SlideShare a Scribd company logo
Angelo Baggini, angelo.baggini@unibg.it, Bergamo University - Engineering Department
Via Marconi 5, 24044 Dalmine (BG) – Italy
Failure analysis of a dry type cast resin MV/LV transformer
Failure analysis
of a dry type cast resin MV/LV
transformer
1. Introduction
2. Chronological events
3. Visual inspection
4. Causes of failures
5. Conclusions
Power Transformers Design Principles
INTRODUCTION
Installation Site and other
• Where: Office building of
a bank group - Milan city
center (Italy)
• When: following planned
maintenance works that
required the whole
installation to be turned
off
• Consequence: half the
building being without
power for 2 days
Electrical layout
Main characteristics of the transformer
Power Transformers Design Principles
CHRONOLOGICAL EVENTS
Chronological events
from 7.30 am to 9.30 am July 14th 2008
Main chronological events
#1
Q6 to Q21 were opened
to prepare for the
permanent disconnection
of some LV cables
Main chronological events
#2
The two main LV
switches (Q1 and Q3)
were opened
Main chronological events
#3
The back panels of the
main LV distribution
board are opened in
order to carry out the
disconnection
operations.
Main chronological events
#4
The lines are
disconnected and the
terminals of cables are
extracted
Main chronological events
#5
Once the disconnection
is completed the network
is restored
The main LV switch of
the transformer 2 (Q3) is
closed while Q6 to Q21
remain open.
Main chronological events
#6
The on site maintenance
personnel perceive a
buzzing (“frying”) noise
and two blows in fast
sequence.
Main chronological events
#7
The two MV switches of
the transformer (Q4 and
Q5) trip, while the main
MV switch (Q2) does not
trip
Main chronological events
#8 and #9
In order to understand
which transformer was
out of order, the
technicians on site try to
rearm the MV switch of
the transformer 2 (Q5).
Once (Q5) is closed the
main MV switch (Q2)
trips immediately, but not
the main MV switch of
the electrical company
(ENEL).
Main chronological events
#10 to #11
The MV switch is
restored (Q2).
The transformer 1 is put
into service, by closing
Q4, without any problem.
Main chronological events
#12 to #13
The enclosure of
transformer 2 is opened,
following prescribed
procedures.
Technicians on site
found considerable
damage to phase W of
transformer 2
Failure analysis
of a dry type cast resin MV/LV
transformer
VISUAL INSPECTION
Visual inspection
W and U windings:
black smoke traces.
Visual inspection
MV-LV channel:
electric arc traces
Visual inspection Lower part of LV-MV channel:
overheating traces
Visual inspection
Parts of winding
below the lower part
of winding W
Failure analysis
of a dry type cast resin MV/LV
transformer
CAUSES OF FAILURE
LV Windings
Sheet (or slab) type
• The windings were constituted by
thin Cu sheet with height almost
equal to the height of the column
• radially wounded coils were
separated by insulating sheets
MV Windings
Cast resin section type
Coils axially separated by insulating
spacers
Causes of failures
• consequence of a low number of coils inside the MV winding is an
high layer voltage
• partial discharges have damaged the insulation of the MV windings
and accelerated its breakdown
• The overvoltage, associated with the reconnection of the transformer at
the end of the maintenance operation, was sufficient to trigger a
breakdown through the weakened insulation
• the earlier failure of the same transformer supports the conclusion.
Causes of failures
• the discharge between the LV and MV windings was not the primary cause of
failure as the air insulation gap (channel MV/LV) was sufficiently large to
withstand the most severe overvoltage to which the transformer could
reasonably have been expected to be exposed;
• the structure of the network and the peak values of the impulse which the
transformer has been designed to withstand indicate that the transformer
would not have been affected by the over-voltage if the insulation system had
not been previously damaged;
• degradation of the insulating system by over-stressing, such as that assumed
here in order to explain the failure does not enable the prediction of the time of
the inevitable dielectric failure
• a degraded transformer could remain in service under these conditions for as
long as several years or for just a few months. What is certain is that failure
will occur.
Failure analysis
of a dry type cast resin MV/LV
transformer
CONCLUSIONS
Conclusions
• To agree with the transformer manufacturer that all MV windings and
the failed LV winding would be replaced. Taking into account the fact
that the fault is a result of a construction defect, even though it
became apparent some years into service life and considering the age
of the transformer, the costs should be shared accordingly between
supplier and customer.
• During dismantling of the transformer the conditions of the other
windings (not currently inspected) should be checked, with particular
attention to the central phase which may have been partially affected
by the fault on phase W.
• This solution would result in a practically new transformer at a modest
cost.
Additional conclusions
• To avoid the risk of a repetition of the same problem, it would be wise to
evaluate the possibility of replacing all the MV windings of the other
transformer (T1), since it is based on the same electromagnetic design. Of
course, even in this case the benefits are the same as indicated for the unit
currently out of service.
• The electrical layout should be modified to avoid the situation of having half the
building out of service in the event of a single fault. This could be achieved by
adopting a double radial scheme or by providing the ability to feed both LV
busbars from a single transformer (at reduced total load or increasing the
capacity of each transformer).
Failure analysis
of a dry type cast resin MV/LV
transformer
1. Introduction
2. Chronological events
3. Visual inspection
4. Causes of failures
5. Conclusions
Thank you
| Presentation title and date
For more information please contact
Angelo Baggini
Università di Bergamo
Dipartimento di Ingegneria
Viale Marconi 5,
24044 Dalmine (BG) Italy
email: angelo.baggini@unibg.it
ECD Engineering Consulting and Design
Via Maffi 21 27100 PAVIA Italy

