The document discusses annual equivalent cost analysis for engineering economics. It provides examples of calculating the annual equivalent cost or revenue for alternatives with different cash flow patterns, including revenue-dominated, cost-dominated, and combinations of initial investment, annual cash flows, and salvage value. The annual equivalent method can be used to compare project alternatives and select the most economically favorable option based on having the highest net annual equivalent revenue or lowest net annual equivalent cost.
This document provides an overview of rate of return analysis techniques for evaluating engineering projects and investments. It defines internal rate of return as the interest rate that makes the net present value of a project's cash flows equal to zero. It discusses how to calculate IRR using tables, trial and error, or numerical methods. The document also introduces incremental rate of return analysis for comparing competing alternatives, and defines the minimum attractive rate of return used to determine which project to select. Several examples are provided to illustrate IRR, incremental analysis, and solving practice problems.
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERINGAsha A
This document discusses value engineering interest formulas and their applications. It begins by defining value analysis and its aims to critically analyze costs and design of components. Different types of values like cost, exchange and use values are explained. Interest formulas for single payment compound amount, present worth amount and uniform gradient series are provided along with examples. The key steps in value engineering procedure are outlined. Effective interest rate calculation is also demonstrated with an example.
Engineering economics deals with evaluating the costs and benefits of engineering projects over time. It uses time value of money concepts like present and future value to analyze cash flows. Cash flows are summarized in diagrams with costs below and benefits above the time line. Equivalence techniques convert cash flows to a common point in time to compare project alternatives. Present worth analysis discounts all cash flows to the present using a discount rate to determine the net present value of projects.
The document provides an introduction to engineering economics. It discusses how engineering deals with using materials and natural forces for the economic benefit of humanity. It also covers concepts like the need for engineering due to resource and energy crises, how successful companies meet customer wants and needs economically, and the physical and economic environments that engineers must consider. Key aspects of engineering economics like cost concepts, supply and demand, efficiency, and elementary economic analysis are introduced.
The document discusses various capital budgeting techniques including:
- Present worth method for revenue and cost dominated cash flows
- Future worth method for revenue and cost dominated cash flows
- Annual equivalent method for revenue and cost dominated cash flows
- Rate of return method and its applications
Examples are provided to illustrate how to use each method to evaluate investment alternatives and select the best option. The rate of return method is discussed as a useful technique to compare investment performance and maximize returns.
The document discusses various interest formulas and their applications. It introduces compound interest, where interest is calculated on both the principal amount and accumulated interest from previous periods. Formulas are provided to calculate the compound amount, present worth amount, equal payment series compound amount, equal payment series sinking fund, equal payment series present worth amount, and equal payment series capital recovery amount. An example calculation is shown for each formula to illustrate how to use it to solve investment problems.
This document discusses three methods of depreciation: straight line, written down value, and annuity. The straight line method evenly depreciates the asset over its useful life until its book value reaches the estimated scrap value. The written down value method uses a fixed depreciation percentage each year on the asset's declining book value. The annuity method calculates depreciation based on the asset's estimated usage, such as miles driven for a vehicle, rather than by time. Examples are provided for each method.
Payback period (PP) is the number of years it takes for a company to recover its original investment in a project, when net cash flow equals zero. In the calculation of the payback period, the cash flows of the project must first be estimated. The payback period is then a simple calculation.
This document provides an overview of rate of return analysis techniques for evaluating engineering projects and investments. It defines internal rate of return as the interest rate that makes the net present value of a project's cash flows equal to zero. It discusses how to calculate IRR using tables, trial and error, or numerical methods. The document also introduces incremental rate of return analysis for comparing competing alternatives, and defines the minimum attractive rate of return used to determine which project to select. Several examples are provided to illustrate IRR, incremental analysis, and solving practice problems.
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERINGAsha A
This document discusses value engineering interest formulas and their applications. It begins by defining value analysis and its aims to critically analyze costs and design of components. Different types of values like cost, exchange and use values are explained. Interest formulas for single payment compound amount, present worth amount and uniform gradient series are provided along with examples. The key steps in value engineering procedure are outlined. Effective interest rate calculation is also demonstrated with an example.
Engineering economics deals with evaluating the costs and benefits of engineering projects over time. It uses time value of money concepts like present and future value to analyze cash flows. Cash flows are summarized in diagrams with costs below and benefits above the time line. Equivalence techniques convert cash flows to a common point in time to compare project alternatives. Present worth analysis discounts all cash flows to the present using a discount rate to determine the net present value of projects.
The document provides an introduction to engineering economics. It discusses how engineering deals with using materials and natural forces for the economic benefit of humanity. It also covers concepts like the need for engineering due to resource and energy crises, how successful companies meet customer wants and needs economically, and the physical and economic environments that engineers must consider. Key aspects of engineering economics like cost concepts, supply and demand, efficiency, and elementary economic analysis are introduced.
The document discusses various capital budgeting techniques including:
- Present worth method for revenue and cost dominated cash flows
- Future worth method for revenue and cost dominated cash flows
- Annual equivalent method for revenue and cost dominated cash flows
- Rate of return method and its applications
Examples are provided to illustrate how to use each method to evaluate investment alternatives and select the best option. The rate of return method is discussed as a useful technique to compare investment performance and maximize returns.
The document discusses various interest formulas and their applications. It introduces compound interest, where interest is calculated on both the principal amount and accumulated interest from previous periods. Formulas are provided to calculate the compound amount, present worth amount, equal payment series compound amount, equal payment series sinking fund, equal payment series present worth amount, and equal payment series capital recovery amount. An example calculation is shown for each formula to illustrate how to use it to solve investment problems.
This document discusses three methods of depreciation: straight line, written down value, and annuity. The straight line method evenly depreciates the asset over its useful life until its book value reaches the estimated scrap value. The written down value method uses a fixed depreciation percentage each year on the asset's declining book value. The annuity method calculates depreciation based on the asset's estimated usage, such as miles driven for a vehicle, rather than by time. Examples are provided for each method.
Payback period (PP) is the number of years it takes for a company to recover its original investment in a project, when net cash flow equals zero. In the calculation of the payback period, the cash flows of the project must first be estimated. The payback period is then a simple calculation.
This document summarizes key concepts from Chapter 4 of the 15th edition of the textbook "Engineering Economy" by William G. Sullivan, Elin M. Wicks, and C. Patrick Koelling. It discusses the time value of money, including compound and simple interest, present and future value calculations, and cash flow diagrams. It also introduces uniform series calculations to analyze projects with multiple cash flows over time. Spreadsheet functions like NPER and RATE are presented as tools to solve problems with unknown interest rates or time periods. The objective is to explain time value of money calculations and illustrate economic equivalence.
The chapter addresses when to replace currently owned assets, considering physical deterioration, changed requirements, and new technology. It discusses options for existing assets and reasons for replacement. Key terms include economic, ownership, physical, and useful life. It provides methods for analyzing the costs and lives of challengers and defenders to determine the most economic option. Taxes can also impact replacement decisions.
This document provides an introduction and syllabus for an engineering economics course taught by Dr. Mohsin Siddique. It outlines the course details including the instructor's contact information, course goals and objectives, topics to be covered, assessment criteria, textbook information, and tentative schedule. The course aims to provide engineering students with the basic concepts of engineering economics to aid in decision making for engineering projects. Key topics include cost estimation, interest calculation, present worth analysis, rate of return analysis, and depreciation. Students will be assessed through quizzes, exams, assignments, and a final exam.
The payback period is the time it takes for a project's cash inflows to repay its initial cash outflows. It is calculated by dividing the initial investment by the annual cash inflow. The document provides an example of calculating the 2.5 year payback period of Machine X, which costs $25,000 with annual cash inflows of $10,000. Since Machine X's payback period is less than the company's maximum of 3 years, it would be purchased.
This document provides an overview of present worth analysis for evaluating competing project alternatives. It discusses how to apply the present worth method to alternatives with equal, unequal, and infinite project lives. Examples are provided to illustrate how to calculate the present worth of each alternative's cash flows and compare their net present worth values to select the optimal choice. The document also covers how to compare multiple alternatives by computing the net present worth for each and choosing the one with the highest value.
