SlideShare a Scribd company logo
Khairpur Mir`s
Assignment of Power Distribution & Utilizations System
SubmittedTo: Sir Irfan Ahmed
SubmittedBy: Zulfiqar Mangrio (K-13EL-79)
Topic:Substation equipment’s and its Function
Department: Electrical Engineering
Date: 28-Jan-2016
K-13EL-37 Page 2
Substation equipment’s and its Function
Distribution System
The major function of distribution system is to provide power to individual consumer
requirement. Supply of electric power to different consumers is done at low voltage level.
Any Distribution of electric power is done by distribution networks. Distribution
Substations distribute the power. As many equipment`s are used in substation which can
lower the voltage level Control the whole system. Which are given below;
Substation equipment’s
1. Power Transformer
2. Circuit Breaker
3. Disconnecting Switches & Isolator
4. Bus Bar
5. Current Transformer
6. Potential Transformer
7. Current Limiting Reactor
8. Shunt Reactor
9. Series Capacitor
10. Capacitor Voltage Transformer (CVT)
11. Coupling Capacitor Voltage Transformer (CCVT)
12. Shunt Capacitor
13. Grounding System
14. Lightning Arrester
15. Line Trap
16. Protective Relays
17. Station Batteries
1. Power Transformer
A transformer is an electric static machine used to change the voltage and current
without changing the frequency and power. The power transformer is different
K-13EL-37 Page 3
from the distribution transformer because due to its high rating or it depends on the
ratings. In case of a 220 KV or above KV level auto transformers are used.
As in casethe of lower KV line such as less than 132KV line double
winding transformers are used
2. Circuit Breaker
The circuit breakers are used to control (Break) the circuit if any fault occurs in any
of the Substation system. These circuit breaker breaks for a fault which can damage other
equipment in the station. For any fault over the substation station we need to break the
circuit it means that line current. This is done by automatically Circuit breaker by the
help of relay.
Some of the type of Circuit Breaker
 Oil circuit breaker.
 Air circuit breaker.
 SF6 circuit breaker.
 Vacuum circuit breaker
K-13EL-37 Page 4
3. Disconnecting Switches & Isolator
Isolator is a mechanical switch which can separate the part from circuit in the system
when it is required. Electrical isolators separate a part of the system from rest for safe
maintenance works. This isolator is to protect the transformer and the other equipment in
the system. The isolator isolates or cut the circuit from the high voltage to the ground. It
is protecting device.
4. Bus Bar
A bus bars in electrical power distribution are the conductors which are made up of thick
strips of copper or aluminum that conduct electricitywithin a switchboard, distribution
board, substation, or other electrical apparatus. The bus is a line in which the incoming
feeders come into and get into the instruments for further step up or step down. There
may be double line in the bus so that if any fault occurs in the one the other can still have
the current and the supply will not stop.
K-13EL-37 Page 5
5. Current Transformer
A current transformer is defined as an instrument transformer in which the secondary
current is substantially proportional to the primary current.Current transformers are used when
the magnitude of AC currents exceeds the safe value of current of measuring instruments.
Current transformers are basically used to take the readings of the currents entering the
substation. This transformer steps down the current from 800 amps to 1 amp. This is done
because we have no instrument for measuring of such a large current. The main use of this
transformer is
a. Distance Protection
b. Backup Protection
c. Measurement
6. Potential transformer
The potential transformer usages a bus isolator care for itself. The main use of this
transformer is to measure the voltage through the bus. This is done so as to get the
detail information of the voltage passing through the bus to the apparatus. There are
two main parts in it
a. Measurement
b. Protection
K-13EL-37 Page 6
7. Current Limiting Reactor
The Current limiting reactor is an electrical inductance made up of a number of turns of
wire of low ohmic resistance and inserted in series with a line to limit the current that can
flow under short circuit.
8. Shunt Reactor
Shunt reactor is the absorption of reactive power in the case of Ferranti effect, and thus
assembling the energy efficiency of the system. It is the most compact device normally
used to compensate for reactive power transmission lines in high-voltage long and cable
systems. Shunt reactor can be connected directly to the power line or to higher power
transformer. It is used to improve and adjust the reactive power consumed reactor can
also be a variable rating.
K-13EL-37 Page 7
9. Series Capacitor
• Increase power
• Transmission capability
• Improve system stability
• Reduce system losses
• Improve voltage profile
• Optimize power flow between
Parallel lines
10. Shunt Capacitor
A capacitor bank is very essential equipment of an electrical power system. The energy
required to run all the electrical devices are useful load power is the active power. It is
expressed in active power KW or MW. The maximum load connected to the electric
power system is essentially inductive in nature such as electric transformers, induction
motors, synchronous motor, electric ovens, and fluorescent lighting are all inductive in
nature. The current causes the capacitor to lead the effort; the capacitive reactance can be
used to cancel the inductive reactance of the system.
K-13EL-37 Page 8
11. Capacitor Voltage Transformer
A capacitor voltage transformer (CVT) is a transformer used in power systems to
stepping down high-voltage signals and providing additional low voltage signals either to
