LECTURE NO.4
OFFER – TENDRING – PLANNING
Building Construction Technology I
International Burch university
Architecture department
Sarajevo
Course : Building Construction Technology I
Date : xx / xx / xxxx
Professor : Prof.dr.Nerman Rustempasic
Assistant : M.Sc. Ahmed El Sayed
INTRODUCTION
 Offer – tendering and construction site are very important
themes for every engineer. Without understanding these
terms and process, a lot of problems will occur such as :
why we didn’t get this project? Why the other company or
designers are getting the jobs and not us?
 This kind of questions can be answered if the designer (
engineer ) learns the realtion between designing and
winning in tender.
 Without the tenderation there are no projects, which means
that designers will have no jobs to do.
TENDER OFFER FROM THE CLIENT'S AND
ARCHITECT'S PERSPECTIVE
 Perception of the stages of a construction project often
varies between the client/architect and the contractor.
 Client and architect are involved in the project for months
before the actual construction work commences, for a
contractor however stages of the project include only the
tender offer and construction stages.
 Tender procedure, from client’s and architect’s point of view,
is regulated by NJCC (National Joint Consultative
Committee for Building).
TENDER OFFER FROM THE CLIENT'S AND
ARCHITECT'S PERSPECTIVE
 Most small projects apply the "Single Stage Selective
Tendering” which can be characterized in the following way:
 Invitation to tender – the contractors are contacted if they would be
willing to tender. The enquiry is issued in writing 4-6 weeks before
the tender and it should contain a brief description of the investment
and the commencement date.
 Number of contractors tendering – recommended maximum
number of contractors is 6, with additional in reserve. The limitation
is due to the fact, that the tenders tend to be expensive and it is
irresponsible to unnecessarily inflate prices in the construction
industry.
TENDER OFFER FROM THE CLIENT'S AND
ARCHITECT'S PERSPECTIVE
 Tender documentation – the aim of tender documentation all offers
will be presented on the same basis, so the competition may only be
about the price. It is assumed that each contractor will complete
works in a way specified in documentation.
 Time to prepare tender offer – in smaller projects it is usually 3-4
weeks, in bigger and more complex investments it can take longer.
 Changes in tender documentation – contractors should not make any
changes. They should instead send an enquiry min. 10 days before
the tender date. Architect should send a reply to all contractors to
provide them all the same chances.
TENDER OFFER FROM THE CLIENT'S AND
ARCHITECT'S PERSPECTIVE
 It is often disregarded in practice, due to the short time
allowed to prepare an estimate or vagueness.
 Withdrawal of the offer – tender offer can be withdrawn by the
contractor at all times, as long as it has not been chosen by the
investor. Acceptance of an offer constitutes an agreement between
the investor and contractor.
 Tender offers analysis – tender offers should be analyzed soon after
they were returned. After the contract is awarded architect should
inform all participants about the offers received, without naming the
companies, which put them forward. Even though it gives contractors
an insight into competitor’s pricing policy, it is often disregarded.
TENDER OFFER FROM THE CLIENT'S AND
ARCHITECT'S PERSPECTIVE
 Error check – the winning estimate is checked and the erroneous
calculations are sent back to the contractor. There are two
procedures to resolve those: "Alternative 1" – where the contractor
can confirm or withdraw the offer and "Alternative 2" - where the
contractor can confirm the offer or correct mistakes.
 Price negotiation – procedures allow pricing negotiations leading to
lowering the prices if the lowest offer exceeds investor’s budget.
BASICS OF COST ESTIMATE PREPARATION
 Preparation of tender offer requires various documentation
types, as specified by an architect or an investor. They
involve different terms of settlement and risk.
 Regardless of the type of documentation one should take
into account costs not directly connected with corresponding
construction works, e.g. cost of the toilet, on-site safety,
company standing costs etc. Those costs are usually
included in the "Preliminaries", at the beginning of the
estimate.
SPECIFICATION & DRAWINGS
 This type of documentation contains drawings and
specification; it can also contain a separate scope of works
to clarify the full costs.
 Contractor is responsible for surveying the works. Any errors
in measurements and cost estimates will not be taken into
consideration and the contractor will be required to conduct
all the works indicated in the documentation, regardless of
whether they are specified by the scope of work. It means
that contractor needs to check all documentation carefully,
since each its element included in any part of
documentation constitutes part of contract and needs to be
completed.
BILL OF QUANTITIES
 In case of bigger projects, tender documents often consist of
"Bill of Quantities" (BoQ). It is a list of all required works
(with all measurements already made) – the contractor
needs to provide their rates for each of the works.
 BoQ is prepared by "Quantity Surveyor" employed by the
investor, according to Standard Method of Measurement -
SMM.
 The latest version is SMM7, but the smaller project still often
use.
BILL OF QUANTITIES
 The rates given in BoQ will be used to calculate the cost
of additional works of the same type during the project,
it is therefore worth to try to foresee potential additional
works and raise the rate for the corresponding type of
works.
 The errors in the BoQ are the liability of the investor – the
contractor needs to be paid for all works required, even if
they are erroneous or if some works are omitted. Because
of that BoQ is not used often anymore.
 If the investor cannot state exact measurements, the
approximate quantities are applied.
SCHEDULE OF RATES
 "Schedule of Rates" is the list of the rates and it’s used very
rarely, only in case if the scope of work is impossible to define.
 The contractor is accountable for completed works according to
the time and agreed hourly or daily rates.
 It is of course an ideal basis for cooperation from contractor's
point of view, because they are not at any risk and all the
materials and employees working time is being paid for.
 In case of such cooperation form it is crucial to keep a detailed
record of time and resources spent during the project. Those are