This document provides an introduction to the concepts of engineering economics and engineering. It defines engineering economics as the application of economic principles to the evaluation of design and engineering alternatives. Some key points covered include:
- Engineering economics involves formulating, estimating, and evaluating economic outcomes of alternatives using mathematical relationships to compare cash flows. It must deal with risk and uncertainty.
- The time value of money is a central concept, dealing with how the value of money changes over time due to factors like investment opportunities and inflation. Interest rates and discount rates are used to relate amounts over different time periods.
- Engineering economics helps engineers make good decisions by assessing alternatives in economic terms and identifying the most efficient solution based on costs, benefits
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
This document discusses factors related to time and interest rates that affect money. It covers single payment factors, uniform series factors, arithmetic and geometric gradients, and methods for finding unknown interest rates or time periods. Key learning outcomes include single payment, uniform series, and gradient factors as well as techniques for determining factor values for untabulated rates or periods. Examples are provided to illustrate concepts such as single payments, uniform series, arithmetic gradients, and finding unknown rates or time periods.
Annual worth (AW) analysis allows engineers to evaluate project alternatives over multiple life cycles by converting all cash flows to equivalent uniform annual amounts at a discount rate. Key aspects of AW analysis include calculating the capital recovery rate to determine the equivalent annual cost of initial investments, and summing equivalent annual cash flows for operating, maintenance, and replacement costs over the life of each alternative. Life-cycle cost analysis takes a broader perspective by considering all costs from project inception through disposal or replacement.
Full balance sheet_&_profit_&_loss_analysisAdil Shaikh
The document discusses balance sheet analysis and profit and loss account analysis. It outlines the key components of a balance sheet, including sources of funds like capital, reserves, liabilities and uses of funds like assets. It describes items in reserves, tangible net worth, term liabilities, current liabilities, contingent liabilities, fixed assets, investments, current and non-current assets. It also discusses the components of a profit and loss account like gross sales, net sales, cost of production, selling and administrative expenses, cost of goods sold, gross profit, operating profit and net profit.
This document discusses various types of engineering costs and methods for estimating costs. It describes fixed and variable, direct and indirect, marginal and average, sunk and opportunity costs. It also discusses recurring and non-recurring costs, incremental costs, cash and book costs, and life-cycle costs. The document then explains methods for estimating costs, including using per-unit models, work breakdown structure (WBS) models, and cost indices. It provides examples to illustrate key cost concepts.
This document provides an overview of engineering cost estimation. It defines various types of engineering cost estimates such as rough, semi-detailed, and detailed estimates. It discusses common difficulties in making cost estimates such as one-of-a-kind estimates and limitations of time and resources. The document also describes several common mathematical models used for cost estimating, including the per unit model, segmenting model, cost indexes, power-sizing model, and triangulation. It provides examples of how to use these models to estimate costs. Finally, it discusses the impact of learning curves on cost estimates over time.
This document provides examples and explanations for conducting benefit-cost analysis to evaluate engineering projects and alternatives. It defines the key steps and techniques in benefit-cost analysis including identifying project benefits and costs, quantifying them, discounting cash flows, and calculating the benefit-cost ratio. Examples are provided to demonstrate computing benefit-cost ratios, incremental analysis, and selecting the alternative with the highest ratio or most desirable increment above 1 to indicate project acceptance.
The document defines accounting rate of return (ARR) as the ratio of estimated accounting profit to average investment. ARR is calculated by taking the average accounting profit and dividing it by the average investment. Projects should be accepted if their ARR is greater than or equal to the required accounting rate of return, and between mutually exclusive projects the one with the highest ARR should be accepted. An example calculation is shown to illustrate determining ARR for a project with initial investment, annual cash inflows, depreciation, and scrap value.
Comparing alternatives in Engineering Economics and ManagementNzar Braim
Comparing alternatives in Engineering Economics and Management
In the real world, the majority of engineering economic analysis problems are
alternative comparisons. In these problems, two or more mutually exclusive
investments compete for limited funds. A variety of methods exists for selecting
the superior alternative from a group of proposals. Each method has its own merits
and applications
This report focuses on the Cost-Benefit Analysis which is effective tool and a rational technique for economic valuation where market information is either non-existent or deficient is.
This document discusses net present value (NPV) as a method for evaluating investment projects. It defines NPV as the difference between the present value of cash inflows and outflows. Positive NPV means the project is acceptable, zero means it may be acceptable, and negative means it should be rejected. The document provides a formula for calculating NPV and an example of applying the method to evaluate acquiring another company. Advantages include accounting for the time value of money, while disadvantages include difficulty of use and setting the discount rate.
This document outlines the key concepts and formulas covered in the Engineering Economics and Cost Analysis course. It discusses topics like profit calculation, break-even analysis, time value of money formulas, capital investment evaluation methods, depreciation techniques, replacement analysis, and public project evaluation. The course aims to teach students methods to make economic decisions that minimize costs and maximize benefits for business organizations.
This document defines accounting rate of return (ARR) as the ratio of estimated accounting profit to average investment of a project. It ignores the time value of money. ARR is calculated by dividing average accounting profit by initial investment. Average accounting profit is the mean of annual profits over the project life. Initial investment may be replaced by average investment due to declining book value over time. Projects are accepted if their ARR is not less than the required rate of return. Examples show calculating ARR for projects with given cash flows. ARR is an easy method but ignores the time value of money and can be calculated inconsistently using accounting versus cash flows.
time value of money
,
concept of time value of money
,
significance of time value of money
,
present value vs future value
,
solve for the present value
,
simple vs compound interest rate
,
nominal vs effective annual interest rates
,
future value of a lump sum
,
solve for the future value
,
present value of a lump sum
,
types of annuity
,
future value of an annuity
Here are the key steps to solve this problem:
* Future sum (F) = Rs. 1,00,000
* Interest rate (i) = 15%
* Number of periods (n) = 10 years
* Interest is compounded annually
* To find the present worth (P):
* P = F / (1 + i)^n
* P = Rs. 1,00,000 / (1 + 0.15)^10
* P = Rs. 1,00,000 / 2.472
* P = Rs. Rs. 40,320
Therefore, the single payment that should be made now to receive Rs. 1,00,000 after 10 years at
This document discusses various cash flow analysis methods including present worth, future worth, rate of return, and annual equivalent. It provides examples and formulas for revenue-dominated and cost-dominated cash flows. Key points include:
- Present worth discounts all cash flows to time zero using a discount rate to find the maximum or minimum value. Future worth grows all cash flows using a rate to find the maximum or minimum value.
- Annual equivalent converts net present worth to an equivalent annual revenue or cost using a capital recovery factor for comparison.
- Rate of return finds the discount rate that sets the net present worth equal to zero to determine the highest returning project.
- Examples apply the methods to alternatives with
The document summarizes key concepts in engineering economy including:
1) Time value of money, cash flow diagrams, and equivalence are used to analyze costs over time. Depreciation, inflation, and interest rates must also be considered.
2) Cash flows describe monetary inflows and outflows over time and are used to evaluate alternatives. Present and future values translate cash flows into common units for comparison.
3) Methods like present/future worth, rate of return, payback period, and breakeven analysis can be used to compare project alternatives based on costs, benefits, and investment returns.
This document summarizes key concepts from Chapter 4 of the 15th edition of the textbook "Engineering Economy" by William G. Sullivan, Elin M. Wicks, and C. Patrick Koelling. It discusses the time value of money, including compound and simple interest, present and future value calculations, and cash flow diagrams. It also introduces uniform series calculations to analyze projects with multiple cash flows over time. Spreadsheet functions like NPER and RATE are presented as tools to solve problems with unknown interest rates or time periods. The objective is to explain time value of money calculations and illustrate economic equivalence.