measure or for the operation of the protective relay. In its simplest form, the device
consists of three parts: two capacitors across the divided voltage signal, which is used to
adjust the inductive device on the pace of supply and transformers, used to isolate and
further stepped down the voltage of the devices or relay protective element. The voltage
level of this transformer is measure voltage 200KV same as potential transformer.
12. Capacitance Coupled Voltage Transformer (CCVT)
A capacitance Coupled voltage transformer (CCVT) is a same like CVT , which is used
in power systems to step-down extra high voltage signals and provide low voltage signals
either for measurement or to operate a protective relay. Mostly it is use EXTRA high
voltage 500kv to sample the voltage for measurement purpose.
K-13EL-37 Page 9
13. Grounding System
To provide an earth mat for connecting neutral points, equipment body, support structures
to the ground. For the safety of staff and to enable ground fault protection to provide a
path to empty the land of neutral currents, errors, surge arresters, overhead shielding wire
etc. with a safe step and touch potential possibilities.
14. Lightning Arrester
Lightening arrestors are the instrument that are used in the incoming feeders so that to
prevent the high voltage entering the main station. This high voltage is very unsafe from
the equipment`s used in the substation. Even equipment are very expensive, so as to
prevent any damage using lightning arresters. The lightning arresters do not let the
lightning to fall on the substation. In the case of some lightning and lightning arresters
K-13EL-37 Page 10
drag and ground it to the ground.
15. Line Trap
A line trap also called wave trap free parallel resonant circuit, connected series with high
voltage transmission power lines to provide high frequency (40 kHz to 1000 kHz) carrier
signals of power line communication purpose.
16. Protective Relays
Protectionrelays used to detect defective or device lines and to isolate the defective
equipment. Relays are also used to detect abnormal operating conditions or undesirable
from those caused by damaged equipment and either a warning or isolate the equipment.
Protectionrelays are used in electrical system protection by causing defective device or
lines to be separate or disconnect the equipment and to maintain continuity of service to
the rest of the system.
K-13EL-37 Page 11
18. Station Batteries
Batteries are supply the direct current to the relays for control purpose, as
well as store the energy so use for the when there is no power in the substation it
means that all the system is open or any fault condition. These are connected in
series to increase the voltage level.
Another Apparatus
 Protection system
To provide alarm or automatic tripping of faulty part from healthy part and also to
minimize damage to faulty equipment and associated system
 Control cable
It provide supply to various auxiliary equipment’s and machines.
 Auxiliary standby power system
For supplying starting power, standby power for auxiliaries.
 Firefighting system
K-13EL-37 Page 12
To sense the occurrence of fire by sensors and to initiate water spray, to disconnect power
supply to affected region to pin point location of fire by indication in control room.
How to Determine the Primary current and secondary current in
transformer? As the input voltage is 11kv, output phase voltage is 220v
and rated as;
1. TransformerRated At 50 KVA
(a) Primary Current:
As we know that Power transformer’s Primary winding connected in Delta Connection,
So,
IL =√3 x Ip
VL = Vp
Now,
Apparent power is;
S = V.I => I = S/V
IPrimary =
5000
11000
IPrimary =4.545 A
(b) Secondary Current:
K-13EL-37 Page 13
The Secondaryof the Power transformer winding are connected in Delta or
Wye.
So,
IL = IP
VL =√3 x Vp
As Output Voltages are 220 V
S = V.I => I = S/V
ISec =
5000
220
ISec = 227.27 A
2. Transformerrated At 100KVA
(a) .Primary Current:
As we know that Power transformer’s Primary winding connected in Delta Connection,
So,
By Using Apparent power Formula, we get;
S = V.I => I = S/V
IPrimary =
100 ,000
11000
IPrimary =9.090 A
(b) Secondary Current:
So,
Using apparent power formula, we get;
IL = IP
VL =√3 x Vp
As Output Voltages are 220 V
K-13EL-37 Page 14
S = V.I => I = S/V
ISec =
100,000
220
ISec = 454.54 A
3. TransformerRated At 200 KVA
(a) Primary Current:
As we know that Power transformer’s Primary winding connected in Delta Connection,
So,
By Using Apparent power Formula, we get;
S = V.I => I = S/V
IPrimary =
200 ,000
11000
IPrimary = 18.181 A
(b) Secondary Current:
So,
Using apparent power formula, we get;
IL = IP
VL =√3 x Vp
As Output Voltages are 220 V
S = V.I=> I = S/V
ISec =
200,000
220
ISec = 909.09 A
K-13EL-37 Page 15
4. TransformerRated At 400 KVA
(a) Primary Current:
As we know that Power transformer’s Primary winding connected in Delta Connection,
So,
By Using Apparent power Formula, we get;
S = V.I => I = S/V
IPrimary =
400 ,000
11000
IPrimary = 36.36 A
(b) Secondary Current:
So,
Using apparent power formula, we get;
IL = IP
VL =√3 x Vp
As Output Voltages are 220 V
S = V.I => I = S/V
ISec =
400,000
220
ISec =1818.18 A
5. TransformerRated At 630 KVA
(a) Primary Current:
K-13EL-37 Page 16
As we know that Power transformer’s Primary winding connected in Delta Connection,
So,
By Using Apparent power Formula, we get;
S = V.I => I = S/V
IPrimary =
630 ,000
11000
IPrimary = 57.27 A
(b) Secondary Current:
So,
Using apparent power formula, we get;
IL = IP
VL =√3 x Vp
As Output Voltages are 220 V
S = V.I=> I = S/V
ISec =
630,000
220
ISec = 2863.63 A
Bus Scheme`s Used in Pakistan
K-13EL-37 Page 17
I) breaker and Half scheme:
II) Siemens GIS substation with Main & Transfer bus scheme
(2 BB)
K-13EL-37 Page 18

