SlideShare a Scribd company logo
1 of 36
PRESENTED BY
RAVI KUMAR JAISWAL
1303340839
 DIESEL LOCOMOTIVE WORKS (DLW), Varanasi (India) an ISO
9001:14001 & OHS 18001 certified production unit owned by Indian
Railways, it is a central unit of Govt. of India (ministry of Railway).
 It was laying of foundation stone of factory by the first president of
India Late Dr. Rajendra Prasad in 1956 & Diesel Locomotive Works
came existence in 1961.
 To meet the increased transportation needs of the Indian railways it
was established in near ancient city varanasi collaboration with
ALCO( American Locomotive Company), USA in 1961.
 First locomotive rolled out and dedicated to nation in January, 1964.
 Got its first ISO certification in 1997 and ISO-9001 and ISO-14001 in
December 2002.
 State of the art Design and manufacturing facility to manufacture
200 locomotive per annum with wide range of related products viz.
DG Sets , Loco components and sub-assemblies.
 A large base of delighted customers among many countries viz.
Myanmar ,sri lank, Malaysia, Vietnam, Bangladesh, Tanzania,
Angola, to name a few bearing testimony to product leadership in its
category.
 At present the latest locomotive produced by DLW; i.e. WDG 5 has
capacity upto 5000 HP & trying to make it 5500 HP.
 First loco realesed by late lal bahadur sastri in 1964 ,WDM2
 DLW’S annul Production -275
 Component are manufacture -2000
component
 Cost of one LOCO -25
crore(EMD)
 Weight of one LOCO -121 ton
 Fuel consumption at full load -540 lit/hr
 Fuel consumption at idle load -40 lit/hr
 Max. Speed -160km/hr
 Dia. of wheel -1092mm
Locos, except the older steam ones, have classification codes that
identify them. This code is of the form
WDG5A “ [ gauge ][ power ][load ][ series ][ sub type ]”
• The first letter (gauge)
W- Indian broad gauge
Y- meter gauge
Z- narrow gauge(2.5 ft)
N- narrow gauge (2 ft)
• The second letter (motive power)
D- Diesel
C- DC electric (can run under DC traction only)
A- AC electric (can run under AC traction only)
CA- Both DC and AC (can run under both AC and DC tractions)
B- Battery electric locomotive (rare)
• The third letter (load type)
G-goods
P-passenger
M-mixed traffic ; both goods and passenger
S-Used for shunting
U-Electric multiple units (E.M.U.)
R-Railcars
• THE fourth letter (series)
The series digit identifies the horsepower range of the locomotive.
Example for the series letter ‘3’ means that the locomotive has power over 3000 hp but less
than 4000 hp.
• The fifth letter (subtype)
an optional letter or number that indicates some smaller variations in the basic model.
For ex: ‘A’ for 100 hp,
‘B’ for 200 hp and so on……..
 WDG5 5500 HP AC/AC Freight operation
 type locomotive
 WDG4 4000 HP AC/AC Freight Traffic
 Locomotive
 WDP4 4000 HPAC/AC Broad Gauge High
 Speed
 WDG3D 3400 HP AC/AC Broad Gauge Mixed Traffic
 Micro-Processor Controlled Locomotive.
 WDP3A 3100 HP AC/DC Broad Gauge High Speed
 passenger Locomotive
 WDM2 2600 HP AC/DC Broad Gauge Mixed Traffic
 Locomotive
 YDM4 1350 HP AC/DC &DC/DC Broad Gauge Mixed
 Locomotive
 WDP4D 4400 HP ac/ac Broad Gauge High Speed
BLOCK DIVISION
ENGINE DIVISION
LOCO DIVISION
•BLOCK DIVISION:
1.Heavy Weld Shop
2.Heavy Machine shop
•Engine Divisions:
1.Light Machine Shop
2.Engine Erection Shop
3.Engine Testing Shop
4.Sub Assembly Shop
5.Rotor Shop
6.Heat Treatment Shop
Loco Divisions:
1. Loco Frame Shop
2. Pipe Shop
3. Truck Machine Shop
4. Sheet Metal Shop
5. Traction Assembly Shop
6. Loco Assembly Shop
7. Loco Test Shop
8. Loco Paint Shop
SAS LAS
LPS
HMS
My four week training was confined to four
different sections
 Wheel and Axle assembly
 Brake rigging assembly
 Traction motor & gear case assembly
Animated View
This shop carries out the machining of
Cylinder BLOCK main base, saddler Main
bearing caps, Turbo Super Charger, Lube Oil,
Fuel Oil & Water header) com bearing housing.
 Planning,
 Milling,
 Drilling,
 Tapping,
 Boring Honing,
 Angular Boring,
 Serration milling etc.
• Tested engines are receives from Engine Division.
• Similarly under frames are received from Loco frame
shop and assembled trucks from Truck machine shop.
• Super structure compartments and contractor
compartment are received from respective manufacturing
and assembly shops of Vehicle Division.
• Important alignments like crank shaft deflection,
compressor alignment and Eddy Current clutch/radiator
fan alignment are done during assembly stage.
• Electrical control equipments are fitted and control
cable harnessing is undertaken.
• The complete locomotive is thus assembled before
being sent onwards for final testing and spray
painting.
• All locomotive are rigorous tested as per laid down
test procedures before the locomotive is taken up for
final painting and dispatch for service.
After the Loco (engine) is made they are sent for
final work of painting. Loco painting is done by
spray paint. Skilled workers are employed who
can make markings take shape and size under
consideration.
In loco paint shop the loco is spray painted by the
air tight paint booth.
In DLW, Loco Paint Shop is divided into different- different section, which under
section different -different portion painted for a specified colours.
BODERING:
Deep Yellow colour are used for WDG4. And Dazzling white, Golden yellow
colour are used for WDP4.
FINISHING:
Sky Blue Colour are used for WDG4. And French Blue colour are used for
WDP4.
FOR TRUCK PORTION:
Black paint used in both WDG4 & WDP4.
In DLW, Two types paint are used:-
1. Enamel Paint
2. Poly vinyl Paint
For safety purpose from dust particle used glass, rubber, builder plates,cables. And
resist from dust particle, Loco is spry by EZP (EPOXY ZINC PHOSPHATE).
Epoxy Surface:-
It is a process in paint (epoxy paint) is used for fill up all the gaps properly.
THANK U !

