SlideShare a Scribd company logo
Incorporating Pile Set-Up Capacity in
Design of Driven Steel Pipe Piles at
Fort Hills
Martin Lun, M.Sc., P.Eng.
Co-Authors of Paper: Subhamoy Dasgupta (Suncor Energy)
Changyoung Kim (SK Engineering)
October 3, 2016
PRESENTATION SUMMARY
• Mechanism of Pile Set-Up in Sand
• Literature Review
• Pile Designs at Fort Hills
• Data Interpretation for Estimation of Pile Set-Up
• Application of Pile Set-up to Pile Design
2
MECHANISM OF PILE SET-UP IN SAND
• A number of researches attempted to
investigate the mechanism of pile set-up
but it is still not well understood
• Principal mechanisms include:
• Pore-water dissipation
• Stress Relaxation (due to soil arching)
• Soil aging (re-arrangement of particles)
3
MECHANISM OF PILE SET-UP IN SAND
4
LITERATURE REVIEW
• A number of empirical relationships have
been proposed for predicting set-up.
• Most researches exclude the initial pore-
water pressure phase as it is difficult to model
due to the non-linear behaviour.
• Empirical relationship established by Skov
and Denver (1988) is the most popular.
5
ESTABLISHED CORRELATIONS
6
PILE DESIGNS AT FORT HILLS
• Surficial geology consists of about 80 m thick
kame deposit (silty sand) over Clearwater
and/or McMurray Formation.
• Thurber completed over 100 auger test holes
and CPT soundings at Secondary Extraction
in 2013
• 2 static pile load tests completed
• Pile designs based on load tests.
• Soil variability assessed by CPTs and THs
7
8
9
PILE LOAD TESTS
• Two static load tests completed on a 610 mm
and 914 mm diameter steel pipe piles.
• Both piles installed to 18 m depth.
• 610 mm size pile reached maximum test load
of 6,200 kN without failure
• 914 mm size pile failed at a load of 9,000 kN.
• Average ultimate shaft resistance ranges
from 75 to 120 kPa based on the load tests
10
DURING CONSTRUCTION
• Pile acceptance based on driving set criteria
derived from PDA test results
• About 100 driving set criteria were
established based on site conditions, pile
sizes, design loads and driving hammers.
• Of the 10% production piles tested by PDA,
69% were tested at End of Initial Drive
(EOID); 25% at Beginning of Re-Strike
(BOR); 6% at both EOID and BOR.
11
CHALLENGES DURING CONSTRUCTION
• Aggressive designs based on load tests
(including set-up)
• Need to verify pile capacities during
construction by PDA tests
• Allow to do 10% PDA tests
• Selected piles were PDA tested at BOR.
• Congested site. Access was an issue.
• At the end, project was completed on
schedule and within budget.
12
PDA TEST DATA INTERPRETATION
• After completion of pile construction, the PDA
test data was screened with respect to soil
conditions, data from both EOID and BOR.
• 24 piles (610 and 762 mm dia.) were installed
in similar silty sand materials with PDA tested
completed on both EOID and BOR.
• Use Skov and Denver 1988 empirical
relationship to fit test data
13
14
DISCUSSIONS
• Based on my experience at Fort Hills, the
following guidelines may be followed to
consider setup in pile design:
• Need adequate test holes and CPTs to
delineate subsurface conditions
• A minimum 10% production piles to be
PDA tested at both EOID and BOR,
preferably at the start of construction
• Adequate re-strike required to confirm set-
up
15
CONCLUSION
• The objective of my paper is to incorporate set-up
and thus, provide better estimate of pile lengths for
future pile designs at Fort Hills.
• An average setup of 60% over 40 days from EOID
may be considered for similar soil type and driving
condition at Fort Hills, provided it can be further
assessed before and/or during construction.
• A thoughtful QA/QC program during construction
provides more than just quality. It may also reduce
project cost in relation to shorter pile lengths.
16
QUESTIONS?
17

More Related Content

What's hot

Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binder
Cheng (Wayne) Zhu
 
Sellountou evalaución integridad de pilotes
Sellountou   evalaución integridad de pilotesSellountou   evalaución integridad de pilotes
Sellountou evalaución integridad de pilotes
cfpbolivia
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
cfpbolivia
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
Alaa Metwally
 
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
impersal
 
Pile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionPile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile construction
Infocengrs63
 
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)Paul Brett
 
Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
Infocengrs63
 
Statnamic testing of soils
Statnamic testing of soilsStatnamic testing of soils
Statnamic testing of soilsSravan Muguda
 
A Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial Buildings
A Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial BuildingsA Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial Buildings
A Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial Buildings
IRJET Journal
 
