SlideShare a Scribd company logo
1 of 40
BABU BANARSI DAS NATIONAL INSTITUTE 
OF TECHNOLOGY & MANAGEMENT, 
LUCKNOW 
A 
INDUSTRIAL TRAINING REPORT 
ON 
DISEL LOCOMOTIVE WORKSHOP 
SUBMITTED TO: SUBMITTED BY: 
RAMENDRA Kr. VISEN HIMANSHU S. SINGH 
(Sr. LECTURER) ROLL NO: 1105440044 
B.Tech (MECHANICAL) 
B. B. D. N. I. T. M.
DIESEL LOCOMOTIVE WORKSHOP 
VARANSI 
A 
INDUSTRIAL TRAINING REPORT 
ON 
DISEL LOCOMOTIVE WORKSHOP 
SUBMITTED TO: SUBMITTED BY: 
RAMENDRA Kr. VISEN HIMANSHU S. SINGH 
(Sr. LECTURER) ROLL NO: 1105440044 
B.Tech (MECHANICAL) 
B. B. D. N. I. T. M.
ACKNOWLEDGEMENT 
I take this opportunity my sincere thanks and deep gratitude to 
S.P. ASTHANA (HEAD OF MECHANICAL DEPARTMENT) all 
these people who extended their whole hearted co-operation and helped 
me in completing this project successfully. 
First of all I would like to thanks all the S.S.E. and J.E. of the 
all the sections for creating oppurtunities to undertake me in this 
esteemed organization. Special thanks to all the department for all the 
help and guidance extended to me by them in every stage during my 
training. His inspiring suggestions and timely guidance enabled me to 
perceive the various aspects of the project in the new light. 
In all I found a congenial work environment in DIESEL 
LOCOMOTIVE WORKSHOP, VARANSI and this completion of the 
project will mark a new beginning for me in the coming days. 
SUBMITTED TO: SUBMITTED BY: 
RAMENDRA Kr. VISEN HIMANSHU S. SINGH 
(Sr. LECTURER) ROLL NO: 1105440044 
B.TECH (MECHANICAL) 
B. B. D. N. I. T. M.
INTRODUCTION 
OF 
INDIAN RAILWAY 
Indian Railways is the state-owned railway company of India. It 
comes under the Ministry of Railways. Indian Railways has one of the largest and 
busiest rail networks in the world, transporting over 18 million passengers and 
more than 2 million tonnes of freight daily. Its revenue is Rs.107.66 billion. It is 
the world's largest commercial employer, with more than 1.4 million employees. It 
operates rail transport on 6,909 stations over a total route length of more than 
63,327 kilometers(39,350 miles).The fleet of Indian railway includes over 200,000 
(freight) wagons, 50,000 coaches and 8,000 locomotives. It also owns locomotive 
and coach production facilities. It was founded in 1853 under the East India 
Company. 
Indian Railways is administered by the Railway Board. Indian 
Railways is divided into 16 zones. Each zone railway is made up of a certain 
number of divisions. There are a total of sixty-seven divisions.It also operates the 
Kolkata metro. There are six manufacturing plants of the Indian Railways. The 
total length of track used by Indian Railways is about 108,805 km (67,608 mi) 
while the total route length of the network is 63,465 km (39,435 mi). About 40% 
of the total track kilometer is electrified & almost all electrified sections use 
25,000 V AC. Indian railways uses four rail track gauges 
Indian Railways operates about 9,000 passenger trains and transports 
18 million passengers daily .Indian Railways makes 70% of its revenues and most 
of its profits from the freight sector, and uses these profits to cross-subsidies the 
loss-making passenger sector. The Rajdhani Express and Shatabdi Express are the 
fastest trains of India.
INTRODUCTION 
TO 
DIESEL LOCOMOTIVE WORKSHOP 
Diesel locomotive works is a production unit under the ministry of railways. This 
was set up in collaboration with American locomotive company (ALCO) USA in 
1961 and the first locomotive was rolled out in 1964 .This unit produce diesel 
electronic locomotives and DG sets for Indian railways and other customers in 
India and abroad. 
Subsequently a contract for transfer of technology of 4000 HP microprocessors 
controlled AC/AC freight (GT 46 MAC)/passenger (GT 46 PAC) locomotives 
and family of 710 engines has been signed with electromotive division of general 
motor of USA for manufacture in DLW . The production of this locomotive has 
now started and thus DLW is only manufacture diesel electric locomotives with 
both ALCO and general motor technologies in the world.
BRIFF HISTORY OF DLW 
Diesel electric locomotives were introduced on Indian Railways in 
1950’s to exploit their versatile y, better hauling capabilities, low maintenance 
requirement and cost effectiveness is compared to the steam locomotives. 
DIESEL LOCOMOTIVE WORK was established in 1961 in 
collaboration with M/s ALCO,USA in t5he ancient temple city of Varanasi is 
undertake indigenous manufacture of diesel locomotives and meet the increased 
transportation needs of Indian railways over the year. 
DLW’s production has progressively increased and it produced 164 
locomotives, the highest number ever in the year 1997-98 as against 4 locomotives 
produced in the first year of its production in 1963-64 presently the locomotives 
are almost fully indigenous the import comet of the locomotives has come down 
from 98% in 63-64 to less then 5% as at present through in house development 
efforts, the original imported dowsing has been made 79 mare fuel-efficient and 
has axon been successfully up rated to deliver about 30% mere power. 
By end of March’2005 DLW has manufactured 4707 locomotives and 
39 high capacities dies generating sets. This includes 321 locomotives for non 
railways customers is India like power plants port trusts/steel plant etc. And 75 
locomotives export to TANZANIA.VIETNAM.SRI LANKA .and Bangladesh 
& Malaysia 36 ydm4 locomotives manufactured by DLW are also operating 
on lease in Malaysia.
In order to upgrade the technology and keep pace with latest, Indian 
railways entered into an agreement with M/s general motors, USA for transfer of 
technology for the manufacture of 4000 HP state-of-the-art, AC-AC, 
microprocessor controlled fuel efficient WDG4/WDP4 locomotives at DLW these 
locos are now under man facture at DLW the first indigenous,WDG4 freight loco, 
was manufactured in mar,2002 and the first passenger version,WDP4,in march30 
with 50% indigenous content straightway.51 such locomotives have been 
manufactured so far indigenous content increased to 70%. 
DLW got its first ISO certification in 1997.recently DLW has 
obtained the “integrated Quality and environment management system” 
certification based on ISO-9001 an ISO14001 indec.2002.DLW is proud to be the 
pioneer in this area amongst the government/public sector units in the country.
SALIENT FEATURE 
Annual production capacity` 125 Locomotives 
Annual turn-over (Rs) 5000 million 
Total number of staff 7223 
Workshop land 89 Hectares 
Township area 211 Hectares 
Covered area in shops 86300 Sq.m 
Covered area of other 
Service buildings 73700 Sq.m 
Electrical power requirement 3468 KVA 
(Average maximum demand) 
Electrical energy consumption 
(units/year) 19.8 million 
Stand by power generation capacity 3000 KW
DIFFERENT WORKS AT DLW 
UNDER FRAMES & SUPERSTRUCTURES: 
Precision cutting and formatting of sheet metal is utilized for 
manufacture of superstructures including driver cab, engine hoods, and 
compartment for housing electric equipment. All activities connected with pipes 
like pickling, bending, cutting, forming and threading of pipes of various work 
area, all electrical equipment is assembled in the fabricated control compartment 
and driver’s control stands. 
Under frames are fabricated taking all due care to ensure designed 
weld strength. Care is taken to impart the requisite camber to the under frame 
during fabrication it self. Wherever required, welds are tested radio graphically. 
Welder training and their technical competence is periodically reviewed 
FIG NO 1( SUPER STRUCTURE OF ENGINE)
BOGIE MANUFACTURING: 
Large special purpose machines are utilized for machining cast and 
fabricated bogie frames in the same work area, axel and wheel disc machining is 
undertaken on sophisticated CNC machines. Inner diameter of wheels discs are 
carefully matched with the outer diameter of. Axles before the wheel discs are 
pressed onto, at designated pressure, using a specially designed wheel press. The 
complete truck (bogie), including bogie frames, wheels and axles, brake rigging 
and traction motor is assemble d before being sent onwards for locomotive 
assembly. 
FIG NO 2 ( BOGIE)
LOCOMOTIVE ASSEMBLY AND TESTING: 
Assembled and tested engines are received in this shop from Engine 
Division. Also , under frame , assembled truck , superstructures and contractor 
compartment are receive from respective manufacturing and assembly shops of 
Vehicle Division. Important alignments like crank shaft deflection, compressor 
alignment like crank shaft deflection, compressor alignment and Eddy Current 
clutch/radiator fan alignment are done during assembly stage if self. 
Electrical control equipments are fitted and control cable harnessing is 
undertaken. The complete locomotive is thus assembled before being sent onwards 
for final testing and spray painting. 
Rigorous testing of all locomotive system is conducted as per laid 
down test procedures before the locomotives is taken up for final painting and 
dispatch. 
The engine block, crankshaft, camshaft, cylinder liners, pistons, 
connecting rods, cylinder heads, exhaust manifold, turbo-supercharger and all 
related piping is assembled to make a complete engine. This is followed by 
mounting of electrical machines like traction alternator, auxiliary generator and 
exacter. This power pack is tested for horsepower output and other parameters of 
engine heath on computerized Engine test beds. Only after the engine parameters 
are found perfect the power pack is allowed to be moved to the locomotives 
assembly area. 
Important alignments like crank shaft deflection, compressor 
alignment and Eddy Current clutch/radiator fan alignment are done during 
assembly stage. Electrical control equipments are fitted and control cable 
harnessing is undertaken. The complete locomotive is thus assembled before being 
sent onwards for final testing and .all locomotive systems are rigorous tested as per 
laid down test procedures before the locomotive is taken up for final painting and 
dispatch.
CLASSIFICATION 
1. Standard “Gauge” designations and dimensions:- 
 W = Broad gauge (1.67 m) 
 Y = Medium gauge ( 1 m) 
 Z = Narrow gauge ( 0.762 m) 
 N = Narrow gauge ( 0.610 m) 
2. “ Type of Traction” designations:- 
 D = Diesel-electric traction 
 C = DC traction 
 A = AC traction 
 CA=Dual power AC/DC traction 
3. The “ type of load” or “Service” designations:- 
 M= Mixed service 
 P = Passenger 
 G= Goods 
 S = Shunting 
4. “ Horse power ” designations from June 2002 (except WDP-1 & WDM-2 
LOCOS) 
 ‘ 3 ’ For 3000 horsepower 
 ‘ 4 ’ For 4000 horsepower 
 ‘ 5 ’ For 5000 horsepower 
 ‘ A ’ For extra 100 horsepower 
 ‘B’ For extra 200 horsepower and so on 
. 
Hence ‘WDM-3A’ indicates a broad gauge loco with diesel-electric 
traction. It is for mixed services and has 3100 horsepower.
OVERVIEW OF DIESEL 
LOCOMOTIVE 
FIG NO 3 ( OVERVIEW OF LOCOMOTIVE) 
 