More Related Content

What's hot

Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit current
Leonardo ENERGY
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
Rohit Dave
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_final
Snehangshu Ghosh
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
ajayknows
 

What's hot (20)

Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit current
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
 
Power transformer losses
Power transformer lossesPower transformer losses
Power transformer losses
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitPRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_final
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 

Similar to Transformer failure case study

Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Low
 
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and UmbilicalsReel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
wevans1
 

Similar to Transformer failure case study (20)

Example of Substation Maintenance & Assessment Audits for Training - Niels In...
Example of Substation Maintenance & Assessment Audits for Training - Niels In...Example of Substation Maintenance & Assessment Audits for Training - Niels In...
Example of Substation Maintenance & Assessment Audits for Training - Niels In...
 
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by NielsEquipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses report
 
Thermoelectricity
ThermoelectricityThermoelectricity
Thermoelectricity
 
G04714245
G04714245G04714245
G04714245
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
 
Heavy maintenance
Heavy maintenanceHeavy maintenance
Heavy maintenance
 
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankur
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Circuit breakers
Circuit breakersCircuit breakers
Circuit breakers
 
Executive summary
Executive summaryExecutive summary
Executive summary
 
TRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptxTRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptx
 
Electrical Installations, MCB, MCCB, ELCB
Electrical Installations, MCB, MCCB, ELCBElectrical Installations, MCB, MCCB, ELCB
Electrical Installations, MCB, MCCB, ELCB
 
Art%20 e sierra%20etp%20mantenimiento
Art%20 e sierra%20etp%20mantenimientoArt%20 e sierra%20etp%20mantenimiento
Art%20 e sierra%20etp%20mantenimiento
 
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and UmbilicalsReel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
 
Design_of_Power_Transformers.ppt
Design_of_Power_Transformers.pptDesign_of_Power_Transformers.ppt
Design_of_Power_Transformers.ppt
 
MV Switchgear from IEEE
MV Switchgear from IEEEMV Switchgear from IEEE
MV Switchgear from IEEE
 
Entership Presentation (1).pptx
Entership Presentation (1).pptxEntership Presentation (1).pptx
Entership Presentation (1).pptx
 
switching & control devices
switching & control devicesswitching & control devices
switching & control devices
 

More from Leonardo ENERGY

More from Leonardo ENERGY (20)

A new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performanceA new generation of instruments and tools to monitor buildings performance
A new generation of instruments and tools to monitor buildings performance
 
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...Addressing the Energy Efficiency First Principle in a National Energy and Cli...
Addressing the Energy Efficiency First Principle in a National Energy and Cli...
 