necessary to establish the payment and eliminate potential
conflicts between contractor and investor.
SCHEDULING AND PLANNING CONSTRUCTION
WORKS
 Without proper planning it is difficult to make a construction
project run smoothly and be completed on time and within
budget. Of course, smaller and less complex projects very often
do not have a formulated formal plan or schedule, since all
planning takes place in manager’s head.
 It is an acceptable solution, however everyone’s perception has
its limits, and in most cases it is impossible to manage all aspects
of a months-long project without the use of additional tools. The
main reasons for planning in construction works can be summed
up as:
 Improved management of works and resources, their sequence and
consequences of any changes that may take place
 Ability to establish a realistic completion date
 Improved efficiency control
 Facilitated risk assessment process of the project
 Basis for solving contractual claims resulting from delays
SCHEDULING AND PLANNING CONSTRUCTION
WORKS
 Appropriate schedule of works allows to establish
completion dates for all stages and elements of works, e.g.
when will the electrician be needed, when will the garden
door be installed, floor panels delivered etc. Of course,
scheduling is not about planning works a week in advance –
this can be done by every skilled worker.
 A correctly designed work schedule allows such information
to be provided months in advance. Such information often
proves crucial, especially when orders have to be made
long before the delivery.
PLANNING TECHNIQUES
 The only technique commonly applied in small and middle
sized projects is “Gantt chart" or "Bar chart” (both names
refer to the same method).
 Other techniques (arrow diagrams, precedence diagrams,
line of balance, time-chainage diagrams) are only applied to
large projects, often involving infrastructural works. Please
contact us for further information about these methods.
GANTT CHART
 Gantt or Bar chart is the easiest available planning
technique, and probably the only one commonly understood
without prior training. Despite its simplicity, a correctly
designed chart will provide a lot of information necessary to
complete the project.
 Each line on the chart indicates a task or group of tasks
necessary in the project. The length of a bar is relative to
the time necessary to carry out a task.
 Individual tasks stand in dynamic dependency relationships
that reflect the order of completion. This allows for a fast
check of how, e.g. a delay of task A will influence the
completion of task C, taking place 2 months later.
GANTT CHART
 Appropriately prepared chart indicates the critical tasks, i.e.
the ones that determine the timely completion of the entire
project. These form a "critical path". This allows for more
attention to be given to the most important tasks.
 Each task can be assigned necessary resources, workers,
equipment and material, which facilitates the procedures of
placing orders and workforce management.
 Additionally, the chart may include, or be the basis for a
detailed analysis of financial flow in the project and risk
management.
GANTT CHART
TYPES OF SCHEDULES
 Schedules can be classified depending on the type and precision of
information provided.
 Master program : It is a general project plan, which does not include
any details, and only shows the main stages of works. It is mainly useful
for the clients and architects supervising the completion time. The
master program must be provided to architect by the contractor.
 Detailed program : It is an expansion of a master program, which
includes all activities and details of works completion. It is used by the
contractor to manage works and resources. Usually it is not passed on
to client or architect. Due to the large amount of information it contains,
the detailed program is often prepared to only embrace a specific period
of time (e.g. 1 or 2 weeks of works).
TYPES OF SCHEDULES
 Purchase Schedule : Additional schedules are created as
necessary by filtering the data included in “Detailed
program”. The most popular is "the purchase schedule",
which indicates the deadlines for making orders. All data is
dynamically related, and therefore if the installation of
windows, which have to be ordered 4 weeks in advance, is
delayed, the schedule will automatically suggest new order
date.
 Using schedules greatly facilitates site management and
reduces risk of making a mistake or missing out important
tasks.
SOFTWARE
 The development of computers and scheduling software has made
preparing and updating of schedules much easier. There are many
programs available, differing in functions advancement, user-
friendliness and price.
 Probably the most popular tools available for MS Windows are:
 MS Project
 Asta PowerProject
 Primavera
 Choosing appropriate planning software depends on individual needs
and preferences. It’s worth to have a look around and choose among
many available additional options. One very useful additional feature is
the possibility to synchronize tasks with calendar, or sharing the plan
among several employees.
RISK MANAGEMENT
 Using planning software makes it possible to expand the
functions of schedules to include project risk management. Easy
scenarios analysis processes allow preparation of many variants
of project, e.g. what will the consequences of a delay for a
particular task be and how to deal with them. This kind of
theoretical analysis allows better understanding the mechanisms
behind the project and preparing alternative plans, should
problems emerge.
 Risk analysis can be summed up with the following:
 Hazard identification ( Identification of dangerous things )
 Probability and consequences estimate
 Deciding on risk management method (avoidance, reduction, sharing
and retention)
 Management and supervision
 Conclusion and report
PROBLEMS WITH SCHEDULES
 Planning and schedules are not problem-free and, as it happens, their
benefits are not fully used.
 One must bear in mind that schedule is a dynamical tool which needs to
be regularly updated in order to serve us most efficiently. Every
construction plan is appropriate only until the project has started. It can
be often seen, that our plans do not reflect reality, in which case the plan
must be updated, otherwise it will lose its adequacy.
 Plan is only as good as the person who created it. Software is only a
tool, not a magical solution to all our problems. If the project deadline we
set is not realistic, there is no plan which will make completion on time
possible.
THANK YOU