SAND BOX 
 RADIATOR 
 RADIATOR FAN 
 TURBO SUPERCHARGER 
 BOGIE(2 SETS)(3AXLE OR 2 AXLE)
 FUEL TANK 
 AIR RESERVOIERS 
 POWER PACK 
 DYNAMO WITH ALTRNATOR 
 BATTERIES 
 DRIVER CABIN 
 WHEEL ASSEMBLY 
 DISC 
 BLOWER 
 TRACTON MOTER 
 TRUCK 
 GEAR AND PENION ASSSEMBLY 
 CYLINDER HEAD 
 CROSS HEAD 
 FUEL INJECTION PUMP 
 BATTERIES (8 OF 8.68 VOLTS) 
 FUEL TANK 
 AFTER COOLING CORE 
 JUNCTION BOX
PRODUCTION SHOPS 
There are three production shops: 
1. BLOCK DIVISION 
2. ENGINE DIVISION 
3. LOCO DIVISION 
BLOCK DIVISION 
There are two block division 
1. HEAVY WELD SHOP 
2. HEAVY MACHINE SHOP 
ENGINE DIVISION 
There are seven engine division 
1. ENGINE ERECTION SHOP 
2. ENGINE TESTING SHOP 
3. LIGHT MACHINE SHOP 
4. SUB ASSEMBLY SHOP 
5. ROTOR SHOP 
6. HEAT TREATMENT SHOP 
7. TURBO SELECTION SHOP
LOCO DIVISION 
There are eight loco division: 
1. LOCO FRAME SHOP 
2. PIPE SHOP 
3. TRUCK MACHINE SHOP 
4. TRACTION ASSEMBLY SHOP 
5. SHEET MEATL SHOP 
6. LOCO AASEMBLY SHOP 
7. LOCO PAINT SHOP 
8. LOCO TEST SHOP
SUB ASSEMBLY SHOP 
This shop deals with following section:-- 
1.Turbo machining section 
2.Cylinder head & shot blast section 
3.Fuel pump, Support, Cam shaft ate section 
4.Cylinder head 
5.Turbo 
6.Governor, Water Pump, Fan drive, Lube oil Pump, After cooler 
assembly section. 
CYLINDER HEAD SECTION 
The lay out of this section is product type. There are different 
machines had do set up per sequence of operation of cylinder head. 
A milling machine provides profile cutting and taper profile 
according of the template. The tracer runs and cutter forms shaper radial 
drilling machine. This machine provides for drilling tapping. Core 
boring operation as per drawing
HEARALD BOROING MACHINE 
This machine having four spindles for boring of guide hole, 
air & exhaust it dimensions are— 
1.Valve inner sheet dia 4 hole- 3.1805-3.1815 
2.Guide hole dia- 1.0625‖-1.0635‖ 
3.Valve sheet depth (E1, E2, A1)- 0.740‖ to 0.745‖ & A2- 
0.950‖ 
4.Depth of sheet (A1 E1, E2)- 0.205‖-0.215‖ 
5.Spring sheet depth (E1, E2, E1)- 1.865‖-1.885 
CONTROL SHAFT ASSEMBLY 
It is a link between Governor & Fuel injector pumps by 
which the mechanical power from the governor transmitted to the fuel 
injection pump Racks. It means to control the amount of fuel according 
to the requirement of load & speed. 
EXPLOSION DOOR COVER ASSEMBLY 
. It is special type of main base door cover which when the 
crank case exhauster failed to work 
CAM SHAFT VIBRATION DAMPER ASSEMBLY 
When vibration developed on the cam shaft will be damped 
by this assembly.
O.S.T. HOUSING ASSEMBLY 
This assembly controls the R.P.M. of crank shaft and keeps it 
a specified limit (1000 to 11500 r.p.m.). When OST is operated in the 
case 16 cylinder engine the engine RPM will come in ideal but in case of 
16 cylinder engines will be stopped. 
FUEL PUMP SUPPORT ASSEMBLY 
It is a support of the fuel pump on which the fuel injection 
pump is mounted and the power of cam shaft is transmitted to operate 
fuel injection pump through the cross head lighter & to operate push rod 
by PRD. Lifter by which the inlet & exhaust valve open & closed 
through the valve lever & yokes. 
ACCELERATION CONTROL DEVICE 
By this device by monopoly of the driver is controlled the air 
& fuel supply is controlled by according to the fuel ratio. It is controlled 
the proper fuel and air ratio. 
FIG NO 4(Schematic diagram of ALCO Engine)
ROTOR SHOP 
This shop is deals with the manufacturing of Turbocharger. 
Turbocharger is known as the Heart of Diesel Locomotive. Basically in 
this section manufacturing of assembly & sub assembly of Turbocharger 
is made. But the outer casing of Turbocharger is made up in Heavy 
Machine Shop. 
Turbocharger is use for the providing fresh air to the engine. 
Due to this the efficiency & power generated by engine is increased. For 
the running of Turbocharger we are not using any extra energy source 
like generator, motor etc. For starting of Turbocharger generally we use 
exhaust gasses. 
COMPONENTS OF TURBOCHARGER 
For assembly of Turbojet following parts are manufactures in 
rotor shop 
1. Impeller 7. Thrust Washer 
2. Inducer 8. Key 
3. Nose piece 9. Oil Slinger 
4. Stud Rotor 10. Turbine Disc 
5. Nut 11. Turbo Shaft 
6. Washer 12. Lock plate
ASSEMBLY OF TURBOCHARGER 
The assembly of turbocharger is done by dividing whole 
turbocharger in three parts. These are as follows 
1. Rotor 
2. Compressor 
3. Casing 
1. ROTOR 
Rotor is the inlet part of turbocharger which is comprises 
with following parts. Turbo Disc, Rotor stud, Turbo shaft, thrust collar, 
Nose disc, Washer & Nut. 
Rotor is rotating at speed of 18000 rpm & working at high 
temperature due to that the rotor is made of steel. 
2. COMPRESSOR 
Compressor is the combination of impeller & inducer. Impeller is made 
up of Al-alloy. Impeller & inducer is use for sucking of fresh air from 
environment 
. 
FIG NO (5) TURBOSUPER CHRAGER
3. CASING 
Casing is made of M.S. & also a special type of coating is 
done. Due to that coating it can easily resist the heat. 
For the proper working & life of Turbocharger balancing of impeller, 
inducer & turbine disc is done by help of Dynamics Balancing Machine. 
For the proper working & life of Turbocharger balancing of impeller, 
inducer & turbine disc is done by help of Dynamics Balancing Machine. 
TURBO SUPERCHARGER AND ITS WORKING 
PRINCIPLE 
The exhaust gas discharge from all the cylinders accumulate in the 
common exhaust manifold at the end of which, turbo- supercharger is fitted. The 
gas under pressure there after enters the turbo- supercharger through the torpedo 
shaped bell mouth connector and then passes through the fixed nozzle ring. Then it 
is directed on the turbine blades at increased pressure and at the most suitable 
angle to achieve rotary motion of the turbine at maximum efficiency. After rotating 
the turbine, the exhaust gas goes out to the atmosphere through the exhaust 
chimney. 
The turbine has a centrifugal blower mounted at the other end of the 
same shaft and the rotation of the turbine drives the blower at the same speed. The 
blower connected to the atmosphere through a set of oil bath filters, sucks air from 
atmosphere, and delivers at higher velocity. The air then passes through the 
diffuser inside the turbo- supercharger, where the velocity is diffused to increase 
the pressure of air before it is delivered from the turbo- supercharger
Pressurising air increases its density, but due to compression heat 
develops. It causes expansion and reduces the density. This effects supply of high-density 
air to the engine. To take care of this, air is passed through a heat 
exchanger known as after cooler. The after cooler is a radiator, where cooling 
water of lower temperature is circulated through the tubes and around the tubes air 
passes. The heat in the air is thus transferred to the cooling water and air regains its 
lost density. From the after cooler air goes to a common inlet manifold connected 
to each cylinder head. In the suction stroke as soon as the inlet valve opens the 
booster air of higher pressure density rushes into the cylinder completing the 
process of super charging. 
The engine initially starts as naturally aspirated engine. With the 
increased quantity of fuel injection increases the exhaust gas pressure on the 
turbine. Thus the self-adjusting system maintains a proper air and fuel ratio under 
all speed and load conditions of the engine on its own. The maximum rotational 
speed of the turbine is 18000/22000 rpm for the Turbo supercharger and creates 
max. Of 1.8 kg/cm2 air pressure in air manifold of diesel engine, known as Booster 
Air Pressure (BAP). Low booster pressure causes black smoke due to incomplete 
combustion of fuel. High exhaust gas temperature due to after burning of fuel may 
result in considerable damage to the turbo supercharger and other component in the 
engine. 
FIG NO(6)TURBOSUPERCHRGER WORKING
EXPRESSOR 
FIG NO (7) EXPRESSOR 
In Indian Railways, the trains normally work on vacuum brakes 
and the diesel locos on air brakes. As such provision has been made on every 
diesel loco for both vacuum and compressed air for operation of the system as a 
combination brake system for simultaneous application on locomotive and train. 
In ALCO locos the exhauster and the compressor are combined into one unit and 
it is known as EXPRESSOR. It creates 23" of vacuum in the train pipe and 140 
PSI air pressure in the reservoir for operating the brake system and use in the 
control system etc.
The expressor is located at the free end of the engine block and driven through 
the extension shaft attached to the engine crank shaft. The two are coupled together 
by fast coupling (Kopper's coupling). Naturally the expressor crank shaft has eight 
speeds like the engine crank shaft. There are two types of expressor are, 6CD,4UC 
& 6CD,3UC. In 6CD,4UC expressor there are six cylinder and four exhauster 
whereas 6CD,3UC contain six cylinder and three exhauster. 
WORKING OF EXHAUSTER 
Air from vacuum train pipe is drawn into the exhauster cylinders 