The chapter addresses when to replace currently owned assets, considering physical deterioration, changed requirements, and new technology. It discusses options for existing assets and reasons for replacement. Key terms include economic, ownership, physical, and useful life. It provides methods for analyzing the costs and lives of challengers and defenders to determine the most economic option. Taxes can also impact replacement decisions.
This document provides an introduction and syllabus for an engineering economics course taught by Dr. Mohsin Siddique. It outlines the course details including the instructor's contact information, course goals and objectives, topics to be covered, assessment criteria, textbook information, and tentative schedule. The course aims to provide engineering students with the basic concepts of engineering economics to aid in decision making for engineering projects. Key topics include cost estimation, interest calculation, present worth analysis, rate of return analysis, and depreciation. Students will be assessed through quizzes, exams, assignments, and a final exam.
The payback period is the time it takes for a project's cash inflows to repay its initial cash outflows. It is calculated by dividing the initial investment by the annual cash inflow. The document provides an example of calculating the 2.5 year payback period of Machine X, which costs $25,000 with annual cash inflows of $10,000. Since Machine X's payback period is less than the company's maximum of 3 years, it would be purchased.
This document provides an overview of present worth analysis for evaluating competing project alternatives. It discusses how to apply the present worth method to alternatives with equal, unequal, and infinite project lives. Examples are provided to illustrate how to calculate the present worth of each alternative's cash flows and compare their net present worth values to select the optimal choice. The document also covers how to compare multiple alternatives by computing the net present worth for each and choosing the one with the highest value.
This document provides an introduction to the concepts of engineering economics and engineering. It defines engineering economics as the application of economic principles to the evaluation of design and engineering alternatives. Some key points covered include:
- Engineering economics involves formulating, estimating, and evaluating economic outcomes of alternatives using mathematical relationships to compare cash flows. It must deal with risk and uncertainty.
- The time value of money is a central concept, dealing with how the value of money changes over time due to factors like investment opportunities and inflation. Interest rates and discount rates are used to relate amounts over different time periods.
- Engineering economics helps engineers make good decisions by assessing alternatives in economic terms and identifying the most efficient solution based on costs, benefits
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
This document discusses factors related to time and interest rates that affect money. It covers single payment factors, uniform series factors, arithmetic and geometric gradients, and methods for finding unknown interest rates or time periods. Key learning outcomes include single payment, uniform series, and gradient factors as well as techniques for determining factor values for untabulated rates or periods. Examples are provided to illustrate concepts such as single payments, uniform series, arithmetic gradients, and finding unknown rates or time periods.
Annual worth (AW) analysis allows engineers to evaluate project alternatives over multiple life cycles by converting all cash flows to equivalent uniform annual amounts at a discount rate. Key aspects of AW analysis include calculating the capital recovery rate to determine the equivalent annual cost of initial investments, and summing equivalent annual cash flows for operating, maintenance, and replacement costs over the life of each alternative. Life-cycle cost analysis takes a broader perspective by considering all costs from project inception through disposal or replacement.
Full balance sheet_&_profit_&_loss_analysisAdil Shaikh
The document discusses balance sheet analysis and profit and loss account analysis. It outlines the key components of a balance sheet, including sources of funds like capital, reserves, liabilities and uses of funds like assets. It describes items in reserves, tangible net worth, term liabilities, current liabilities, contingent liabilities, fixed assets, investments, current and non-current assets. It also discusses the components of a profit and loss account like gross sales, net sales, cost of production, selling and administrative expenses, cost of goods sold, gross profit, operating profit and net profit.
This document discusses various types of engineering costs and methods for estimating costs. It describes fixed and variable, direct and indirect, marginal and average, sunk and opportunity costs. It also discusses recurring and non-recurring costs, incremental costs, cash and book costs, and life-cycle costs. The document then explains methods for estimating costs, including using per-unit models, work breakdown structure (WBS) models, and cost indices. It provides examples to illustrate key cost concepts.
This document provides an overview of engineering cost estimation. It defines various types of engineering cost estimates such as rough, semi-detailed, and detailed estimates. It discusses common difficulties in making cost estimates such as one-of-a-kind estimates and limitations of time and resources. The document also describes several common mathematical models used for cost estimating, including the per unit model, segmenting model, cost indexes, power-sizing model, and triangulation. It provides examples of how to use these models to estimate costs. Finally, it discusses the impact of learning curves on cost estimates over time.
This document provides examples and explanations for conducting benefit-cost analysis to evaluate engineering projects and alternatives. It defines the key steps and techniques in benefit-cost analysis including identifying project benefits and costs, quantifying them, discounting cash flows, and calculating the benefit-cost ratio. Examples are provided to demonstrate computing benefit-cost ratios, incremental analysis, and selecting the alternative with the highest ratio or most desirable increment above 1 to indicate project acceptance.
The document defines accounting rate of return (ARR) as the ratio of estimated accounting profit to average investment. ARR is calculated by taking the average accounting profit and dividing it by the average investment. Projects should be accepted if their ARR is greater than or equal to the required accounting rate of return, and between mutually exclusive projects the one with the highest ARR should be accepted. An example calculation is shown to illustrate determining ARR for a project with initial investment, annual cash inflows, depreciation, and scrap value.
Comparing alternatives in Engineering Economics and ManagementNzar Braim
Comparing alternatives in Engineering Economics and Management
In the real world, the majority of engineering economic analysis problems are
alternative comparisons. In these problems, two or more mutually exclusive
investments compete for limited funds. A variety of methods exists for selecting
the superior alternative from a group of proposals. Each method has its own merits
and applications
This report focuses on the Cost-Benefit Analysis which is effective tool and a rational technique for economic valuation where market information is either non-existent or deficient is.
This document discusses net present value (NPV) as a method for evaluating investment projects. It defines NPV as the difference between the present value of cash inflows and outflows. Positive NPV means the project is acceptable, zero means it may be acceptable, and negative means it should be rejected. The document provides a formula for calculating NPV and an example of applying the method to evaluate acquiring another company. Advantages include accounting for the time value of money, while disadvantages include difficulty of use and setting the discount rate.
This document outlines the key concepts and formulas covered in the Engineering Economics and Cost Analysis course. It discusses topics like profit calculation, break-even analysis, time value of money formulas, capital investment evaluation methods, depreciation techniques, replacement analysis, and public project evaluation. The course aims to teach students methods to make economic decisions that minimize costs and maximize benefits for business organizations.
This document defines accounting rate of return (ARR) as the ratio of estimated accounting profit to average investment of a project. It ignores the time value of money. ARR is calculated by dividing average accounting profit by initial investment. Average accounting profit is the mean of annual profits over the project life. Initial investment may be replaced by average investment due to declining book value over time. Projects are accepted if their ARR is not less than the required rate of return. Examples show calculating ARR for projects with given cash flows. ARR is an easy method but ignores the time value of money and can be calculated inconsistently using accounting versus cash flows.
time value of money
,
concept of time value of money
,
significance of time value of money
,
present value vs future value
,
solve for the present value
,
simple vs compound interest rate
,
nominal vs effective annual interest rates
,
future value of a lump sum
,
solve for the future value
,
present value of a lump sum
,
types of annuity
,
future value of an annuity
Here are the key steps to solve this problem:
* Future sum (F) = Rs. 1,00,000
* Interest rate (i) = 15%
* Number of periods (n) = 10 years
* Interest is compounded annually
* To find the present worth (P):
* P = F / (1 + i)^n
* P = Rs. 1,00,000 / (1 + 0.15)^10
* P = Rs. 1,00,000 / 2.472
* P = Rs. Rs. 40,320
Therefore, the single payment that should be made now to receive Rs. 1,00,000 after 10 years at
This document discusses various cash flow analysis methods including present worth, future worth, rate of return, and annual equivalent. It provides examples and formulas for revenue-dominated and cost-dominated cash flows. Key points include:
- Present worth discounts all cash flows to time zero using a discount rate to find the maximum or minimum value. Future worth grows all cash flows using a rate to find the maximum or minimum value.
- Annual equivalent converts net present worth to an equivalent annual revenue or cost using a capital recovery factor for comparison.