Drill Bit Parameters
Drill Bit ParametersDrill Bit Parameters
Drill Bit Parameters
vaskelslide
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
Bhavik A Shah
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
Sohail Khan
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Er.Karan Chauhan
 
Pile load test
Pile load testPile load test
Pile load test
Naman Kantesaria
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
Infocengrs63
 
Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
Imran Nawaz
 
IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...
IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...
IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...
IRJET Journal
 

What's hot (20)

Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
Oxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binderOxidative aging and rheological performance of modified asphalt binder
Oxidative aging and rheological performance of modified asphalt binder
 
Sellountou evalaución integridad de pilotes
Sellountou   evalaución integridad de pilotesSellountou   evalaución integridad de pilotes
Sellountou evalaución integridad de pilotes
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
 
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
Sources recent publications conference proceedings_icap-isap_icap2006, 10th, ...
 
Aashto design
Aashto designAashto design
Aashto design
 
Pile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile constructionPile integrity testing for monitoring pile construction
Pile integrity testing for monitoring pile construction
 
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
Ultra-High-Pressure-Risers-for-Deepwater-Drilling-(DOT-Intl-09)
 
Foundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarhFoundation stabilization of the janmabhoomi temple at mangarh
Foundation stabilization of the janmabhoomi temple at mangarh
 
Statnamic testing of soils
Statnamic testing of soilsStatnamic testing of soils
Statnamic testing of soils
 
A Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial Buildings
A Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial BuildingsA Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial Buildings
A Parametric Study of Reinforced Concrete Slabs-on-Grade in Industrial Buildings
 
Drill Bit Parameters
Drill Bit ParametersDrill Bit Parameters
Drill Bit Parameters
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan Chauhan
 
Pile load test
Pile load testPile load test
Pile load test
 
Quality assurance for_deep_bored_piles
Quality assurance for_deep_bored_pilesQuality assurance for_deep_bored_piles
Quality assurance for_deep_bored_piles
 
Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
 
IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...
IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...
IRJET- A Review on Seismic Performance of Different Types of Flat Slab Buildi...
 

Similar to GeoVancouver Presentation

Study of design and construction methods of bored piles
Study of design and construction methods of bored pilesStudy of design and construction methods of bored piles
Study of design and construction methods of bored piles
Sahl Buhary
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
MailapalliJayaRaju
 
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
muralikrishna317515
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
ProSIM R & D Pvt. Ltd.
 
addition consideration in pile
addition consideration in pileaddition consideration in pile
addition consideration in pile
TharachJanesupasaere
 
Experimental investigation of reinforcement couplers as replacement of bent-bar
Experimental investigation of reinforcement couplers as replacement of bent-barExperimental investigation of reinforcement couplers as replacement of bent-bar
Experimental investigation of reinforcement couplers as replacement of bent-bar
rk pandey
 
PERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptx
PERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptxPERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptx
PERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptx
NetflixNetflix20
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeTong Seng Chua
 
GeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, AGeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, ATong Seng Chua
 
GeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, SingaporeGeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, SingaporeTong Seng Chua
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
DongyuanWang1
 
481_Final_Presentation_With_Transitions
481_Final_Presentation_With_Transitions481_Final_Presentation_With_Transitions
481_Final_Presentation_With_TransitionsCharles Ferriera
 
culverts-channeline-international.pptx
culverts-channeline-international.pptxculverts-channeline-international.pptx
culverts-channeline-international.pptx
raviyemmadi
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichau
nacetwincities
 
CRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BAR
CRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BARCRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BAR
CRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BAR
rk pandey
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptx
ReigerRoyal
 
50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction
Center for Transportation Research - UT Austin
 
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdfUHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
SriRam101316
 

Similar to GeoVancouver Presentation (20)

Study of design and construction methods of bored piles
Study of design and construction methods of bored pilesStudy of design and construction methods of bored piles
Study of design and construction methods of bored piles
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
 
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
addition consideration in pile
addition consideration in pileaddition consideration in pile
addition consideration in pile
 
Experimental investigation of reinforcement couplers as replacement of bent-bar
Experimental investigation of reinforcement couplers as replacement of bent-barExperimental investigation of reinforcement couplers as replacement of bent-bar
Experimental investigation of reinforcement couplers as replacement of bent-bar
 
PERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptx
PERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptxPERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptx
PERFORMANCE EVALUATION OF SCC BY INCORPORATING IOT AND.pptx
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
Kaplan05analysis
Kaplan05analysisKaplan05analysis
Kaplan05analysis
 
GeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, AGeoSS,18SEAGS,CTS,04062013, A
GeoSS,18SEAGS,CTS,04062013, A
 
GeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, SingaporeGeoSS,18SEAGS, 2013, Singapore
GeoSS,18SEAGS, 2013, Singapore
 