through the open inlet valves in the cylinder heads during its suction stroke. Each 
of the exhauster cylinders has one or two inlet valves and two discharge valves in 
the cylinder head. A study of the inlet and discharge valves as given in a separate 
diagram would indicate that individual components like 
(1) plate valve outer 
(2) plate valve inner 
(3) spring outer 
(4) spring inner etc. are all interchangeable parts. 
Only basic difference is that they are arranged in the reverse 
manner in the valve assemblies which may also have different size and shape. The 
retainer stud in both the assemblies must project upward to avoid hitting the 
piston. 
The pressure differential between the available pressure in the vacuum train 
pipe and inside the exhauster cylinder opens the inlet valve and air is drawn into 
the cylinder from train pipe during suction stroke. In the next stroke of the piston 
the air is compressed and forced out through the discharge valve while the inlet 
valve remains closed. The differential air pressure also automatically open or 
close the discharge valves, the same way as the inlet valves operate. This process 
of suction of air from the train pipe continues to create required amount of 
vacuum and discharge the same air to atmosphere. The VA-1 control valve helps 
in maintaining the vacuum to requisite level despite continued working of the 
exhauster.
COMPRESSOR 
The compressor is a two stage compressor with one low pressure 
cylinder and one high pressure cylinder. During the first stage of compression 
it is done in the low pressure cylinder where suction is through a wire mesh 
filter. After compression in the LP cylinder air is delivered into the discharge 
manifold at a pressure of 30 / 35 PSI. 
Workings of the inlet and exhaust valves are similar to that of 
exhauster which automatically open or close under differential air pressure. For 
inter-cooling air is then passed through a radiator known as inter-cooler. This is an 
air to air cooler where compressed air passes through the element tubes and 
cool atmospheric air is blown on the out side fins by a fan fitted on the expressor 
crank shaft. . 
A safety valve known as inter cooler safety valve set at 60 PSI is 
provided after the inter cooler as a protection against high pressure developing 
in the after cooler due to defect of valves. 
After the first stage of compression and after-cooling the air is again 
compressed in a cylinder of smaller diameter to increase the pressure to 135-140 
PSI in the same way. This is the second stage of compression in the HP cylinder. 
Air again needs cooling before it is finally sent to the air reservoir and this is done 
while the air passes through a set of coiled tubes after cooler.
LOCMOTIVE /TRUCK 
MACHINE SHOP 
FIG NO (7)TRUCK MACHINE SHOP
FABRICATION OF ENGINE BLOCK 
Steel plates of sizes up to 80 mm thick are ultrasonically tested 
before being precision cut by numerically controlled flame cutting machines. 
Fabrication of engine block is completed by submerged arc welding using semi-automatic 
welding machines. Down-hand welding is ensured using specially 
designed petitioners. Special fixtures are used for making down-hand welding 
possible in inaccessible areas. Critical welds are subjected to radiographic 
examination. All welders are periodically tested and re-qualified for the assigned 
job 
FIG NO (8) FABRICATION OF ENGINE BLOCK
MACHINING OF ENGINE BLOCK 
The fabricated engine block is then taken up for a variety of 
machining operations like planning, enveloping and end drilling. All these 
operations use heavy duty planers and CNC drilling machines. V-boring of 
cylinder liner bores is a process requiring a high degree of precision and is 
undertaken using a specially designed machine. Recent addition of a Plano-milling 
centre has provided further fillip to the quality and speed of enveloping 
operation. 12 Cylinder and 16 Cylinder Blocks have V angle of 45°, whereas the 
6 Cylinder Block is inline type. 
FIG NO (9) TESTING OF THE LOCOMOTIVE OR TRUCK
COMPONENT MANUFACTURING 
Over 2000 components are manufactured in-house at DLW. These 
include ALCO turbo superchargers, lubricating oil pumps, cam shafts, cylinder 
heads, chrome plated cylinder liners, connecting rods and various gears. Our 
well-equipped Machine Shops have dedicated lines for operations like turning, 
milling, gear hobbing, drilling, grinding and planning etc. In addition, DLW is 
equipped with a variety of special purpose machines and a large number of 
state-of-the-art CNC machines to ensure quality and precision. All related 
processes like heat treatment and induction hardening are also carried out in-house. 
A completely new Chrome Plating Shop for Cylinder Liners has been set 
up with modern infrastructure like fume extraction system and Programmable 
Logic Controlled material movement system. 
FIG NO(10) COMPONENT MANUFACTURING
ENGINE ASSEMBLY & TESTING 
The engine block, crankshaft, camshafts, cylinder liners, pistons, 
connecting rods, cylinder heads, exhaust manifold, turbo-supercharger and all 
related piping is assembled to make a complete engine. This is followed by 
mounting of electrical machines like traction alternator, auxiliary generator and 
exciter. This power pack is tested for horsepower output and other parameters of 
engine health on computerized Engine Test Beds. Only after the engine 
parameters are found perfect the power pack is allowed to be moved to the 
locomotive assembly area 
FIG NO(11)ASSEMBLED ENGINE
VEHICLE DIVISION 
UNDERFRAMES & SUPERSTRUCTURES 
FIG NO (12) SUPERSTRUCTURE 
Precision cutting and forming of sheet metal is utilized for 
manufacture of superstructures including drivers cab, engine hoods, 
and compartments for housing electrical equipment. All activities 
connected with pipes like pickling, bending, cutting, forming and 
threading of pipes of various sizes are undertaken in another well-equipped 
work area. In yet another work area, all electrical equipment 
is assembled in the fabricated control compartments and driver’s 
control stands. Under frames are fabricated taking all due care to 
ensure designed weld strength. Care is taken to impart the requisite 
camber to the under frame during fabrication itself. Wherever required, 
welds are tested radio graphically. Welder training and their technical 
competence is periodically reviewed.
BOGIE MANUFACTURING 
FIG NO (13) BOGIE MANUFACTURING 
Large special purpose machines are utilized for machining cast and 
fabricated bogie frames. In the same work area, axle and wheel disc machining is 
undertaken on sophisticated CNC machines. Inner diameter of wheel discs are 
carefully matched with the outer diameter of axles before the wheel discs are 
pressed onto axles, at designated pressure, using a specially designed wheel 
press. The complete truck (bogie), including bogie frames, wheels and axles, 
brake rigging and traction motors is assembled before being sent onwards for 
locomotive assembly.
LOCOMOTIVE ASSEMBLY & TESTING 
FIG NO(14) ENGINE TESTING 
Assembled and tested engines are receive in this Shop from Engine 
Division. Also, under frames, assembled trucks, superstructures and contractor 
compartments are received from respective manufacturing and assembly shops of 
Vehicle Division. Important alignments like crank shaft deflection, compressor 
alignment and Eddy Current clutch/radiator fan alignment are done during assembly 
stage itself. Electrical control equipments are fitted and control cable harnessing is 
undertaken. The complete locomotive is thus assembled before being sent onwards for 
final testing and spray painting. Rigorous testing of all locomotive systems is conducted 
as per laid down test procedures before the locomotive is taken up for final painting and 
dispatch.
MACHINE SHOP 
There are some important machines which used in the different 
type of shops. 
1. LATHE MACHINE
2. SLOTTER MACHINE 
3.PLANER MACHINE
4.CNC WHEEL SURFACE LATHE 
5.CNC WHEEL TURRET LATHE
6.CNC BIG BORE LATHE WITH SPINDLE
CONCLUSION 
I have completed my training from the DIESEL 
LOCOMOTIVE WORKSHOP , VARANSI . I have observed many 
shop in the workshop I mainly performed my training in the the LAS, 
SAS , ROTOR SHOP AND TMS SHOP. 
In the locomotive workshop ,all the SSE and JE and 
SUPERVISIORS of all te shops helped very much. Without hisor her 
supervision I was not able to perform the training in all the workshops. I 
am very grateful to him . 
We have learned too much in the workshop, DIFFERENT 
TYPE OF WORKSHOP TECHNOLOGY, TESTING OF THE PARTS 
OF THE LOCOMOTIVE AND THE PROPER FUNCTIONING of the 
different locomotive parts as a TURBOSUPERCHARGER, 
EXPRESSOR, POWER PACK OF THE LOCOMOTVE , RADIATOR 
SECTION ,OIL SUMP, DYNAMO AND BOGIE AND 
FABRICATION OF THE BODY OF LOCOMOTIVE .
REFRENCES 
 Workshop technology by Hazara & Chaudhary 
 Production technology by P.C. SHARMA 
 Study material provided by TECHNICAL TRAINING CENTRE 
 Workshop technology by S. K. GARG 
 WWW.RAILWAY TECHNICAL.CO.IN 
 WWW.HOWSTUFFWORKS.IN 
 WWW.IRFCA.CO.IN

