SlideShare a Scribd company logo
1 INTRODUCTION
The driven cast in-situ (DCIS) piling method has
been in use for many decades and has over this peri-
od demonstrated its effectiveness and efficiency.
Examples of more recently completed large struc-
tures supported on DCIS piles installed by Keller in
the UK include the O2 Arena (constructed within the
Millennium Dome – itself supported in DCIS piles)
and the London 2012 Olympic stadium.
The body of published literature relating to the
design of DCIS piling is not large. Neely (1991) cre-
ated a database of load tests on DCIS piles with ex-
panded bases and developed correlations for design.
Evers et al (2003) provided a useful study for the
performance of DCIS piles compared to CFA piles
at a site in France and Flynn et al (2012) present a
case study for the performance of a DCIS test pile at
a site in London.
Development of a complete theoretical model for
the design of DCIS piles is complicated by the very
significant disruption in soil structure and insitu
stress regime caused by the installation process.
Even the selection of appropriate soil parameters for
use in design equations from ground investigation
tests is problematic due to the state changes occur-
ring during pile installation.
Even though much research effort is expended on
complex numerical modeling and reduced scale la-
boratory or centrifuge modeling there remains the
difficulty of translating the knowledge gained into
practical prediction tools appropriate for routine de-
sign and installation of the full size product in the
field. This paper considers a method to estimate
DCIS geotechnical capacity based on installation pa-
rameters measured during the installation of a pile
by modern instrumented piling rigs.
2 MODERN DCIS PILING EXECUTION
In recent times advances in piling rig instrumen-
tation and telecommunications have enabled a new
level of sophistication in the recording of installation
parameters and this opens up the potential of as-
sessing pile capacity in real time.
DCIS design using a static design approach,
based on ground parameters derived from boreholes
and laboratory testing has for many years been the
approach used to estimate ultimate pile capacity, but,
as noted above, this approach has its difficulties. At
the start of execution of piling, trial drives, are un-
dertaken to validate the ground conditions are as en-
visaged in the initial design. (Historically with man-
ual counting of the number of hammer blows to
The Load Capacity of Driven Cast In-Situ Piles Derived from Installation
Parameters
D. Egan
Chief Engineer, Keller Foundations
ABSTRACT: The theoretical estimation of the ultimate capacity and serviceability performance of common
displacement foundation systems such driven cast in-situ (DCIS) piles is difficult due to the huge disruption
in soil structure and insitu stress regime caused by the installation process. Even though much research effort
is expended on complex numerical modeling and reduced scale laboratory or centrifuge modeling there re-
mains the difficulty of translating the knowledge gained into practical prediction tools appropriate for routine
design and installation of the full size product in the field. So to advance and validate the conclusions drawn
from numerical and small scale research the third strand of measuring and analysing full size field behaviour
must be added. This paper will summarise recent advances made in the field measurement and analysis of in-
stallation parameters to predict the load capacity of driven cast in-situ piles. The results from installation and
testing of a DCIS pile is used to illustrate the methodology now being routinely by Keller Foundations in the
UK. The conclusions drawn from this paper are already raising the standard of reliability, efficiency and sus-
tainability of DCIS piles on routine projects.
Remedy Geotechnics Ltd
Technical Paper R19
www.remedygeotechnics.com
achieve a given penetration.) The control criteria can
then be set for installation of the production piles.
Where required this can be supplemented with pro-
ject specific static load testing to support and vali-
date the achieved pile load capacity. While this ap-
proach has been used satisfactorily for the
installation of hundreds of thousands of piles over
many decades, modern instrumentation now allows
both robust and detailed control and feedback of the
pile driving process, in real time, for every pile in-
stalled.
On modern instrumented DCIS piling rigs the en-
ergy delivered to each pile can now be measured and
used to validate that pile’s ultimate load capacity. As
the pile is driven the driving parameters (drive ener-
gy, drive tube depth and rate of advancement) are
displayed to the rig driver giving a high degree of
control to the installation process. Additional bene-
fits of an automated electronic data capture system
include a reduction of manual recording and on-site
paperwork (which requires a finite manpower re-
source), robust archiving of records and real time
access to installation data remote from the work site.
From the experience of developing a large data-
base of systematically acquired pile installation data
it has been possible to map the process required to
allow real time assessment of pile capacity. Initially
focused on piles founded in granular soils an empiri-
cal approach has been developed which has been
used to validate, in near real time, the adequacy of
DCIS piles as they are driven. Of course these ad-
vances should be seen in the context of dynamic pile
driving formulae which have been used on pre-
formed piles for many decades. Not withstanding
widespread the use of set calculations for pre-formed
piles, their applicability (and reliability) for driven