Thesis new
Thesis newThesis new
Thesis new
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
 
481_Final_Presentation_With_Transitions
481_Final_Presentation_With_Transitions481_Final_Presentation_With_Transitions
481_Final_Presentation_With_Transitions
 
culverts-channeline-international.pptx
culverts-channeline-international.pptxculverts-channeline-international.pptx
culverts-channeline-international.pptx
 
New Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary KrichauNew Rulemakings: What Can We Expect - Gary Krichau
New Rulemakings: What Can We Expect - Gary Krichau
 
CRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BAR
CRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BARCRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BAR
CRITICAL REVIEW ON MECHANICAL ANCHORAGE AS REPLACEMENT OF BENT BAR
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptx
 
50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction50 years of Innovation in Bridge Design & Construction
50 years of Innovation in Bridge Design & Construction
 
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdfUHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
UHPFRC-Gaps in Design & Construction Guidelines by Shri Aditya Sharma.pdf
 

GeoVancouver Presentation

  • 1. Incorporating Pile Set-Up Capacity in Design of Driven Steel Pipe Piles at Fort Hills Martin Lun, M.Sc., P.Eng. Co-Authors of Paper: Subhamoy Dasgupta (Suncor Energy) Changyoung Kim (SK Engineering) October 3, 2016
  • 2. PRESENTATION SUMMARY • Mechanism of Pile Set-Up in Sand • Literature Review • Pile Designs at Fort Hills • Data Interpretation for Estimation of Pile Set-Up • Application of Pile Set-up to Pile Design 2
  • 3. MECHANISM OF PILE SET-UP IN SAND • A number of researches attempted to investigate the mechanism of pile set-up but it is still not well understood • Principal mechanisms include: • Pore-water dissipation • Stress Relaxation (due to soil arching) • Soil aging (re-arrangement of particles) 3
  • 4. MECHANISM OF PILE SET-UP IN SAND 4
  • 5. LITERATURE REVIEW • A number of empirical relationships have been proposed for predicting set-up. • Most researches exclude the initial pore- water pressure phase as it is difficult to model due to the non-linear behaviour. • Empirical relationship established by Skov and Denver (1988) is the most popular. 5
  • 7. PILE DESIGNS AT FORT HILLS • Surficial geology consists of about 80 m thick kame deposit (silty sand) over Clearwater and/or McMurray Formation. • Thurber completed over 100 auger test holes and CPT soundings at Secondary Extraction in 2013 • 2 static pile load tests completed • Pile designs based on load tests. • Soil variability assessed by CPTs and THs 7
  • 8. 8
  • 9. 9
  • 10. PILE LOAD TESTS • Two static load tests completed on a 610 mm and 914 mm diameter steel pipe piles. • Both piles installed to 18 m depth. • 610 mm size pile reached maximum test load of 6,200 kN without failure • 914 mm size pile failed at a load of 9,000 kN. • Average ultimate shaft resistance ranges from 75 to 120 kPa based on the load tests 10
  • 11. DURING CONSTRUCTION • Pile acceptance based on driving set criteria derived from PDA test results • About 100 driving set criteria were established based on site conditions, pile sizes, design loads and driving hammers. • Of the 10% production piles tested by PDA, 69% were tested at End of Initial Drive (EOID); 25% at Beginning of Re-Strike (BOR); 6% at both EOID and BOR. 11
  • 12. CHALLENGES DURING CONSTRUCTION • Aggressive designs based on load tests (including set-up) • Need to verify pile capacities during construction by PDA tests • Allow to do 10% PDA tests • Selected piles were PDA tested at BOR. • Congested site. Access was an issue. • At the end, project was completed on schedule and within budget. 12
  • 13. PDA TEST DATA INTERPRETATION • After completion of pile construction, the PDA test data was screened with respect to soil conditions, data from both EOID and BOR. • 24 piles (610 and 762 mm dia.) were installed in similar silty sand materials with PDA tested completed on both EOID and BOR. • Use Skov and Denver 1988 empirical relationship to fit test data 13
  • 14. 14
  • 15. DISCUSSIONS • Based on my experience at Fort Hills, the following guidelines may be followed to consider setup in pile design: • Need adequate test holes and CPTs to delineate subsurface conditions • A minimum 10% production piles to be PDA tested at both EOID and BOR, preferably at the start of construction • Adequate re-strike required to confirm set- up 15
  • 16. CONCLUSION • The objective of my paper is to incorporate set-up and thus, provide better estimate of pile lengths for future pile designs at Fort Hills. • An average setup of 60% over 40 days from EOID may be considered for similar soil type and driving condition at Fort Hills, provided it can be further assessed before and/or during construction. • A thoughtful QA/QC program during construction provides more than just quality. It may also reduce project cost in relation to shorter pile lengths. 16