More Related Content

What's hot

Diesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine ShopDiesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine ShopGaurav Mishra
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedisomesh dwivedi
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasiShubham​ Yadav
 
Diesel locomotive work
Diesel locomotive workDiesel locomotive work
Diesel locomotive workvipin rai
 
DLW Summer training report
DLW Summer  training  reportDLW Summer  training  report
DLW Summer training reportEshver chandra
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyshubhangpandey5
 
DLW varanasi summer training report
DLW varanasi summer training reportDLW varanasi summer training report
DLW varanasi summer training reportshubham chaurasiya
 
Report on dlw varanasi
Report on  dlw varanasiReport on  dlw varanasi
Report on dlw varanasiSanjay Yadav
 
Vocational training Report for ECE department
Vocational training  Report for ECE departmentVocational training  Report for ECE department
Vocational training Report for ECE departmentManoj Verma
 
Dlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit TiwariDlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit TiwariSumitTiwari76
 
Summer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSummer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSHAILESH SHUKLA
 
DLW TRAINING REPORT
DLW TRAINING REPORTDLW TRAINING REPORT
DLW TRAINING REPORTdevesh soni
 
DLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL BranchDLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL BranchRahul Gupta
 
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Devendra Kumar
 
INDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,VaranasiINDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,Varanasiak3793
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training reportGyanendra Prakash
 

What's hot (20)

Diesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine ShopDiesel locomotive works - Truck Machine Shop
Diesel locomotive works - Truck Machine Shop
 
diesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedidiesel locomotive works training report by somesh dwivedi
diesel locomotive works training report by somesh dwivedi
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasi
 
Diesel locomotive work
Diesel locomotive workDiesel locomotive work
Diesel locomotive work
 
DLW Summer training report
DLW Summer  training  reportDLW Summer  training  report
DLW Summer training report
 
BLW SUMMER TRAINING REPORT
BLW SUMMER TRAINING REPORTBLW SUMMER TRAINING REPORT
BLW SUMMER TRAINING REPORT
 
Dlw training
Dlw trainingDlw training
Dlw training
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandey
 
DLW varanasi summer training report
DLW varanasi summer training reportDLW varanasi summer training report
DLW varanasi summer training report
 
Dlw SUMMER TRAINING
Dlw SUMMER TRAININGDlw SUMMER TRAINING
Dlw SUMMER TRAINING
 
Report on dlw varanasi
Report on  dlw varanasiReport on  dlw varanasi
Report on dlw varanasi
 
Vocational training Report for ECE department
Vocational training  Report for ECE departmentVocational training  Report for ECE department
Vocational training Report for ECE department
 
DLW WORKSHOP , VARANSI
DLW WORKSHOP , VARANSIDLW WORKSHOP , VARANSI
DLW WORKSHOP , VARANSI
 
Dlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit TiwariDlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit Tiwari
 
Summer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSummer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW Varanasi
 
DLW TRAINING REPORT
DLW TRAINING REPORTDLW TRAINING REPORT
DLW TRAINING REPORT
 
DLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL BranchDLW, Varanasi Summer Training Report- CIVIL Branch
DLW, Varanasi Summer Training Report- CIVIL Branch
 
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
 
INDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,VaranasiINDUSTRIAL TRAINING(PPT) DLW,Varanasi
INDUSTRIAL TRAINING(PPT) DLW,Varanasi
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
 

Viewers also liked

Machinary shop
Machinary shopMachinary shop
Machinary shopHome
 
presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)shubham vishwakarma
 
Diesel loco modernization
Diesel loco modernizationDiesel loco modernization
Diesel loco modernizationAmitoj Kaur
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaArjun Gaur
 
Manufacturing processes
Manufacturing processesManufacturing processes
Manufacturing processesYPP
 
Download presentation
Download presentationDownload presentation
Download presentationwebhostingguy
 

Viewers also liked (8)

INDUSTRIAL TRAINING REPORT ON DIESEL LOCOMOTIVE TECHNOLOGY REPORT 2015 (LUCKNOW)
INDUSTRIAL TRAINING REPORT ON DIESEL LOCOMOTIVE TECHNOLOGY REPORT 2015 (LUCKNOW)INDUSTRIAL TRAINING REPORT ON DIESEL LOCOMOTIVE TECHNOLOGY REPORT 2015 (LUCKNOW)
INDUSTRIAL TRAINING REPORT ON DIESEL LOCOMOTIVE TECHNOLOGY REPORT 2015 (LUCKNOW)
 
Machinary shop
Machinary shopMachinary shop
Machinary shop
 
presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)presentation on diesel locomotive works (dlw)
presentation on diesel locomotive works (dlw)
 
Diesel loco modernization
Diesel loco modernizationDiesel loco modernization
Diesel loco modernization
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
 
Introduction to manufacturing process
Introduction to manufacturing processIntroduction to manufacturing process
Introduction to manufacturing process
 
