1. Introduction.
2. Manufacturing process of bricks.
3. Practical Training.
3Fahad 2714041
Elmaimani Red Brick
and
Clay products factories
• It was found in 1980 in Madina
Munawara.
• Considered as one of the biggest brick
manufacturing companies in the Kingdom
of Saudi Arabia.
• It produces nearly 2000 tons per day of red
clay brick in different types ,sizes and colors
• It is considered as the first company who
has introduced the Load Bearing
Construction System in the construction
field.
Some projects
from
Elmaimani factories
• Old Madina Mosque like Quba,
Qiblatain and Miqath .
• Group of Private Villas for Aramco
Staff in Industrial Yanbu City.
• Saraya Compound – Bahrain.
• Dorrat Al Aroos Resort – Jeddah.
• Residential District - Yanbu
4
5Fahad 2714041
MATERIAL
PREPARATION
WET
PREPARATION
EXTRUSION
SETTING
MACHINE
TUNNEL
DRYER
TUNNEL KILN
UNLOADING
MACHINE
PACKING
Sand Box
Feeder
Wet Pan
Mill
Coarse
Roller
Mill Fine
Roller
Mill
6Fahad 2714041
7Fahad 2714041
Locations / Customer
Grouping And Setting
8Fahad 2714041
9Fahad 2714041
The job I did is I worked as an operator for some of
their machines. The main section in the company I
worked in are:-
• Quality Control (Q.C) Department.
• Maintenance Department – Machinery & Shops.
• Maintenance Department – Mechanical Field.
• Technical Department – Inspection Group.
• Performance of wet pan mill scrapers and its
guide. condition of clay spreaders.
• Always refer to Lab. Sieve Test and
Moisture content results one hour after
operation had started and make
necessary adjustment if necessary.
• Before the start of each shifts operation
the operator is required to check the
following :-
• Condition of box feeder's slat conveyor
speed setting and sand silo setting.
While operating routinely and frequently
check the following-:
•Sizes, type and quantity of materials being fed by
loading shovel operators.
•Box feeder paddle shafts.
•Slat conveyor links and slat.
•Always use metal detector. Material spillages
piling-up of the tail end of the conveyors and
metal structures holding the conveyors must be
regularly removed.
10
Paddle bladesPaddle shaft
ScrapersWet Pan Mill
•Possible leakage in the vacuum
chamber will occur if any of the
following conditions exist.
1.Uncleaned tapered hubs or if the hubs
have a lot of dry and hard clay build up.
2.Insufficient feeding of material.
3.Leakages in pipes, barrels and doors.
•There are occasions that vacuum is low
or insufficient in this regard the
following measures have to be taken.
1.Check the temperature. This should
not go higher than 80°C.
2.Check vacuum filters.
3.Check the pump.
4.Check the suction pipe for leakage.
5.Check the suction pipe for leakage.
•Clearance or condition of wet pan mill
roller scrapers and conveyor scrapers.
•Condition of motor drive belts.
•Conduct determination of roller mill
clearance regularly and properly (Half
Hour before each shift ends). Hardened
material sticking to the surface of the
rollers must be removed before feeding the
copper wire.
11
Vacuum Chamber
•PROCEDURE IN CHANGING THE DIE MOULD
•Empty the slat conveyor and the conveyor after the die
mould.
•Loosen the bolts firmly holding the die mould. wait for a
few minutes for the pressure to drop.
•Switch-On the clutch for the extruder at manual to push
the die mould and the clay in the pressure head.
•Remove the clay that is in the pressure head up to the
point where the vacated space is good enough for the die
mould to be fitted.
•Fit-in the die mould, check for its levelness, and put back
all the bolts.
•Before re-starting up ensure that the bolts are firmly and
tightly fix.
•Refill the die mould with material by manually operating
the extruder, until the die mould is complete filled.
•Level the green conveyor, cutting table, black belts and
other conveying system.
•Start the operation in automatic mode.
•At running time, check the cutting length.
Perpendicularity, Pressure and Vacuum.
12
DEPARTMENTLABORATORY Q.C
SIEVE ANALYSIS TEST
DRY CLAY + SAND + WATER MIXING WET CLAY
PRODUCED
Measuring test ( sand test)
1.500 grams wet clay took in water in few minutes. After that
clay washing thru 200 MESH (+0.075 mm).
Now all clay going out from above mesh. Sand get from
mesh.
1.Above sand 45 minutes put in oven for dry. Dry after that
sample put in various size of mesh no. 09 , 16 ,18 ,20 ,100 ,200
for analysis.
2.Total grams ÷ dry weight ×100 = Equivalent % 38 – 40 % is
good for produced bricks.
3.M.C. Test to get % water, 100 Grams wet material put in
oxen 45 minutes after take and weight.
4.M.C Test
=
13
For example :
M.C Test =
= = 17.64 M.C %
14
Coro vane Pump
• Problem: There is a noise in the unloading Diesel
pump- and take long time to full Diesel tank which has
capacity 36000 liter/min.
Sol.
So, this time to fully the diesel tank.
How to make evaluation of the new
pump?
Bring 4 drums of empty oil of lubrication and
raining the pump to give liquid to the 4 drums
and calculate the time need to full 4 drums by
stop watch.
15
t = 60 sec = 1 min
We check the pipe line, then we find the problem in the
float valve it plugged.
16
And send the pump to maintenance department to replace it and solve the
noise, after one hour we find the problem noise in the vanes.
final steps change the vane according to the guidance manual.
Fahad 2714041 17
Thank you
If you have any question?

