AGILE PRODUCT DEVELOPMENT
Because our world is Hybrid…
Shift our language from “Agile Software Development” to
“Agile Product Development” to cover both Software and
Hardware!
!
Some Differences between Hardware & Software
•  Software is easier to change than hardware. !
•  Hardware cannot be “refactored” after
manufacturing !
•  Hardware designs are constrained by the need to
incorporate standard parts!
•  Hardware components have much longer lead
times for acquisition !
•  Hardware design is driven by architectural
decisions. !
…!
Let’s Compare the Development Cycle
Recommended Scrum Process for
HardwareStory Types:
Hard vs. Soft (expect more technical stories)!
!
Sprint Length:
Recommended 2-8 weeks, but keep standard length through development!
!
Release Planning:
non-negotiable !
!
Variation of Sprints during Release Cycle
Beginning: requirements, architecture, silicon selection!
Middle: Repeating sprints of design/build/test!
End: emphasis on scale – build/test!
Agile Benefits Apply to Hardware Too!
Improved visibility, predictability, ability to respond to
changing business needs, Improved ability to
collaborate with software teams using Scrum to
develop associated software!
!
But, does it work?
YES!
We have implemented Agile hardware
development successfully
The Mission: !
Thermo Fisher Scientific, Inc., is a major biotechnology
company that makes a wide variety of analytical and
laboratory products, such as mass spectrometers,
chromatography equipment, and so forth. They were also
our very first Agile Hardware client!!
 !
We narrowed their initial goal to building a product for
analytical chemistry, intended for laboratory and medical
use.!
!
The Plan:
 !
Week 1:
Scrum Training, Write high-level requirements (Epics)!
!
Week 2:
Draft Release Plan, including estimates for all Epics, Write
User and Technical Stories to prepare for Sprint 1!
!
Week 3 (first week of Sprint 1):
Sprint Planning, Develop and test deliverables!
!
Week 4 (second week of Sprint 1):
Develop and test deliverables!
!
The Result:
This is what their FIRST week’s Burndown Chart looked like!
The second and third sprints built on the lessons learned
over time, and the Team continued to improve.
Quote from Product Owner, Dr. Bedford
“First and foremost, running this project with Scrum is an ongoing
success. The team has formed nicely and we have proper buy-in from
each team member. I make technical decisions with more input from
the team than any other project that I have worked on. Grooming is a
hassle because it takes so much time and requires us to stop doing
and think, but the drawbacks I mention are also the clear benefits. We
take time to plan. And we plan together. The daily standup is a life
saver. As is the board. I can quickly understand where we are and
what needs to be done. Release planning has been beneficial
because it really focused the team onto what our big goals are as
opposed to smaller engineering goals. I feel that management here in
San Jose is excited about Scrum. I have had many of the bosses and
decision makers stop by and ask about the process. I am curious to
see if another team pops up in the near future.”!
LESSONS LEARNED
From Agile Hardware Development
Lesson #1: Product Owner as Team Member
 !
The people who would
most commonly lead
the definition of a
product, as Product
Owner, are likely to
participate as Team
members as well. This
was indeed the case at
Thermo Fisher.!
!
Lesson #3: User-Experience Information may not
Lead to many User Stories
Each user experience can be considered atomically, and
adding many of them adds code to all layers of the product.!
!
The problem is not that
writing requirements for
hardware is inherently
more difficult than writing
requirements for
software. !
Lesson #3: Writing Hardware Requirements is
Difficult to Learn
Lesson #4: Much is Behind the Scenes, Not
much is in Front
Few of the deliverables for Trailblazer reflected any meaningful user
experience, while most were behind the scenes. In Scrum language, there
were lots of Technical Stories, and relatively few User Stories.
Lesson #5: The Product Owner Writes Few Stories
For Software products, the
Product Owner writes User
Stories, while the Team writes
Technical Stories. These
statements are true for hardware
development as well, but the shift
in Story types means that the
Product Owner wrote a much
smaller number of Stories.
Lesson #6: Stories are Tested by Implementers
The deliverable of a Story generally is tested by the person or people who
developed it because deliverables vary so widely that they are the only ones
who will understand the deliverable.
Lesson #7: Scope Decomposition is Component-
Oriented, not Functionality-Oriented
Greater volume of Technical
Stories over User Stories
reflects the reality that the
natural scope decomposition
is into components, not areas
of functionality.
Lesson #8: Time-Based Estimation is Essential
Time-based units, such as
Person-Days work well. If the
Team cannot develop a
consensus norm of sizing
that is not based on time,
then the concept of relative
sizing, and the use of Story
Points as units, is not
applicable.!
!
Lesson #9: Swarming is Always Good, but Ability
to Swarm is Decreased
Swarming is difficult because it
depends on certain factors. The
scope of the Story must be large
enough for the work to be
decomposed into pieces for
multiple people to work on it. Also,
the skill sets of Team members and
types of work required for the Story
must be such that two or more
people can work on the pieces at
the same time!
!
Lesson #10: Ranking is Important, but not Literally Achievable
In Hardware development, Stories
are can be implemented by only
one person on the Team. Thus
more Stories are likely to be in
process at any one, and
unforeseen issues or disruptions
are more likely to cause some
Stories that have been started to
not complete in the Sprint. !
Lesson #11: Velocity Matters, but is not Definitive
Velocity is less definitive as a planning tool in Hardware development. Stories
are often one-person exercises, so we must pay much closer attention to how
loaded each person on the Team is. It is easy to select a Sprint Backlog that
satisfies the Velocity limit, but which overloads some people and leaves others
idle. !
 !

Understanding Agile Hardware

  • 1.