- Rate of return finds the discount rate that sets the net present worth equal to zero to determine the highest returning project.
- Examples apply the methods to alternatives with
The document summarizes key concepts in engineering economy including:
1) Time value of money, cash flow diagrams, and equivalence are used to analyze costs over time. Depreciation, inflation, and interest rates must also be considered.
2) Cash flows describe monetary inflows and outflows over time and are used to evaluate alternatives. Present and future values translate cash flows into common units for comparison.
3) Methods like present/future worth, rate of return, payback period, and breakeven analysis can be used to compare project alternatives based on costs, benefits, and investment returns.
The document summarizes key concepts in engineering economy including:
1) Time value of money, cash flow diagrams, and equivalence are used to analyze costs over time. Depreciation, inflation, and interest rates must also be considered.
2) Cash flows describe monetary inflows and outflows over time and are used to calculate present and future values through equivalence.
3) Methods for evaluating alternatives include present/future worth analysis, rate of return, payback period, and benefit-cost ratio. Cash flow diagrams and equivalence are applied to compare costs.
This document discusses various topics related to construction project management including:
- Project cost control methods like cost planning, direct costs, indirect costs, and total cost curves.
- Economic analysis methods for construction projects such as present worth, equivalent annual cost, and discounted cash flow.
- Depreciation analysis and break-even cost analysis for construction projects.
- The importance of cost planning and economic comparisons of alternatives in selecting the most cost-effective option.
- An example comparing the present worth of two alternatives for purchasing a concrete mixer to demonstrate the economic comparison method.
This document provides an introduction to value engineering interest formulas and their applications. It defines key terms like value, cost value, exchange value, use value, esteem value, primary function, secondary function, and tertiary function. It describes the value analysis/value engineering procedure and discusses types of values, functions, and differences between value analysis and value engineering. The document also presents various interest formulas for single payment compound amount, single payment present worth, uniform gradient series method, effective interest rate, equal payment series present worth amount, and equal payment series capital recovery amount. It includes examples of problems solved using these formulas.
The document discusses various methods for evaluating economic alternatives, including the present worth method. The present worth method discounts all future cash flows to present value for comparison. There are two ways to set up the cash flow diagram for this method - cost dominated and revenue dominated. The document provides examples of both and shows how to calculate present worth using the diagrams to evaluate which alternative has the highest net present value and is most economically favorable.
This document provides an introduction to value engineering interest formulas and their applications. It defines key terms like value, cost value, exchange value, use value, esteem value and different types of functions. It describes the value analysis/value engineering procedure and discusses when it should be used. Various interest formulas are explained including compound amount, present worth, uniform series and capital recovery. Examples are provided to demonstrate how to use the formulas to calculate future values, single payments, and equal installment amounts.
1. The document discusses methods for life cycle costing analysis, specifically the present worth method where all costs are discounted to their present value using a discount rate.
2. Examples are provided to illustrate how to calculate and compare the present worth of projects or equipment with equal or different expected lifetimes to determine the alternative with the lowest total cost over the analysis period.
3. The key steps are to identify the relevant cash flows over time for each alternative, discount those cash flows to the present using the interest rate, and compare the total present worth values to select the lowest cost option.
This document discusses depreciation and related concepts. It defines depreciation as the process of allocating the cost of tangible assets over their estimated useful lives. It lists various causes of depreciation as wear and tear, obsolescence, depletion, and lapse of time. The document describes different methods of calculating depreciation including straight-line, declining balance, sum-of-the-years digits, and sinking fund methods. It also discusses why depreciation is provided for fixed assets and how to evaluate public alternatives while adjusting for inflation.
This document provides an overview of annual worth analysis, which is an approach for comparing investment alternatives that have different lifetimes under life-cycle cost assumptions. It defines key terms like capital recovery, annual worth, salvage value, and annual amount. It presents examples of how to calculate the annual worth of various alternatives and choose the one with the highest annual worth value. The document also discusses how to evaluate permanent investments that have an infinite lifetime by calculating their perpetual equivalent annual worth. Overall, the summary provides the essential details on how to use annual worth analysis to evaluate capital investment options.
This document provides an overview of annual worth analysis, which is an approach for comparing investment alternatives that have different lifetimes under life-cycle cost assumptions. It defines key terms like capital recovery, annual worth, salvage value, and annual amount. It also presents examples of how to calculate annual worth for various cash flow scenarios and use it to evaluate mutually exclusive project alternatives. The annual worth is calculated as the capital recovery minus the annual costs or benefits over the study period. For permanent investments, the annual worth is simply the present worth times the interest rate.
The document discusses annual worth (AW) analysis and rate of return (ROR) calculations. It defines AW as converting cash flows to an equivalent uniform annual amount over one life cycle. Calculating ROR involves finding the interest rate that sets the present worth of cash flows equal to zero. ROR can be used to evaluate projects by comparing to the minimum acceptable rate of return.
The document discusses annual worth (AW) analysis and rate of return (ROR) calculations. It defines AW as converting cash flows to an equivalent uniform annual amount over one life cycle. Calculating ROR involves finding the interest rate that sets the present worth of cash flows equal to zero. ROR can be used to evaluate projects by comparing to the minimum acceptable rate of return.
Systematic Economic Analysis Technique for analysisNaganna Chetty
Ranking Methods or Incremental Methods
Present Worth
Future Worth
Annual Worth
Capitalized Worth
Discounted Payback Period
Payback Period
Incremental Methods
Internal Rate of Return
External Rate of Return
Modified Internal Rate of Return
Benefit/Cost Ratio
The document provides an overview of incremental analysis and other engineering economy methods for evaluating projects. It defines incremental rate of return analysis and discusses how to calculate and compare the incremental rates of return for multiple alternative projects. The key steps in incremental analysis are to identify all alternatives, calculate the rate of return for each, arrange them in order of increasing cost, perform two-alternative analyses to identify the preferred option, and continue this process until a best alternative is selected. The document also briefly covers other methods like benefit-cost ratio analysis, present value analysis, payback period, and breakeven analysis.
This document discusses annual worth (AW) analysis and its advantages over other methods. It provides the key assumptions and formulas for calculating AW. For mutually exclusive alternatives, the alternative with the highest positive or least negative AW should be selected. Examples are given to demonstrate calculating AW for alternatives with different lives and salvage values over one or multiple life cycles. The relationship between AW, present worth, and future worth is also explained.
This document contains summaries of key concepts in engineering economics including:
- Cash flow diagrams present the flow of cash over time as arrows scaled to the magnitude of cash flows. Expenses are down arrows and receipts are up arrows.
- Discount factors are used to convert between present, future, and uniform cash flows based on the interest rate and time period.
- Nonannual compounding and continuous compounding formulas are provided to calculate effective annual interest rates.
- Methods for comparing project alternatives include present worth, capitalized costs, annual cost, cost-benefit analysis, and rate of return calculations.
- Depreciation methods like straight-line and accelerated cost recovery system (ACRS) calculate annual depreciation
The document discusses cost-benefit analysis and various methods used to evaluate costs and benefits of projects. It defines key terms like tangible/intangible and direct/indirect costs and benefits. Several evaluation methods are described - net benefit analysis, present value analysis, net present value, payback period analysis, break-even analysis and cash flow analysis. Their formulas, examples and advantages/disadvantages are provided. The document concludes that cost-benefit analysis involves identifying, categorizing and evaluating costs and benefits to interpret results and take action regarding alternative systems.
OJP data from firms like Vicinity Jobs have emerged as a complement to traditional sources of labour demand data, such as the Job Vacancy and Wages Survey (JVWS). Ibrahim Abuallail, PhD Candidate, University of Ottawa, presented research relating to bias in OJPs and a proposed approach to effectively adjust OJP data to complement existing official data (such as from the JVWS) and improve the measurement of labour demand.
Seminar: Gender Board Diversity through Ownership NetworksGRAPE
Seminar on gender diversity spillovers through ownership networks at FAME|GRAPE. Presenting novel research. Studies in economics and management using econometrics methods.