More Related Content

What's hot

Slurry Seal Mix Design
Slurry Seal Mix DesignSlurry Seal Mix Design
Cement ppt by alpana
Cement ppt by alpanaCement ppt by alpana
Cement ppt by alpana
Alpana Gupta
 
Slurry Seal Presentation for CalAPA LA Tech Meeting
Slurry Seal Presentation for CalAPA LA Tech MeetingSlurry Seal Presentation for CalAPA LA Tech Meeting
Slurry Seal Presentation for CalAPA LA Tech Meeting
California Asphalt Pavement Association
 
How to determine Initial and Final Setting Time of Cement?
How to determine Initial and Final Setting Time of Cement?How to determine Initial and Final Setting Time of Cement?
How to determine Initial and Final Setting Time of Cement?
Civil Insider
 
Softening point of bitumious
Softening point of bitumiousSoftening point of bitumious
Softening point of bitumious
Taha Samir
 
Viscosity test 3
Viscosity test 3Viscosity test 3
Viscosity test 3
allu9745552572
 
OCL INDIA LIMITED, RAJGANGPUR
OCL INDIA LIMITED, RAJGANGPUROCL INDIA LIMITED, RAJGANGPUR
OCL INDIA LIMITED, RAJGANGPUR
Sudhanshu Shekhar
 
Motar-Amit Payal
Motar-Amit PayalMotar-Amit Payal
Motar-Amit Payal
AMIT PAYAL
 
cement-plant-operation-handbook
cement-plant-operation-handbookcement-plant-operation-handbook
cement-plant-operation-handbook
Vijay Kumar
 
Setting time test
Setting time testSetting time test
Setting time test
Muhammad Saleem
 
Fineness test on cement
Fineness test on cementFineness test on cement
Fineness test on cement
HARISH B A
 
4 soundness of cement.
4 soundness of cement.4 soundness of cement.
4 soundness of cement.
University of Salahaddin-Erbil
 
Compression strength test
Compression strength testCompression strength test
Compression strength test
HARISH B A
 
Report on the manufacturing process step
Report on the manufacturing process stepReport on the manufacturing process step
Report on the manufacturing process step
Nur Natasya Umira
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
Tarun kumar
 
Viscosity test of bitumen
Viscosity test of bitumenViscosity test of bitumen
Viscosity test of bitumen
Amrit pandit
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
FeteneBefekadu
 
Penetration test
Penetration testPenetration test
Penetration test
Priyansh Singh
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
AMIT PAYAL
 