More Related Content

What's hot

Diesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine ShopDiesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine ShopGaurav Mishra
 
6 weeks vocational traning report about dlw varanasi
6 weeks vocational traning report about dlw varanasi6 weeks vocational traning report about dlw varanasi
6 weeks vocational traning report about dlw varanasiABHISHEK PRIYADARSHI
 
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Vivek Yadav
 
Ppt presentation on 4 weeks EE DLW Summer Traning
 Ppt presentation on 4 weeks  EE DLW Summer Traning Ppt presentation on 4 weeks  EE DLW Summer Traning
Ppt presentation on 4 weeks EE DLW Summer TraningGaurav Singh
 
Summer training repoart on dlw ,varanasi
Summer training repoart on dlw ,varanasiSummer training repoart on dlw ,varanasi
Summer training repoart on dlw ,varanasiARJUN MAURYA
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyshubhangpandey5
 
DLW Summer training report
DLW Summer  training  reportDLW Summer  training  report
DLW Summer training reportEshver chandra
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedisomesh dwivedi
 
Dlw summer training report 2018(2)
Dlw summer training report 2018(2)Dlw summer training report 2018(2)
Dlw summer training report 2018(2)SaurabhGupta912
 
Ind training ppt
Ind training pptInd training ppt
Ind training pptyamipatel
 
presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)shubham vishwakarma
 
DLW Industrial training presentation
DLW Industrial training presentationDLW Industrial training presentation
DLW Industrial training presentationSaurabhGupta912
 
Dlw varanasi training ppt
Dlw varanasi training pptDlw varanasi training ppt
Dlw varanasi training pptPraveen Tiwari
 

What's hot (20)

Diesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine ShopDiesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine Shop
 
Shubhankar Singh
Shubhankar SinghShubhankar Singh
Shubhankar Singh
 
6 weeks vocational traning report about dlw varanasi
6 weeks vocational traning report about dlw varanasi6 weeks vocational traning report about dlw varanasi
6 weeks vocational traning report about dlw varanasi
 
dlw training PPT
 dlw training PPT dlw training PPT
dlw training PPT
 
DLW training PPT
DLW   training  PPTDLW   training  PPT
DLW training PPT
 
Sks
SksSks
Sks
 
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
 
Dlw varanasi
Dlw varanasiDlw varanasi
Dlw varanasi
 
Ppt presentation on 4 weeks EE DLW Summer Traning
 Ppt presentation on 4 weeks  EE DLW Summer Traning Ppt presentation on 4 weeks  EE DLW Summer Traning
Ppt presentation on 4 weeks EE DLW Summer Traning
 
