SlideShare a Scribd company logo
1 of 6
Download to read offline
Building Economy ARE 431
Dr. Mohammad A. Hassanain 1
1
Life Cycle Costing
Present worth method:
In this case, all costs or savings (cash flows) which
occur during the life time of an investment are
discounted to present value of money.
P
n-120 1 3 n-2 n
F
n
Fn = P(1 + i)n or P = Fn
1
(1 + i)n
2
Life Cycle Costing
Present worth method:
P
n-120 1 3 n-2 n
F
n
An alterative method, instead of using the F and P
formulas, is to use interest tables with the following
notations:
(F/P, i%, n) Find F given P
(P/F, i%, n) Find P given F
Building Economy ARE 431
Dr. Mohammad A. Hassanain 2
3
Life Cycle Costing
Example: Make a present-worth comparison of the equal-service life
projects for which costs are shown below, if i = 10%. Which project
would you select?
55Project service life (years)
$350,000$200,000Salvage value, F
$700,000$900,000Annual operating cost, A
$3,500,000$2,500,000First cost, P
Project BProject A
Present Worth Comparison of Equal-Lived Alternatives
4
Life Cycle Costing
A = $900,000
42
0
1 3
5
i = 10%
$2,500,000
$200,000
Project A
A = $700,000
42
0
1 3
5
i = 10%
$3,500,000
$350,000
Project B
PA = $2,500,000 + $900,000 (P/A, 10%, 5) - $200,000 (P/F, 10%, 5)
= $5,788,000
PB = $3,500,000 + $700,000 (P/A, 10%, 5) - $350,000 (P/F, 10%, 5)
= $5,936,000
Project A should be selected since PA < PB
Building Economy ARE 431
Dr. Mohammad A. Hassanain 3
5
Life Cycle Costing
Example: Two machines are under consideration for a carpentry
workshop. Machine A will have a first cost of $5,000, an annual
operation and maintenance cost of $300, and a $1,200 salvage
value. Machine B will have a first cost of $7,000, an annual
operation and maintenance cost of $200, and a $1,300 salvage
value. If both machines are expected to last for ten years, determine
which machine should be selected on the basis of their present-
worth values using an interest rate of 10%.
1010Service life (years), n
$1,300$1,200Salvage value, F
$200$300Operation and Maintenance cost, A
$7,000$5,000First cost, P
Machine BMachine A
Present Worth Comparison of Equal-Lived Alternatives
6
Life Cycle Costing
Example: Make a present-worth comparison of the different-service
life machines for which costs are shown below, if i = 15%. Which
machine would you select?
96Service life (years)
$2,000$1,000Salvage value
$3,100$3,500Annual operating cost
$18,000$11,000First cost
Machine BMachine A
Present Worth Comparison of Different-Lived Alternatives
The cash flow for one cycle of an alternative must be duplicated
for the least common multiple of years, so that service life is
compared over the total life for each alternative.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 4
7
Life Cycle Costing
Since the machines have different lives, they must be compared
Over the least common multiple of years, which is 18 years.
A = $3,500
42
0
1 3 5 7 8 9 10 11 13
$11,000
14 15 16 17
$1,000 $1,000 $1,000
18
$11,000 $11,000
Machine A
A = $3,100
42
0
1 3 5 7 8 10 11 13
$18,000
14 15 16 17
$2,000 $2,000
18
Machine B
6 12
$18,000
8
Life Cycle Costing
PA = $11,000 + $11,000 (P/F, 15%, 6) + $11,000 (P/F, 15%, 12) +
$3,500 (P/A, 15%, 18) - $1,000 (P/F, 15%, 6) - $1,000 (P/F, 15%, 12) -
PB = $18,000 + $18,000 (P/F, 15%, 9) + $3,100 (P/A, 15%, 18) -
= $41,384
Machine A should be selected since PA < PB
$1,000 (P/F, 15%, 18)
= $38,559
$2,000 (P/F, 15%, 9) - $2,000 (P/F, 15%, 18)
Building Economy ARE 431
Dr. Mohammad A. Hassanain 5
9
Life Cycle Costing
Example: A company is trying to decide between two different
garbage disposals. A regular (RS) disposal has an initial cost of $65
and a life of 4 years. The alternative is a corrosion-resistant
disposal constructed of stainless steel (SS). The initial cost of the
SS disposal is $110, but it is expected to last 10 years.
The SS disposal is expected to cost $5 per year more than the
RS disposal. If the interest rate is 6%, which disposal should be
selected, assuming both have no salvage value?
104Service life (years)
--Salvage value
$5-Additional cost per year
$110$65Initial cost
SSRS
Present Worth Comparison of Different-Lived Alternatives
10
Life Cycle Costing
Since the disposals have different lives, they must be compared
Over the least common multiple of years, which is 20 years.
$65
420 1 3 5 7 8 9 10 11 13 14 15 16 17 18
RS Disposal
19 206
$65 $65$65 $65
12
Extra Cost (A) = $5
42
0
1 3 5 7 8 10 11 13
$110
14 15 16 17 18
SS Disposal
6 12 19 209
$110
Building Economy ARE 431
Dr. Mohammad A. Hassanain 6
11
Life Cycle Costing
$65 (P/F, 6%, 16)
PRS = $65 + $65 (P/F, 6%, 4) + $65 (P/F, 6%, 8) + $65 (P/F, 6%, 12) +
PSS = $110 + $110 (P/F, 6%, 10) + $5 (P/A, 6%, 20)
= $229
Disposal RS should be selected since PRS < PSS
= $215
12
Life Cycle Costing
Example: Two machines are under consideration for a carpentry
workshop. Machine A will have a first cost of $5,000, an annual
operation and maintenance cost of $300, and a $1,200 salvage
value. Machine B will have a first cost of $7,000, an annual
operation and maintenance cost of $200, and a $1,300 salvage
value. If machine A is expected to last for 10 years, while Machine B
would last for 15 years, determine which machine should be
selected on the basis of their present-worth values using an interest
rate of 10%.
1010Service life (years), n
$1,300$1,200Salvage value, F
$200$300Operation and Maintenance cost, A
$7,000$5,000First cost, P
Machine BMachine A
Present Worth Comparison of Different-Lived Alternatives