Auctions for energy efficiency and the experience of renewables
 Auctions for energy efficiency and the experience of renewables Auctions for energy efficiency and the experience of renewables
Auctions for energy efficiency and the experience of renewables
 
Energy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock finalEnergy efficiency first – retrofitting the building stock final
Energy efficiency first – retrofitting the building stock final
 
How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects How auction design affects the financing of renewable energy projects
How auction design affects the financing of renewable energy projects
 
Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)Energy Efficiency Funds in Europe (updated)
Energy Efficiency Funds in Europe (updated)
 
Energy Efficiency Funds in Europe
Energy Efficiency Funds in EuropeEnergy Efficiency Funds in Europe
Energy Efficiency Funds in Europe
 
Five actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculationsFive actions fit for 55: streamlining energy savings calculations
Five actions fit for 55: streamlining energy savings calculations
 
Recent energy efficiency trends in the EU
Recent energy efficiency trends in the EURecent energy efficiency trends in the EU
Recent energy efficiency trends in the EU
 
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
Energy and mobility poverty: Will the Social Climate Fund be enough to delive...
 
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
Does the EU Emission Trading Scheme ETS Promote Energy Efficiency?
 
Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...Energy efficiency, structural change and energy savings in the manufacturing ...
Energy efficiency, structural change and energy savings in the manufacturing ...
 
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
Energy Sufficiency Indicators and Policies (Lea Gynther, Motiva)
 
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
The Super-efficient Equipment and Appliance Deployment (SEAD) Initiative Prod...
 
Modelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windingsModelling and optimisation of electric motors with hairpin windings
Modelling and optimisation of electric motors with hairpin windings
 
Casting zero porosity rotors
Casting zero porosity rotorsCasting zero porosity rotors
Casting zero porosity rotors
 
Direct coil cooling through hollow wire
Direct coil cooling through hollow wireDirect coil cooling through hollow wire
Direct coil cooling through hollow wire
 
Motor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member StatesMotor renovation - Potential savings and views from various EU Member States
Motor renovation - Potential savings and views from various EU Member States
 
The need for an updated European Motor Study - key findings from the 2021 US...
The need for  an updated European Motor Study - key findings from the 2021 US...The need for  an updated European Motor Study - key findings from the 2021 US...
The need for an updated European Motor Study - key findings from the 2021 US...
 
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
Efficient motor systems for a Net Zero world, by Conrad U. Brunner - Impact E...
 

Recently uploaded

Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Peter Udo Diehl
 

Recently uploaded (20)

The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
 
НАДІЯ ФЕДЮШКО БАЦ «Професійне зростання QA спеціаліста»
НАДІЯ ФЕДЮШКО БАЦ  «Професійне зростання QA спеціаліста»НАДІЯ ФЕДЮШКО БАЦ  «Професійне зростання QA спеціаліста»
НАДІЯ ФЕДЮШКО БАЦ «Професійне зростання QA спеціаліста»
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Quantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIsQuantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIs
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
UiPath New York Community Day in-person event
UiPath New York Community Day in-person eventUiPath New York Community Day in-person event
UiPath New York Community Day in-person event
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 