Penetration of bitumious
Penetration of bitumiousPenetration of bitumious
Penetration of bitumious
Taha Samir
 

What's hot (20)

Slurry Seal Mix Design
Slurry Seal Mix DesignSlurry Seal Mix Design
Slurry Seal Mix Design
 
Cement ppt by alpana
Cement ppt by alpanaCement ppt by alpana
Cement ppt by alpana
 
Slurry Seal Presentation for CalAPA LA Tech Meeting
Slurry Seal Presentation for CalAPA LA Tech MeetingSlurry Seal Presentation for CalAPA LA Tech Meeting
Slurry Seal Presentation for CalAPA LA Tech Meeting
 
How to determine Initial and Final Setting Time of Cement?
How to determine Initial and Final Setting Time of Cement?How to determine Initial and Final Setting Time of Cement?
How to determine Initial and Final Setting Time of Cement?
 
Softening point of bitumious
Softening point of bitumiousSoftening point of bitumious
Softening point of bitumious
 
Viscosity test 3
Viscosity test 3Viscosity test 3
Viscosity test 3
 
OCL INDIA LIMITED, RAJGANGPUR
OCL INDIA LIMITED, RAJGANGPUROCL INDIA LIMITED, RAJGANGPUR
OCL INDIA LIMITED, RAJGANGPUR
 
Motar-Amit Payal
Motar-Amit PayalMotar-Amit Payal
Motar-Amit Payal
 
cement-plant-operation-handbook
cement-plant-operation-handbookcement-plant-operation-handbook
cement-plant-operation-handbook
 
Setting time test
Setting time testSetting time test
Setting time test
 
Fineness test on cement
Fineness test on cementFineness test on cement
Fineness test on cement
 
4 soundness of cement.
4 soundness of cement.4 soundness of cement.
4 soundness of cement.
 
Compression strength test
Compression strength testCompression strength test
Compression strength test
 
Report on the manufacturing process step
Report on the manufacturing process stepReport on the manufacturing process step
Report on the manufacturing process step
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Viscosity test of bitumen
Viscosity test of bitumenViscosity test of bitumen
Viscosity test of bitumen
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
 
Penetration test
Penetration testPenetration test
Penetration test
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
 
Penetration of bitumious
Penetration of bitumiousPenetration of bitumious
Penetration of bitumious
 

Similar to Summer training 2008

Program Development of Cement Industry at Jamshoro, Sindh
Program Development of Cement Industry at Jamshoro, SindhProgram Development of Cement Industry at Jamshoro, Sindh
Program Development of Cement Industry at Jamshoro, Sindh
Rana Ahtisham
 
Casting process and moulding process file for trainning report complet trainn...
Casting process and moulding process file for trainning report complet trainn...Casting process and moulding process file for trainning report complet trainn...
Casting process and moulding process file for trainning report complet trainn...
chourasiya12345
 
Transportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfTransportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdf
RESHMAFEGADE
 
A presentation on industrial attachment at everest wire industries
A presentation on industrial attachment at everest wire industriesA presentation on industrial attachment at everest wire industries
A presentation on industrial attachment at everest wire industries
DinanathSharma4
 
Cement manufacturing process by shubham malviya
Cement manufacturing process by shubham malviyaCement manufacturing process by shubham malviya
Cement manufacturing process by shubham malviya
ShubhamMalviya25
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
Kundan Sanap
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
Safdar Ali
 
Permeable concrete pavement
Permeable concrete pavementPermeable concrete pavement
Permeable concrete pavement
pratik vanam
 
koyesha hydropower.pptx
koyesha hydropower.pptxkoyesha hydropower.pptx
koyesha hydropower.pptx
YonatanFikadu
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
Salman H. Sindhoo
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Mayur Rahangdale
 
Cement Industries
Cement IndustriesCement Industries
Cement Industries
SAFFI Ud Din Ahmad
 
M. LABBE : Stainless Steel Boilers Manufacturing
M. LABBE : Stainless Steel Boilers ManufacturingM. LABBE : Stainless Steel Boilers Manufacturing
M. LABBE : Stainless Steel Boilers Manufacturing
THOMASLABBE
 