cast in-situ piling, where the drive tube is firstly
driven into the ground and then removed and re-
placed by cast in place concrete, is highly questiona-
ble.
The development of real time assessment of
DCIS pile capacity for piles driven into coarse
grained soils is presented in detail below. This
method has been developed over a period of time
and is based on drive data and load test data carried
out on a series of sites. However to better illustrate
the process reference to a single test pile (TP3) in-
stalled at a site in Erith, London is made.
3 DESCRIPTION OF TEST SITE
The test site was located within the Thames basin
to the south of the river at Erith, London. The
ground conditions comprised a mantle of Made
Ground, overlying soft and very soft clay and peat
Alluvium. The piles were founded in coarse grained
River Terrace Deposits (RTD) comprising medium
dense to very dense gravelly sand. Thanet Sand was
found beneath the RTD. Figure 1 shows a typical
bore hole for the site. The Made Ground and Alluvi-
um were not considered as contributing to the pile
geotechnical capacity, but rather a source of poten-
tial negative skin friction, they are ignored in the as-
sessment of ultimate pile capacity for design purpos-
es.
Figure 1 Typical Borehole from the test site.
4 DRIVEN CAST INSITU PILE INSTALLATION
Figure 2 illustrates the pertinent features of the
DCIS system. A steel drive tube, closed at the base
by a sacrificial base plate, is top driven to the re-
quired depth. The steel tube is then charged with a
free flowing concrete and withdrawn from the
ground. Steel reinforcement can be inserted in the
pile bore before or after the concrete is placed. The
requirements for the execution of DCIS piles are set
out in EN 12699 ‘Execution of special geotechnical
works – Displacement piles’. In addition Keller
monitor all aspects of the installation process by on-
board computer, with the key parameters for capaci-
ty assessment being the hammer energy imparted for
each blow, the rate of advancement of the tube per
blow and the tube and base plate geometry. The rec-
Remedy Geotechnics Ltd
Technical Paper R19
www.remedygeotechnics.com
orded data are instantly fed back to the design office
by modem enabling secure backup of the infor-
mation as well as providing the facility for the de-
sign engineer to see feedback on the ground condi-
tions encountered immediately the pile is completed.
5 RECORDED INSTALLATION PARAMETERS
From the recorded parameters the tube drive re-
sistance with depth is calculated, where Ru is the
drive resistance, N is the hammer energy, s is the
rate of tube advancement per hammer blow and c is
the elastic compression of the tube.
!! =
!!!!!
!!
!
!
The factors f1 and f2 are hammer and energy
transfer efficiency factors. The elastic compression
of the drive tube is calculated using the following
equation, which is based on the Danish pile driving
formula, and where N is the hammer energy, L is the
tube length, A is the cross sectional area of the tube
and E the elastic modulus.
! =
2!!!!!"
!"
Figure 3 shows the drive resistance, Ru, plotted
with depth for TP3 and the four associated anchor
piles used for reaction in the subsequent maintained
load test. The piles were DCIS piles of nominal di-
ameter, d, of 340mm with a base plate diameter, db,
of 380mm. TP 3 was driven fractionally over 11.0m
(11.01m) and the anchor piles to 15m.
Figure 2 The DCIS installation process.
The Made Ground and Alluvium proved to be of
very low strength which drive tube easily penetrated
with little energy required. The RTD was encoun-
tered at around 8.25m depth as indicated by a sharp
increase in drive resistance to between 500kN and
700kN as shown in Figure 3. This corresponds to
medium dense to dense gravelly RTD. Below 12m
the anchor piles encountered a further sharp increase
in drive resistance to around 2300kN at 15m, which
is thought to coincide with the top of the Thanet
Sand at this location. The test pile was intentionally
stopped within the medium dense zone so as to en-
sure geotechnical failure during the maintained load
test.
Figure 3 Dynamic drive resistance, Run, plotted with depth.
6 CORRELATION OF PILE INSTALLATION
PARAMETERS WITH SOIL PARAMETERS
The installation of each pile where state of the art
instrumentation is used can be considered as a form
of large scale ground investigation test from which
ground parameters may be derived. Dividing the
drive resistance by the area of the base plate, Ab,
gives the bearing pressure, qpc, at the pile toe.
!!" =
!!
!!
Taking qpc to be analogous to the cone resistance,
qc, obtained by a static cone penetration test a ready
and quick evaluation of the nature of the ground into
which the pile is being driven can be obtained. In
developing the analogy between qpc and CPT qc fac-
tors leading to energy losses within the drive/tube
system such as frictional losses along the drive tube
shaft, rate effects and size effects have all to be con-
sidered.
Field tests using dynamic pile driving analysis
have been undertaken to assess the loss in energy be-
tween the point of impact of the hammer at the top
of the drive tube and the pile base plate.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
0 500 1000 1500 2000 2500 3000
Depth&(m)
Dynamic&Drive&Resistance,& Ru&(kN)
Erith&Test&Pile&3
Ru&Values
340mm&Piles&&Driven&8&9/11/12
PILETEST3 AP18 AP17 AP16
Remedy Geotechnics Ltd
Technical Paper R19
www.remedygeotechnics.com
The ratio of the area of the base plates of different
sizes of DCIS pile and a standard CPT range be-
tween 26 and 6, and taken in the round this is con-
sidered beneficial. One of the characteristics of the
CPT, especially in coarse soils, is the propensity for