Summer training repoart on dlw ,varanasi
Summer training repoart on dlw ,varanasiSummer training repoart on dlw ,varanasi
Summer training repoart on dlw ,varanasi
 
Anas
AnasAnas
Anas
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandey
 
Dlw short ppt
Dlw short pptDlw short ppt
Dlw short ppt
 
DLW Summer training report
DLW Summer  training  reportDLW Summer  training  report
DLW Summer training report
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedi
 
Dlw summer training report 2018(2)
Dlw summer training report 2018(2)Dlw summer training report 2018(2)
Dlw summer training report 2018(2)
 
Ind training ppt
Ind training pptInd training ppt
Ind training ppt
 
presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)
 
DLW Industrial training presentation
DLW Industrial training presentationDLW Industrial training presentation
DLW Industrial training presentation
 
Dlw varanasi training ppt
Dlw varanasi training pptDlw varanasi training ppt
Dlw varanasi training ppt
 

Viewers also liked

DLW varanasi summer training report
DLW varanasi summer training reportDLW varanasi summer training report
DLW varanasi summer training reportshubham chaurasiya
 
Dlw summer training animated persentation by shoaib
Dlw summer training animated persentation by shoaibDlw summer training animated persentation by shoaib
Dlw summer training animated persentation by shoaibShoaib Ansari
 
Brijeh yadav ppt
Brijeh yadav pptBrijeh yadav ppt
Brijeh yadav pptbky2756
 
Mechanical Vibration
Mechanical VibrationMechanical Vibration
Mechanical VibrationAnkur Shukla
 
Diesel Locomotive Works (DLW)
 Diesel Locomotive Works (DLW) Diesel Locomotive Works (DLW)
Diesel Locomotive Works (DLW)Neha Gethe
 
Summer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSummer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSHAILESH SHUKLA
 
Summer Training Report, DLW Varanasi
Summer Training Report, DLW VaranasiSummer Training Report, DLW Varanasi
Summer Training Report, DLW VaranasiSHAILESH SHUKLA
 
Presentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel LocomotivePresentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel LocomotiveAbhishek Agarwal
 

Viewers also liked (8)

DLW varanasi summer training report
DLW varanasi summer training reportDLW varanasi summer training report
DLW varanasi summer training report
 
Dlw summer training animated persentation by shoaib
Dlw summer training animated persentation by shoaibDlw summer training animated persentation by shoaib
Dlw summer training animated persentation by shoaib
 
Brijeh yadav ppt
Brijeh yadav pptBrijeh yadav ppt
Brijeh yadav ppt
 
Mechanical Vibration
Mechanical VibrationMechanical Vibration
Mechanical Vibration
 
Diesel Locomotive Works (DLW)
 Diesel Locomotive Works (DLW) Diesel Locomotive Works (DLW)
Diesel Locomotive Works (DLW)
 
Summer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSummer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW Varanasi
 
Summer Training Report, DLW Varanasi
Summer Training Report, DLW VaranasiSummer Training Report, DLW Varanasi
Summer Training Report, DLW Varanasi
 
Presentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel LocomotivePresentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel Locomotive
 

Similar to Summer training at dlw varanasi

Diesel locomotive work
Diesel locomotive workDiesel locomotive work
Diesel locomotive workvipin rai
 
INDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,VaranasiINDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,Varanasiak3793
 
DLW vocational training report
DLW vocational training reportDLW vocational training report
DLW vocational training reportPrashantSharma897
 
Dlw summer training presentation
Dlw summer training presentationDlw summer training presentation
Dlw summer training presentationVarun Mishra
 
Summer traning dlw repoart
Summer  traning dlw repoartSummer  traning dlw repoart
Summer traning dlw repoartARJUN MAURYA
 
dlw taining file
dlw taining filedlw taining file
dlw taining fileRam Bahadur
 
Blw summer training report Mechanical LAS LFS HWS EEE CTS TR
Blw summer training report Mechanical LAS LFS HWS EEE CTS TRBlw summer training report Mechanical LAS LFS HWS EEE CTS TR
Blw summer training report Mechanical LAS LFS HWS EEE CTS TRAjitDubey22
 
dokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptx
dokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptxdokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptx
dokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptx7009AKASHMODANWAL
 
DLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indoreDLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indoreSANJEET KUMAR
 
CLW VOCATIONAL TRAINING REPORT- 2018
CLW VOCATIONAL TRAINING REPORT- 2018CLW VOCATIONAL TRAINING REPORT- 2018
CLW VOCATIONAL TRAINING REPORT- 2018SohagSarkar2
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaArjun Gaur
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaArjun Gaur
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasiShubham​ Yadav
 
Diesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentationDiesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentationShubham​ Yadav
 
DLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL BranchDLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL BranchRahul Gupta
 
Indian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~iIndian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~ihaxxo24
 

Similar to Summer training at dlw varanasi (20)

Diesel locomotive work
Diesel locomotive workDiesel locomotive work
Diesel locomotive work
 
INDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,VaranasiINDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,Varanasi
 
introuduction DLW varanaesi
introuduction DLW varanaesiintrouduction DLW varanaesi
introuduction DLW varanaesi
 
DLW vocational training report
DLW vocational training reportDLW vocational training report
DLW vocational training report
 
Dlw summer training presentation
Dlw summer training presentationDlw summer training presentation
Dlw summer training presentation
 
Summer traning dlw repoart
Summer  traning dlw repoartSummer  traning dlw repoart
Summer traning dlw repoart
 
dlw taining file
dlw taining filedlw taining file
dlw taining file
 
Blw summer training report Mechanical LAS LFS HWS EEE CTS TR
Blw summer training report Mechanical LAS LFS HWS EEE CTS TRBlw summer training report Mechanical LAS LFS HWS EEE CTS TR
Blw summer training report Mechanical LAS LFS HWS EEE CTS TR
 
dokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptx
dokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptxdokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptx
dokumen.tips_ppt-presentation-on-4-weeks-ee-dlw-summer-traning.pptx
 
DLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indoreDLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indore
 
CLW VOCATIONAL TRAINING REPORT- 2018
CLW VOCATIONAL TRAINING REPORT- 2018CLW VOCATIONAL TRAINING REPORT- 2018
CLW VOCATIONAL TRAINING REPORT- 2018
 
Dlw training
Dlw trainingDlw training
Dlw training
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasi
 
Diesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentationDiesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentation
 
DLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL BranchDLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL Branch
 
Shivendra singh
Shivendra singhShivendra singh
Shivendra singh
 
Indian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~iIndian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~i
 
Dlw locomotive workshop
Dlw locomotive workshopDlw locomotive workshop
Dlw locomotive workshop
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 

