SlideShare a Scribd company logo
1 of 27
Download to read offline
Exploring the challenges of underground
construction in urban areas
Underground Infrastructure and Deep Foundations
UAE 16 & 17 November 2015
16 November 2015 1
Benoît Latapie
Technical Manager, Ground Engineering
WS Atkins & Partners Overseas
Underground construction in urban areas
1. A good quality ground investigation is essential
2. The context of urban areas
3. A concise approach to underground design
4. Numerical modelling has come a long way
5. Recent project example
6. Managing geotechnical risk during the project
16 November 2015 2
Table of contents
1. A good quality ground investigation is essential
16 November 2015 3
Weak to medium strong, off-white to pale
yellow Limestone with inclusions of silt/clay
Non intact core recovered as medium to
coarse gravel of weak dolomitic limestone
Conventional single tube core barrel Rotary coring with double tube core barrel
Two sites a few kilometres away
from each other, at similar depth
(with plastic lining)
1. A good quality ground investigation is essential
16 November 2015 4
Weak to medium strong, off-white to pale
yellow Limestone with inclusions of silt/clay
Non intact core recovered as medium to
coarse gravel of weak dolomitic limestone
Conventional single tube core barrel Rotary coring with double tube core barrel
(with plastic lining)
Rock modelled as soil
Erroneous prediction of ground movements
Effects on existing assets misunderstood
Rock modelled as rock
Realistic prediction of ground movements
Impact on existing assets well estimated
Low strength/stiffness High strength/stiffness
2. The context of urban areas in Dubai
• Prime locations/sites are mostly developed
• Remaining sites are constrained:
– Existing buildings
– Existing infrastructures (roads, services, quay walls…)
– Irregular plot shapes
– Building height race: deep basements and deep foundations
• Additional constraints often means that additional authorities/parties
approval are required
16 November 2015 5
2. The context of urban areas in Dubai
16 November 2015 6
Dubai construction 10 years ago Dubai construction today
2. The context of urban areas in Dubai
16 November 2015 7
3. A concise approach to underground design
16 November 2015 8
1. Knowing the location, size and sensitivity
of existing assets to ground movements
is key
2. Good understanding of the ground /
High quality ground investigation
3. Understanding the interaction
mechanisms between existing structures,
proposed works and the ground
4. Measuring the impact of the construction
sequence on surrounding assets
Excavation near existing buildings, structures and services means:
Topographic survey
As-built drawings
Pre-construction condition surveys
Experienced SI contractor
+
Design and supervision by
specialist consultant
Finite element modelling including:
• Soil/rock behaviour
• Existing structures
• Temporary supports
• Dewatering
• Construction sequence
3. A concise approach to underground design
16 November 2015 9
1. Design the appropriate support stiffness
for temporary works
2. Instrumentation and monitoring of
temporary works
3. Instrumentation and monitoring of
existing assets
Excavation near existing buildings, structures and services means:
Contiguous bored pile wall
Diaphragm wall
Pre-stressed struts/anchors
Inclinometers, strain gauges,
observation wells, piezometers,
ground settlement points,
building monitoring points,
crackmeters, extensometers
4. Numerical modelling has come a long way
16 November 2015 10
1. Commercial codes have become much quicker to run
2. 3D analyses no longer require top spec computers nor long calculation times and are
used more routinely on projects
3. Input procedures have become more user-friendly which enables very fast model
generation
4. It is possible to generate 3D ground models with several boreholes and import
information from drawing files
5. Improved constitutive models closer to predicting true soil/rock behaviour
6. Experience gained in confidently deriving more sophisticated parameters from ground
investigation results
7. 2D and 3D groundwater flow analyses are possible, in conjunction with the modelling
of a multi-stage construction sequence
4. Numerical modelling has come a long way
16 November 2015 11
PMT
Pressuremeter test
DMT
Dilatometer test
CPTU
Piezocone penetration test
SCPT
Seismic cone penetration test
Mohr-Coulomb:
A single stiffness parameter, the
Young’s Modulus E = E50.
Hardening Soil:
Three different stiffnesses
E50: secant stiffness
Ei: initial stiffness
Ei ≈ 1.8 x E50
Eur: unloading/reloading stiffness
Eur ≈ 3.0 x E50