the tip resistance to be influenced by larger soil par-
ticles (or localised weaker or softer layers) in the
soil. In contrast the larger diameter of the DCIS base
plates stresses a greater depth of soil leading to
somewhat of lower bound (and safe) smoothing ef-
fect when compared to the CPT qc. Indeed the zone
of soil stressed beneath the pile toe at the end of
driving is exactly that which will be stressed by the
finished pile in the working condition. (This is in the
context of a single pile, where piles are grouped
such that they interact suitable consideration of
group effect must be made in the design.)
Figure 4 Comparison of qc and qpc for TP3.
Figure 4 compares qc from a CPT test undertaken
about 4m from TP3, and pile toe bearing pressure,
qpc, and illustrates the lower bound averaging effect
of qpc compared to the CPT qc values.
Once qpc is derived a correlation with effective
angle of friction, φ’, may be made, for example us-
ing the method shown in Lunne et al (1997).
From the measured drive resistance, Ru, the dy-
namic bearing pressure, qpc, is derived and correlated
to in-situ angle of friction for the gravelly sand
founding stratum. Figure 5 shows the derived angle
of friction over the socket length of TP3 driven into
the RTD.
Figure 5 Angle of friction, φ’, from drive resistance Ru.
7 ESTIMATE OF PILE CAPACITY FROM
INSTALLATION PARAMETERS
The ultimate pile socket capacity, Qult, compris-
ing a shaft component, Qs,ult, and base component,
Qb,ult, may now be derived using standard soil me-
chanics principles, where:-
Q!"# = Q!,!"# +!Q!,!"#
Q!"! = β. σ!
′
. π. d. l +!N!.σ!
′
. A!
The above equation is readily implemented in
commercially available software or spreadsheets.
The program Oasys Pile, using the angles of friction
shown in Figure 5 and the Berezantzev formulation
for the bearing capacity factor, Nq, (Oasys Pile user
manual, 2012) was used to give:-
Q!"#,!"#$%& = 217kN + 1763k = 1980kN
Test Pile 3 was subjected to a maintained extend-
ed proof load test to failure following the procedure
outlined in the ICE Specification for Piling and Em-
bedded Retaining Walls (2007). Figure 6 shows the
load settlement response. A plunging failure of the
pile under an applied load, Qf, of 1947kN and at a
displacement of 45mm was observed.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
30 32 34 36 38 40 42 44 46 48 50
Depth&(m)
Angle&of&Friction&(Deg))
Erith&Test&Pile&3
Derived&Angle&of&Friction&from&
Dynamic&Drive&Resistance&Ru.
Angle1of1friction1from1Ru
0
2
4
6
8
10
12
14
16
18
0 10 20 30 40 50 60
Depth&(m)
qc/qpc&(MPa)
CPT&qc&&&qpc&for&TP3
CPT,qc
qpc
Remedy Geotechnics Ltd
Technical Paper R19
www.remedygeotechnics.com
Figure 6 Load settlement response of Test Pile 3.
In the analysis of the pile test results the tempo-
rary hold up resistance generated over the pile shaft
passing through the made ground and alluvium was
estimated at 80kN, which must be added to Qult,socket
as calculated in Oasys Pile to give the true anticipat-
ed theoretical pile capacity of 2060kN.
Thus the pile under test achieved 94% of its the-
oretical capacity which is considered an excellent
correlation between the calculated capacity and that
shown by the static load test.
The results of the illustration of the installation
and load testing of pile TP3 show that a rational pro-
cedure to assess the ultimate capacity of DCIS piles
located in coarse grained soils based in pile installa-
tion data is available.
8 CONCLUSIONS
Driven cast in-situ piling has proved a popular
and efficient piling method over many decades,
which, in suitable ground conditions, produces piles
of high capacity and efficiency. Recent develop-
ments in rig instrumentation have enabled the rou-
tine and systematic acquisition of high quality instal-
lation records. The benefits of an automated
electronic data capture system include a reduction of
manual recording and on-site paperwork (which re-
quires a finite manpower resource), robust archiving
of records and real time access to installation data
remote from the work site. In addition Keller has
demonstrated the development of a real time valida-
tion method for DCIS piles is viable. A rational link
between the installation parameters, fundamental
soil parameters relevant after pile installation, the
physical mechanisms of load generation and ob-
served load capacity has been established.
These developments in the driven cast in-situ pil-
ing process have lead to improved efficiency (and
hence sustainability) of the DCIS method.
REFERENCES
EN 12699:2001 Execution of special geotechnical
works – Displacement Piles. (2001). BSI. London.
Evers, G., Hass, G., Frossard, A., Bustamante, M.,
Borel, S. & Skinner, H. (2003) Comparative performanc-
es of continuous flight auger and driven cast in place
piles in sands. Deep foundations on bored and auger
piles, Van Imp (ed) Millpress, Rotterdam.
Flynn, K,. McCabe, B.A. & Egan, D (2012) Proceed-
ings 9th
International conference on testing and design
methods for deep foundations, Kanazawa, Japan.
ICE Specification for Piling and Embedded Retaining
Walls (2007) 2nd Ed. ICE. London.
Lune T., Robertson P.K. & Powell, J.J.M (1997)
Cone Penetration testing in geotechnical Practice.
Neely, W.J. (1990) bearing capacity of expanded-base
piles with compacted concrete shafts. Journal of geotech-
nical Engineering, 116(9): 1309-1324
Oasys Pile 19.2 User manual (2012) http://www.oasys-
soft-
ware.com/media/Manuals/Latest_Manuals/Pile19.2_man
ual.pdf.
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
0 5 10 15 20 25 30 35 40 45 50
Load(kN)
Settlement (mm)
Erith Test Pile 3
Maintained Load Settlement
Response
Test Data Elast Shortening
Remedy Geotechnics Ltd
Technical Paper R19
www.remedygeotechnics.com

