Pre Phase
Initiation
phase
Design &
Developm
ent
Phase
Conclusi
on
Operation
phase
 Energy crisis
 Strengthen agriculture system
 Regulate the flow of Indus river to avoid
flood.
 On april 1948,India cutoff supply of water from
three rivers Ravi,Satlaj & Beas.
 It causes a setback to our national economy and
disrupted Pakistan water resourses development
plan.
 To overcome this situation Indus water treaty(IWT)
was signed on 19 September 1960.
 Indus Basin Project was developed under IWT.
 Indus Basin Project had two subprojects on
Jhelum(Mangla) and Indus(Tarbella).
 Stakeholders were Government of Pakistan
and the people of Pakistan.
 Environment and climate
• In lower Indus plan , the temperature is 14-20
degree in winter and 42-44 degree in summer.
• Average rain fall in Indus plain is about
23cm.In lower Indus areas receives about 9cm
of average rainfall annually.
• Location of Tarbella Dam is such that about
90% of annual river is derived from snowmelt.
 Internal Constraints
• Provential Government
• Central Government
 External Constraints
• Indus Water Treaty(IWT):
 Affected Families
• About 135 villages were effected.
• It resulted in displacement of
population of about 9,6000 people.
• Land acquisition and a cash
compensation of RS.469.65 million
allotted to effected families.
 Design characteristics of Tarbella were evolved on the basis of
site investigation area over the period 1955-62.
 Searching the site for Dam was the responsibility of WAPDA,
which stated site investigation.
 It took 3 years of thorough investigation to select site.
 Sites Investigated
Three sites were chosen namely:
• Bara with Potential storage capacity of 13.7bcm.
• Kiara with potential storage capacity of 12.3bcm.
• Kirpalian with potential storage capacity of 5.3bcm.
 Final site chosen was Bara.
 Studies indicated that Bara had more favorable
geology.
 Bara would result in less expensive project.
 Contractor of projects
• Tarbella dam project was built by Tarbella dam
project venture , which was led by Italian
contractor Impregilo.
• The joint venture consist of 3 Italians and 3
French Civil Engineers.
• Five German and 2 Swiss companies joined them
in 1969.
• Chief Engr. Mr. SS Kerman was entrusted with
responsibility of evaluating technical aspects of
design on behalf of WAPDA.
• Estimated Hydropower potential was 2100MW.
 An estimate of financial requirement of Tarbella dam
project according to Lieftinck report were 1047.3 million
dollars including land resettlement and first eight power
units of 175MW each.
 This also include 150.5 million$ for import duties but
excluded interests during construction.
 Correspondingly estimated financial requirement
excluding Mechanical and Electrical power , but including
Civil Engineering work for eight power units was 99.6
million $.
Duration Capital Cost US$
Up to June 65 51 million
65-66 3 million
66-67 55 million
67-68 140million
68-69 618 million
69-70 983 million
70-71 1191 million
71-72 1159 million
72-73 394 million
73-74 612 million
74-75 497 million
75-76 334 million
 To meet capital cost balance of $354 million were
transferred from Indus Basin development fund to create
Tarbella development fund(TDF).
 TDF had a capital base of $ 989 million with commitment
from Govt. of Pakistan.
 Resources of Tarbella development fund.
Countries Funds( million $)
Australia 1
Canada 14
France 30
Germany 16
Italy 56
UK 51
USA 60
World Bank 71
Saudi Arabia 59
Kuwait 18
Abu Dhabi 25
Pakistan 697
Others 25
 Predicted and actual Impacts:
• Power House
Power Units Planned Actual(MW)
Tunnel 1 4*175=700MW 700MW(1977-78)
Tunnel 2 4*175=700MW 1050MW(1982-85)
Tunnel 3 4*175=700MW 1728MW(1992-93)
Total Installed
Capacity
2100MW 3478MW
 Predicted and actual Impacts:
• Schedule
Construction
Stages
Project
Component
Activities
Scheduled Actual
Mobilization Including award
of main contract
Jun1967- Dec1969 May1968-Dec 70
Stage 1 River diversion Jan 1968-Sep 70 May 68-Sep 70
Stage 2 Spillways,
Tunnels
Oct 70-Sep 73 Oct 70-Sep 73
Stage 3 Auxiliary Dam &
Power Station
Oct 73 –Sep 74 Sep 73-Sep 74
Flow through
Tunnel
Stage 4 Unit 1 & 2 Jan 75 – Mar 75 April 77-may 77
Commissioning
of Power
Unit 3 & 4 Oct 75 –Mar 76 Jun 77 – July 77
 Due to high demand of Electricity instead of making new
projects , the Govt. of Pakistan started to upgrade the
existing projects.
 In Sep 2013 , WAPDA signed RS:26.053 billion contract
with Chinese firm Sino hydro for executing Civil works on
the 1410MW Tarbella extension project.
 Work on the Project will be completed in 3 &1/2 years at
an estimated cost of $928 million.
 In June 2013 , The World Bank has agreed to provide a
$840 million loan for project.
 On completion , the project will increase generation
capacity from 3478MW to 4888 MW.
 Prime Minister Nawaz Sharif ordered WAPDA to increase
the feasibility study of Tarbella.
 Next extension would increase additional generation of
1320MW electricity and increase overall capacity to
6208MW.
 The Australian Govt. has shown its keen interest to
finance this latest extension.