GEA BTT qatar
GEA BTT qatarGEA BTT qatar
GEA BTT qatar
AADIL ISMAIL
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
David H Moloney
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
David H Moloney
 
Presentation on Highwall Mining
Presentation on Highwall MiningPresentation on Highwall Mining
Presentation on Highwall Mining
Jasmeet Singh Saluja
 
precast manholes
precast manholesprecast manholes
precast manholes
Engineer Imtiaz Rehman
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
David H Moloney
 
Aggregate testing .pptx
Aggregate testing .pptxAggregate testing .pptx
Aggregate testing .pptx
ZaidAhmed283925
 

Similar to Summer training 2008 (20)

Program Development of Cement Industry at Jamshoro, Sindh
Program Development of Cement Industry at Jamshoro, SindhProgram Development of Cement Industry at Jamshoro, Sindh
Program Development of Cement Industry at Jamshoro, Sindh
 
Casting process and moulding process file for trainning report complet trainn...
Casting process and moulding process file for trainning report complet trainn...Casting process and moulding process file for trainning report complet trainn...
Casting process and moulding process file for trainning report complet trainn...
 
Transportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfTransportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdf
 
A presentation on industrial attachment at everest wire industries
A presentation on industrial attachment at everest wire industriesA presentation on industrial attachment at everest wire industries
A presentation on industrial attachment at everest wire industries
 
Cement manufacturing process by shubham malviya
Cement manufacturing process by shubham malviyaCement manufacturing process by shubham malviya
Cement manufacturing process by shubham malviya
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Permeable concrete pavement
Permeable concrete pavementPermeable concrete pavement
Permeable concrete pavement
 
koyesha hydropower.pptx
koyesha hydropower.pptxkoyesha hydropower.pptx
koyesha hydropower.pptx
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
 
Cement Industries
Cement IndustriesCement Industries
Cement Industries
 
M. LABBE : Stainless Steel Boilers Manufacturing
M. LABBE : Stainless Steel Boilers ManufacturingM. LABBE : Stainless Steel Boilers Manufacturing
M. LABBE : Stainless Steel Boilers Manufacturing
 
GEA BTT qatar
GEA BTT qatarGEA BTT qatar
GEA BTT qatar
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 
Presentation on Highwall Mining
Presentation on Highwall MiningPresentation on Highwall Mining
Presentation on Highwall Mining
 
precast manholes
precast manholesprecast manholes
precast manholes
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Aggregate testing .pptx
Aggregate testing .pptxAggregate testing .pptx
Aggregate testing .pptx
 

Recently uploaded

A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 

Recently uploaded (20)

