The document discusses the need for large dams in Pakistan to address water scarcity issues due to increasing population and depletion of existing reservoir storage capacities. It presents details of the proposed Kalabagh Dam project, including its design, costs, and environmental and resettlement impacts. It also summarizes the key apprehensions of Khyber Pakhtunkhwa and Sindh provinces regarding the project and provides factual responses to address those concerns. The document advocates that studies are being conducted to further analyze environmental concerns and minimum water flows required downstream.
Presentation on the benefits of Kalabagh Dam and addressing concerns
1. PRESENTATION TO OFFICERS OF KHARIAN GARRISONPRESENTATION TO OFFICERS OF KHARIAN GARRISON
June 25, 2005June 25, 2005
WATER AND POWER DEVELOPMENT AUTHORITY
WATER RESOURCES AND ISSUES
2. 2
PAKISTAN’S NEED FOR LARGE DAMS
• WATER SCARCE COUNTRY AS PER GLOBAL
CRITERIA
• RAPIDLY INCREASING POPULATION
• DEPLETING ON-LINE STORAGES
• LARGE ESCAPAGES OF UNCONTROLLED FLOOD
FLOWS IN SEA
• EFFECTIVE RIVER REGULATION AND INTEGRATION
OF EXISTING IRRIGATION SYSTEM
3. 3
WATER APPORTIONMENT ACCORD 1991
PARA-6
THE NEED FOR STORAGES, WHEREEVER
FEASIBLE ON THE INDUS AND OTHER
RIVERS WAS ADMITTED AND RECOGNIZED
BY THE PARTICIPANTS FOR PLANNED
FUTURE AGRICULTURAL DEVELOPMENT
4. 4
WATER DEMAND
• POPULATION 2005 141 million
2025 220 million
• URBAN POPULATION Currently 35%
2025 60%
• TOTAL AREA 196 M ACRES
CULTIVABLE 77 MA
CULTIVATED 54.5 MA
REMAINING 22.5 MA Needs Add. Water
• To increase the crop yield requires additional water.
• Net Crop Water Requirement 2003-4 77.4 MAF
2010-11 89 MAF
2024-25 114.64 MAF
• Domestic Demand Currently≈ 4.0 MAF
2025 ≈ 10.5MAF
5. 5
WATER AVAILABILITY Vs POPULATION GROWTH
5260
3888
2751
2129
1555
1282
1066
915
858
34
46
65
84
115
139.5
195.5
167.72
208.4
0
1000
2000
3000
4000
5000
6000
1951 1961 1971 1981 1991 2002 2010 2020 2025
YEAR
PERCAPITAAVAILABILITY(M)3
30
50
70
90
110
130
150
170
190
210
230
PER CAPITA
AVAILIBILITY
POPULATION
GROWTH
WATERAVAILABILITY(MAF)
POPULATION(Million)
1234 m3
2004
151.11 Million
(2004)
6. 6
ARABIAN SEA
Chenab
River
DISPUTED
TERRITORY
IN
D
U
S
RIVER
KABUL RIVER
Ravi River
JhelumRiver
Sutlej River
LEGEND
MOUNTAINS
DESERTS
AREA UNDER
IRRIGATION
AREA THAT
CAN BE BROUGHT
UNDER IRRIGATION
CATEGORY AREA (MA)
GEOGRAPHICAL AREA 196.0
AREA SUITABLE FOR AGRICULTURE 77.1
CULTIVATED AREA
(IRRIGATED + BARANI)
54.5
AREA UNDER IRRIGATION
(BY ALL SOURCES)
44.4
ADDITIONAL AREA THAT CAN BE
BROUGHT UNDER IRRIGATED
AGRICULTURE