Manufacturing processes
Manufacturing processesManufacturing processes
Manufacturing processes
 
Download presentation
Download presentationDownload presentation
Download presentation
 

Similar to Dlw locomotive workshop

TAS MRS LAS COLONY.pdf
TAS MRS LAS COLONY.pdfTAS MRS LAS COLONY.pdf
TAS MRS LAS COLONY.pdfpriyanshupal26
 
DLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indoreDLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indoreSANJEET KUMAR
 
TRAINING REPORT FULL
TRAINING REPORT FULLTRAINING REPORT FULL
TRAINING REPORT FULLanish malan
 
DLW SUMMER TRAINING REPORT FOR ECE BRANCH
DLW SUMMER TRAINING REPORT FOR ECE BRANCH DLW SUMMER TRAINING REPORT FOR ECE BRANCH
DLW SUMMER TRAINING REPORT FOR ECE BRANCH SUBHAM SINGH
 
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...ABHINAV KUMAR
 
Railway Training Report
Railway Training ReportRailway Training Report
Railway Training ReportVishal Singh
 
Electric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New DelhiElectric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New DelhiPrabjeet Singh
 
Internship Training (Mechanical Harnaut)
Internship Training (Mechanical Harnaut)Internship Training (Mechanical Harnaut)
Internship Training (Mechanical Harnaut)TathagatSingh5
 
Anish report
Anish reportAnish report
Anish reportrboy001
 
Dlw summer training report 2018(2)
Dlw summer training report 2018(2)Dlw summer training report 2018(2)
Dlw summer training report 2018(2)SaurabhGupta912
 
Summer traning dlw repoart
Summer  traning dlw repoartSummer  traning dlw repoart
Summer traning dlw repoartARJUN MAURYA
 
Summer Training Report Front page (DLW).
Summer Training Report Front page (DLW).Summer Training Report Front page (DLW).
Summer Training Report Front page (DLW).Vivek Yadav
 
Shivam pajpati pptx presebntation
Shivam  pajpati pptx presebntationShivam  pajpati pptx presebntation
Shivam pajpati pptx presebntationShivam Prajapati
 
Indian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~iIndian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~ihaxxo24
 

Similar to Dlw locomotive workshop (20)

TAS MRS LAS COLONY.pdf
TAS MRS LAS COLONY.pdfTAS MRS LAS COLONY.pdf
TAS MRS LAS COLONY.pdf
 
Bh
BhBh
Bh
 
DLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indoreDLW, VARANASI training report for LNCT college indore
DLW, VARANASI training report for LNCT college indore
 
TRAINING REPORT FULL
TRAINING REPORT FULLTRAINING REPORT FULL
TRAINING REPORT FULL
 
DLW SUMMER TRAINING REPORT FOR ECE BRANCH
DLW SUMMER TRAINING REPORT FOR ECE BRANCH DLW SUMMER TRAINING REPORT FOR ECE BRANCH
DLW SUMMER TRAINING REPORT FOR ECE BRANCH
 
DLW training report
DLW  training reportDLW  training report
DLW training report
 
diesel shed izzatnagar report part 2
diesel shed izzatnagar report part 2diesel shed izzatnagar report part 2
diesel shed izzatnagar report part 2
 
renew the project
renew the projectrenew the project
renew the project
 
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
 
Railway Training Report
Railway Training ReportRailway Training Report
Railway Training Report
 
Electric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New DelhiElectric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New Delhi
 
himanshu (1)
himanshu (1)himanshu (1)
himanshu (1)
 
Internship Training (Mechanical Harnaut)
Internship Training (Mechanical Harnaut)Internship Training (Mechanical Harnaut)
Internship Training (Mechanical Harnaut)
 
Anish report
Anish reportAnish report
Anish report
 
Dlw summer training report 2018(2)
Dlw summer training report 2018(2)Dlw summer training report 2018(2)
Dlw summer training report 2018(2)
 
Summer traning dlw repoart
Summer  traning dlw repoartSummer  traning dlw repoart
Summer traning dlw repoart
 
Shivendra singh
Shivendra singhShivendra singh
Shivendra singh
 
Summer Training Report Front page (DLW).
Summer Training Report Front page (DLW).Summer Training Report Front page (DLW).
Summer Training Report Front page (DLW).
 
Shivam pajpati pptx presebntation
Shivam  pajpati pptx presebntationShivam  pajpati pptx presebntation
Shivam pajpati pptx presebntation
 
Indian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~iIndian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~i
 

More from Shivam Prajapati

Designinginterestingmoments 090918130401-phpapp01
Designinginterestingmoments 090918130401-phpapp01Designinginterestingmoments 090918130401-phpapp01
Designinginterestingmoments 090918130401-phpapp01Shivam Prajapati
 
Whyelectriccars 141014161130-conversion-gate01
Whyelectriccars 141014161130-conversion-gate01Whyelectriccars 141014161130-conversion-gate01
Whyelectriccars 141014161130-conversion-gate01Shivam Prajapati
 
Wds leanengineering-141103233017-conversion-gate02
Wds leanengineering-141103233017-conversion-gate02Wds leanengineering-141103233017-conversion-gate02
Wds leanengineering-141103233017-conversion-gate02Shivam Prajapati
 
Studentsproject groundnutshellarmachine-140507061025-phpapp02
Studentsproject groundnutshellarmachine-140507061025-phpapp02Studentsproject groundnutshellarmachine-140507061025-phpapp02
Studentsproject groundnutshellarmachine-140507061025-phpapp02Shivam Prajapati
 

More from Shivam Prajapati (8)

tidal energy
tidal energytidal energy
tidal energy
 
Designinginterestingmoments 090918130401-phpapp01
Designinginterestingmoments 090918130401-phpapp01Designinginterestingmoments 090918130401-phpapp01
Designinginterestingmoments 090918130401-phpapp01
 
Whyelectriccars 141014161130-conversion-gate01
Whyelectriccars 141014161130-conversion-gate01Whyelectriccars 141014161130-conversion-gate01
Whyelectriccars 141014161130-conversion-gate01
 
Wds leanengineering-141103233017-conversion-gate02
Wds leanengineering-141103233017-conversion-gate02Wds leanengineering-141103233017-conversion-gate02
Wds leanengineering-141103233017-conversion-gate02
 
Hoe to make engg
Hoe to make enggHoe to make engg
Hoe to make engg
 
Studentsproject groundnutshellarmachine-140507061025-phpapp02
Studentsproject groundnutshellarmachine-140507061025-phpapp02Studentsproject groundnutshellarmachine-140507061025-phpapp02
Studentsproject groundnutshellarmachine-140507061025-phpapp02
 