5 Tips for Creating Standard Financial ReportsEasyReports
Well-crafted financial reports serve as vital tools for decision-making and transparency within an organization. By following the undermentioned tips, you can create standardized financial reports that effectively communicate your company's financial health and performance to stakeholders.
1. Elemental Economics - Introduction to mining.pdfNeal Brewster
After this first you should: Understand the nature of mining; have an awareness of the industry’s boundaries, corporate structure and size; appreciation the complex motivations and objectives of the industries’ various participants; know how mineral reserves are defined and estimated, and how they evolve over time.
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic DataChampak Jhagmag
In this presentation, we will explore the rise of generative AI in finance and its potential to reshape the industry. We will discuss how generative AI can be used to develop new products, combat fraud, and revolutionize risk management. Finally, we will address some of the ethical considerations and challenges associated with this powerful technology.
1. 12/23/2018
1
ENGINEERING ECONOMICS
COST ANALYSIS
&
MG 6863 ENGINEERING ECONOMICS
(Common to Mechanical, Production, Automobile, Metallurgy,
Mechatronics - VIII Semester Elective)
OBJECTIVES
To learn about the basics of economics and cost analysis related to engineering
so as to take economically sound decisions.
UNIT I INTRODUCTION TO ECONOMICS 8
Introduction to Economics- Flow in an economy, Law of supply and demand, Concept of
Engineering Economics – Engineering efficiency, Economic efficiency, Scope of
engineering economics- Element of costs, Marginal cost, Marginal Revenue, Sunk cost,
Opportunity cost, Break-even analysis- P/V ratio, Elementary economic Analysis –
Material selection for product, Design selection for a product, Process planning.
SYLLABUS
2
UNIT II VALUE ENGINEERING 10
Make or buy decision, Value engineering – Function, aims, Value engineering procedure.
Interest formulae and their applications –Time value of money, Single payment compound
amount factor, Single payment present worth factor, Equal payment series sinking fund
factor, Equal payment series payment Present worth factor- equal payment series capital
recovery factor-Uniform gradient series annual equivalent factor, Effective interest rate,
Examples in all the methods.
UNIT III CASH FLOW 9
Methods of comparison of alternatives – present worth method (Revenue dominated cash
flow diagram), Future worth method (Revenue dominated cash flow diagram, cost
dominated cash flow diagram), Annual equivalent method (Revenue dominated cash flow
diagram, cost dominated cash flow diagram), rate of return method, Examples in all the
methods.
3
UNIT IV REPLACEMENT AND MAINTENANCE ANALYSIS 9
Replacement and Maintenance analysis – Types of maintenance, types of
replacement problem, determination of economic life of an asset, Replacement of
an asset with a new asset – capital recovery with return and concept of challenger
and defender, Simple probabilistic model for items which fail completely.
UNIT V DEPRECIATION 9
Depreciation- Introduction, Straight line method of depreciation, declining balance
method of depreciation-Sum of the years digits method of depreciation, sinking
fund method of depreciation/ Annuity method of depreciation, service output
method of depreciation-Evaluation of public alternatives- introduction, Examples,
Inflation adjusted decisions – procedure to adjust inflation, Examples on
comparison of alternatives and determination of economic life of asset.
TEXT BOOKS
“Engineering Economics”, Panneer Selvam. R,
Prentice Hall of India Ltd, New Delhi, 2001.
4
U N I T I I I
A N N U A L
E Q U I V A L E N T
M E T H O D
5
First the annual equivalent cost or the revenue of
each alternative will be computed.
Then the alternative with the maximum annual
equivalent revenue in the case of revenue-based
comparison or with the minimum annual equivalent
cost in the case of cost based comparison will be
selected as the best alternative.
6
1. INTRODUCTION
2. 12/23/2018
2
7
2. REVENUE-DOMINATED
CASH FLOW DIAGRAM
P = Initial investment
Rj = Net revenue at the end of the jth year
S = Salvage value at the end of the nth year.
First step:
Net present worth of the cash flow diagram for a given interest rate ‘i’:
PW(i) = – P + R1/(1 + i)1 + R2/(1 + i)2 + ... + Rj/(1 + i) j + ... + Rn/(1 + i)n +
S/(1 + i)n
Expenditure is assigned with a negative sign.
Revenues are assigned with a positive sign.
Second step:
Annual equivalent revenue is computed as
8
where (A/P, i, n) is called equal payment
series capital recovery factor
Corresponding annual equivalent revenues are to be computed and
compared If we have some more alternatives.
Alternative with the maximum annual equivalent revenue should be
selected as the best alternative.
9
3. COST-DOMINATED
CASH FLOW DIAGRAM
P = Initial investment
Cj = Net cost of operation and maintenance at the
end of the jth year
S = Salvage value at the end of the nth year.
First step:
Net present worth of the cash flow diagram for a given interest rate ‘i’:
PW(i) = P + C1/(1 + i)1 + C2/(1 + i)2 + ... + Cj/(1 + i) j + ... + Cn/(1 + i)n –
S/(1 + i)n
Expenditure is assigned with positive sign.
Revenues are assigned with negative sign.
Second step:
Annual equivalent cost is computed as
10
where (A/P, i, n) is called equal payment
series capital recovery factor
Corresponding annual equivalent costs are to be computed and
compared If we have some more alternatives.
Alternative with the minimum annual equivalent cost should be
selected as the best alternative.
11
4. ALTERNATE APPROACH
Instead of first finding the PW & then figuring out the AE
cost/revenue, an alternate method can be used.
Future worth of the cash flow diagram of each of the alternatives
can be found in the first step. Then, the AE cost/revenue can be
obtained by using the equation:
where (A/F, i, n) is equal-payment series sinking fund factor
EXAMPLE 1:
A company provides a car to its chief executive. The owner of the
company is concerned about the increasing cost of petrol. The cost
perlitre of petrol for the first year of operation is Rs. 21. He feels that
the cost of petrol will be increasing by Re.1 every year. His experience
with his company car indicates that it averages 9 km per litre of petrol.
The executive expects to drive an average of 20,000 km each year for
the next four years. What is the annual equivalent cost of fuel over
this period of time?. If he is offered similar service with the same
quality on rental basis at Rs. 60,000 per year, should the owner
continue to provide company car for his executive or alternatively
provide a rental car to his executive? Assume i = 18%. If the rental car
is preferred, then the company car will find some other use within the
company. 12
3. 12/23/2018
3
Average number of km run/year = 20,000 km
Number of km/litre of petrol = 9 km
Therefore,
Petrol consumption/year = 20,000/9 = 2222.2 litre
Cost/litre of petrol for the 1st year = Rs. 21
Cost/litre of petrol for the 2nd year = Rs. 21.00 + Rs. 1.00
= Rs. 22.00
Cost/litre of petrol for the 3rd year = Rs. 22.00 + Rs. 1.00
= Rs. 23.00
Cost/litre of petrol for the 4th year = Rs. 23.00 + Rs. 1.00
= Rs. 24.00
13
A = A1 + G (A/G, 18%, 4) = 46,666.20 + 2222.2 (1.2947) = Rs. 49,543.28
Proposal of using the company car by spending for petrol will
cost an annual equivalent amount of Rs. 49,543.28 for 4 years.
This amount is less than the annual rental value of Rs. 60,000.
Therefore, the company should continue to provide its own car
to its executive.
Fuel expenditure for 1st year = 2222.2 x 21 = Rs. 46,666.20
Fuel expenditure for 2nd year = 2222.2 x 22 = Rs. 48,888.40
Fuel expenditure for 3rd year = 2222.2 x 23 = Rs. 51,110.60
Fuel expenditure for 4th year = 2222.2 x 24 = Rs. 53,332.80
Annual equal increment of the above expenditures is Rs. 2,222.20 (G).
14
15
EXAMPLE 2:
A company is planning to purchase an advanced machine centre. Three
original manufacturers have responded to its tender whose particulars
are tabulated as follows:
Determine the best alternative based on the annual equivalent
method by assuming i = 20%, compounded annually.