4. Numerical modelling has come a long way
16 November 2015 12
A better definition of ground stiffness
Ei
E50
Eur
E
5. Recent project example
16 November 2015 13
1. Small, complex plot geometry
2. Plot constrained on all sides by existing structures and services:
– Existing road bridge on one side
– Existing quay wall on one side
– Existing roads and services on two sides
3. The temporary works proposal required approval from 3 different authorities
4. Shallow groundwater, near the sea
5. Stratigraphy comprising 13m of various cemented sand densities overlying rock
Project context:
5. Recent project example
16 November 2015 14
Atkins approach:
1. Obtain as-built information for the existing bridge:
– Foundations’ positions and dimensions
– Loads and moments transferred through the bridge bearings
– Structural tolerance to movement
2. Obtain as-built information for roads and services and for the quay wall
3. Produce a 3D finite element model of the temporary works for the entire plot and
including the surrounding assets. This enables:
– Consideration of 3D effects and asymmetrical loading due to the plot geometry
and different surcharge intensities around the site
5m
15m
5. Recent project example
16 November 2015 15
Site Plan:
Quay wall
canal
Bridge pier
Bridge abutment
Gravity
retaining walls
Edge of road
Temporary retaining wall
Temporary support
Plot boundary
Bridge
6m
5. Recent project example
16 November 2015 16
Ground conditions: +4.5mDMD
-8.6mDMD
-21.0mDMD
13.10m
12.40m
Final Excavation level for 3
basements at -10.5mDMD
In situ groundwater
level at +1.3mDMD
Cemented
Sand
Calcarenite
Calcisiltite
Layer
γ UCS Erm ϕ’ c’
[kN/m3] [MPa] [MPa] [°] [kPa]
Sand 19 – 50 32 5
Calcarenite 21 1.0 200 40 125
Calcisiltite 21 3.4 750 30 300
5. Recent project example
16 November 2015 17
FE model in plan:
5. Recent project example
16 November 2015 18
FE model in 3D:
NB: the top soil layer was ‘turned off’ so that the bridge’s elements are visible.
5. Recent project example
16 November 2015 19
Construction sequence – following the site history:
1. Construct the quay wall
2. Construct the bridge components, including the approach embankment
3. Apply bridge service loads to the pier, abutment and embankment
4. Build perimeter retaining wall
5. Excavate and apply supports in sequence until reaching formation level
5. Recent project example
16 November 2015 20
Outputs:
Ground settlement
contours, sensitive to:
• Wall type and
stiffness
• Support stiffness
and applied struts
preload
Maximum settlement 33mm
5. Recent project example
16 November 2015 21
Outputs:
Position of output sections:
• A-A through pier foundation
• B-B through abutment
foundation
• C-C through wall and quay
wall
• D-D through wall, near
existing road
• E-E through wall, near
bridge abutment
5. Recent project example
16 November 2015 22
Outputs:
Total ground movement contours at final excavation
pier (cross section A, left) and abutment (cross section B, right)
5. Recent project example
16 November 2015 23
Outputs:
Total ground movement contours at final excavation
cross sections C (left), D (middle) and E (right)
5. Recent project example
16 November 2015 24
Outputs:
5. Recent project example
16 November 2015 25
What we achieved:
1. Demonstrate that the construction of multiple basement levels is possible in a
constrained environment
2. Temporary works can be designed to have a negligible impact on the bridge and its
support
3. Evaluate the impact of the proposed works on the adjacent asset with a single
analysis
4. Instrumentation and monitoring plan tailored to the situation and using the output of
the analysis to establish AAA values
6. Managing geotechnical risk during the project
16 November 2015 28
Design
1. Employ a competent
ground engineering
specialist
2. Design the right site
investigation
3. Supervise the site
investigation
4. Select the right support
stiffness for the local
situation/conditions
5. Do the right analyses
Build
1. Employ a competent and
experienced temporary
works contractor
2. Ensure that designer and
contractor work together
3. Get the designer
involved in site
supervision and help the
contractor resolve
potential site issues
Monitor
1. Install adequate I&M
apparatus
2. Implement regular
monitoring
3. Keep the designer
involved in reviewing the
data regularly
4. Back analysis of the in
situ condition, as required
+ +
15 November 2015 29
Thank you
Underground Infrastructure and Deep Foundations
UAE 16 & 17 November 2015
Benoît Latapie
Technical Manager, Ground Engineering
WS Atkins & Partners Overseas
benoit.latapie@atkinsglobal.com +971 (0) 553003797