More Related Content

What's hot

Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionHamdija Velagic
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
R.R.G.S Bandara
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Antonio Coladarce
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
Dr K M SONI
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
Timun Loh
 
jeremiah lukwesa kaluba
jeremiah lukwesa kalubajeremiah lukwesa kaluba
jeremiah lukwesa kaluba
JeremiahLukwesa
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Antonio Coladarce
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - siteAbdulaziz Kaya
 
EPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk ManagementEPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk Management
rockporshe
 
4 storied building superstructure construction proposal
4 storied building superstructure construction proposal4 storied building superstructure construction proposal
4 storied building superstructure construction proposal
Mkh Nantu
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
Galala University
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 

What's hot (20)

Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Construction management
Construction managementConstruction management
Construction management
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
2014-2015
2014-20152014-2015
2014-2015
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
jeremiah lukwesa kaluba
jeremiah lukwesa kalubajeremiah lukwesa kaluba
jeremiah lukwesa kaluba
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
API 510 RESUME
API 510 RESUMEAPI 510 RESUME
API 510 RESUME
 
CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015
 
CV (1)
CV (1)CV (1)
CV (1)
 
EPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk ManagementEPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk Management
 
4 storied building superstructure construction proposal
4 storied building superstructure construction proposal4 storied building superstructure construction proposal
4 storied building superstructure construction proposal
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 

Viewers also liked

Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
Tender Process
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
politeknik malaysia
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldingsHamdija Velagic
 