16
Alternative 1
Down payment, P = Rs. 5,00,000
Yearly equal instalment, A = Rs. 2,00,000
n = 15 years
i = 20%, compounded annually
Annual equivalent cost expression of the above cash flow diagram is
AE1 (20%) = 5,00,000 (A/P, 20%, 15) + 2,00,000
= 5,00,000 (0.2139) + 2,00,000
= 3,06,950
17
Alternative 2
Down payment, P = Rs. 4,00,000
Yearly equal installment, A = Rs. 3,00,000
n = 15 years
i = 20%, compounded annually
Annual equivalent cost expression of the above cash flow diagram is
AE2(20%) = 4,00,000 (A/P, 20%, 15) + 3,00,000
= 4,00,000 (0.2139) + 3,00,000
= Rs. 3,85,560. 18
Alternative 3
Down payment, P = Rs. 6,00,000
Yearly equal installment, A = Rs. 1,50,000
n = 15 years
i = 20%, compounded annually
Annual equivalent cost expression of the above cash flow diagram is
AE3(20%) = 6,00,000 (A/P, 20%, 15) + 1,50,000
= 6,00,000 (0.2139) + 1,50,000
= Rs. 2,78,340.
Annual equivalent cost of manufacturer 3 < manufacturer 1 & 2.
Company should buy the advanced machine centre from
manufacturer 3.
4. 12/23/2018
4
19
EXAMPLE 3:
A company invests in one of the two mutually exclusive alternatives.
The life of both alternatives is estimated to be 5 years with the
following investments, annual returns and salvage values.
Determine the best alternative based on the annual equivalent
method by assuming i = 25%.
20
Alternative A
Initial investment, P = Rs. 1,50,000
Annual equal return, A = Rs. 60,000
Salvage value at the end of machine life, S = Rs. 15,000
Life = 5 years
Interest rate, i = 25%, compounded annually
Annual equivalent revenue expression of the above cash flow diagram
AEA(25%) = –1,50,000 (A/P, 25%, 5) + 60,000 + 15,000 (A/F, 25%, 5)
= –1,50,000 (0.3718) + 60,000 + 15,000 (0.1218)
= Rs. 6,057
21
Alternative B
Initial investment, P = Rs. 1,75,000
Annual equal return, A = Rs. 70,000
Salvage value at the end of machine life, S = Rs. 35,000
Life = 5 years
Interest rate, i = 25%, compounded annually
Annual equivalent revenue expression of the above cash flow diagram
AEB(25%) = –1,75,000 (A/P, 25%, 5) + 70,000 + 35,000 (A/F, 25%, 5)
= –1,75,000 (0.3718) + 70,000 + 35,000 (0.1218)
= Rs. 9,198
Annual equivalent net return of alternative B > alternative A.
Thus, the company should select alternative B.
EXAMPLE 4:
A certain individual firm desires an economic analysis to determine
which of the two machines is attractive in a given interval of time. The
minimum attractive rate of return for the firm is 15%. The following
data are to be used in the analysis:
Machine X Machine Y
First cost Rs. 1,50,000 Rs. 2,40,000
Estimated life 12 years 12 years
Salvage value Rs. 0 Rs. 6,000
Annual maintenance cost Rs. 0 Rs. 4,500
Which machine would you choose? Base your answer on annual
equivalent cost. 22
23
Machine X
First cost, P = Rs. 1,50,000
Life, n = 12 years
Estimated salvage value at the end of machine life, S = Rs. 0.
Annual maintenance cost, A = Rs. 0.
Interest rate, i = 15%, compounded annually.
Annual equivalent cost expression of the above cash flow diagram
AEX (15%) = 1,50,000 (A/P, 15%, 12)
= 1,50,000 (0.1845)
= Rs. 27,675 24
Machine Y
First cost, P = Rs. 2,40,000
Life, n = 12 years
Estimated salvage value at the end of machine life, S = Rs. 60,000
Annual maintenance cost, A = Rs. 4,500
Interest rate, i = 15%, compounded annually.
Annual equivalent cost expression of the above cash flow diagram is
AEY(15%) = 2,40,000 (A/P, 15%, 12) + 4,500 – 6,000 (A/F, 15%, 12)
= 2,40,000 (0.1845) + 4,500 – 6,000 (0.0345)
= Rs. 48,573
Annual equivalent cost of machine X < machine Y.
Machine X is the more cost effective machine.
5. 12/23/2018
5
25
EXAMPLE 5:
Two possible routes for laying a power line are under study. Data on
the routes are as follows:
If 15% interest is used, should the power line be routed around the
lake or under the lake?
26
Alternative 1 – Around the lake
First cost = 1,50,000 x 15 = Rs. 22,50,000
Maintenance cost/year = 6,000 x 15 = Rs. 90,000
Power loss/year = 15,000 x 15 = Rs. 2,25,000
Maintenance cost & power loss/year = Rs. 90,000 + Rs. 2,25,000
= Rs. 3,15,000
Salvage value = 90,000 x 15 = Rs. 13,50,000
Annual equivalent cost expression of the above cash flow diagram
AE1 (15%) = 22,50,000 (A/P, 15%, 15) + 3,15,000 – 13,50,000 (A/F, 15%, 15)
= 22,50,000 (0.1710) + 3,15,000 – 13,50,000 (0.0210) = Rs. 6,71,400
27
Alternative 2 – Under the lake
First cost = 7,50,000 x 5 = Rs. 37,50,000
Maintenance cost/year = 12,000 x 5 = Rs. 60,000
Power loss/year = 15,000 x 5 = Rs. 75,000
Maintenance cost & power loss/year = Rs. 60,000 + Rs. 75,000
= Rs. 1,35,000
Salvage value = 1,50,000 x 5 = Rs. 7,50,000
Annual equivalent cost expression of the above cash flow diagram
AE2 (15%) = 37,50,000 (A/P, 15%, 15) + 1,35,000 – 7,50,000 (A/F, 15%, 15)
= 37,50,000 ( 0.1710) + 1,35,000 – 7,50,000 (0.0210) = Rs. 7,60,500
Annual equivalent cost of alternative 1 < alternative 2.
Select the route around the lake for laying the power line.
Determine the more economical choice if interest rate is 20%,
compounded annually. 28
EXAMPLE 6:
A suburban taxi company is analyzing the proposal of buyingbcars with
diesel engines instead of petrol engines. The cars average 60,000 km a
year with a useful life of three years for the petrol taxi and four years
for the diesel taxi. Other comparative details are as follows:
29
Alternative 1 – Purchase of diesel taxi
Vehicle cost = Rs. 3,90,000
Life = 4 years
Number of litres/year = 60,000/30 = 2,000 litres
Fuel cost/year = 2,000 x 8 = Rs. 16,000
Fuel cost, annual repairs and insurance premium/year
= Rs. 16,000 + Rs. 9,000 + Rs. 15,000 = Rs. 40,000
Salvage value at the end of vehicle life = Rs. 60,000
Annual equivalent cost expression of the above cash flow diagram
AE (20%) = 3,90,000 (A/P, 20%, 4) + 40,000 – 60,000 (A/F, 20%, 4)
= 3,90,000 (0.3863) + 40,000 – 60,000 (0.1863) = Rs. 1,79,479
Alternative 2 – Purchase of petrol taxi
Vehicle cost = Rs. 3,60,000
Life = 3 years 30
Number of litres/year = 60,000/20 = 3,000 litres
Fuel cost/year = 3,000 x 20 = Rs. 60,000
Fuel cost, annual repairs and insurance premium/year
= Rs. 60,000 + Rs. 6,000 + Rs. 15,000 = Rs. 81,000
Salvage value at the end of vehicle life = Rs. 90,000
Annual equivalent cost expression of the above cash flow diagram
AE (20%) = 3,60,000 (A/P, 20%, 3) + 81,000 – 90,000 (A/F, 20%, 3)
= 3,60,000(0.4747) + 81,000 – 90,000(0.2747) = Rs. 2,27,169
Annual equivalent cost of purchase and operation of the cars
with diesel engine < with petrol engine.