22.5
SOURCE: AGRICULTURAL STATISTICS OF PAKISTAN 1998-99
LAND USE IN PAKISTAN
IndusRiver
Sindh 3.6 MA
Punjab 4.3 MA
NWFP 3.0 MA
Baloch. 11.6 MA
TOTAL 22.5 MA
7. 7
AVAILABILITY
From Western Rivers at RIM Stations 141 MAF
Above Rim Stations 5 MAF
TOTAL 146 MAF
USES
Above RIM Stations 5 MAF
Canal Diversion 106 MAF
TOTAL 111 MAF
BALANCE AVAILABLE 35 MAF
WATER AVAILABILITY IN PAKISTAN
8. 8
ESCAPAGE BELOW KOTRI
HYDROLOGICAL YEAR FROM APRIL TO MARCH
30.39 29.81
9.68
45.91
29.55
26.90
17.53
52.86
17.22
42.34
53.29
81.49
29.11
91.83
62.76
45.40
0.77 1.93
20.18
69.08
33.79 35.15
2.37
8.83
20.79
80.59
20.10
10.98
0
20
40
60
80
100
1976-77
1977-78
1978-79
1979-80
1980-81
1981-82
1982-83
1983-84
1984-85
1985-86
1986-87
1987-88
1988-89
1989-90
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
1997-98
1998-99
1999-2000
2000-01
2001-02
2002-03
2003-04
YEARS
ANNUALDISCHARGE(MAF)
AVG. (34.7)
Source: WRMD WAPDA
Source: WRMD WAPDA based on data supplied by Govt. of Sindh
April 2005 1.6 MAF
May 2005 0.74 MAF
2.34 MAF
9. 9
RESERVOIR
GROSS STORAGE
CAPACITY
(MAF)
GROSS STORAGE LOSS
ORIGINAL YEAR 2004
YEAR 2004
(MAF)
YEAR 2010
(MAF)
YEAR 2025
(MAF)
TARBELA
11.62
(1974)
8.36 (72%) 3.26 (28%) 3.95 (34%) 5.51 (47%)
MANGLA 5.88 (1967) 4.64 (78%) 1.24 (22%) 1.60 (27%) 1.97 (34%)
CHASHMA 0.87 (1971) 0.48 (55%) 0.39 (45%) 0.58 (55%) 0.50 (57%)
TOTAL 18.37 13.48 (73%) 4.89 (27%) 6.03 (33%) 7.98 (43%)
RESERVOIR SEDIMENTATION (MAF)
10. 10
KALABAGH DAM PROJECT
NUMBER OF DAMS UNDER CONSTRUCTION
IN SOME COUNTRIES
Country
Total No. of Dams
Above 50 Ft. Above 200 Ft.
CHINA 253 59
TURKEY 113 22
INDIA 28 6
IRAN 52 28
JAPAN 97 35
PAKISTAN 4 1 (Gomal Dam)
Source: ICOLD register of Dams
14. 14
KALABAGH DAM PROJECT
SALIENT FEATURES
• Dam Type Earth Core Rock Fill
• Gross Storage 7.9 MAF
• Live Storage 6.1 MAF
• Dam Height 260 ft.
• Power 3600 MW
• Cost $ 6.0 Billion
• No Canal Outlets from Dam
• It Will Function As Seasonal Carry Over Dam
15. 15
KALABAGH DAM PROJECT
(Current Status)
• Feasibility Report 1984
• PC-I submitted (1989) Approval pending
• Project Planning Studies Completed
• Completion Time 6 Years
16. 16
KALABAGH DAM PROJECT
ENVIRONMENTAL IMPACT
PROVINCE
POPULATION *
TO BE
RESETTLED
LAND AFFECTED (ACRES)
BARANI IRRIGATED TOTAL
PUNJAB 78,000 21,600 2,900 24,500
N.W.F.P 42,000 2,900 100 3,000
TOTAL 120,000 24,500 3,000 27,500
* December 1999 (Being updated)
17. KALABAGH DAM PROJECT
COST ESTIMATES (US $ Million)
Sr
No
Description July 1987 Prices
Escalated to
Dec. 2004 Prices
1 Diversions & Embankment/Dam 554.1 850
2 Spillways & Outlet Works 476.9 750