MECHANICAL PROJECT
MECHANICAL PROJECTMECHANICAL PROJECT
MECHANICAL PROJECT
 
LOCO TRAINING REPORT
LOCO TRAINING REPORTLOCO TRAINING REPORT
LOCO TRAINING REPORT
 

Recently uploaded

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

Dlw locomotive workshop

  • 1. BABU BANARSI DAS NATIONAL INSTITUTE OF TECHNOLOGY & MANAGEMENT, LUCKNOW A INDUSTRIAL TRAINING REPORT ON DISEL LOCOMOTIVE WORKSHOP SUBMITTED TO: SUBMITTED BY: RAMENDRA Kr. VISEN HIMANSHU S. SINGH (Sr. LECTURER) ROLL NO: 1105440044 B.Tech (MECHANICAL) B. B. D. N. I. T. M.
  • 2. DIESEL LOCOMOTIVE WORKSHOP VARANSI A INDUSTRIAL TRAINING REPORT ON DISEL LOCOMOTIVE WORKSHOP SUBMITTED TO: SUBMITTED BY: RAMENDRA Kr. VISEN HIMANSHU S. SINGH (Sr. LECTURER) ROLL NO: 1105440044 B.Tech (MECHANICAL) B. B. D. N. I. T. M.
  • 3. ACKNOWLEDGEMENT I take this opportunity my sincere thanks and deep gratitude to S.P. ASTHANA (HEAD OF MECHANICAL DEPARTMENT) all these people who extended their whole hearted co-operation and helped me in completing this project successfully. First of all I would like to thanks all the S.S.E. and J.E. of the all the sections for creating oppurtunities to undertake me in this esteemed organization. Special thanks to all the department for all the help and guidance extended to me by them in every stage during my training. His inspiring suggestions and timely guidance enabled me to perceive the various aspects of the project in the new light. In all I found a congenial work environment in DIESEL LOCOMOTIVE WORKSHOP, VARANSI and this completion of the project will mark a new beginning for me in the coming days. SUBMITTED TO: SUBMITTED BY: RAMENDRA Kr. VISEN HIMANSHU S. SINGH (Sr. LECTURER) ROLL NO: 1105440044 B.TECH (MECHANICAL) B. B. D. N. I. T. M.
  • 4. INTRODUCTION OF INDIAN RAILWAY Indian Railways is the state-owned railway company of India. It comes under the Ministry of Railways. Indian Railways has one of the largest and busiest rail networks in the world, transporting over 18 million passengers and more than 2 million tonnes of freight daily. Its revenue is Rs.107.66 billion. It is the world's largest commercial employer, with more than 1.4 million employees. It operates rail transport on 6,909 stations over a total route length of more than 63,327 kilometers(39,350 miles).The fleet of Indian railway includes over 200,000 (freight) wagons, 50,000 coaches and 8,000 locomotives. It also owns locomotive and coach production facilities. It was founded in 1853 under the East India Company. Indian Railways is administered by the Railway Board. Indian Railways is divided into 16 zones. Each zone railway is made up of a certain number of divisions. There are a total of sixty-seven divisions.It also operates the Kolkata metro. There are six manufacturing plants of the Indian Railways. The total length of track used by Indian Railways is about 108,805 km (67,608 mi) while the total route length of the network is 63,465 km (39,435 mi). About 40% of the total track kilometer is electrified & almost all electrified sections use 25,000 V AC. Indian railways uses four rail track gauges Indian Railways operates about 9,000 passenger trains and transports 18 million passengers daily .Indian Railways makes 70% of its revenues and most of its profits from the freight sector, and uses these profits to cross-subsidies the loss-making passenger sector. The Rajdhani Express and Shatabdi Express are the fastest trains of India.
  • 5. INTRODUCTION TO DIESEL LOCOMOTIVE WORKSHOP Diesel locomotive works is a production unit under the ministry of railways. This was set up in collaboration with American locomotive company (ALCO) USA in 1961 and the first locomotive was rolled out in 1964 .This unit produce diesel electronic locomotives and DG sets for Indian railways and other customers in India and abroad. Subsequently a contract for transfer of technology of 4000 HP microprocessors controlled AC/AC freight (GT 46 MAC)/passenger (GT 46 PAC) locomotives and family of 710 engines has been signed with electromotive division of general motor of USA for manufacture in DLW . The production of this locomotive has now started and thus DLW is only manufacture diesel electric locomotives with both ALCO and general motor technologies in the world.
  • 6. BRIFF HISTORY OF DLW Diesel electric locomotives were introduced on Indian Railways in 1950’s to exploit their versatile y, better hauling capabilities, low maintenance requirement and cost effectiveness is compared to the steam locomotives. DIESEL LOCOMOTIVE WORK was established in 1961 in collaboration with M/s ALCO,USA in t5he ancient temple city of Varanasi is undertake indigenous manufacture of diesel locomotives and meet the increased transportation needs of Indian railways over the year. DLW’s production has progressively increased and it produced 164 locomotives, the highest number ever in the year 1997-98 as against 4 locomotives produced in the first year of its production in 1963-64 presently the locomotives are almost fully indigenous the import comet of the locomotives has come down from 98% in 63-64 to less then 5% as at present through in house development efforts, the original imported dowsing has been made 79 mare fuel-efficient and has axon been successfully up rated to deliver about 30% mere power. By end of March’2005 DLW has manufactured 4707 locomotives and 39 high capacities dies generating sets. This includes 321 locomotives for non railways customers is India like power plants port trusts/steel plant etc. And 75 locomotives export to TANZANIA.VIETNAM.SRI LANKA .and Bangladesh & Malaysia 36 ydm4 locomotives manufactured by DLW are also operating on lease in Malaysia.
  • 7. In order to upgrade the technology and keep pace with latest, Indian railways entered into an agreement with M/s general motors, USA for transfer of technology for the manufacture of 4000 HP state-of-the-art, AC-AC, microprocessor controlled fuel efficient WDG4/WDP4 locomotives at DLW these locos are now under man facture at DLW the first indigenous,WDG4 freight loco, was manufactured in mar,2002 and the first passenger version,WDP4,in march30 with 50% indigenous content straightway.51 such locomotives have been manufactured so far indigenous content increased to 70%. DLW got its first ISO certification in 1997.recently DLW has obtained the “integrated Quality and environment management system” certification based on ISO-9001 an ISO14001 indec.2002.DLW is proud to be the pioneer in this area amongst the government/public sector units in the country.
  • 8. SALIENT FEATURE Annual production capacity` 125 Locomotives Annual turn-over (Rs) 5000 million Total number of staff 7223 Workshop land 89 Hectares Township area 211 Hectares Covered area in shops 86300 Sq.m Covered area of other Service buildings 73700 Sq.m Electrical power requirement 3468 KVA (Average maximum demand) Electrical energy consumption (units/year) 19.8 million Stand by power generation capacity 3000 KW
  • 9. DIFFERENT WORKS AT DLW UNDER FRAMES & SUPERSTRUCTURES: Precision cutting and formatting of sheet metal is utilized for manufacture of superstructures including driver cab, engine hoods, and compartment for housing electric equipment. All activities connected with pipes like pickling, bending, cutting, forming and threading of pipes of various work area, all electrical equipment is assembled in the fabricated control compartment and driver’s control stands. Under frames are fabricated taking all due care to ensure designed weld strength. Care is taken to impart the requisite camber to the under frame during fabrication it self. Wherever required, welds are tested radio graphically. Welder training and their technical competence is periodically reviewed FIG NO 1( SUPER STRUCTURE OF ENGINE)
  • 10. BOGIE MANUFACTURING: Large special purpose machines are utilized for machining cast and fabricated bogie frames in the same work area, axel and wheel disc machining is undertaken on sophisticated CNC machines. Inner diameter of wheels discs are carefully matched with the outer diameter of. Axles before the wheel discs are pressed onto, at designated pressure, using a specially designed wheel press. The complete truck (bogie), including bogie frames, wheels and axles, brake rigging and traction motor is assemble d before being sent onwards for locomotive assembly. FIG NO 2 ( BOGIE)
  • 11. LOCOMOTIVE ASSEMBLY AND TESTING: Assembled and tested engines are received in this shop from Engine Division. Also , under frame , assembled truck , superstructures and contractor compartment are receive from respective manufacturing and assembly shops of Vehicle Division. Important alignments like crank shaft deflection, compressor alignment like crank shaft deflection, compressor alignment and Eddy Current clutch/radiator fan alignment are done during assembly stage if self. Electrical control equipments are fitted and control cable harnessing is undertaken. The complete locomotive is thus assembled before being sent onwards for final testing and spray painting. Rigorous testing of all locomotive system is conducted as per laid down test procedures before the locomotives is taken up for final painting and dispatch. The engine block, crankshaft, camshaft, cylinder liners, pistons, connecting rods, cylinder heads, exhaust manifold, turbo-supercharger and all related piping is assembled to make a complete engine. This is followed by mounting of electrical machines like traction alternator, auxiliary generator and exacter. This power pack is tested for horsepower output and other parameters of engine heath on computerized Engine test beds. Only after the engine parameters are found perfect the power pack is allowed to be moved to the locomotives assembly area. Important alignments like crank shaft deflection, compressor alignment and Eddy Current clutch/radiator fan alignment are done during assembly stage. Electrical control equipments are fitted and control cable harnessing is undertaken. The complete locomotive is thus assembled before being sent onwards for final testing and .all locomotive systems are rigorous tested as per laid down test procedures before the locomotive is taken up for final painting and dispatch.