More Related Content

What's hot

The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading testAlaa Metwally
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structuresEva Lantsoght
 
Shear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersShear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersEva Lantsoght
 
Expansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalExpansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalRailways and Harbours
 
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumboBuilding a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumboAndrew Wachtel
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structuresEva Lantsoght
 
"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par...
"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par..."The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par...
"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par...Remedy Geotechnics Ltd
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderCheng (Wayne) Zhu
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testingcfpbolivia
 
Proof load testing of the viaduct De Beek
Proof load testing of the viaduct De BeekProof load testing of the viaduct De Beek
Proof load testing of the viaduct De BeekEva Lantsoght
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Eva Lantsoght
 
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Pagkratios Chitas
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Eva Lantsoght
 
Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...
Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...
Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...ziiishan
 
Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practiceWeb2Present
 
Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook920728035348
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdIndependent Geoscience
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaStephen McKnight
 

What's hot (20)

The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structures
 
Shear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersShear testing of prestressed concrete girders
Shear testing of prestressed concrete girders
 
Expansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalExpansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container Terminal
 
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumboBuilding a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structures
 
"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par...
"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par..."The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par...
"The Load Capacity of Driven Cast-In-Situ Piles Derived from Installation Par...
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binder
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
Proof load testing of the viaduct De Beek
Proof load testing of the viaduct De BeekProof load testing of the viaduct De Beek
Proof load testing of the viaduct De Beek
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...
 
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...
 
Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...
Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...
Comparative Analysis of Performance of Horizontal and Hydraulically Fractured...
 
Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practice
 
Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty Ltd
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
ICDE2006, Singapore
ICDE2006, SingaporeICDE2006, Singapore
ICDE2006, Singapore
 

Similar to 151111 Exploring the challenges of underground construction in urban areas_Benoit Latapie

Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
Introduction to civil Engg.pptx
Introduction to civil Engg.pptxIntroduction to civil Engg.pptx
Introduction to civil Engg.pptxpriyanka415514
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.vragabata
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation Davis Ciprikis
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16Don Dwyer
 
Maulana azad national institute of technology
Maulana azad national institute of technologyMaulana azad national institute of technology
Maulana azad national institute of technologyBhanuPratapSingh170
 
Introduction to Site Investigation Methods
Introduction to Site Investigation MethodsIntroduction to Site Investigation Methods
Introduction to Site Investigation MethodsMohdBilal430488
 
Group 2 , ce471
Group 2  ,  ce471Group 2  ,  ce471
Group 2 , ce471ktx500
 
Presentation on centrifuge modelling for building tilt correction
Presentation on centrifuge modelling for building tilt correctionPresentation on centrifuge modelling for building tilt correction
Presentation on centrifuge modelling for building tilt correctionvivekprakashmani
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdfShrutiGarg261479
 
Applications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil EngineeringApplications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil EngineeringLawrence Le Roux
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadIRJET Journal
 
Geotechnical Examples using OpenSees
Geotechnical Examples using OpenSeesGeotechnical Examples using OpenSees
Geotechnical Examples using OpenSeesopenseesdays
 

Similar to 151111 Exploring the challenges of underground construction in urban areas_Benoit Latapie (20)

Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
Bridge report
Bridge reportBridge report
Bridge report
 
Introduction to civil Engg.pptx
Introduction to civil Engg.pptxIntroduction to civil Engg.pptx
Introduction to civil Engg.pptx
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Site report 1
Site report 1Site report 1
Site report 1
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16
 
Maulana azad national institute of technology
Maulana azad national institute of technologyMaulana azad national institute of technology
Maulana azad national institute of technology
 
Introduction to Site Investigation Methods
Introduction to Site Investigation MethodsIntroduction to Site Investigation Methods
Introduction to Site Investigation Methods
 
Group 2 , ce471
Group 2  ,  ce471Group 2  ,  ce471
Group 2 , ce471
 
Presentation on centrifuge modelling for building tilt correction
Presentation on centrifuge modelling for building tilt correctionPresentation on centrifuge modelling for building tilt correction
Presentation on centrifuge modelling for building tilt correction
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf
 
Applications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil EngineeringApplications of EPS Geofoam in Civil Engineering
Applications of EPS Geofoam in Civil Engineering
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing Road
 
Geotechnical Examples using OpenSees
Geotechnical Examples using OpenSeesGeotechnical Examples using OpenSees
Geotechnical Examples using OpenSees
 