Thank You

Tarbela dam project

  • 3.
  • 4.
     Energy crisis Strengthen agriculture system  Regulate the flow of Indus river to avoid flood.
  • 5.
     On april1948,India cutoff supply of water from three rivers Ravi,Satlaj & Beas.  It causes a setback to our national economy and disrupted Pakistan water resourses development plan.  To overcome this situation Indus water treaty(IWT) was signed on 19 September 1960.
  • 6.
     Indus BasinProject was developed under IWT.  Indus Basin Project had two subprojects on Jhelum(Mangla) and Indus(Tarbella).
  • 7.
     Stakeholders wereGovernment of Pakistan and the people of Pakistan.  Environment and climate • In lower Indus plan , the temperature is 14-20 degree in winter and 42-44 degree in summer. • Average rain fall in Indus plain is about 23cm.In lower Indus areas receives about 9cm of average rainfall annually. • Location of Tarbella Dam is such that about 90% of annual river is derived from snowmelt.
  • 8.
     Internal Constraints •Provential Government • Central Government  External Constraints • Indus Water Treaty(IWT):
  • 9.
     Affected Families •About 135 villages were effected. • It resulted in displacement of population of about 9,6000 people. • Land acquisition and a cash compensation of RS.469.65 million allotted to effected families.
  • 10.
     Design characteristicsof Tarbella were evolved on the basis of site investigation area over the period 1955-62.  Searching the site for Dam was the responsibility of WAPDA, which stated site investigation.  It took 3 years of thorough investigation to select site.  Sites Investigated Three sites were chosen namely: • Bara with Potential storage capacity of 13.7bcm. • Kiara with potential storage capacity of 12.3bcm. • Kirpalian with potential storage capacity of 5.3bcm.  Final site chosen was Bara.
  • 11.
     Studies indicatedthat Bara had more favorable geology.  Bara would result in less expensive project.  Contractor of projects • Tarbella dam project was built by Tarbella dam project venture , which was led by Italian contractor Impregilo. • The joint venture consist of 3 Italians and 3 French Civil Engineers.
  • 12.
    • Five Germanand 2 Swiss companies joined them in 1969. • Chief Engr. Mr. SS Kerman was entrusted with responsibility of evaluating technical aspects of design on behalf of WAPDA. • Estimated Hydropower potential was 2100MW.
  • 13.
     An estimateof financial requirement of Tarbella dam project according to Lieftinck report were 1047.3 million dollars including land resettlement and first eight power units of 175MW each.  This also include 150.5 million$ for import duties but excluded interests during construction.  Correspondingly estimated financial requirement excluding Mechanical and Electrical power , but including Civil Engineering work for eight power units was 99.6 million $.
  • 14.
    Duration Capital CostUS$ Up to June 65 51 million 65-66 3 million 66-67 55 million 67-68 140million 68-69 618 million 69-70 983 million 70-71 1191 million 71-72 1159 million 72-73 394 million 73-74 612 million 74-75 497 million 75-76 334 million
  • 15.
     To meetcapital cost balance of $354 million were transferred from Indus Basin development fund to create Tarbella development fund(TDF).  TDF had a capital base of $ 989 million with commitment from Govt. of Pakistan.
  • 16.
     Resources ofTarbella development fund. Countries Funds( million $) Australia 1 Canada 14 France 30 Germany 16 Italy 56 UK 51 USA 60 World Bank 71 Saudi Arabia 59 Kuwait 18 Abu Dhabi 25 Pakistan 697 Others 25
  • 17.
     Predicted andactual Impacts: • Power House Power Units Planned Actual(MW) Tunnel 1 4*175=700MW 700MW(1977-78) Tunnel 2 4*175=700MW 1050MW(1982-85) Tunnel 3 4*175=700MW 1728MW(1992-93) Total Installed Capacity 2100MW 3478MW
  • 18.
     Predicted andactual Impacts: • Schedule Construction Stages Project Component Activities Scheduled Actual Mobilization Including award of main contract Jun1967- Dec1969 May1968-Dec 70 Stage 1 River diversion Jan 1968-Sep 70 May 68-Sep 70 Stage 2 Spillways, Tunnels Oct 70-Sep 73 Oct 70-Sep 73 Stage 3 Auxiliary Dam & Power Station Oct 73 –Sep 74 Sep 73-Sep 74 Flow through Tunnel Stage 4 Unit 1 & 2 Jan 75 – Mar 75 April 77-may 77 Commissioning of Power Unit 3 & 4 Oct 75 –Mar 76 Jun 77 – July 77
  • 19.
     Due tohigh demand of Electricity instead of making new projects , the Govt. of Pakistan started to upgrade the existing projects.  In Sep 2013 , WAPDA signed RS:26.053 billion contract with Chinese firm Sino hydro for executing Civil works on the 1410MW Tarbella extension project.  Work on the Project will be completed in 3 &1/2 years at an estimated cost of $928 million.  In June 2013 , The World Bank has agreed to provide a $840 million loan for project.
  • 20.
     On completion, the project will increase generation capacity from 3478MW to 4888 MW.  Prime Minister Nawaz Sharif ordered WAPDA to increase the feasibility study of Tarbella.  Next extension would increase additional generation of 1320MW electricity and increase overall capacity to 6208MW.  The Australian Govt. has shown its keen interest to finance this latest extension.
  • 21.