Summer training at dlw varanasi

  • 1. PRESENTED BY RAVI KUMAR JAISWAL 1303340839
  • 2.  DIESEL LOCOMOTIVE WORKS (DLW), Varanasi (India) an ISO 9001:14001 & OHS 18001 certified production unit owned by Indian Railways, it is a central unit of Govt. of India (ministry of Railway).  It was laying of foundation stone of factory by the first president of India Late Dr. Rajendra Prasad in 1956 & Diesel Locomotive Works came existence in 1961.  To meet the increased transportation needs of the Indian railways it was established in near ancient city varanasi collaboration with ALCO( American Locomotive Company), USA in 1961.  First locomotive rolled out and dedicated to nation in January, 1964.
  • 3.  Got its first ISO certification in 1997 and ISO-9001 and ISO-14001 in December 2002.  State of the art Design and manufacturing facility to manufacture 200 locomotive per annum with wide range of related products viz. DG Sets , Loco components and sub-assemblies.  A large base of delighted customers among many countries viz. Myanmar ,sri lank, Malaysia, Vietnam, Bangladesh, Tanzania, Angola, to name a few bearing testimony to product leadership in its category.  At present the latest locomotive produced by DLW; i.e. WDG 5 has capacity upto 5000 HP & trying to make it 5500 HP.  First loco realesed by late lal bahadur sastri in 1964 ,WDM2
  • 4.  DLW’S annul Production -275  Component are manufacture -2000 component  Cost of one LOCO -25 crore(EMD)  Weight of one LOCO -121 ton  Fuel consumption at full load -540 lit/hr  Fuel consumption at idle load -40 lit/hr  Max. Speed -160km/hr  Dia. of wheel -1092mm
  • 5.
  • 6. Locos, except the older steam ones, have classification codes that identify them. This code is of the form WDG5A “ [ gauge ][ power ][load ][ series ][ sub type ]” • The first letter (gauge) W- Indian broad gauge Y- meter gauge Z- narrow gauge(2.5 ft) N- narrow gauge (2 ft) • The second letter (motive power) D- Diesel C- DC electric (can run under DC traction only) A- AC electric (can run under AC traction only) CA- Both DC and AC (can run under both AC and DC tractions) B- Battery electric locomotive (rare)
  • 7. • The third letter (load type) G-goods P-passenger M-mixed traffic ; both goods and passenger S-Used for shunting U-Electric multiple units (E.M.U.) R-Railcars • THE fourth letter (series) The series digit identifies the horsepower range of the locomotive. Example for the series letter ‘3’ means that the locomotive has power over 3000 hp but less than 4000 hp. • The fifth letter (subtype) an optional letter or number that indicates some smaller variations in the basic model. For ex: ‘A’ for 100 hp, ‘B’ for 200 hp and so on……..
  • 8.  WDG5 5500 HP AC/AC Freight operation  type locomotive  WDG4 4000 HP AC/AC Freight Traffic  Locomotive  WDP4 4000 HPAC/AC Broad Gauge High  Speed  WDG3D 3400 HP AC/AC Broad Gauge Mixed Traffic  Micro-Processor Controlled Locomotive.  WDP3A 3100 HP AC/DC Broad Gauge High Speed  passenger Locomotive  WDM2 2600 HP AC/DC Broad Gauge Mixed Traffic  Locomotive  YDM4 1350 HP AC/DC &DC/DC Broad Gauge Mixed  Locomotive  WDP4D 4400 HP ac/ac Broad Gauge High Speed
  • 9.
  • 11. •BLOCK DIVISION: 1.Heavy Weld Shop 2.Heavy Machine shop •Engine Divisions: 1.Light Machine Shop 2.Engine Erection Shop 3.Engine Testing Shop 4.Sub Assembly Shop 5.Rotor Shop 6.Heat Treatment Shop Loco Divisions: 1. Loco Frame Shop 2. Pipe Shop 3. Truck Machine Shop 4. Sheet Metal Shop 5. Traction Assembly Shop 6. Loco Assembly Shop 7. Loco Test Shop 8. Loco Paint Shop
  • 12. SAS LAS LPS HMS My four week training was confined to four different sections
  • 13.  Wheel and Axle assembly  Brake rigging assembly  Traction motor & gear case assembly
  • 14.
  • 15.
  • 17. This shop carries out the machining of Cylinder BLOCK main base, saddler Main bearing caps, Turbo Super Charger, Lube Oil, Fuel Oil & Water header) com bearing housing.
  • 18.  Planning,  Milling,  Drilling,  Tapping,  Boring Honing,  Angular Boring,  Serration milling etc.
  • 19.
  • 20.
  • 21.
  • 22. • Tested engines are receives from Engine Division. • Similarly under frames are received from Loco frame shop and assembled trucks from Truck machine shop. • Super structure compartments and contractor compartment are received from respective manufacturing and assembly shops of Vehicle Division. • Important alignments like crank shaft deflection, compressor alignment and Eddy Current clutch/radiator fan alignment are done during assembly stage.
  • 23. • Electrical control equipments are fitted and control cable harnessing is undertaken. • The complete locomotive is thus assembled before being sent onwards for final testing and spray painting. • All locomotive are rigorous tested as per laid down test procedures before the locomotive is taken up for final painting and dispatch for service.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29. After the Loco (engine) is made they are sent for final work of painting. Loco painting is done by spray paint. Skilled workers are employed who can make markings take shape and size under consideration. In loco paint shop the loco is spray painted by the air tight paint booth.
  • 30.
  • 31.
  • 32. In DLW, Loco Paint Shop is divided into different- different section, which under section different -different portion painted for a specified colours. BODERING: Deep Yellow colour are used for WDG4. And Dazzling white, Golden yellow colour are used for WDP4. FINISHING: Sky Blue Colour are used for WDG4. And French Blue colour are used for WDP4. FOR TRUCK PORTION: Black paint used in both WDG4 & WDP4. In DLW, Two types paint are used:- 1. Enamel Paint 2. Poly vinyl Paint For safety purpose from dust particle used glass, rubber, builder plates,cables. And resist from dust particle, Loco is spry by EZP (EPOXY ZINC PHOSPHATE). Epoxy Surface:- It is a process in paint (epoxy paint) is used for fill up all the gaps properly.
  • 33.
  • 34.
  • 35.