151111 Exploring the challenges of underground construction in urban areas_Benoit Latapie

  • 1. Exploring the challenges of underground construction in urban areas Underground Infrastructure and Deep Foundations UAE 16 & 17 November 2015 16 November 2015 1 Benoît Latapie Technical Manager, Ground Engineering WS Atkins & Partners Overseas
  • 2. Underground construction in urban areas 1. A good quality ground investigation is essential 2. The context of urban areas 3. A concise approach to underground design 4. Numerical modelling has come a long way 5. Recent project example 6. Managing geotechnical risk during the project 16 November 2015 2 Table of contents
  • 3. 1. A good quality ground investigation is essential 16 November 2015 3 Weak to medium strong, off-white to pale yellow Limestone with inclusions of silt/clay Non intact core recovered as medium to coarse gravel of weak dolomitic limestone Conventional single tube core barrel Rotary coring with double tube core barrel Two sites a few kilometres away from each other, at similar depth (with plastic lining)
  • 4. 1. A good quality ground investigation is essential 16 November 2015 4 Weak to medium strong, off-white to pale yellow Limestone with inclusions of silt/clay Non intact core recovered as medium to coarse gravel of weak dolomitic limestone Conventional single tube core barrel Rotary coring with double tube core barrel (with plastic lining) Rock modelled as soil Erroneous prediction of ground movements Effects on existing assets misunderstood Rock modelled as rock Realistic prediction of ground movements Impact on existing assets well estimated Low strength/stiffness High strength/stiffness
  • 5. 2. The context of urban areas in Dubai • Prime locations/sites are mostly developed • Remaining sites are constrained: – Existing buildings – Existing infrastructures (roads, services, quay walls…) – Irregular plot shapes – Building height race: deep basements and deep foundations • Additional constraints often means that additional authorities/parties approval are required 16 November 2015 5
  • 6. 2. The context of urban areas in Dubai 16 November 2015 6 Dubai construction 10 years ago Dubai construction today
  • 7. 2. The context of urban areas in Dubai 16 November 2015 7
  • 8. 3. A concise approach to underground design 16 November 2015 8 1. Knowing the location, size and sensitivity of existing assets to ground movements is key 2. Good understanding of the ground / High quality ground investigation 3. Understanding the interaction mechanisms between existing structures, proposed works and the ground 4. Measuring the impact of the construction sequence on surrounding assets Excavation near existing buildings, structures and services means: Topographic survey As-built drawings Pre-construction condition surveys Experienced SI contractor + Design and supervision by specialist consultant Finite element modelling including: • Soil/rock behaviour • Existing structures • Temporary supports • Dewatering • Construction sequence
  • 9. 3. A concise approach to underground design 16 November 2015 9 1. Design the appropriate support stiffness for temporary works 2. Instrumentation and monitoring of temporary works 3. Instrumentation and monitoring of existing assets Excavation near existing buildings, structures and services means: Contiguous bored pile wall Diaphragm wall Pre-stressed struts/anchors Inclinometers, strain gauges, observation wells, piezometers, ground settlement points, building monitoring points, crackmeters, extensometers
  • 10. 4. Numerical modelling has come a long way 16 November 2015 10 1. Commercial codes have become much quicker to run 2. 3D analyses no longer require top spec computers nor long calculation times and are used more routinely on projects 3. Input procedures have become more user-friendly which enables very fast model generation 4. It is possible to generate 3D ground models with several boreholes and import information from drawing files 5. Improved constitutive models closer to predicting true soil/rock behaviour 6. Experience gained in confidently deriving more sophisticated parameters from ground investigation results 7. 2D and 3D groundwater flow analyses are possible, in conjunction with the modelling of a multi-stage construction sequence
  • 11. 4. Numerical modelling has come a long way 16 November 2015 11 PMT Pressuremeter test DMT Dilatometer test CPTU Piezocone penetration test SCPT Seismic cone penetration test
  • 12. Mohr-Coulomb: A single stiffness parameter, the Young’s Modulus E = E50. Hardening Soil: Three different stiffnesses E50: secant stiffness Ei: initial stiffness Ei ≈ 1.8 x E50 Eur: unloading/reloading stiffness Eur ≈ 3.0 x E50 4. Numerical modelling has come a long way 16 November 2015 12 A better definition of ground stiffness Ei E50 Eur E