More Related Content

What's hot

Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4Nour Dagher
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 
Chapter-4 Time value of money
Chapter-4  Time value of moneyChapter-4  Time value of money
Chapter-4 Time value of moneyBibek Paudyal
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3bAbdulaziz AlSuwaidi
 
Evaluating a Single Project
Evaluating a Single ProjectEvaluating a Single Project
Evaluating a Single ProjectNafis Ahmad
 
Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]Mohsin Siddique
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
Annuities and gradient
Annuities and gradientAnnuities and gradient
Annuities and gradientReyman Solas
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflationBich Lien Pham
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
5 more interest formulas
5 more interest formulas5 more interest formulas
5 more interest formulasMohsin Siddique
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering EconomyAmeen San
 
Simple and Compound Interest
Simple and Compound InterestSimple and Compound Interest
Simple and Compound InterestHector Tibo
 
Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)Syed Muhammad Bilal
 

What's hot (20)

Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 
Chapter-4 Time value of money
Chapter-4  Time value of moneyChapter-4  Time value of money
Chapter-4 Time value of money
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
 
Evaluating a Single Project
Evaluating a Single ProjectEvaluating a Single Project
Evaluating a Single Project
 
Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]Engineering Economics: Solved exam problems [ch1-ch4]
Engineering Economics: Solved exam problems [ch1-ch4]
 
Introduction to engineering economy
Introduction to engineering economyIntroduction to engineering economy
Introduction to engineering economy
 
Chapter 5
Chapter 5Chapter 5
Chapter 5
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Annuities and gradient
Annuities and gradientAnnuities and gradient
Annuities and gradient
 