3 Power Features 684.7 750
4 Transmission/Collector Station 111.7 125
5 Resettlement 225.7 700
6 Preliminary Works 289.7 250
Sub Total 2342.8 3,420
7 Contingencies @ 10% 234.3 342
Sub Total 2577.1 3,762
8 Engg. & Admin.@ 10% 257.7 376.2
Total 2834.8 4,138.2
9 Financial Costs @ 40% 1133.9 1653.3
10 Excise & Custom Duties @ 5% 141.7 206.9
GRAND TOTAL 4110.4 5998.4
Say 6.0 Billion
19. 19
KALABAGH DAM PROJECT
APPREHENSIONS OF NWFP
APPREHENSIONS FACTUAL POSITION
• POSSIBILITY OF FLOODING OF
NOWSHERA TOWN AND
PESHAWAR VALLEY IN CASE OF
UNPRECEDENTED FLOOD
• MODERN FLOOD WARNING SYSTEM
WOULD PROVIDE ADEQUATE WARNING
AGAINST FLOODS
• TARBELA IS ALSO ON LINE NOW
• DRAINAGE OF MARDAN, PABBI
AND SWABI WILL BE
ADVERSELY AFFECTED
• CONSERVATION LEVEL OF KALABAGH
DAM IS 915 FT WHICH IS LOWER THAN
THE LOWEST GROUND LEVEL OF
MARDAN, PABBI AND SWABI SCARP
AREAS
• FERTILE CULTIVATED LAND
WOULD BE SUBMERGED
• 2,900 ACRES OF BARANI LAND AND
ONLY 100 ACRES OF IRRIGATED LAND
WOULD BE SUBMERGED IN THE
RESERVOIR
• LARGE POPULATION WOULD BE
DISPLACED
• RESETTLEMENT PLAN WOULD ENSURE
PROPER COMPENSATION TO THE
AFFECTEES
PUNJAB NWFP TOTAL
NO. OF AFFECTEES 78,000 42,000 120,000
LAND AFFECTED (Acres) 24,500 3,000 27,500
22. 22
DRAINAGE LEVELS IN KABUL VALLEY WITH KALABAGH
910
930
950
970
990
1010
150 140 130 120 110 100 90 80
SWABI
CHARSADDA
PABBI
NOWSHERA
MARDAN
RESERVOIR RETENATION
EL. 915
DISTANCE U/S DAM SITE IN MILES
LEVELINFEET
955 960
940
970
1000
23. 23
KALABAGH DAM PROJECT
MODIFICATIONS
MODIFICATION IMPACT
Maximum Conservation Level • Effective Drainage Outlet of:
Original 925 Ft. Charsada 955 Ft.
Reduced 915 Ft. Pabbi 960 Ft.
Nowshera 940 Ft.
Mardan 970 Ft.
Swabi 1000 Ft.
• Reduction in Storage Capacity from 7
MAF to 6.1 MAF
No Canal outlets from Dam It will function as seasonal Carry over Dam
31. 31
KALABAGH DAM PROJECT
APPREHENSIONS OF SINDH
APPREHENSIONS FACTUAL POSITION
•NO WATER IS AVAILABLE FOR
FILLING KALABAGH RESERVOIR
• AVERAGE ANNUAL OUTFLOW BELOW
KOTRI IS 34.7 MAF
• MOST CONSERVATIVE ESTIMATE SHOWS
15 MAF FOR STORAGE / DEVELOPMENT
• ABOUT 6 MAF IS JUST REPLACEMENT
FOR TARBELA, MANGLA AND CHASHMA
DUE TO SEDIMENTATION
•SINDH WOULD BE CONVERTED INTO
A DESERT
• AFTER MANGLA & TARBELA DAMS,
SINDH CANAL WITHDRAWALS
INCREASED FROM 37.20 MAF TO 44.47
MAF
• CANAL WITHDRAWALS FOR SINDH
WOULD FURTHER INCREASE BY 2 MAF
AFTER KALABAGH
32. 32
KALABAGH DAM PROJECT
APPREHENSIONS OF SINDH
APPREHENSIONS FACTUAL POSITION
• RIVERINE AREA WOULD GO OUT OF
PRODUCTION DUE TO CONTROL OVER
RIVER
• FLOOD PEAKS IN EXCESS OF 300,000