  • 12. CLASSIFICATION 1. Standard “Gauge” designations and dimensions:-  W = Broad gauge (1.67 m)  Y = Medium gauge ( 1 m)  Z = Narrow gauge ( 0.762 m)  N = Narrow gauge ( 0.610 m) 2. “ Type of Traction” designations:-  D = Diesel-electric traction  C = DC traction  A = AC traction  CA=Dual power AC/DC traction 3. The “ type of load” or “Service” designations:-  M= Mixed service  P = Passenger  G= Goods  S = Shunting 4. “ Horse power ” designations from June 2002 (except WDP-1 & WDM-2 LOCOS)  ‘ 3 ’ For 3000 horsepower  ‘ 4 ’ For 4000 horsepower  ‘ 5 ’ For 5000 horsepower  ‘ A ’ For extra 100 horsepower  ‘B’ For extra 200 horsepower and so on . Hence ‘WDM-3A’ indicates a broad gauge loco with diesel-electric traction. It is for mixed services and has 3100 horsepower.
  • 13. OVERVIEW OF DIESEL LOCOMOTIVE FIG NO 3 ( OVERVIEW OF LOCOMOTIVE)  SAND BOX  RADIATOR  RADIATOR FAN  TURBO SUPERCHARGER  BOGIE(2 SETS)(3AXLE OR 2 AXLE)
  • 14.  FUEL TANK  AIR RESERVOIERS  POWER PACK  DYNAMO WITH ALTRNATOR  BATTERIES  DRIVER CABIN  WHEEL ASSEMBLY  DISC  BLOWER  TRACTON MOTER  TRUCK  GEAR AND PENION ASSSEMBLY  CYLINDER HEAD  CROSS HEAD  FUEL INJECTION PUMP  BATTERIES (8 OF 8.68 VOLTS)  FUEL TANK  AFTER COOLING CORE  JUNCTION BOX
  • 15. PRODUCTION SHOPS There are three production shops: 1. BLOCK DIVISION 2. ENGINE DIVISION 3. LOCO DIVISION BLOCK DIVISION There are two block division 1. HEAVY WELD SHOP 2. HEAVY MACHINE SHOP ENGINE DIVISION There are seven engine division 1. ENGINE ERECTION SHOP 2. ENGINE TESTING SHOP 3. LIGHT MACHINE SHOP 4. SUB ASSEMBLY SHOP 5. ROTOR SHOP 6. HEAT TREATMENT SHOP 7. TURBO SELECTION SHOP
  • 16. LOCO DIVISION There are eight loco division: 1. LOCO FRAME SHOP 2. PIPE SHOP 3. TRUCK MACHINE SHOP 4. TRACTION ASSEMBLY SHOP 5. SHEET MEATL SHOP 6. LOCO AASEMBLY SHOP 7. LOCO PAINT SHOP 8. LOCO TEST SHOP
  • 17. SUB ASSEMBLY SHOP This shop deals with following section:-- 1.Turbo machining section 2.Cylinder head & shot blast section 3.Fuel pump, Support, Cam shaft ate section 4.Cylinder head 5.Turbo 6.Governor, Water Pump, Fan drive, Lube oil Pump, After cooler assembly section. CYLINDER HEAD SECTION The lay out of this section is product type. There are different machines had do set up per sequence of operation of cylinder head. A milling machine provides profile cutting and taper profile according of the template. The tracer runs and cutter forms shaper radial drilling machine. This machine provides for drilling tapping. Core boring operation as per drawing
  • 18. HEARALD BOROING MACHINE This machine having four spindles for boring of guide hole, air & exhaust it dimensions are— 1.Valve inner sheet dia 4 hole- 3.1805-3.1815 2.Guide hole dia- 1.0625‖-1.0635‖ 3.Valve sheet depth (E1, E2, A1)- 0.740‖ to 0.745‖ & A2- 0.950‖ 4.Depth of sheet (A1 E1, E2)- 0.205‖-0.215‖ 5.Spring sheet depth (E1, E2, E1)- 1.865‖-1.885 CONTROL SHAFT ASSEMBLY It is a link between Governor & Fuel injector pumps by which the mechanical power from the governor transmitted to the fuel injection pump Racks. It means to control the amount of fuel according to the requirement of load & speed. EXPLOSION DOOR COVER ASSEMBLY . It is special type of main base door cover which when the crank case exhauster failed to work CAM SHAFT VIBRATION DAMPER ASSEMBLY When vibration developed on the cam shaft will be damped by this assembly.
  • 19. O.S.T. HOUSING ASSEMBLY This assembly controls the R.P.M. of crank shaft and keeps it a specified limit (1000 to 11500 r.p.m.). When OST is operated in the case 16 cylinder engine the engine RPM will come in ideal but in case of 16 cylinder engines will be stopped. FUEL PUMP SUPPORT ASSEMBLY It is a support of the fuel pump on which the fuel injection pump is mounted and the power of cam shaft is transmitted to operate fuel injection pump through the cross head lighter & to operate push rod by PRD. Lifter by which the inlet & exhaust valve open & closed through the valve lever & yokes. ACCELERATION CONTROL DEVICE By this device by monopoly of the driver is controlled the air & fuel supply is controlled by according to the fuel ratio. It is controlled the proper fuel and air ratio. FIG NO 4(Schematic diagram of ALCO Engine)
  • 20. ROTOR SHOP This shop is deals with the manufacturing of Turbocharger. Turbocharger is known as the Heart of Diesel Locomotive. Basically in this section manufacturing of assembly & sub assembly of Turbocharger is made. But the outer casing of Turbocharger is made up in Heavy Machine Shop. Turbocharger is use for the providing fresh air to the engine. Due to this the efficiency & power generated by engine is increased. For the running of Turbocharger we are not using any extra energy source like generator, motor etc. For starting of Turbocharger generally we use exhaust gasses. COMPONENTS OF TURBOCHARGER For assembly of Turbojet following parts are manufactures in rotor shop 1. Impeller 7. Thrust Washer 2. Inducer 8. Key 3. Nose piece 9. Oil Slinger 4. Stud Rotor 10. Turbine Disc 5. Nut 11. Turbo Shaft 6. Washer 12. Lock plate
  • 21. ASSEMBLY OF TURBOCHARGER The assembly of turbocharger is done by dividing whole turbocharger in three parts. These are as follows 1. Rotor 2. Compressor 3. Casing 1. ROTOR Rotor is the inlet part of turbocharger which is comprises with following parts. Turbo Disc, Rotor stud, Turbo shaft, thrust collar, Nose disc, Washer & Nut. Rotor is rotating at speed of 18000 rpm & working at high temperature due to that the rotor is made of steel. 2. COMPRESSOR Compressor is the combination of impeller & inducer. Impeller is made up of Al-alloy. Impeller & inducer is use for sucking of fresh air from environment . FIG NO (5) TURBOSUPER CHRAGER
  • 22. 3. CASING Casing is made of M.S. & also a special type of coating is done. Due to that coating it can easily resist the heat. For the proper working & life of Turbocharger balancing of impeller, inducer & turbine disc is done by help of Dynamics Balancing Machine. For the proper working & life of Turbocharger balancing of impeller, inducer & turbine disc is done by help of Dynamics Balancing Machine. TURBO SUPERCHARGER AND ITS WORKING PRINCIPLE The exhaust gas discharge from all the cylinders accumulate in the common exhaust manifold at the end of which, turbo- supercharger is fitted. The gas under pressure there after enters the turbo- supercharger through the torpedo shaped bell mouth connector and then passes through the fixed nozzle ring. Then it is directed on the turbine blades at increased pressure and at the most suitable angle to achieve rotary motion of the turbine at maximum efficiency. After rotating the turbine, the exhaust gas goes out to the atmosphere through the exhaust chimney. The turbine has a centrifugal blower mounted at the other end of the same shaft and the rotation of the turbine drives the blower at the same speed. The blower connected to the atmosphere through a set of oil bath filters, sucks air from atmosphere, and delivers at higher velocity. The air then passes through the diffuser inside the turbo- supercharger, where the velocity is diffused to increase the pressure of air before it is delivered from the turbo- supercharger
  • 23. Pressurising air increases its density, but due to compression heat develops. It causes expansion and reduces the density. This effects supply of high-density air to the engine. To take care of this, air is passed through a heat exchanger known as after cooler. The after cooler is a radiator, where cooling water of lower temperature is circulated through the tubes and around the tubes air passes. The heat in the air is thus transferred to the cooling water and air regains its lost density. From the after cooler air goes to a common inlet manifold connected to each cylinder head. In the suction stroke as soon as the inlet valve opens the booster air of higher pressure density rushes into the cylinder completing the process of super charging. The engine initially starts as naturally aspirated engine. With the increased quantity of fuel injection increases the exhaust gas pressure on the turbine. Thus the self-adjusting system maintains a proper air and fuel ratio under all speed and load conditions of the engine on its own. The maximum rotational speed of the turbine is 18000/22000 rpm for the Turbo supercharger and creates max. Of 1.8 kg/cm2 air pressure in air manifold of diesel engine, known as Booster Air Pressure (BAP). Low booster pressure causes black smoke due to incomplete combustion of fuel. High exhaust gas temperature due to after burning of fuel may result in considerable damage to the turbo supercharger and other component in the engine. FIG NO(6)TURBOSUPERCHRGER WORKING
  • 24. EXPRESSOR FIG NO (7) EXPRESSOR In Indian Railways, the trains normally work on vacuum brakes and the diesel locos on air brakes. As such provision has been made on every diesel loco for both vacuum and compressed air for operation of the system as a combination brake system for simultaneous application on locomotive and train. In ALCO locos the exhauster and the compressor are combined into one unit and it is known as EXPRESSOR. It creates 23" of vacuum in the train pipe and 140 PSI air pressure in the reservoir for operating the brake system and use in the control system etc.