More Related Content

What's hot

Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Pagkratios Chitas
 
Sellountou evalaución integridad de pilotes
Sellountou   evalaución integridad de pilotesSellountou   evalaución integridad de pilotes
Sellountou evalaución integridad de pilotes
cfpbolivia
 
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles""Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"
Remedy Geotechnics Ltd
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty Ltd
Independent Geoscience
 
Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook920728035348
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
Alaa Metwally
 
Research paper
Research paperResearch paper
Research paper
Ghulam Mehdi
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
cfpbolivia
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
IJERA Editor
 
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
impersal
 
Performance Based Evaluation of Conventional RC Framed Structure Compared wit...
Performance Based Evaluation of Conventional RC Framed Structure Compared wit...Performance Based Evaluation of Conventional RC Framed Structure Compared wit...
Performance Based Evaluation of Conventional RC Framed Structure Compared wit...
IRJET Journal
 
Smart Fractured Reservoir Development Strategies
Smart Fractured Reservoir Development StrategiesSmart Fractured Reservoir Development Strategies
Smart Fractured Reservoir Development Strategies
ITE Oil&Gas
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...Benoit Latapie
 
Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practice
Web2Present
 
What is Pile Integrity Test ?
What is Pile Integrity Test ?What is Pile Integrity Test ?
What is Pile Integrity Test ?
Hamed Layssi, PEng, PhD
 
Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...
Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...
Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...
IRJET Journal
 
Evaluating the use of OpenSees for lifetime seismic performance assessment of...
Evaluating the use of OpenSees for lifetime seismic performance assessment of...Evaluating the use of OpenSees for lifetime seismic performance assessment of...
Evaluating the use of OpenSees for lifetime seismic performance assessment of...
openseesdays
 
Naval Engineering Journal March 2016 DoS Probe Final
Naval Engineering Journal March 2016 DoS Probe FinalNaval Engineering Journal March 2016 DoS Probe Final
Naval Engineering Journal March 2016 DoS Probe FinalRyan Dunn
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 

What's hot (20)

Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
 
Sellountou evalaución integridad de pilotes
Sellountou   evalaución integridad de pilotesSellountou   evalaución integridad de pilotes
Sellountou evalaución integridad de pilotes
 
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles""Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty Ltd
 
Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
 
Research paper
Research paperResearch paper
Research paper
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
 
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
 
Performance Based Evaluation of Conventional RC Framed Structure Compared wit...
Performance Based Evaluation of Conventional RC Framed Structure Compared wit...Performance Based Evaluation of Conventional RC Framed Structure Compared wit...
Performance Based Evaluation of Conventional RC Framed Structure Compared wit...
 
Smart Fractured Reservoir Development Strategies
Smart Fractured Reservoir Development StrategiesSmart Fractured Reservoir Development Strategies
Smart Fractured Reservoir Development Strategies
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
 
Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practice
 
What is Pile Integrity Test ?
What is Pile Integrity Test ?What is Pile Integrity Test ?
What is Pile Integrity Test ?
 
Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...
Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...
Study of Structural Behaviour of Intze Water Tank through an user Friendly Pr...
 
Evaluating the use of OpenSees for lifetime seismic performance assessment of...
Evaluating the use of OpenSees for lifetime seismic performance assessment of...Evaluating the use of OpenSees for lifetime seismic performance assessment of...
Evaluating the use of OpenSees for lifetime seismic performance assessment of...
 
Aashto design
Aashto designAashto design
Aashto design
 
Naval Engineering Journal March 2016 DoS Probe Final
Naval Engineering Journal March 2016 DoS Probe FinalNaval Engineering Journal March 2016 DoS Probe Final
Naval Engineering Journal March 2016 DoS Probe Final
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 

Similar to "The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Parameters"

2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)
Ryan Coggins, P.E.
 