  • 13. 5. Recent project example 16 November 2015 13 1. Small, complex plot geometry 2. Plot constrained on all sides by existing structures and services: – Existing road bridge on one side – Existing quay wall on one side – Existing roads and services on two sides 3. The temporary works proposal required approval from 3 different authorities 4. Shallow groundwater, near the sea 5. Stratigraphy comprising 13m of various cemented sand densities overlying rock Project context:
  • 14. 5. Recent project example 16 November 2015 14 Atkins approach: 1. Obtain as-built information for the existing bridge: – Foundations’ positions and dimensions – Loads and moments transferred through the bridge bearings – Structural tolerance to movement 2. Obtain as-built information for roads and services and for the quay wall 3. Produce a 3D finite element model of the temporary works for the entire plot and including the surrounding assets. This enables: – Consideration of 3D effects and asymmetrical loading due to the plot geometry and different surcharge intensities around the site
  • 15. 5m 15m 5. Recent project example 16 November 2015 15 Site Plan: Quay wall canal Bridge pier Bridge abutment Gravity retaining walls Edge of road Temporary retaining wall Temporary support Plot boundary Bridge 6m
  • 16. 5. Recent project example 16 November 2015 16 Ground conditions: +4.5mDMD -8.6mDMD -21.0mDMD 13.10m 12.40m Final Excavation level for 3 basements at -10.5mDMD In situ groundwater level at +1.3mDMD Cemented Sand Calcarenite Calcisiltite Layer γ UCS Erm ϕ’ c’ [kN/m3] [MPa] [MPa] [°] [kPa] Sand 19 – 50 32 5 Calcarenite 21 1.0 200 40 125 Calcisiltite 21 3.4 750 30 300
  • 17. 5. Recent project example 16 November 2015 17 FE model in plan:
  • 18. 5. Recent project example 16 November 2015 18 FE model in 3D: NB: the top soil layer was ‘turned off’ so that the bridge’s elements are visible.
  • 19. 5. Recent project example 16 November 2015 19 Construction sequence – following the site history: 1. Construct the quay wall 2. Construct the bridge components, including the approach embankment 3. Apply bridge service loads to the pier, abutment and embankment 4. Build perimeter retaining wall 5. Excavate and apply supports in sequence until reaching formation level
  • 20. 5. Recent project example 16 November 2015 20 Outputs: Ground settlement contours, sensitive to: • Wall type and stiffness • Support stiffness and applied struts preload Maximum settlement 33mm
  • 21. 5. Recent project example 16 November 2015 21 Outputs: Position of output sections: • A-A through pier foundation • B-B through abutment foundation • C-C through wall and quay wall • D-D through wall, near existing road • E-E through wall, near bridge abutment
  • 22. 5. Recent project example 16 November 2015 22 Outputs: Total ground movement contours at final excavation pier (cross section A, left) and abutment (cross section B, right)
  • 23. 5. Recent project example 16 November 2015 23 Outputs: Total ground movement contours at final excavation cross sections C (left), D (middle) and E (right)
  • 24. 5. Recent project example 16 November 2015 24 Outputs:
  • 25. 5. Recent project example 16 November 2015 25 What we achieved: 1. Demonstrate that the construction of multiple basement levels is possible in a constrained environment 2. Temporary works can be designed to have a negligible impact on the bridge and its support 3. Evaluate the impact of the proposed works on the adjacent asset with a single analysis 4. Instrumentation and monitoring plan tailored to the situation and using the output of the analysis to establish AAA values
  • 26. 6. Managing geotechnical risk during the project 16 November 2015 28 Design 1. Employ a competent ground engineering specialist 2. Design the right site investigation 3. Supervise the site investigation 4. Select the right support stiffness for the local situation/conditions 5. Do the right analyses Build 1. Employ a competent and experienced temporary works contractor 2. Ensure that designer and contractor work together 3. Get the designer involved in site supervision and help the contractor resolve potential site issues Monitor 1. Install adequate I&M apparatus 2. Implement regular monitoring 3. Keep the designer involved in reviewing the data regularly 4. Back analysis of the in situ condition, as required + +
  • 27. 15 November 2015 29 Thank you Underground Infrastructure and Deep Foundations UAE 16 & 17 November 2015 Benoît Latapie Technical Manager, Ground Engineering WS Atkins & Partners Overseas benoit.latapie@atkinsglobal.com +971 (0) 553003797