  • 25. The expressor is located at the free end of the engine block and driven through the extension shaft attached to the engine crank shaft. The two are coupled together by fast coupling (Kopper's coupling). Naturally the expressor crank shaft has eight speeds like the engine crank shaft. There are two types of expressor are, 6CD,4UC & 6CD,3UC. In 6CD,4UC expressor there are six cylinder and four exhauster whereas 6CD,3UC contain six cylinder and three exhauster. WORKING OF EXHAUSTER Air from vacuum train pipe is drawn into the exhauster cylinders through the open inlet valves in the cylinder heads during its suction stroke. Each of the exhauster cylinders has one or two inlet valves and two discharge valves in the cylinder head. A study of the inlet and discharge valves as given in a separate diagram would indicate that individual components like (1) plate valve outer (2) plate valve inner (3) spring outer (4) spring inner etc. are all interchangeable parts. Only basic difference is that they are arranged in the reverse manner in the valve assemblies which may also have different size and shape. The retainer stud in both the assemblies must project upward to avoid hitting the piston. The pressure differential between the available pressure in the vacuum train pipe and inside the exhauster cylinder opens the inlet valve and air is drawn into the cylinder from train pipe during suction stroke. In the next stroke of the piston the air is compressed and forced out through the discharge valve while the inlet valve remains closed. The differential air pressure also automatically open or close the discharge valves, the same way as the inlet valves operate. This process of suction of air from the train pipe continues to create required amount of vacuum and discharge the same air to atmosphere. The VA-1 control valve helps in maintaining the vacuum to requisite level despite continued working of the exhauster.
  • 26. COMPRESSOR The compressor is a two stage compressor with one low pressure cylinder and one high pressure cylinder. During the first stage of compression it is done in the low pressure cylinder where suction is through a wire mesh filter. After compression in the LP cylinder air is delivered into the discharge manifold at a pressure of 30 / 35 PSI. Workings of the inlet and exhaust valves are similar to that of exhauster which automatically open or close under differential air pressure. For inter-cooling air is then passed through a radiator known as inter-cooler. This is an air to air cooler where compressed air passes through the element tubes and cool atmospheric air is blown on the out side fins by a fan fitted on the expressor crank shaft. . A safety valve known as inter cooler safety valve set at 60 PSI is provided after the inter cooler as a protection against high pressure developing in the after cooler due to defect of valves. After the first stage of compression and after-cooling the air is again compressed in a cylinder of smaller diameter to increase the pressure to 135-140 PSI in the same way. This is the second stage of compression in the HP cylinder. Air again needs cooling before it is finally sent to the air reservoir and this is done while the air passes through a set of coiled tubes after cooler.
  • 27. LOCMOTIVE /TRUCK MACHINE SHOP FIG NO (7)TRUCK MACHINE SHOP
  • 28. FABRICATION OF ENGINE BLOCK Steel plates of sizes up to 80 mm thick are ultrasonically tested before being precision cut by numerically controlled flame cutting machines. Fabrication of engine block is completed by submerged arc welding using semi-automatic welding machines. Down-hand welding is ensured using specially designed petitioners. Special fixtures are used for making down-hand welding possible in inaccessible areas. Critical welds are subjected to radiographic examination. All welders are periodically tested and re-qualified for the assigned job FIG NO (8) FABRICATION OF ENGINE BLOCK
  • 29. MACHINING OF ENGINE BLOCK The fabricated engine block is then taken up for a variety of machining operations like planning, enveloping and end drilling. All these operations use heavy duty planers and CNC drilling machines. V-boring of cylinder liner bores is a process requiring a high degree of precision and is undertaken using a specially designed machine. Recent addition of a Plano-milling centre has provided further fillip to the quality and speed of enveloping operation. 12 Cylinder and 16 Cylinder Blocks have V angle of 45°, whereas the 6 Cylinder Block is inline type. FIG NO (9) TESTING OF THE LOCOMOTIVE OR TRUCK
  • 30. COMPONENT MANUFACTURING Over 2000 components are manufactured in-house at DLW. These include ALCO turbo superchargers, lubricating oil pumps, cam shafts, cylinder heads, chrome plated cylinder liners, connecting rods and various gears. Our well-equipped Machine Shops have dedicated lines for operations like turning, milling, gear hobbing, drilling, grinding and planning etc. In addition, DLW is equipped with a variety of special purpose machines and a large number of state-of-the-art CNC machines to ensure quality and precision. All related processes like heat treatment and induction hardening are also carried out in-house. A completely new Chrome Plating Shop for Cylinder Liners has been set up with modern infrastructure like fume extraction system and Programmable Logic Controlled material movement system. FIG NO(10) COMPONENT MANUFACTURING
  • 31. ENGINE ASSEMBLY & TESTING The engine block, crankshaft, camshafts, cylinder liners, pistons, connecting rods, cylinder heads, exhaust manifold, turbo-supercharger and all related piping is assembled to make a complete engine. This is followed by mounting of electrical machines like traction alternator, auxiliary generator and exciter. This power pack is tested for horsepower output and other parameters of engine health on computerized Engine Test Beds. Only after the engine parameters are found perfect the power pack is allowed to be moved to the locomotive assembly area FIG NO(11)ASSEMBLED ENGINE
  • 32. VEHICLE DIVISION UNDERFRAMES & SUPERSTRUCTURES FIG NO (12) SUPERSTRUCTURE Precision cutting and forming of sheet metal is utilized for manufacture of superstructures including drivers cab, engine hoods, and compartments for housing electrical equipment. All activities connected with pipes like pickling, bending, cutting, forming and threading of pipes of various sizes are undertaken in another well-equipped work area. In yet another work area, all electrical equipment is assembled in the fabricated control compartments and driver’s control stands. Under frames are fabricated taking all due care to ensure designed weld strength. Care is taken to impart the requisite camber to the under frame during fabrication itself. Wherever required, welds are tested radio graphically. Welder training and their technical competence is periodically reviewed.
  • 33. BOGIE MANUFACTURING FIG NO (13) BOGIE MANUFACTURING Large special purpose machines are utilized for machining cast and fabricated bogie frames. In the same work area, axle and wheel disc machining is undertaken on sophisticated CNC machines. Inner diameter of wheel discs are carefully matched with the outer diameter of axles before the wheel discs are pressed onto axles, at designated pressure, using a specially designed wheel press. The complete truck (bogie), including bogie frames, wheels and axles, brake rigging and traction motors is assembled before being sent onwards for locomotive assembly.
  • 34. LOCOMOTIVE ASSEMBLY & TESTING FIG NO(14) ENGINE TESTING Assembled and tested engines are receive in this Shop from Engine Division. Also, under frames, assembled trucks, superstructures and contractor compartments are received from respective manufacturing and assembly shops of Vehicle Division. Important alignments like crank shaft deflection, compressor alignment and Eddy Current clutch/radiator fan alignment are done during assembly stage itself. Electrical control equipments are fitted and control cable harnessing is undertaken. The complete locomotive is thus assembled before being sent onwards for final testing and spray painting. Rigorous testing of all locomotive systems is conducted as per laid down test procedures before the locomotive is taken up for final painting and dispatch.
  • 35. MACHINE SHOP There are some important machines which used in the different type of shops. 1. LATHE MACHINE
  • 36. 2. SLOTTER MACHINE 3.PLANER MACHINE
  • 37. 4.CNC WHEEL SURFACE LATHE 5.CNC WHEEL TURRET LATHE
  • 38. 6.CNC BIG BORE LATHE WITH SPINDLE
  • 39. CONCLUSION I have completed my training from the DIESEL LOCOMOTIVE WORKSHOP , VARANSI . I have observed many shop in the workshop I mainly performed my training in the the LAS, SAS , ROTOR SHOP AND TMS SHOP. In the locomotive workshop ,all the SSE and JE and SUPERVISIORS of all te shops helped very much. Without hisor her supervision I was not able to perform the training in all the workshops. I am very grateful to him . We have learned too much in the workshop, DIFFERENT TYPE OF WORKSHOP TECHNOLOGY, TESTING OF THE PARTS OF THE LOCOMOTIVE AND THE PROPER FUNCTIONING of the different locomotive parts as a TURBOSUPERCHARGER, EXPRESSOR, POWER PACK OF THE LOCOMOTVE , RADIATOR SECTION ,OIL SUMP, DYNAMO AND BOGIE AND FABRICATION OF THE BODY OF LOCOMOTIVE .
  • 40. REFRENCES  Workshop technology by Hazara & Chaudhary  Production technology by P.C. SHARMA  Study material provided by TECHNICAL TRAINING CENTRE  Workshop technology by S. K. GARG  WWW.RAILWAY TECHNICAL.CO.IN  WWW.HOWSTUFFWORKS.IN  WWW.IRFCA.CO.IN