The 7 principles of Engineering Economy
The 7 principles of Engineering EconomyThe 7 principles of Engineering Economy
The 7 principles of Engineering Economy
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflation
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
5 more interest formulas
5 more interest formulas5 more interest formulas
5 more interest formulas
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Cost Estimation
Cost EstimationCost Estimation
Cost Estimation
 
Simple and Compound Interest
Simple and Compound InterestSimple and Compound Interest
Simple and Compound Interest
 
Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)Interest Formulae (Gradient Series)
Interest Formulae (Gradient Series)
 

Viewers also liked

UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.pptAsha A
 
Therequiv
TherequivTherequiv
Therequivcqpate
 
MG 6863 Unit III cash flow
MG 6863 Unit III cash flowMG 6863 Unit III cash flow
MG 6863 Unit III cash flowAsha A
 
4. annual dan gradien value
4. annual dan gradien value4. annual dan gradien value
4. annual dan gradien valuekusmira
 
Importance of engineering economics
Importance of engineering economicsImportance of engineering economics
Importance of engineering economicssohail_azhar
 
Intro to engineering economy
Intro to engineering economyIntro to engineering economy
Intro to engineering economyKwesi Kissiedu
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Akhil Sabu
 

Viewers also liked (8)

UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.ppt
 
Therequiv
TherequivTherequiv
Therequiv
 
MG 6863 Unit III cash flow
MG 6863 Unit III cash flowMG 6863 Unit III cash flow
MG 6863 Unit III cash flow
 
Factors and their use
Factors and their useFactors and their use
Factors and their use
 
4. annual dan gradien value
4. annual dan gradien value4. annual dan gradien value
4. annual dan gradien value
 
Importance of engineering economics
Importance of engineering economicsImportance of engineering economics
Importance of engineering economics
 
Intro to engineering economy
Intro to engineering economyIntro to engineering economy
Intro to engineering economy
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
 

Similar to 7.1 present worth method

Eit orginal
Eit orginalEit orginal
Eit orginalanamsini
 
Eit orginal
Eit orginalEit orginal
Eit orginalanamsini
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysisMohsin Siddique
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01abidiqbal55
 
Systematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysisSystematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysisNaganna Chetty
 
Replacement Analysis Economic Life.pptx.
Replacement Analysis Economic Life.pptx.Replacement Analysis Economic Life.pptx.
Replacement Analysis Economic Life.pptx.Athar739197
 
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.pptLeland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.pptssuser1ba731
 
Chapter 2 full slides to students
Chapter 2   full slides to studentsChapter 2   full slides to students
Chapter 2 full slides to studentsSaad Ul Fataah
 
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.pptLeland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.pptssuser1ba731
 
ISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptgadha13
 
Chapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdfChapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdf18010YeashRahman
 
REPLACEMENT DECISIONS.ppt
REPLACEMENT   DECISIONS.pptREPLACEMENT   DECISIONS.ppt
REPLACEMENT DECISIONS.pptJeanClaudeEid1
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 

Similar to 7.1 present worth method (20)

Chap6
Chap6Chap6
Chap6
 
theoty x and y
theoty x and ytheoty x and y
theoty x and y
 
Replacement Theory. by Dr. Babasaheb. J. Mohite
Replacement Theory. by  Dr. Babasaheb. J. MohiteReplacement Theory. by  Dr. Babasaheb. J. Mohite
Replacement Theory. by Dr. Babasaheb. J. Mohite
 
Eit orginal
Eit orginalEit orginal
Eit orginal
 
Eit orginal
Eit orginalEit orginal
Eit orginal
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysis
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01
 
Chap. 6.pptx
Chap. 6.pptxChap. 6.pptx
Chap. 6.pptx
 
Unit 3 ppt
Unit 3 pptUnit 3 ppt
Unit 3 ppt
 
Systematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysisSystematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysis
 
replacement model problems.pptx
replacement model problems.pptxreplacement model problems.pptx
replacement model problems.pptx
 
Replacement Analysis Economic Life.pptx.
Replacement Analysis Economic Life.pptx.Replacement Analysis Economic Life.pptx.
Replacement Analysis Economic Life.pptx.
 
