SlideShare a Scribd company logo
1 of 1
Download to read offline
70 PM NETWORK MAY 2016 WWW.PMI.ORG
Ed LeBard, PMP, is a project manager and
architect at Gensler, Washington, D.C., USA.
Estimate,
Then Repeat
Outdated prices can doom construction projects.
Avoid them with the right estimating process.
By Ed LeBard, PMP
liminary bids need to be obtained and when the
design documents have to be submitted. Com-
munication and consensus are key. For example,
if you’re leading a design team of architects and
engineers on a ground-up 30,000-square-foot
(2,800-square-meter) project, ensure that the client
and preconstruction consultant agree to the design
submission milestones prior to the start of the
project. Cost-estimating reviews always should be
factored into the project scope and project sched-
ule. A two-week time frame is standard for a cost-
estimating effort. For extremely large projects, such
as a 1 million-square-foot (93,000-square-meter)
stadium, more than two weeks may be needed.
RIGHT PRICE AT THE RIGHT TIME
Regardless of the project delivery approach
(design/build or design/bid/build), the cost-esti-
mating process should recur frequently. Here is
where you should schedule cost estimates during
each phase:
Conceptual design phase: at the end of the phase
or for each conceptual design scheme/option
Schematic design phase: at the end of the phase
Design development phase: at the 50 percent
milestone and the end of the phase
Construction document phase: at the 50 percent
and 95 percent milestones
This approach will keep the project team, client
and preconstruction consultant on the same page.
By drawing on up-to-date prices, you will reduce
the risk of the lowest bid proposal from the general
contractor far surpassing what you had expected to
pay. Should the lowest bid still surpass the earlier
cost estimates, the client and project team have
four options: cancel the bids and re-bid later, over-
haul the project requirements, reduce the building
area or cancel the project altogether.
By tracking and documenting cost-estimating
milestones, and sharing results with critical stake-
holders, your project team increases the prospect
of a successful project and a happy client. PM
I
magine you discover your construction
project has been using outdated pric-
ing estimates.
When the current figures come in,
you realize that you’ve derailed your
project and your relationship with the client and
possibly endangered your job security. Now the
client, architect and preconstruction consultant
have to sit together and review how and why the
project team got to this point. Tough decisions—
such as overhauling the project’s requirements,
cutting the building area or reducing design qual-
ity—have to be made. If your project already has
submitted a building permit, you likely will have
to submit a new one, adding significant time and
expense.
How can we prevent this scenario from
happening?
The best way to responsibly manage cost-
estimating efforts during the design phase of
a project is to document and track when pre-
Getting It Done PROJECT MANAGEMENT IN ACTION
Cost-
estimating
reviews
should
always be
factored into
the project
scope and
project
schedule.

More Related Content

Similar to PMN0516 GID LeBard

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 
Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014
William Crenshaw
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
마 이환
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
Abdulaziz Kaya
 
092811 Updated Contech Brochure
092811 Updated Contech Brochure092811 Updated Contech Brochure
092811 Updated Contech Brochure
Paul Smith
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016
Chris Nash
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
Hamdija Velagic
 

Similar to PMN0516 GID LeBard (20)

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014Brooks 972 Project WriteUp-03-17-2014
Brooks 972 Project WriteUp-03-17-2014
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
 
Residential Design Build Whitepaper
Residential Design Build WhitepaperResidential Design Build Whitepaper
Residential Design Build Whitepaper
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 
092811 Updated Contech Brochure
092811 Updated Contech Brochure092811 Updated Contech Brochure
092811 Updated Contech Brochure
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016pdf 25 NCON Brochure 1.19.2016
pdf 25 NCON Brochure 1.19.2016
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Apt portfolio
Apt portfolioApt portfolio
Apt portfolio
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Ultimate Guide to Architectural CAD Drafting Services in USA
Ultimate Guide to Architectural CAD Drafting Services in USAUltimate Guide to Architectural CAD Drafting Services in USA
Ultimate Guide to Architectural CAD Drafting Services in USA
 

PMN0516 GID LeBard

  • 1. 70 PM NETWORK MAY 2016 WWW.PMI.ORG Ed LeBard, PMP, is a project manager and architect at Gensler, Washington, D.C., USA. Estimate, Then Repeat Outdated prices can doom construction projects. Avoid them with the right estimating process. By Ed LeBard, PMP liminary bids need to be obtained and when the design documents have to be submitted. Com- munication and consensus are key. For example, if you’re leading a design team of architects and engineers on a ground-up 30,000-square-foot (2,800-square-meter) project, ensure that the client and preconstruction consultant agree to the design submission milestones prior to the start of the project. Cost-estimating reviews always should be factored into the project scope and project sched- ule. A two-week time frame is standard for a cost- estimating effort. For extremely large projects, such as a 1 million-square-foot (93,000-square-meter) stadium, more than two weeks may be needed. RIGHT PRICE AT THE RIGHT TIME Regardless of the project delivery approach (design/build or design/bid/build), the cost-esti- mating process should recur frequently. Here is where you should schedule cost estimates during each phase: Conceptual design phase: at the end of the phase or for each conceptual design scheme/option Schematic design phase: at the end of the phase Design development phase: at the 50 percent milestone and the end of the phase Construction document phase: at the 50 percent and 95 percent milestones This approach will keep the project team, client and preconstruction consultant on the same page. By drawing on up-to-date prices, you will reduce the risk of the lowest bid proposal from the general contractor far surpassing what you had expected to pay. Should the lowest bid still surpass the earlier cost estimates, the client and project team have four options: cancel the bids and re-bid later, over- haul the project requirements, reduce the building area or cancel the project altogether. By tracking and documenting cost-estimating milestones, and sharing results with critical stake- holders, your project team increases the prospect of a successful project and a happy client. PM I magine you discover your construction project has been using outdated pric- ing estimates. When the current figures come in, you realize that you’ve derailed your project and your relationship with the client and possibly endangered your job security. Now the client, architect and preconstruction consultant have to sit together and review how and why the project team got to this point. Tough decisions— such as overhauling the project’s requirements, cutting the building area or reducing design qual- ity—have to be made. If your project already has submitted a building permit, you likely will have to submit a new one, adding significant time and expense. How can we prevent this scenario from happening? The best way to responsibly manage cost- estimating efforts during the design phase of a project is to document and track when pre- Getting It Done PROJECT MANAGEMENT IN ACTION Cost- estimating reviews should always be factored into the project scope and project schedule.