Introduction to Arch Week 14
Introduction to Arch Week 14Introduction to Arch Week 14
Introduction to Arch Week 14Hamdija Velagic
 
Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Hamdija Velagic
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materialsHamdija Velagic
 
Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction siteHamdija Velagic
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
nipuna_bopage
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
Mincore Capability and Experience Profile
Mincore Capability and Experience ProfileMincore Capability and Experience Profile
Mincore Capability and Experience ProfileCameron Bain
 
Must have interiors in dubai
Must have interiors in dubaiMust have interiors in dubai
Must have interiors in dubai
RhoOmega
 
Company Profile Industrial English
Company Profile Industrial EnglishCompany Profile Industrial English
Company Profile Industrial English
cnmrarq
 
10 me667 chap3 organizing and staffing
10 me667 chap3 organizing and staffing10 me667 chap3 organizing and staffing
10 me667 chap3 organizing and staffingPavan Kumar
 
Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Hamdija Velagic
 
Building Construction 4. tender offer
Building Construction 4. tender offerBuilding Construction 4. tender offer
Building Construction 4. tender offerHamdija Velagic
 
Introduction to Arch Week 11
Introduction to Arch Week 11Introduction to Arch Week 11
Introduction to Arch Week 11Hamdija Velagic
 

Viewers also liked (20)

Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldings
 
Introduction to Arch Week 14
Introduction to Arch Week 14Introduction to Arch Week 14
Introduction to Arch Week 14
 
Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction site
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
Mincore Capability and Experience Profile
Mincore Capability and Experience ProfileMincore Capability and Experience Profile
Mincore Capability and Experience Profile
 
Must have interiors in dubai
Must have interiors in dubaiMust have interiors in dubai
Must have interiors in dubai
 
Company Profile Industrial English
Company Profile Industrial EnglishCompany Profile Industrial English
Company Profile Industrial English
 
10 me667 chap3 organizing and staffing
10 me667 chap3 organizing and staffing10 me667 chap3 organizing and staffing
10 me667 chap3 organizing and staffing
 
Into. to Arch Week 2
Into. to Arch Week 2Into. to Arch Week 2
Into. to Arch Week 2
 
Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]
 
Building Construction 4. tender offer
Building Construction 4. tender offerBuilding Construction 4. tender offer
Building Construction 4. tender offer
 
Into. to Arch Week 3
Into. to Arch Week 3Into. to Arch Week 3
Into. to Arch Week 3
 
Introduction to Arch Week 11
Introduction to Arch Week 11Introduction to Arch Week 11
Introduction to Arch Week 11
 

Similar to Building Construction 4. offer tendering - site

Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
Muthanna Abbu
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
AprilRosal1
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
Arissa Loh
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
Kai Yun Pang
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
Ngo Jia Haur
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
NithyaPotterhead
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
Lwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
Lwj Welson
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
tfkc1212
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
Gregoire Lesecq
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
Ar.Vijay Kumar
 
QSS
QSSQSS
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
Js Cheok
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
Jy Chong
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
Ashok Tundare
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
Sahl Buhary
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 

Similar to Building Construction 4. offer tendering - site (20)

Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
QSS
QSSQSS
QSS
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
Qsx
QsxQsx
Qsx
 

More from Hamdija Velagic

Introduction to Arch Week 13
Introduction to Arch Week 13Introduction to Arch Week 13
Introduction to Arch Week 13Hamdija Velagic
 
Introduction to Arch List of potential questions
Introduction to Arch List of potential questionsIntroduction to Arch List of potential questions
Introduction to Arch List of potential questionsHamdija Velagic
 
Architecture form space order
Architecture form space orderArchitecture form space order
Architecture form space orderHamdija Velagic
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffoldingHamdija Velagic
 
Building Construction 6. intro to building materials
Building Construction 6. intro to building materialsBuilding Construction 6. intro to building materials
Building Construction 6. intro to building materialsHamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
New Intro to Architecture Week 4
New Intro to Architecture Week 4New Intro to Architecture Week 4
New Intro to Architecture Week 4Hamdija Velagic
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionHamdija Velagic
 
1. Introduction to Project Management
1. Introduction to Project Management1. Introduction to Project Management
1. Introduction to Project ManagementHamdija Velagic
 