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.pptLeland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
 
OR 14 15-unit_3
OR 14 15-unit_3OR 14 15-unit_3
OR 14 15-unit_3
 
Chapter 2 full slides to students
Chapter 2   full slides to studentsChapter 2   full slides to students
Chapter 2 full slides to students
 
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.pptLeland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
 
ISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.ppt
 
Chapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdfChapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdf
 
REPLACEMENT DECISIONS.ppt
REPLACEMENT   DECISIONS.pptREPLACEMENT   DECISIONS.ppt
REPLACEMENT DECISIONS.ppt
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 

More from Ali Juma Albahrani (19)

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return method
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
 
6.4 multiple factors
6.4 multiple factors6.4 multiple factors
6.4 multiple factors
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tables
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interest
 
5.3 estimate setup
5.3 estimate setup5.3 estimate setup
5.3 estimate setup
 
5.2 unit pricing
5.2 unit pricing5.2 unit pricing
5.2 unit pricing
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
5.0 detailed estimating
5.0 detailed estimating5.0 detailed estimating
5.0 detailed estimating
 
4.3 assemblies estimating
4.3 assemblies estimating4.3 assemblies estimating
4.3 assemblies estimating
 
4.2 square foot estimating
4.2 square foot estimating4.2 square foot estimating
4.2 square foot estimating
 
4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimates
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerations
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 

Recently uploaded

Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxnuruddin69
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...Health
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfsmsksolar
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stageAbc194748
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 

Recently uploaded (20)

Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 

7.1 present worth method

  • 1. Building Economy ARE 431 Dr. Mohammad A. Hassanain 1 1 Life Cycle Costing Present worth method: In this case, all costs or savings (cash flows) which occur during the life time of an investment are discounted to present value of money. P n-120 1 3 n-2 n F n Fn = P(1 + i)n or P = Fn 1 (1 + i)n 2 Life Cycle Costing Present worth method: P n-120 1 3 n-2 n F n An alterative method, instead of using the F and P formulas, is to use interest tables with the following notations: (F/P, i%, n) Find F given P (P/F, i%, n) Find P given F
  • 2. Building Economy ARE 431 Dr. Mohammad A. Hassanain 2 3 Life Cycle Costing Example: Make a present-worth comparison of the equal-service life projects for which costs are shown below, if i = 10%. Which project would you select? 55Project service life (years) $350,000$200,000Salvage value, F $700,000$900,000Annual operating cost, A $3,500,000$2,500,000First cost, P Project BProject A Present Worth Comparison of Equal-Lived Alternatives 4 Life Cycle Costing A = $900,000 42 0 1 3 5 i = 10% $2,500,000 $200,000 Project A A = $700,000 42 0 1 3 5 i = 10% $3,500,000 $350,000 Project B PA = $2,500,000 + $900,000 (P/A, 10%, 5) - $200,000 (P/F, 10%, 5) = $5,788,000 PB = $3,500,000 + $700,000 (P/A, 10%, 5) - $350,000 (P/F, 10%, 5) = $5,936,000 Project A should be selected since PA < PB
  • 3. Building Economy ARE 431 Dr. Mohammad A. Hassanain 3 5 Life Cycle Costing Example: Two machines are under consideration for a carpentry workshop. Machine A will have a first cost of $5,000, an annual operation and maintenance cost of $300, and a $1,200 salvage value. Machine B will have a first cost of $7,000, an annual operation and maintenance cost of $200, and a $1,300 salvage value. If both machines are expected to last for ten years, determine which machine should be selected on the basis of their present- worth values using an interest rate of 10%. 1010Service life (years), n $1,300$1,200Salvage value, F $200$300Operation and Maintenance cost, A $7,000$5,000First cost, P Machine BMachine A Present Worth Comparison of Equal-Lived Alternatives 6 Life Cycle Costing Example: Make a present-worth comparison of the different-service life machines for which costs are shown below, if i = 15%. Which machine would you select? 96Service life (years) $2,000$1,000Salvage value $3,100$3,500Annual operating cost $18,000$11,000First cost Machine BMachine A Present Worth Comparison of Different-Lived Alternatives The cash flow for one cycle of an alternative must be duplicated for the least common multiple of years, so that service life is compared over the total life for each alternative.
  • 4. Building Economy ARE 431 Dr. Mohammad A. Hassanain 4 7 Life Cycle Costing Since the machines have different lives, they must be compared Over the least common multiple of years, which is 18 years. A = $3,500 42 0 1 3 5 7 8 9 10 11 13 $11,000 14 15 16 17 $1,000 $1,000 $1,000 18 $11,000 $11,000 Machine A A = $3,100 42 0 1 3 5 7 8 10 11 13 $18,000 14 15 16 17 $2,000 $2,000 18 Machine B 6 12 $18,000 8 Life Cycle Costing PA = $11,000 + $11,000 (P/F, 15%, 6) + $11,000 (P/F, 15%, 12) + $3,500 (P/A, 15%, 18) - $1,000 (P/F, 15%, 6) - $1,000 (P/F, 15%, 12) - PB = $18,000 + $18,000 (P/F, 15%, 9) + $3,100 (P/A, 15%, 18) - = $41,384 Machine A should be selected since PA < PB $1,000 (P/F, 15%, 18) = $38,559 $2,000 (P/F, 15%, 9) - $2,000 (P/F, 15%, 18)
  • 5. Building Economy ARE 431 Dr. Mohammad A. Hassanain 5 9 Life Cycle Costing Example: A company is trying to decide between two different garbage disposals. A regular (RS) disposal has an initial cost of $65 and a life of 4 years. The alternative is a corrosion-resistant disposal constructed of stainless steel (SS). The initial cost of the SS disposal is $110, but it is expected to last 10 years. The SS disposal is expected to cost $5 per year more than the RS disposal. If the interest rate is 6%, which disposal should be selected, assuming both have no salvage value? 104Service life (years) --Salvage value $5-Additional cost per year $110$65Initial cost SSRS Present Worth Comparison of Different-Lived Alternatives 10 Life Cycle Costing Since the disposals have different lives, they must be compared Over the least common multiple of years, which is 20 years. $65 420 1 3 5 7 8 9 10 11 13 14 15 16 17 18 RS Disposal 19 206 $65 $65$65 $65 12 Extra Cost (A) = $5 42 0 1 3 5 7 8 10 11 13 $110 14 15 16 17 18 SS Disposal 6 12 19 209 $110
  • 6. Building Economy ARE 431 Dr. Mohammad A. Hassanain 6 11 Life Cycle Costing $65 (P/F, 6%, 16) PRS = $65 + $65 (P/F, 6%, 4) + $65 (P/F, 6%, 8) + $65 (P/F, 6%, 12) + PSS = $110 + $110 (P/F, 6%, 10) + $5 (P/A, 6%, 20) = $229 Disposal RS should be selected since PRS < PSS = $215 12 Life Cycle Costing Example: Two machines are under consideration for a carpentry workshop. Machine A will have a first cost of $5,000, an annual operation and maintenance cost of $300, and a $1,200 salvage value. Machine B will have a first cost of $7,000, an annual operation and maintenance cost of $200, and a $1,300 salvage value. If machine A is expected to last for 10 years, while Machine B would last for 15 years, determine which machine should be selected on the basis of their present-worth values using an interest rate of 10%. 1010Service life (years), n $1,300$1,200Salvage value, F $200$300Operation and Maintenance cost, A $7,000$5,000First cost, P Machine BMachine A Present Worth Comparison of Different-Lived Alternatives