"The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety""The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety"
Remedy Geotechnics Ltd
 
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
IRJET Journal
 
STRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADS
STRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADSSTRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADS
STRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADS
IRJET Journal
 
Numerical simulation and optimization of pile design
Numerical simulation and optimization of pile designNumerical simulation and optimization of pile design
Numerical simulation and optimization of pile design
IRJET Journal
 
OCPW Wintersburg Channel Deep Soil Mixing
OCPW Wintersburg Channel Deep Soil MixingOCPW Wintersburg Channel Deep Soil Mixing
OCPW Wintersburg Channel Deep Soil Mixing
American Society of Civil Engineers, Orange County Branch
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportRajendra Jhurawat
 
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)Paul Brett
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
Miklos Peller, Sr.
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
MailapalliJayaRaju
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
Abhishek Paul
 
A012140107
A012140107A012140107
A012140107
IOSR Journals
 
Large Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof StructureLarge Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof Structure
IOSR Journals
 
Large Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof StructureLarge Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof Structure
IOSR Journals
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
Ramin Vaghei
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
DongyuanWang1
 
Thesis Powerpoint
Thesis PowerpointThesis Powerpoint
Thesis Powerpointneha47
 

Similar to "The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Parameters" (20)

2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)
 
"The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety""The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety"
 
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
 
STRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADS
STRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADSSTRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADS
STRUCTURAL ANALYSIS OF BRIDGES AND PILE FOUNDATION SUBJECTED TO SEISMIC LOADS
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
Numerical simulation and optimization of pile design
Numerical simulation and optimization of pile designNumerical simulation and optimization of pile design
Numerical simulation and optimization of pile design
 
Kaplan05analysis
Kaplan05analysisKaplan05analysis
Kaplan05analysis
 
OCPW Wintersburg Channel Deep Soil Mixing
OCPW Wintersburg Channel Deep Soil MixingOCPW Wintersburg Channel Deep Soil Mixing
OCPW Wintersburg Channel Deep Soil Mixing
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
 
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
A012140107
A012140107A012140107
A012140107
 
Large Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof StructureLarge Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof Structure
 
Large Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof StructureLarge Span Lattice Frame Industrial Roof Structure
Large Span Lattice Frame Industrial Roof Structure
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
 
Thesis Powerpoint
Thesis PowerpointThesis Powerpoint
Thesis Powerpoint
 
7436 2
7436 27436 2
7436 2
 

More from Remedy Geotechnics Ltd

Digital data & its use in geotechnical design & construction
Digital data & its use in geotechnical design & constructionDigital data & its use in geotechnical design & construction
Digital data & its use in geotechnical design & construction
Remedy Geotechnics Ltd
 
"The Design of High Performance Anchored Retaining Walls within the Eurocode ...
"The Design of High Performance Anchored Retaining Walls within the Eurocode ..."The Design of High Performance Anchored Retaining Walls within the Eurocode ...
"The Design of High Performance Anchored Retaining Walls within the Eurocode ...
Remedy Geotechnics Ltd
 
"A Review of the Settlement of Stone Columns in Compressible Soils"
"A Review of the Settlement of Stone Columns in Compressible Soils""A Review of the Settlement of Stone Columns in Compressible Soils"
"A Review of the Settlement of Stone Columns in Compressible Soils"
Remedy Geotechnics Ltd
 
"A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils""A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils"
Remedy Geotechnics Ltd
 
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction""Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
Remedy Geotechnics Ltd
 
"Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay"
"Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay""Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay"
"Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay"
Remedy Geotechnics Ltd
 
"Earthworks Management: Have we got our designs right?"
"Earthworks Management: Have we got our designs right?""Earthworks Management: Have we got our designs right?"
"Earthworks Management: Have we got our designs right?"
Remedy Geotechnics Ltd
 
"The Performance of Embankment Stabilisation Measures"
"The Performance of Embankment Stabilisation Measures""The Performance of Embankment Stabilisation Measures"
"The Performance of Embankment Stabilisation Measures"
Remedy Geotechnics Ltd
 
"Modelling of High Pressure Grouted Compaction Anchors"
"Modelling of High Pressure Grouted Compaction Anchors""Modelling of High Pressure Grouted Compaction Anchors"
"Modelling of High Pressure Grouted Compaction Anchors"
Remedy Geotechnics Ltd
 

More from Remedy Geotechnics Ltd (9)

Digital data & its use in geotechnical design & construction
Digital data & its use in geotechnical design & constructionDigital data & its use in geotechnical design & construction
Digital data & its use in geotechnical design & construction
 
"The Design of High Performance Anchored Retaining Walls within the Eurocode ...
"The Design of High Performance Anchored Retaining Walls within the Eurocode ..."The Design of High Performance Anchored Retaining Walls within the Eurocode ...
"The Design of High Performance Anchored Retaining Walls within the Eurocode ...
 
"A Review of the Settlement of Stone Columns in Compressible Soils"
"A Review of the Settlement of Stone Columns in Compressible Soils""A Review of the Settlement of Stone Columns in Compressible Soils"
"A Review of the Settlement of Stone Columns in Compressible Soils"
 
"A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils""A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils"
 
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction""Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
 
"Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay"
"Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay""Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay"
"Observed Installation Effects of Vibro Replacement Stone Columns in Soft Clay"
 
"Earthworks Management: Have we got our designs right?"
"Earthworks Management: Have we got our designs right?""Earthworks Management: Have we got our designs right?"
"Earthworks Management: Have we got our designs right?"
 