More from Hamdija Velagic (9)

Introduction to Arch Week 13
Introduction to Arch Week 13Introduction to Arch Week 13
Introduction to Arch Week 13
 
Introduction to Arch List of potential questions
Introduction to Arch List of potential questionsIntroduction to Arch List of potential questions
Introduction to Arch List of potential questions
 
Architecture form space order
Architecture form space orderArchitecture form space order
Architecture form space order
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffolding
 
Building Construction 6. intro to building materials
Building Construction 6. intro to building materialsBuilding Construction 6. intro to building materials
Building Construction 6. intro to building materials
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
New Intro to Architecture Week 4
New Intro to Architecture Week 4New Intro to Architecture Week 4
New Intro to Architecture Week 4
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
 
1. Introduction to Project Management
1. Introduction to Project Management1. Introduction to Project Management
1. Introduction to Project Management
 

Recently uploaded

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
Auditing study material for b.com final year students
Auditing study material for b.com final year  studentsAuditing study material for b.com final year  students
Auditing study material for b.com final year students
narasimhamurthyh4
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
FelixPerez547899
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Training my puppy and implementation in this story
Training my puppy and implementation in this storyTraining my puppy and implementation in this story
Training my puppy and implementation in this story
WilliamRodrigues148
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
JeremyPeirce1
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdf
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdfBài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdf
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdf
daothibichhang1
 
An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.
Any kyc Account
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
Aggregage
 

Recently uploaded (20)

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
Auditing study material for b.com final year students
Auditing study material for b.com final year  studentsAuditing study material for b.com final year  students
Auditing study material for b.com final year students
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Training my puppy and implementation in this story
Training my puppy and implementation in this storyTraining my puppy and implementation in this story
Training my puppy and implementation in this story
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdf
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdfBài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdf
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc.pdf
 