CUSECS WOULD STILL BE COMING
• ASSURED WATER SUPPLY THROUGH
PROPOSED TUBEWELLS WILL BE MADE
ROUND THE YEAR
• INDUS DELTA MANGROVE FOREST
WOULD VANISH
• ONLY 7,000 ACRES OUT OF 294,000
ACRES MANGROVE FOREST ARE IN
INDUS ACTIVE DELTA ESTABLISHED
THROUGH SATELLITE IMAGERY
• NO SIGNIFICANT IMPACT IS EXPECTED
AS REQUIRED MINIMUM WATER (AS PER
LATEST STUDIES) WILL STILL BE
FLOWING BELOW KOTRI
33. 33
KALABAGH DAM PROJECT
APPREHENSIONS OF SINDH
APPREHENSIONS FACTUAL POSITION
• FISH PRODUCTION BELOW KOTRI
WOULD BE AFFECTED
• No EVIDENCE ESTABLISHES THIS
APPREHENSION AS FISH PRODUCTION
INCREASED
• MARINE FISH (THOUSAND TONS)
- 1995 283 - 1999 351
- 1996 270 - 2000 308
- 1997 292 - 2001 315
- 1998 303
• STUDY REQUIRED TO DETERMINE
ESCAPAGE DOWNSTREAM KOTRI
• TWO STUDIES: (I) TO DETERMINE THE
MINIMUM ESCAPAGES REQUIRED BELOW
KOTRI TO CHECK SEA INTRUSION
• (II) TO ADDRESS ENVIRONMENTAL
CONCERNS BELOW KOTRI ARE
UNDERWAY
• THE THIRD STUDY ON ENVIRONMENTAL
CONCERNS OF ALL THE FOUR
PROVINCES IS ALSO TAKEN UP
34. 34
APPREHENSIONS FACTUAL POSITION
• Royalty from Kalabagh would go to
Punjab although the Project would be
Federally Funded
• It is a Constitutional Matter.
• Desilt Tarbela Instead of Building
Kalabagh Dam
• Desilting Tarbela Reservoir not a
practical option
• Save 40-50 MAF lost in seepage through
Canal System Lining
• Lining is Complementary to Storage
• Lining is expensive and time taking. It
is not completely effective.
• Seepage from Canals in fresh ground
water areas is not a loss as it is being
pumped out.
• It would not be a carry over storage
and no additional water. It would
improve availability at tails.
KALABAGH DAM PROJECT
APPREHENSIONS OF SINDH
35. 35
KALABAGH DAM PROJECT
ANNUAL BENEFITS
1.
Irrigation Water
Supplies
@ Rs. 2054/AF
6.1 x 2054 = Rs. 12.53 Billion
2
Power Benefits @
Rs. 4.00/Unit
11.736 x 4 = Rs. 46.944 Billion
3 Flood Control 1.50 Billion
Total Rs. 60.97 Billion
37. 37
KALABAGH DAM PROJECT
SEASON-WISE AND ANNUAL CANAL HEAD
WITHDRAWALS OF SINDH (1962-63 TO 1999-2000)
SEASON
PRE-
MANGLA
(1962-67)
AVERAGE
PRE-
TARBELA
(1967-76)
AVERAGE
POST-
TARBELA
(1976-2000)
AVERAGE
ADDITIONAL
WATER FOR
SINDH AFTER
MANGLA AND
TARBELA
KHARIF 26.16 28.66 29.45 3.29 12.6%
RABI 11.04 12.19 15.02 3.98 36.1%
TOTAL 37.20 40.85 44.47 7.27 19.5%
38. 38
KALABAGH DAM PROJECT
HOW SOON CONSTRUCTION CAN START ?
• All designs & Tender Documents ready –
Need Updating
• Revised Environmental/Resettlement Studies
Underway.
• Preliminary Works i.e. Access Roads,
Colonies etc. can start right away.
• Actual Construction can start in early 2006.