Taxi company should buy cars with diesel engine.
Comparisonis done on common multiple lives of 12 years.
6. 12/23/2018
6
EXAMPLE 7:
Ramu, a salesman, needs a new car for use in his business. He
expects that he will be promoted to a supervisory job at the end of
third year and so his concern now is to have a car for the three years
he expects to be “on the road”. The company will reimburse their
salesman each month the fuel cost and maintenance cost. Ramu has
decided to drive a low-priced automobile. He finds, however, that
there are two different ways of obtaining the automobile. In either
case, the fuel cost and maintenance cost are borne by the company.
(a) Purchase for cash at Rs. 3,90,000.
(b) Lease a car. The monthly charge is Rs. 10,500 on a 36-month lease
payable at the end of each month. At the end of the three-year
period, the car is returned to the leasing company.
Ramu believes that he should use a 12% interest rate
compounded monthly in determining which alternative to select. If the
car could be sold for Rs. 1,20,000 at the end of the third year, which
option should he use to obtain it? 31
32
Alternative 1 – Purchase car for cash
Purchase price of the car = Rs. 3,90,000
Life = 3 years = 36 months
Salvage value after 3 years = Rs. 1,20,000
Interest rate = 12% (nominal rate, compounded annually)
= 1% compounded monthly
Monthly equivalent cost expression of the above cash flow diagram
ME (1%) = 3,90,000 (A/P, 1%, 36) – 1,20,000 (A/F, 1%, 36)
= 3,90,000 (0.0332) – 1,20,000 (0.0232)
= Rs. 10,164
33
Alternative 2 – Use of car under lease
Monthly lease amount for 36 months = Rs. 10,500
Monthly equivalent cost = Rs.10,500.
Monthly equivalent cost of alternative 1 < alternative 2.
Salesman should purchase the car for cash.
34
EXAMPLE 8:
A company must decide whether to buy machine A or machine B.
At 15% interest rate, which machine should be purchased?
Machine A
Initial cost = Rs. 3,00,000
Useful life (years) = 4
Salvage value at the end of machine life = Rs. 2,00,000
Annual maintenance = Rs. 30,000
Interest rate = 15%, compounded annually
35
Annual equivalent cost expression of the above cash flow diagram
AE (15%) = 3,00,000 (A/P, 15%, 4) + 30,000 – 2,00,000 (A/F, 15%, 4)
= 3,00,000 (0.3503) + 30,000 – 2,00,000 (0.2003) = Rs. 95,030
Machine B
Initial cost = Rs. 6,00,000
Useful life (years) = 4
Salvage value at the end of machine life = Rs. 3,00,000
Annual maintenance = Rs. 0.
Interest rate = 15%, compounded annually 36
Annual equivalent cost expression of the above cash flow diagram
AE (15%) = 6,00,000 (A/P, 15%, 4) – 3,00,000 (A/F, 15%, 4)
= 6,00,000 (0.3503) – 3,00,000 (0.2003)
= Rs. 1,50,090
Since the annual equivalent cost of machine A is less than that of
machine B, it is advisable to buy machine A.
7. 12/23/2018
7
37
EXAMPLE 9:
Jothi Lakshimi has arranged to buy some home recording
equipment. She estimates that it will have a five year useful life and no
salvage value at the end of equipment life. The dealer, who is a friend
has offered Jothi Lakshimi two alternative ways to pay for the
equipment.
(a) Pay Rs. 60,000 immediately and Rs. 15,000 at the end of one year.
(b) Pay nothing until the end of fourth year when a single payment of
Rs. 90,000 must be made.
If Jothi Lakshimi believes 12% is a suitable interest rate, which
alternative is the best for her? 38
Alternative 1
Down payment = Rs. 60,000
Payment after one year = Rs. 15,000
Present worth equation of the above cash flow diagram
PW (12%) = 60,000 + 15,000 (P/F, 12%, 1)
= 60,000 + 15,000 (0.8929) = 73,393.50
The above present worth is represented in Figure.
39
Annual equivalent expression of the above cash flow diagram
AE (12%) = 73,393.5 (A/P, 12%, 4) = 73,393.5 (0.3292) = Rs. 24,161.14
Alternative 2
Payment after four years = Rs. 90,000
Annual equivalent cost of alternative 2 < alternative 1.
Jothi Lakshimi should select alternative 2 for purchasing the
home equipment.
Annual equivalent cost expression of the above cash flow diagram
AE (12%) = 90,000 (A/F, 12%, 4) = 90,000 (0.2092) = Rs. 18,828
40
EXAMPLE 10:
A transport company has been looking for a new tyre for its truck and
has located the following alternatives:
If the company feels that the warranty period is a good estimate of the
tyre life and that a nominal interest rate (compounded annually) of
12% is appropriate, which tyre should it buy?
41
Interest rate is 12% = 1% per month.
Brand A
Tyre warranty = 12 months
Price/tyre = Rs. 1,200
Annual equivalent cost expression of the above cash flow diagram
AE (1%) = 1,200 (A/P, 1%, 12) = 1,200 (0.0888) = Rs. 106.56
Brand B
Tyre warranty = 24 months
Price/tyre = Rs. 1,800
42
Annual equivalent cost expression of the above cash flow diagram
AE (1%) = 1,800 (A/P, 1%, 24) = 1,800 (0.0471) = Rs. 84.78
Brand C
Tyre warranty = 36 months
Price/tyre = Rs. 2,100
Annual equivalent expression of the above cash flow diagram
AE (1%) = 2,100 (A/P, 1%, 36) = 2,100 (0.0332) = Rs. 69.72
Brand D
Tyre warranty = 48 months
Price/tyre = Rs. 2,700
8. 12/23/2018
8
43
Annual equivalent cost expression of the above cash flow diagram
AE (1%) = 2,700 (A/P, 1%, 48) = 2,700 (0.0263) = Rs. 71.01
Minimum common multiple lives of tyres is 144 months and this
is considered for the comparison.
Annual equivalent cost of brand C < other brands.
Hence, brand C should be used in the vehicles of the trucking
company.
Brand C should be replaced 4 times during the 144 month period.
U N I T V
R A T E
OF
R E T U R N
M E T H O D
44
45
1. INTRODUCTION
Rate of return of a cash flow pattern is the interest rate at which
the present worth of that cash flow pattern reduces to zero.
Rate of return for each alternative is computed.
The alternative which has the highest rate of return is selected as
the best alternative.
In this type of analysis, the expenditures are always assigned
with a negative sign and the revenues/inflows are assigned with
a positive sign.
A generalized cash flow diagram to demonstrate the rate of
return method of comparison is presented in figure.
46
P = Initial investment
Rj = Net revenue at the end of the jth year
S = Salvage value at the end of the nth year.
First step
Find the net present worth of the cash flow diagram using the
following expression at a given interest rate, i.
PW (i) = – P + R1/(1 + i)1 + R2/(1 + i)2 + ... + Rj/(1 + i)j + ... + Rn/(1 + i)n
+ S/(1 + i)n
47
Second step
The above function is to be evaluated for different values of ‘i’ until
the present worth function reduces to zero, as shown in Figure.
Present worth function graph 48
In the figure, the PW goes on decreasing when the interest rate
is increased.
The value of ‘i’ at which the PW curve cuts the X-axis is the rate
of return of the given proposal/project.
It will be very difficult to find the exact value of ‘i’ at which the
PW function reduces to zero.
So, start with an intuitive value of ‘i’ and check whether the PW
function is positive.
If so, increase the value of ‘i’ until PW (i) becomes negative.
Then, the rate of return is determined by interpolation method
in the range of values of ‘i’ for which the sign of the PW function
changes from positive to negative.
9. 12/23/2018
9
EXAMPLE 1:
A person is planning a new business. The initial outlay and cash flow
pattern for the new business are as listed below. The expected life of
the business is five years. Find the rate of return for the new business.