A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 

Summer training 2008

  • 1. Yanbu Industrial College Department of Mechanical Engineering Technology MET D E P A R T M E N T MECHANICAL ENGINEERING T ECHNOLOGY
  • 2. SUMMER TRAINING:MET 400 Prepared By Supervisor By Fahad AL- Harbi Dr. M. Shukri 2Fahad 2714041
  • 3. 1. Introduction. 2. Manufacturing process of bricks. 3. Practical Training. 3Fahad 2714041
  • 4. Elmaimani Red Brick and Clay products factories • It was found in 1980 in Madina Munawara. • Considered as one of the biggest brick manufacturing companies in the Kingdom of Saudi Arabia. • It produces nearly 2000 tons per day of red clay brick in different types ,sizes and colors • It is considered as the first company who has introduced the Load Bearing Construction System in the construction field. Some projects from Elmaimani factories • Old Madina Mosque like Quba, Qiblatain and Miqath . • Group of Private Villas for Aramco Staff in Industrial Yanbu City. • Saraya Compound – Bahrain. • Dorrat Al Aroos Resort – Jeddah. • Residential District - Yanbu 4
  • 8. Locations / Customer Grouping And Setting 8Fahad 2714041
  • 9. 9Fahad 2714041 The job I did is I worked as an operator for some of their machines. The main section in the company I worked in are:- • Quality Control (Q.C) Department. • Maintenance Department – Machinery & Shops. • Maintenance Department – Mechanical Field. • Technical Department – Inspection Group.
  • 10. • Performance of wet pan mill scrapers and its guide. condition of clay spreaders. • Always refer to Lab. Sieve Test and Moisture content results one hour after operation had started and make necessary adjustment if necessary. • Before the start of each shifts operation the operator is required to check the following :- • Condition of box feeder's slat conveyor speed setting and sand silo setting. While operating routinely and frequently check the following-: •Sizes, type and quantity of materials being fed by loading shovel operators. •Box feeder paddle shafts. •Slat conveyor links and slat. •Always use metal detector. Material spillages piling-up of the tail end of the conveyors and metal structures holding the conveyors must be regularly removed. 10 Paddle bladesPaddle shaft ScrapersWet Pan Mill
  • 11. •Possible leakage in the vacuum chamber will occur if any of the following conditions exist. 1.Uncleaned tapered hubs or if the hubs have a lot of dry and hard clay build up. 2.Insufficient feeding of material. 3.Leakages in pipes, barrels and doors. •There are occasions that vacuum is low or insufficient in this regard the following measures have to be taken. 1.Check the temperature. This should not go higher than 80°C. 2.Check vacuum filters. 3.Check the pump. 4.Check the suction pipe for leakage. 5.Check the suction pipe for leakage. •Clearance or condition of wet pan mill roller scrapers and conveyor scrapers. •Condition of motor drive belts. •Conduct determination of roller mill clearance regularly and properly (Half Hour before each shift ends). Hardened material sticking to the surface of the rollers must be removed before feeding the copper wire. 11 Vacuum Chamber
  • 12. •PROCEDURE IN CHANGING THE DIE MOULD •Empty the slat conveyor and the conveyor after the die mould. •Loosen the bolts firmly holding the die mould. wait for a few minutes for the pressure to drop. •Switch-On the clutch for the extruder at manual to push the die mould and the clay in the pressure head. •Remove the clay that is in the pressure head up to the point where the vacated space is good enough for the die mould to be fitted. •Fit-in the die mould, check for its levelness, and put back all the bolts. •Before re-starting up ensure that the bolts are firmly and tightly fix. •Refill the die mould with material by manually operating the extruder, until the die mould is complete filled. •Level the green conveyor, cutting table, black belts and other conveying system. •Start the operation in automatic mode. •At running time, check the cutting length. Perpendicularity, Pressure and Vacuum. 12
  • 13. DEPARTMENTLABORATORY Q.C SIEVE ANALYSIS TEST DRY CLAY + SAND + WATER MIXING WET CLAY PRODUCED Measuring test ( sand test) 1.500 grams wet clay took in water in few minutes. After that clay washing thru 200 MESH (+0.075 mm). Now all clay going out from above mesh. Sand get from mesh. 1.Above sand 45 minutes put in oven for dry. Dry after that sample put in various size of mesh no. 09 , 16 ,18 ,20 ,100 ,200 for analysis. 2.Total grams ÷ dry weight ×100 = Equivalent % 38 – 40 % is good for produced bricks. 3.M.C. Test to get % water, 100 Grams wet material put in oxen 45 minutes after take and weight. 4.M.C Test = 13 For example : M.C Test = = = 17.64 M.C %
  • 14. 14 Coro vane Pump • Problem: There is a noise in the unloading Diesel pump- and take long time to full Diesel tank which has capacity 36000 liter/min. Sol. So, this time to fully the diesel tank. How to make evaluation of the new pump? Bring 4 drums of empty oil of lubrication and raining the pump to give liquid to the 4 drums and calculate the time need to full 4 drums by stop watch.
  • 15. 15 t = 60 sec = 1 min We check the pipe line, then we find the problem in the float valve it plugged.
  • 16. 16 And send the pump to maintenance department to replace it and solve the noise, after one hour we find the problem noise in the vanes. final steps change the vane according to the guidance manual.