An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
 

Building Construction 4. offer tendering - site

  • 1. LECTURE NO.4 OFFER – TENDRING – PLANNING Building Construction Technology I International Burch university Architecture department Sarajevo Course : Building Construction Technology I Date : xx / xx / xxxx Professor : Prof.dr.Nerman Rustempasic Assistant : M.Sc. Ahmed El Sayed
  • 2. INTRODUCTION  Offer – tendering and construction site are very important themes for every engineer. Without understanding these terms and process, a lot of problems will occur such as : why we didn’t get this project? Why the other company or designers are getting the jobs and not us?  This kind of questions can be answered if the designer ( engineer ) learns the realtion between designing and winning in tender.  Without the tenderation there are no projects, which means that designers will have no jobs to do.
  • 3. TENDER OFFER FROM THE CLIENT'S AND ARCHITECT'S PERSPECTIVE  Perception of the stages of a construction project often varies between the client/architect and the contractor.  Client and architect are involved in the project for months before the actual construction work commences, for a contractor however stages of the project include only the tender offer and construction stages.  Tender procedure, from client’s and architect’s point of view, is regulated by NJCC (National Joint Consultative Committee for Building).
  • 4. TENDER OFFER FROM THE CLIENT'S AND ARCHITECT'S PERSPECTIVE  Most small projects apply the "Single Stage Selective Tendering” which can be characterized in the following way:  Invitation to tender – the contractors are contacted if they would be willing to tender. The enquiry is issued in writing 4-6 weeks before the tender and it should contain a brief description of the investment and the commencement date.  Number of contractors tendering – recommended maximum number of contractors is 6, with additional in reserve. The limitation is due to the fact, that the tenders tend to be expensive and it is irresponsible to unnecessarily inflate prices in the construction industry.
  • 5. TENDER OFFER FROM THE CLIENT'S AND ARCHITECT'S PERSPECTIVE  Tender documentation – the aim of tender documentation all offers will be presented on the same basis, so the competition may only be about the price. It is assumed that each contractor will complete works in a way specified in documentation.  Time to prepare tender offer – in smaller projects it is usually 3-4 weeks, in bigger and more complex investments it can take longer.  Changes in tender documentation – contractors should not make any changes. They should instead send an enquiry min. 10 days before the tender date. Architect should send a reply to all contractors to provide them all the same chances.
  • 6. TENDER OFFER FROM THE CLIENT'S AND ARCHITECT'S PERSPECTIVE  It is often disregarded in practice, due to the short time allowed to prepare an estimate or vagueness.  Withdrawal of the offer – tender offer can be withdrawn by the contractor at all times, as long as it has not been chosen by the investor. Acceptance of an offer constitutes an agreement between the investor and contractor.  Tender offers analysis – tender offers should be analyzed soon after they were returned. After the contract is awarded architect should inform all participants about the offers received, without naming the companies, which put them forward. Even though it gives contractors an insight into competitor’s pricing policy, it is often disregarded.
  • 7. TENDER OFFER FROM THE CLIENT'S AND ARCHITECT'S PERSPECTIVE  Error check – the winning estimate is checked and the erroneous calculations are sent back to the contractor. There are two procedures to resolve those: "Alternative 1" – where the contractor can confirm or withdraw the offer and "Alternative 2" - where the contractor can confirm the offer or correct mistakes.  Price negotiation – procedures allow pricing negotiations leading to lowering the prices if the lowest offer exceeds investor’s budget.
  • 8. BASICS OF COST ESTIMATE PREPARATION  Preparation of tender offer requires various documentation types, as specified by an architect or an investor. They involve different terms of settlement and risk.  Regardless of the type of documentation one should take into account costs not directly connected with corresponding construction works, e.g. cost of the toilet, on-site safety, company standing costs etc. Those costs are usually included in the "Preliminaries", at the beginning of the estimate.
  • 9. SPECIFICATION & DRAWINGS  This type of documentation contains drawings and specification; it can also contain a separate scope of works to clarify the full costs.  Contractor is responsible for surveying the works. Any errors in measurements and cost estimates will not be taken into consideration and the contractor will be required to conduct all the works indicated in the documentation, regardless of whether they are specified by the scope of work. It means that contractor needs to check all documentation carefully, since each its element included in any part of documentation constitutes part of contract and needs to be completed.
  • 10. BILL OF QUANTITIES  In case of bigger projects, tender documents often consist of "Bill of Quantities" (BoQ). It is a list of all required works (with all measurements already made) – the contractor needs to provide their rates for each of the works.  BoQ is prepared by "Quantity Surveyor" employed by the investor, according to Standard Method of Measurement - SMM.  The latest version is SMM7, but the smaller project still often use.
  • 11. BILL OF QUANTITIES  The rates given in BoQ will be used to calculate the cost of additional works of the same type during the project, it is therefore worth to try to foresee potential additional works and raise the rate for the corresponding type of works.  The errors in the BoQ are the liability of the investor – the contractor needs to be paid for all works required, even if they are erroneous or if some works are omitted. Because of that BoQ is not used often anymore.  If the investor cannot state exact measurements, the approximate quantities are applied.
  • 12. SCHEDULE OF RATES  "Schedule of Rates" is the list of the rates and it’s used very rarely, only in case if the scope of work is impossible to define.  The contractor is accountable for completed works according to the time and agreed hourly or daily rates.  It is of course an ideal basis for cooperation from contractor's point of view, because they are not at any risk and all the materials and employees working time is being paid for.  In case of such cooperation form it is crucial to keep a detailed record of time and resources spent during the project. Those are necessary to establish the payment and eliminate potential conflicts between contractor and investor.