"The Performance of Embankment Stabilisation Measures"
"The Performance of Embankment Stabilisation Measures""The Performance of Embankment Stabilisation Measures"
"The Performance of Embankment Stabilisation Measures"
 
"Modelling of High Pressure Grouted Compaction Anchors"
"Modelling of High Pressure Grouted Compaction Anchors""Modelling of High Pressure Grouted Compaction Anchors"
"Modelling of High Pressure Grouted Compaction Anchors"
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 

"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Parameters"

  • 1. 1 INTRODUCTION The driven cast in-situ (DCIS) piling method has been in use for many decades and has over this peri- od demonstrated its effectiveness and efficiency. Examples of more recently completed large struc- tures supported on DCIS piles installed by Keller in the UK include the O2 Arena (constructed within the Millennium Dome – itself supported in DCIS piles) and the London 2012 Olympic stadium. The body of published literature relating to the design of DCIS piling is not large. Neely (1991) cre- ated a database of load tests on DCIS piles with ex- panded bases and developed correlations for design. Evers et al (2003) provided a useful study for the performance of DCIS piles compared to CFA piles at a site in France and Flynn et al (2012) present a case study for the performance of a DCIS test pile at a site in London. Development of a complete theoretical model for the design of DCIS piles is complicated by the very significant disruption in soil structure and insitu stress regime caused by the installation process. Even the selection of appropriate soil parameters for use in design equations from ground investigation tests is problematic due to the state changes occur- ring during pile installation. Even though much research effort is expended on complex numerical modeling and reduced scale la- boratory or centrifuge modeling there remains the difficulty of translating the knowledge gained into practical prediction tools appropriate for routine de- sign and installation of the full size product in the field. This paper considers a method to estimate DCIS geotechnical capacity based on installation pa- rameters measured during the installation of a pile by modern instrumented piling rigs. 2 MODERN DCIS PILING EXECUTION In recent times advances in piling rig instrumen- tation and telecommunications have enabled a new level of sophistication in the recording of installation parameters and this opens up the potential of as- sessing pile capacity in real time. DCIS design using a static design approach, based on ground parameters derived from boreholes and laboratory testing has for many years been the approach used to estimate ultimate pile capacity, but, as noted above, this approach has its difficulties. At the start of execution of piling, trial drives, are un- dertaken to validate the ground conditions are as en- visaged in the initial design. (Historically with man- ual counting of the number of hammer blows to The Load Capacity of Driven Cast In-Situ Piles Derived from Installation Parameters D. Egan Chief Engineer, Keller Foundations ABSTRACT: The theoretical estimation of the ultimate capacity and serviceability performance of common displacement foundation systems such driven cast in-situ (DCIS) piles is difficult due to the huge disruption in soil structure and insitu stress regime caused by the installation process. Even though much research effort is expended on complex numerical modeling and reduced scale laboratory or centrifuge modeling there re- mains the difficulty of translating the knowledge gained into practical prediction tools appropriate for routine design and installation of the full size product in the field. So to advance and validate the conclusions drawn from numerical and small scale research the third strand of measuring and analysing full size field behaviour must be added. This paper will summarise recent advances made in the field measurement and analysis of in- stallation parameters to predict the load capacity of driven cast in-situ piles. The results from installation and testing of a DCIS pile is used to illustrate the methodology now being routinely by Keller Foundations in the UK. The conclusions drawn from this paper are already raising the standard of reliability, efficiency and sus- tainability of DCIS piles on routine projects. Remedy Geotechnics Ltd Technical Paper R19 www.remedygeotechnics.com
  • 2. achieve a given penetration.) The control criteria can then be set for installation of the production piles. Where required this can be supplemented with pro- ject specific static load testing to support and vali- date the achieved pile load capacity. While this ap- proach has been used satisfactorily for the installation of hundreds of thousands of piles over many decades, modern instrumentation now allows both robust and detailed control and feedback of the pile driving process, in real time, for every pile in- stalled. On modern instrumented DCIS piling rigs the en- ergy delivered to each pile can now be measured and used to validate that pile’s ultimate load capacity. As the pile is driven the driving parameters (drive ener- gy, drive tube depth and rate of advancement) are displayed to the rig driver giving a high degree of control to the installation process. Additional bene- fits of an automated electronic data capture system include a reduction of manual recording and on-site paperwork (which requires a finite manpower re- source), robust archiving of records and real time access to installation data remote from the work site. From the experience of developing a large data- base of systematically acquired pile installation data it has been possible to map the process required to allow real time assessment of pile capacity. Initially focused on piles founded in granular soils an empiri- cal approach has been developed