  • 2.
    Because our worldis Hybrid… Shift our language from “Agile Software Development” to “Agile Product Development” to cover both Software and Hardware! !
  • 3.
    Some Differences betweenHardware & Software •  Software is easier to change than hardware. ! •  Hardware cannot be “refactored” after manufacturing ! •  Hardware designs are constrained by the need to incorporate standard parts! •  Hardware components have much longer lead times for acquisition ! •  Hardware design is driven by architectural decisions. ! …!
  • 4.
    Let’s Compare theDevelopment Cycle
  • 5.
    Recommended Scrum Processfor HardwareStory Types: Hard vs. Soft (expect more technical stories)! ! Sprint Length: Recommended 2-8 weeks, but keep standard length through development! ! Release Planning: non-negotiable ! ! Variation of Sprints during Release Cycle Beginning: requirements, architecture, silicon selection! Middle: Repeating sprints of design/build/test! End: emphasis on scale – build/test!
  • 6.
    Agile Benefits Applyto Hardware Too! Improved visibility, predictability, ability to respond to changing business needs, Improved ability to collaborate with software teams using Scrum to develop associated software! !
  • 7.
  • 8.
    YES! We have implementedAgile hardware development successfully
  • 9.
    The Mission: ! Thermo FisherScientific, Inc., is a major biotechnology company that makes a wide variety of analytical and laboratory products, such as mass spectrometers, chromatography equipment, and so forth. They were also our very first Agile Hardware client!!  ! We narrowed their initial goal to building a product for analytical chemistry, intended for laboratory and medical use.! !
  • 10.
    The Plan:  ! Week 1: ScrumTraining, Write high-level requirements (Epics)! ! Week 2: Draft Release Plan, including estimates for all Epics, Write User and Technical Stories to prepare for Sprint 1! ! Week 3 (first week of Sprint 1): Sprint Planning, Develop and test deliverables! ! Week 4 (second week of Sprint 1): Develop and test deliverables! !
  • 11.
    The Result: This iswhat their FIRST week’s Burndown Chart looked like!
  • 12.
    The second andthird sprints built on the lessons learned over time, and the Team continued to improve.
  • 13.
    Quote from ProductOwner, Dr. Bedford “First and foremost, running this project with Scrum is an ongoing success. The team has formed nicely and we have proper buy-in from each team member. I make technical decisions with more input from the team than any other project that I have worked on. Grooming is a hassle because it takes so much time and requires us to stop doing and think, but the drawbacks I mention are also the clear benefits. We take time to plan. And we plan together. The daily standup is a life saver. As is the board. I can quickly understand where we are and what needs to be done. Release planning has been beneficial because it really focused the team onto what our big goals are as opposed to smaller engineering goals. I feel that management here in San Jose is excited about Scrum. I have had many of the bosses and decision makers stop by and ask about the process. I am curious to see if another team pops up in the near future.”!
  • 14.
    LESSONS LEARNED From AgileHardware Development
  • 15.
    Lesson #1: ProductOwner as Team Member  ! The people who would most commonly lead the definition of a product, as Product Owner, are likely to participate as Team members as well. This was indeed the case at Thermo Fisher.! !
  • 16.
    Lesson #3: User-ExperienceInformation may not Lead to many User Stories Each user experience can be considered atomically, and adding many of them adds code to all layers of the product.! !
  • 17.
    The problem isnot that writing requirements for hardware is inherently more difficult than writing requirements for software. ! Lesson #3: Writing Hardware Requirements is Difficult to Learn
  • 18.
    Lesson #4: Muchis Behind the Scenes, Not much is in Front Few of the deliverables for Trailblazer reflected any meaningful user experience, while most were behind the scenes. In Scrum language, there were lots of Technical Stories, and relatively few User Stories.
  • 19.
    Lesson #5: TheProduct Owner Writes Few Stories For Software products, the Product Owner writes User Stories, while the Team writes Technical Stories. These statements are true for hardware development as well, but the shift in Story types means that the Product Owner wrote a much smaller number of Stories.
  • 20.
    Lesson #6: Storiesare Tested by Implementers The deliverable of a Story generally is tested by the person or people who developed it because deliverables vary so widely that they are the only ones who will understand the deliverable.
  • 21.
    Lesson #7: ScopeDecomposition is Component- Oriented, not Functionality-Oriented Greater volume of Technical Stories over User Stories reflects the reality that the natural scope decomposition is into components, not areas of functionality.
  • 22.
    Lesson #8: Time-BasedEstimation is Essential Time-based units, such as Person-Days work well. If the Team cannot develop a consensus norm of sizing that is not based on time, then the concept of relative sizing, and the use of Story Points as units, is not applicable.! !
  • 23.
    Lesson #9: Swarmingis Always Good, but Ability to Swarm is Decreased Swarming is difficult because it depends on certain factors. The scope of the Story must be large enough for the work to be decomposed into pieces for multiple people to work on it. Also, the skill sets of Team members and types of work required for the Story must be such that two or more people can work on the pieces at the same time! !
  • 24.
    Lesson #10: Rankingis Important, but not Literally Achievable In Hardware development, Stories are can be implemented by only one person on the Team. Thus more Stories are likely to be in process at any one, and unforeseen issues or disruptions are more likely to cause some Stories that have been started to not complete in the Sprint. !
  • 25.
    Lesson #11: VelocityMatters, but is not Definitive Velocity is less definitive as a planning tool in Hardware development. Stories are often one-person exercises, so we must pay much closer attention to how loaded each person on the Team is. It is easy to select a Sprint Backlog that satisfies the Velocity limit, but which overloads some people and leaves others idle. !  !