41. 41
BASHA DIAMER DAM PROJECT
SALIENT FEATURES
• Concrete Gravity Dam (Roller Compacted)
Endorsed by Panel of Experts
• Gross Storage 9.04 MAF
• Live Storage 7.34 MAF
• Dam Height 281 Meters (922
ft)
• Power 4500 MW
• Cost (Approx.) $ 6.721 Billion
• Construction Period 7 Years
42. 42
BASHA DIAMER DAM PROJECT
(CURRENT STATUS)
• Feasibility Report Submitted Aug 2004
• Detailed Design Dec. 2007
• Prepare Tenders, Advertise Jun 2007 to
Mar 2008
Evaluate & Award
• Up-gradation of KKH June 2008
• Commencement of Construction 2008
• Completion 2015
43. 43
UPGRADATION / RELOCATION OF KKH FOR
BHASHA DIAMER DAM PROJECT
Hasanabdal
Lengthof Section
40km
281
km
94 km
44. 44
KKH UPGRADATION & RELOCATION
325 KM KKH TO UPGRADED RS 9423 M.
140 KM KKH TO BE REPLACED
RS 14333 M.
7 CONTRACT PACKAGES FOR
UPGRADATION WOULD REQUIRE AT
LEAST THREE YEARS .
.
45. 45
S.
No
CALENDER YEAR (JAN-DEC)
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
1 Feasibility Study Stage-I
2 Pre-qualification, Evaluation &
Award of Contract for Stage-II
3 Preparation of Tender Documents
and Detail Engineering
4 Additional Investigation Studies
and Model Testing
5 Pre-construction Activities
Land Acquisition, Up-gradation of
KKH
6 Tendering Process Up to Award
7 Mobilization of Contractor
8 Construction Activities
9 Rehabilitation/ Resettlement
including Relocation of KKH
BASHA DIAMER DAM PROJECTBASHA DIAMER DAM PROJECT
OVERALL IMPLEMENTATION SCHEDULEOVERALL IMPLEMENTATION SCHEDULE
47. 47
AKHORI DAM PROJECT
SALIENT FEATURES*
RESERVOIR
GROSS STORAGE 7 MAF
LIVE STORAGE 6 MAF
POND AREA 56,500 ACRES
MAIN DAM
CREST LEVEL 1470 FT
MAXIMUM HEIGHT 420 FT
LENGTH 17,000 FT
CONVEYANCE SYSTEM
CHANNEL CAPACITY 60,000 CUSECS
LENGTH 20 MILES
POWER POTENTIAL 600 MW
(2100 GWh Per
Year)
ENVIRONMENTAL IMPACT
LAND SUMBERGED 59,217 ACRES
POPULATION 49,320
ESTIMATED COST (Updated) US $ 3.31
BILLION* As per Appraisal Study Report 2002
48. 48
AKHORI DAM PROJECT
IMPLEMENTATION SCHEDULE
AWARD OF CONSULTANCY FOR FEASIBILITY STUDY TO
M/S TECHNO CONSULTANTS & HPE JOINT VENTURE - AUGUST 2003
Duration
(Years) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
2003 2004 2005 2006 2007
KEY ACTIVITIES
2008 2009 2015
D.
FEASIBILITY
STUDIES AND PC-I
DETAILED ENGG.
DESIGN &
TENDER
DOCUMENTS
TENDERING,
EVALUATION &
AWARD
0.75
2
2011
2
2012
E. MOBILIZATION BY
CONTRACTORS 0.5
F. CONSTRUCTION 6
C. ADDITIONAL
EXPLORATIONS,
STUDIES &
MODEL TESTING
2
2014
A.
B.
20132010
50. 50
Airport
Right Bank
KILOMETER
METER
(Through Air-Port)
X-SECTION A-A
RESERVOIR AREA
SKARDU DAM PROJECT
Width = 47 m
Length = 3658 m
Elevation = 2232 m
Left Bank
Road
River Surface
2258 Meters (Capacity=8.0 MAF)
2350 Meters (Capacity=20.30 MAF)
2240 Meters (Capacity=5.2 MAF)
Normal Res. Level
54. 54
HYDROPOWER DEVELOPMENT
• AT 8% GROWTH RATE POWER
SHORTAGE LIKELY FROM 2006
• IN PAST 20 YEARS HYDROPOWER
SHARE REDUCED FROM 60% TO 34%
• THERMAL POWER GENERATION BEING
SEVERAL TIMES AS EXPENSIVE, THE
ELECTRICITY TARIFF HAS GONE UP
• HYDROPOWER POTENTIAL IS ABOUT
40,000 MW