which has been used to validate, in near real time, the adequacy of DCIS piles as they are driven. Of course these ad- vances should be seen in the context of dynamic pile driving formulae which have been used on pre- formed piles for many decades. Not withstanding widespread the use of set calculations for pre-formed piles, their applicability (and reliability) for driven cast in-situ piling, where the drive tube is firstly driven into the ground and then removed and re- placed by cast in place concrete, is highly questiona- ble. The development of real time assessment of DCIS pile capacity for piles driven into coarse grained soils is presented in detail below. This method has been developed over a period of time and is based on drive data and load test data carried out on a series of sites. However to better illustrate the process reference to a single test pile (TP3) in- stalled at a site in Erith, London is made. 3 DESCRIPTION OF TEST SITE The test site was located within the Thames basin to the south of the river at Erith, London. The ground conditions comprised a mantle of Made Ground, overlying soft and very soft clay and peat Alluvium. The piles were founded in coarse grained River Terrace Deposits (RTD) comprising medium dense to very dense gravelly sand. Thanet Sand was found beneath the RTD. Figure 1 shows a typical bore hole for the site. The Made Ground and Alluvi- um were not considered as contributing to the pile geotechnical capacity, but rather a source of poten- tial negative skin friction, they are ignored in the as- sessment of ultimate pile capacity for design purpos- es. Figure 1 Typical Borehole from the test site. 4 DRIVEN CAST INSITU PILE INSTALLATION Figure 2 illustrates the pertinent features of the DCIS system. A steel drive tube, closed at the base by a sacrificial base plate, is top driven to the re- quired depth. The steel tube is then charged with a free flowing concrete and withdrawn from the ground. Steel reinforcement can be inserted in the pile bore before or after the concrete is placed. The requirements for the execution of DCIS piles are set out in EN 12699 ‘Execution of special geotechnical works – Displacement piles’. In addition Keller monitor all aspects of the installation process by on- board computer, with the key parameters for capaci- ty assessment being the hammer energy imparted for each blow, the rate of advancement of the tube per blow and the tube and base plate geometry. The rec- Remedy Geotechnics Ltd Technical Paper R19 www.remedygeotechnics.com
  • 3. orded data are instantly fed back to the design office by modem enabling secure backup of the infor- mation as well as providing the facility for the de- sign engineer to see feedback on the ground condi- tions encountered immediately the pile is completed. 5 RECORDED INSTALLATION PARAMETERS From the recorded parameters the tube drive re- sistance with depth is calculated, where Ru is the drive resistance, N is the hammer energy, s is the rate of tube advancement per hammer blow and c is the elastic compression of the tube. !! = !!!!! !! ! ! The factors f1 and f2 are hammer and energy transfer efficiency factors. The elastic compression of the drive tube is calculated using the following equation, which is based on the Danish pile driving formula, and where N is the hammer energy, L is the tube length, A is the cross sectional area of the tube and E the elastic modulus. ! = 2!!!!!" !" Figure 3 shows the drive resistance, Ru, plotted with depth for TP3 and the four associated anchor piles used for reaction in the subsequent maintained load test. The piles were DCIS piles of nominal di- ameter, d, of 340mm with a base plate diameter, db, of 380mm. TP 3 was driven fractionally over 11.0m (11.01m) and the anchor piles to 15m. Figure 2 The DCIS installation process. The Made Ground and Alluvium proved to be of very low strength which drive tube easily penetrated with little energy required. The RTD was encoun- tered at around 8.25m depth as indicated by a sharp increase in drive resistance to between 500kN and 700kN as shown in Figure 3. This corresponds to medium dense to dense gravelly RTD. Below 12m the anchor piles encountered a further sharp increase in drive resistance to around 2300kN at 15m, which is thought to coincide with the top of the Thanet Sand at this location. The test pile was intentionally stopped within the medium dense zone so as to en- sure geotechnical failure during the maintained load test. Figure 3 Dynamic drive resistance, Run, plotted with depth. 6 CORRELATION OF PILE INSTALLATION PARAMETERS WITH SOIL PARAMETERS The installation of each pile where state of the art instrumentation is used can be considered as a form of large scale ground investigation test from which ground parameters may be derived. Dividing the drive resistance by the area of the base plate, Ab, gives the bearing pressure, qpc, at the pile toe. !!" = !! !! Taking qpc to be analogous to the cone resistance, qc, obtained by a static cone penetration test a ready and quick evaluation of the nature of the ground into which the pile is being driven can be obtained. In developing the analogy between qpc and CPT qc fac- tors leading to energy losses within the drive/tube system such as frictional losses along the drive tube shaft, rate effects and size effects have all to be con- sidered. Field tests using dynamic pile driving analysis have been undertaken to assess the loss in energy be- tween the point of impact of the hammer at the top of the drive tube and the pile base plate. 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 0 500 1000 1500 2000 2500 3000 Depth&(m) Dynamic&Drive&Resistance,& Ru&(kN) Erith&Test&Pile&3 Ru&Values 340mm&Piles&&Driven&8&9/11/12 PILETEST3 AP18 AP17 AP16 Remedy Geotechnics Ltd Technical Paper R19 www.remedygeotechnics.com
