of the project. However this is only half the story the best part came after we signed the contract. Our owner always spoke about their desire to build two buildings on this site but felt that they just could not afford to do this at the time. During the buy-out we inserted into our bid documents the request for the savings if we did two projects, with the second project being released within 90 days of award. Armed with this information for savings we surprised the owner and they awarded us a change-order to start immediately on the “second” phase. Finally due to ground water we lined the pond using bentonite slurry vs. the traditional rubberized liner approach. This simple change allowed us to line the pond in-the-wet saving both time and money.