49
Solution
Initial investment = Rs. 1,00,000
Annual equal revenue = Rs. 30,000
Life = 5 years
50
Present worth function: PW(i) = –1,00,000 + 30,000(P/A, i, 5)
When i = 10%,
PW (10%) = –1,00,000 + 30,000 (P/A, 10%, 5)
= –1,00,000 + 30,000 (3.7908) = Rs. 13,724.
When i = 15%,
PW (15%) = –1,00,000 + 30,000 (P/A, 15%, 5)
= –1,00,000 + 30,000 (3.3522) = Rs. 566.
51
When i = 18%,
PW(18%) = –1,00,000 + 30,000 (P/A, 18%, 5)
= –1,00,000 + 30,000 (3.1272) = Rs. – 6,184
Therefore, the rate of return for the new business is 15.252%.
EXAMPLE 2:
A company is trying to diversify its business in a new product line. The
life of the project is 10 years with no salvage value at the end of its life.
The initial outlay of the project is Rs. 20,00,000. The annual net profit
is Rs. 3,50,000. Find the rate of return for the new business.
52
Life of the product line (n) = 10 years
Initial outlay = Rs. 20,00,000
Annual net profit = Rs. 3,50,000
Scrap value after 10 years = 0
Net present worth function: PW(i) = –20,00,000 + 3,50,000 (P/A, i, 10)
53
When i = 10%,
PW(10%) = –20,00,000 + 3,50,000 (P/A, 10%, 10)
= –20,00,000 + 3,50,000 (6.1446) = Rs. 1,50,610.
When i = 12%,
PW(12%) = –20,00,000 + 3,50,000 (P/A, 12%, 10)
= –20,00,000 + 3,50,000 (5.6502) = Rs. –22,430.
Therefore, the rate of return of the new product line is 11.74%
Find the best alternative based on the rate of return method of
comparison.
54
EXAMPLE 3:
A firm has identified three mutually exclusive investment proposals
whose details are given below. The life of all the three alternatives is
estimated to be five years with negligible salvage value. The minimum
attractive rate of return for the firm is 12%.
10. 12/23/2018
10
55
Calculation of rate of return for alternative A1
Initial outlay = Rs. 1,50,000
Annual profit = Rs. 45,570
Life = 5 years
Net PW of alternative A1: PW(i) = –1,50,000 + 45,570(P/A, i, 5)
When i = 10%,
PW (10%) = –1,50,000 + 45,570 (P/A, 10%, 5)
= –1,50,000 + 45,570 (3.7908) = Rs. 22,746.76
56
When i = 12%,
PW (12%) = –1,50,000 + 45,570 (P/A, 12%, 5)
= –1,50,000 + 45,570 (3.6048) = Rs. 14,270.74
When i = 15%,
PW (15%) = –1,50,000 + 45,570 (P/A, 15%, 5)
= –1,50,000 + 45,570 (3.3522) = Rs. 2,759.75
When i = 18%,
PW (18%) = –1,50,000 + 45,570 (P/A, 18%, 5)
= –1,50,000 + 45,570 (3.1272) = Rs. –7,493.50
Therefore, the rate of return of the alternative A1 is
57
Calculation of rate of return for alternative A2
Initial outlay = Rs. 2,10,000
Annual profit = Rs. 58,260
Life = 5 years
Net PW of alternative A2: PW(i) = –2,10,000 + 58,260(P/A, i, 5)
When i = 12%,
PW (12%) = –2,10,000 + 58,260 (P/A, 12%, 5)
= –2,10,000 + 58,260 (3.6048) = Rs. 15.65
58
When i = 13%,
PW (13%) = –2,10,000 + 58,260 (P/A, 13%, 5)
= –2,10,000 + 58,260 (3.5172) = Rs. –5,087.93
Therefore, the rate of return of alternative A2 is
Calculation of rate of return for alternative A3
Initial outlay = Rs. 2,55,000
Annual profit = Rs. 69,000
Life = 5 years
59
Net PW of alternative A3: PW (i) = –2,55,000 + 69,000 (P/A, i, 5)
When i = 11%,
PW (11%) = – 2,55,000 + 69,000 (P/A, 11%, 5)
= –2,55,000 + 69,000 (3.6959) = Rs. 17.1
When i = 12%,
PW (12%) = – 2,55,000 + 69,000 (P/A, 12%, 5)
= –2,55,000 + 69,000 (3.6048) = Rs. – 6,268.80
60
Therefore, the rate of return for alternative A3 is
The rates of return for the three alternatives are now tabulated.
Rate of return for alternative A3 is less than the minimum
attractive rate of return of 12%. So, it should not be considered
for comparison.
The remaining two alternatives are qualified for consideration.
Rate of return of alternative A1 > alternative A2.
Hence, alternative A1 should be selected.
11. 12/23/2018
11
EXAMPLE 4:
For the cash flow diagram shown in Figure, compute the rate of return.
The amounts are in rupees.
61
For the positive cash flows of the problem: A1 = Rs. 150, G = Rs. 150
Annual equivalent of the positive cash flows of the uniform gradient
series is given by
A = A1 + G (A/G, i, n) = 150 + 150 (A/G, i, 5) 62
PW function: PW (i) = –1,275 + [150 + 150 (A/G, i, 5)] (P/A, i, 5)
PW (10%) = –1,275 + [150 + 150 (A/G, 10%, 5)] (P/A, 10%, 5)
= –1,275 + [150 + 150 (1.8101)] (3.7908) = Rs. 322.88
PW (12%) = –1,275 + [150 + 150 (A/G, 12%, 5)] (P/A, 12%, 5)
= –1,275 + [150 + 150 (1.7746)] (3.6048) = Rs. 225.28
PW (15%) = –1,275 + [150 + 150 (A/G, 15%, 5)] (P/A, 15%, 5)
= –1,275 + [150 + 150 (1.7228)] (3.3522) = Rs. 94.11
PW (18%) = –1,275 + [150 + 150 (A/G, 18%, 5)] (P/A, 18%, 5)
= –1,275 + [150 + 150 (1.6728)] (3.1272) = Rs. –21.24
Therefore, the rate of return for the cash flow diagram is
EXAMPLE 5:
A company is planning to expand its present business activity. It has
two alternatives for the expansion programme and the corresponding
cash flows are tabulated below. Each alternative has a life of five years
and a negligible salvage value. The minimum attractive rate of return
for the company is 12%. Suggest the best alternative to the company.
63 64
Alternative 1
Initial outlay = Rs. 5,00,000
Annual revenue = Rs. 1,70,000
Life = 5 years
Net PW of alternative 1: PW1 (i) = –5,00,000 + 1,70,000 (P/A, i, 5)
PW1 (15%) = –5,00,000 + 1,70,000 (P/A, 15%, 5)
= –5,00,000 + 1,70,000 (3.3522) = Rs. 69,874
PW1 (17%) = –5,00,000 + 1,70,000 (P/A, 17%, 5)
= –5,00,000 + 1,70,000 (3.1993) = Rs. 43,881
65
PW1 (20%) = –5,00,000 + 1,70,000 (P/A, 20%, 5)
= –5,00,000 + 1,70,000 (2.9906) = Rs. 8,402
PW1 (22%) = –5,00,000 + 1,70,000 (P/A, 22%, 5)
= –5,00,000 + 1,70,000 (2.8636) = Rs. –13,188
Therefore, the rate of return of alternative 1 is
Alternative 2
Initial outlay = Rs. 8,00,000
Annual revenue = Rs. 2,70,000
Life = 5 years
66
Net PW of alternative 2: PW2 (i) = – 8,00,000 + 2,70,000 (P/A, i, 5)
PW2 (20%) = – 8,00,000 + 2,70,000 (P/A, 20%, 5)
= – 8,00,000 + 2,70,000 (2.9906) = Rs. 7,462
PW2 (22%) = –8,00,000 + 2,70,000 (P/A, 22%, 5)
= – 8,00,000 + 2,70,000 (2.8636) = Rs. –26,828
Thus, the rate of return of alternative 2 is
Since the rate of return of alternative 1 > alternative 2, select
alternative 1.