  • 4. The ratio of the area of the base plates of different sizes of DCIS pile and a standard CPT range be- tween 26 and 6, and taken in the round this is con- sidered beneficial. One of the characteristics of the CPT, especially in coarse soils, is the propensity for the tip resistance to be influenced by larger soil par- ticles (or localised weaker or softer layers) in the soil. In contrast the larger diameter of the DCIS base plates stresses a greater depth of soil leading to somewhat of lower bound (and safe) smoothing ef- fect when compared to the CPT qc. Indeed the zone of soil stressed beneath the pile toe at the end of driving is exactly that which will be stressed by the finished pile in the working condition. (This is in the context of a single pile, where piles are grouped such that they interact suitable consideration of group effect must be made in the design.) Figure 4 Comparison of qc and qpc for TP3. Figure 4 compares qc from a CPT test undertaken about 4m from TP3, and pile toe bearing pressure, qpc, and illustrates the lower bound averaging effect of qpc compared to the CPT qc values. Once qpc is derived a correlation with effective angle of friction, φ’, may be made, for example us- ing the method shown in Lunne et al (1997). From the measured drive resistance, Ru, the dy- namic bearing pressure, qpc, is derived and correlated to in-situ angle of friction for the gravelly sand founding stratum. Figure 5 shows the derived angle of friction over the socket length of TP3 driven into the RTD. Figure 5 Angle of friction, φ’, from drive resistance Ru. 7 ESTIMATE OF PILE CAPACITY FROM INSTALLATION PARAMETERS The ultimate pile socket capacity, Qult, compris- ing a shaft component, Qs,ult, and base component, Qb,ult, may now be derived using standard soil me- chanics principles, where:- Q!"# = Q!,!"# +!Q!,!"# Q!"! = β. σ! ′ . π. d. l +!N!.σ! ′ . A! The above equation is readily implemented in commercially available software or spreadsheets. The program Oasys Pile, using the angles of friction shown in Figure 5 and the Berezantzev formulation for the bearing capacity factor, Nq, (Oasys Pile user manual, 2012) was used to give:- Q!"#,!"#$%& = 217kN + 1763k = 1980kN Test Pile 3 was subjected to a maintained extend- ed proof load test to failure following the procedure outlined in the ICE Specification for Piling and Em- bedded Retaining Walls (2007). Figure 6 shows the load settlement response. A plunging failure of the pile under an applied load, Qf, of 1947kN and at a displacement of 45mm was observed. 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 30 32 34 36 38 40 42 44 46 48 50 Depth&(m) Angle&of&Friction&(Deg)) Erith&Test&Pile&3 Derived&Angle&of&Friction&from& Dynamic&Drive&Resistance&Ru. Angle1of1friction1from1Ru 0 2 4 6 8 10 12 14 16 18 0 10 20 30 40 50 60 Depth&(m) qc/qpc&(MPa) CPT&qc&&&qpc&for&TP3 CPT,qc qpc Remedy Geotechnics Ltd Technical Paper R19 www.remedygeotechnics.com
  • 5. Figure 6 Load settlement response of Test Pile 3. In the analysis of the pile test results the tempo- rary hold up resistance generated over the pile shaft passing through the made ground and alluvium was estimated at 80kN, which must be added to Qult,socket as calculated in Oasys Pile to give the true anticipat- ed theoretical pile capacity of 2060kN. Thus the pile under test achieved 94% of its the- oretical capacity which is considered an excellent correlation between the calculated capacity and that shown by the static load test. The results of the illustration of the installation and load testing of pile TP3 show that a rational pro- cedure to assess the ultimate capacity of DCIS piles located in coarse grained soils based in pile installa- tion data is available. 8 CONCLUSIONS Driven cast in-situ piling has proved a popular and efficient piling method over many decades, which, in suitable ground conditions, produces piles of high capacity and efficiency. Recent develop- ments in rig instrumentation have enabled the rou- tine and systematic acquisition of high quality instal- lation records. The benefits of an automated electronic data capture system include a reduction of manual recording and on-site paperwork (which re- quires a finite manpower resource), robust archiving of records and real time access to installation data remote from the work site. In addition Keller has demonstrated the development of a real time valida- tion method for DCIS piles is viable. A rational link between the installation parameters, fundamental soil parameters relevant after pile installation, the physical mechanisms of load generation and ob- served load capacity has been established. These developments in the driven cast in-situ pil- ing process have lead to improved efficiency (and hence sustainability) of the DCIS method. REFERENCES EN 12699:2001 Execution of special geotechnical works – Displacement Piles. (2001). BSI. London. Evers, G., Hass, G., Frossard, A., Bustamante, M., Borel, S. & Skinner, H. (2003) Comparative performanc- es of continuous flight auger and driven cast in place piles in sands. Deep foundations on bored and auger piles, Van Imp (ed) Millpress, Rotterdam. Flynn, K,. McCabe, B.A. & Egan, D (2012) Proceed- ings 9th International conference on testing and design methods for deep foundations, Kanazawa, Japan. ICE Specification for Piling and Embedded Retaining Walls (2007) 2nd Ed. ICE. London. Lune T., Robertson P.K. & Powell, J.J.M (1997) Cone Penetration testing in geotechnical Practice. Neely, W.J. (1990) bearing capacity of expanded-base piles with compacted concrete shafts. Journal of geotech- nical Engineering, 116(9): 1309-1324 Oasys Pile 19.2 User manual (2012) http://www.oasys- soft- ware.com/media/Manuals/Latest_Manuals/Pile19.2_man ual.pdf. 0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 0 5 10 15 20 25 30 35 40 45 50 Load(kN) Settlement (mm) Erith Test Pile 3 Maintained Load Settlement Response Test Data Elast Shortening Remedy Geotechnics Ltd Technical Paper R19 www.remedygeotechnics.com