  • 13. SCHEDULING AND PLANNING CONSTRUCTION WORKS  Without proper planning it is difficult to make a construction project run smoothly and be completed on time and within budget. Of course, smaller and less complex projects very often do not have a formulated formal plan or schedule, since all planning takes place in manager’s head.  It is an acceptable solution, however everyone’s perception has its limits, and in most cases it is impossible to manage all aspects of a months-long project without the use of additional tools. The main reasons for planning in construction works can be summed up as:  Improved management of works and resources, their sequence and consequences of any changes that may take place  Ability to establish a realistic completion date  Improved efficiency control  Facilitated risk assessment process of the project  Basis for solving contractual claims resulting from delays
  • 14. SCHEDULING AND PLANNING CONSTRUCTION WORKS  Appropriate schedule of works allows to establish completion dates for all stages and elements of works, e.g. when will the electrician be needed, when will the garden door be installed, floor panels delivered etc. Of course, scheduling is not about planning works a week in advance – this can be done by every skilled worker.  A correctly designed work schedule allows such information to be provided months in advance. Such information often proves crucial, especially when orders have to be made long before the delivery.
  • 15. PLANNING TECHNIQUES  The only technique commonly applied in small and middle sized projects is “Gantt chart" or "Bar chart” (both names refer to the same method).  Other techniques (arrow diagrams, precedence diagrams, line of balance, time-chainage diagrams) are only applied to large projects, often involving infrastructural works. Please contact us for further information about these methods.
  • 16. GANTT CHART  Gantt or Bar chart is the easiest available planning technique, and probably the only one commonly understood without prior training. Despite its simplicity, a correctly designed chart will provide a lot of information necessary to complete the project.  Each line on the chart indicates a task or group of tasks necessary in the project. The length of a bar is relative to the time necessary to carry out a task.  Individual tasks stand in dynamic dependency relationships that reflect the order of completion. This allows for a fast check of how, e.g. a delay of task A will influence the completion of task C, taking place 2 months later.
  • 17. GANTT CHART  Appropriately prepared chart indicates the critical tasks, i.e. the ones that determine the timely completion of the entire project. These form a "critical path". This allows for more attention to be given to the most important tasks.  Each task can be assigned necessary resources, workers, equipment and material, which facilitates the procedures of placing orders and workforce management.  Additionally, the chart may include, or be the basis for a detailed analysis of financial flow in the project and risk management.
  • 19. TYPES OF SCHEDULES  Schedules can be classified depending on the type and precision of information provided.  Master program : It is a general project plan, which does not include any details, and only shows the main stages of works. It is mainly useful for the clients and architects supervising the completion time. The master program must be provided to architect by the contractor.  Detailed program : It is an expansion of a master program, which includes all activities and details of works completion. It is used by the contractor to manage works and resources. Usually it is not passed on to client or architect. Due to the large amount of information it contains, the detailed program is often prepared to only embrace a specific period of time (e.g. 1 or 2 weeks of works).
  • 20. TYPES OF SCHEDULES  Purchase Schedule : Additional schedules are created as necessary by filtering the data included in “Detailed program”. The most popular is "the purchase schedule", which indicates the deadlines for making orders. All data is dynamically related, and therefore if the installation of windows, which have to be ordered 4 weeks in advance, is delayed, the schedule will automatically suggest new order date.  Using schedules greatly facilitates site management and reduces risk of making a mistake or missing out important tasks.
  • 21. SOFTWARE  The development of computers and scheduling software has made preparing and updating of schedules much easier. There are many programs available, differing in functions advancement, user- friendliness and price.  Probably the most popular tools available for MS Windows are:  MS Project  Asta PowerProject  Primavera  Choosing appropriate planning software depends on individual needs and preferences. It’s worth to have a look around and choose among many available additional options. One very useful additional feature is the possibility to synchronize tasks with calendar, or sharing the plan among several employees.
  • 22. RISK MANAGEMENT  Using planning software makes it possible to expand the functions of schedules to include project risk management. Easy scenarios analysis processes allow preparation of many variants of project, e.g. what will the consequences of a delay for a particular task be and how to deal with them. This kind of theoretical analysis allows better understanding the mechanisms behind the project and preparing alternative plans, should problems emerge.  Risk analysis can be summed up with the following:  Hazard identification ( Identification of dangerous things )  Probability and consequences estimate  Deciding on risk management method (avoidance, reduction, sharing and retention)  Management and supervision  Conclusion and report
  • 23. PROBLEMS WITH SCHEDULES  Planning and schedules are not problem-free and, as it happens, their benefits are not fully used.  One must bear in mind that schedule is a dynamical tool which needs to be regularly updated in order to serve us most efficiently. Every construction plan is appropriate only until the project has started. It can be often seen, that our plans do not reflect reality, in which case the plan must be updated, otherwise it will lose its adequacy.  Plan is only as good as the person who created it. Software is only a tool, not a magical solution to all our problems. If the project deadline we set is not realistic, there is no plan which will make completion on time possible.