Transformer failure case study

  • 1. Angelo Baggini, angelo.baggini@unibg.it, Bergamo University - Engineering Department Via Marconi 5, 24044 Dalmine (BG) – Italy Failure analysis of a dry type cast resin MV/LV transformer
  • 2. Failure analysis of a dry type cast resin MV/LV transformer 1. Introduction 2. Chronological events 3. Visual inspection 4. Causes of failures 5. Conclusions
  • 3. Power Transformers Design Principles INTRODUCTION
  • 4. Installation Site and other • Where: Office building of a bank group - Milan city center (Italy) • When: following planned maintenance works that required the whole installation to be turned off • Consequence: half the building being without power for 2 days
  • 6. Main characteristics of the transformer
  • 7. Power Transformers Design Principles CHRONOLOGICAL EVENTS
  • 8. Chronological events from 7.30 am to 9.30 am July 14th 2008
  • 9. Main chronological events #1 Q6 to Q21 were opened to prepare for the permanent disconnection of some LV cables
  • 10. Main chronological events #2 The two main LV switches (Q1 and Q3) were opened
  • 11. Main chronological events #3 The back panels of the main LV distribution board are opened in order to carry out the disconnection operations.
  • 12. Main chronological events #4 The lines are disconnected and the terminals of cables are extracted
  • 13. Main chronological events #5 Once the disconnection is completed the network is restored The main LV switch of the transformer 2 (Q3) is closed while Q6 to Q21 remain open.
  • 14. Main chronological events #6 The on site maintenance personnel perceive a buzzing (“frying”) noise and two blows in fast sequence.
  • 15. Main chronological events #7 The two MV switches of the transformer (Q4 and Q5) trip, while the main MV switch (Q2) does not trip
  • 16. Main chronological events #8 and #9 In order to understand which transformer was out of order, the technicians on site try to rearm the MV switch of the transformer 2 (Q5). Once (Q5) is closed the main MV switch (Q2) trips immediately, but not the main MV switch of the electrical company (ENEL).
  • 17. Main chronological events #10 to #11 The MV switch is restored (Q2). The transformer 1 is put into service, by closing Q4, without any problem.
  • 18. Main chronological events #12 to #13 The enclosure of transformer 2 is opened, following prescribed procedures. Technicians on site found considerable damage to phase W of transformer 2
  • 19. Failure analysis of a dry type cast resin MV/LV transformer VISUAL INSPECTION
  • 20. Visual inspection W and U windings: black smoke traces.
  • 22. Visual inspection Lower part of LV-MV channel: overheating traces
  • 23. Visual inspection Parts of winding below the lower part of winding W
  • 24. Failure analysis of a dry type cast resin MV/LV transformer CAUSES OF FAILURE
  • 25. LV Windings Sheet (or slab) type • The windings were constituted by thin Cu sheet with height almost equal to the height of the column • radially wounded coils were separated by insulating sheets
  • 26. MV Windings Cast resin section type Coils axially separated by insulating spacers
  • 27. Causes of failures • consequence of a low number of coils inside the MV winding is an high layer voltage • partial discharges have damaged the insulation of the MV windings and accelerated its breakdown • The overvoltage, associated with the reconnection of the transformer at the end of the maintenance operation, was sufficient to trigger a breakdown through the weakened insulation • the earlier failure of the same transformer supports the conclusion.
  • 28. Causes of failures • the discharge between the LV and MV windings was not the primary cause of failure as the air insulation gap (channel MV/LV) was sufficiently large to withstand the most severe overvoltage to which the transformer could reasonably have been expected to be exposed; • the structure of the network and the peak values of the impulse which the transformer has been designed to withstand indicate that the transformer would not have been affected by the over-voltage if the insulation system had not been previously damaged; • degradation of the insulating system by over-stressing, such as that assumed here in order to explain the failure does not enable the prediction of the time of the inevitable dielectric failure • a degraded transformer could remain in service under these conditions for as long as several years or for just a few months. What is certain is that failure will occur.
  • 29. Failure analysis of a dry type cast resin MV/LV transformer CONCLUSIONS
  • 30. Conclusions • To agree with the transformer manufacturer that all MV windings and the failed LV winding would be replaced. Taking into account the fact that the fault is a result of a construction defect, even though it became apparent some years into service life and considering the age of the transformer, the costs should be shared accordingly between supplier and customer. • During dismantling of the transformer the conditions of the other windings (not currently inspected) should be checked, with particular attention to the central phase which may have been partially affected by the fault on phase W. • This solution would result in a practically new transformer at a modest cost.
  • 31. Additional conclusions • To avoid the risk of a repetition of the same problem, it would be wise to evaluate the possibility of replacing all the MV windings of the other transformer (T1), since it is based on the same electromagnetic design. Of course, even in this case the benefits are the same as indicated for the unit currently out of service. • The electrical layout should be modified to avoid the situation of having half the building out of service in the event of a single fault. This could be achieved by adopting a double radial scheme or by providing the ability to feed both LV busbars from a single transformer (at reduced total load or increasing the capacity of each transformer).
  • 32. Failure analysis of a dry type cast resin MV/LV transformer 1. Introduction 2. Chronological events 3. Visual inspection 4. Causes of failures 5. Conclusions
  • 33. Thank you | Presentation title and date For more information please contact Angelo Baggini Università di Bergamo Dipartimento di Ingegneria Viale Marconi 5, 24044 Dalmine (BG) Italy email: angelo.baggini@unibg.it ECD Engineering Consulting and Design Via Maffi 21 27100 PAVIA Italy