More Related Content

What's hot

Current Transformer
Current TransformerCurrent Transformer
Current Transformer
MAYURSINH RATHOOD
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Md Irshad Ahmad
 
Design of substation
Design of substationDesign of substation
Design of substation
SayanSarkar55
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
Ravi Phadtare
 
Symmetrical and un-symmetrical fault
Symmetrical and un-symmetrical faultSymmetrical and un-symmetrical fault
Symmetrical and un-symmetrical fault
siddiqui arshad hussain
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
ManishKushwaha97
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
HamzaAbbas43
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
raiamitesh8
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
Raviraj solanki
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
Shubham Patel
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
k,l polytechnic roorkee
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
Jamil Abdullah
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substation
Ashutosh Srivastava
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
ROOPAL PANCHOLI
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
sneh pratap singh
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
sapna186
 
substation internship report
substation internship report substation internship report
substation internship report
Arun Thapa
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
Hemendra Kumar Rajput
 
33kv substation
33kv substation33kv substation
33kv substation
Abhishek Dawachya
 

What's hot (20)

Current Transformer
Current TransformerCurrent Transformer
Current Transformer
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Design of substation
Design of substationDesign of substation
Design of substation
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 
Symmetrical and un-symmetrical fault
Symmetrical and un-symmetrical faultSymmetrical and un-symmetrical fault
Symmetrical and un-symmetrical fault
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substation
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
 
substation internship report
substation internship report substation internship report
substation internship report
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
33kv substation
33kv substation33kv substation
33kv substation
 

Similar to Substation equipment and its function 2

132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
Abhishek Dosaya
 
Powergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial trainingPowergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial training
Akriti Gupta
 
powergrid presentation
powergrid presentationpowergrid presentation
powergrid presentationAkriti Gupta
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
fallinhay
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
jang041
 
Substation
SubstationSubstation
Substation
AbassKhan
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
Ashwani Kumar
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
SNEHAKANWAR1
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
VSRAGHU
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
Satya Prakash Chaurasia
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
Shuvam Pathania
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationEkram Bin Mamun
 
Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviya
Anuj Bansal
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
sohaib268827
 
Substations
SubstationsSubstations
Substations
itfakash
 
SUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptxSUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptx
HimanshuShrivastava74
 
Substation
SubstationSubstation
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
Swatantra SwAt
 
Substations
Substations Substations
Substations
Engr Muhammad Imran
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
Mohitkalal4
 

Similar to Substation equipment and its function 2 (20)

132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
Powergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial trainingPowergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial training
 
powergrid presentation
powergrid presentationpowergrid presentation
powergrid presentation
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
Substation
SubstationSubstation
Substation
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-Station
 
Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviya
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
Substations
SubstationsSubstations
Substations
 
SUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptxSUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptx
 
Substation
SubstationSubstation
Substation
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
Substations
Substations Substations
Substations
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 

More from Zulfiqar Mangrio

Surface Geology and Subsurface Geology
Surface Geology and Subsurface GeologySurface Geology and Subsurface Geology
Surface Geology and Subsurface Geology
Zulfiqar Mangrio
 
Seven c's of communication
Seven c's of communicationSeven c's of communication
Seven c's of communication
Zulfiqar Mangrio
 
Slide Wire Dc potentiometer
Slide Wire Dc potentiometerSlide Wire Dc potentiometer
Slide Wire Dc potentiometer
Zulfiqar Mangrio
 
Transmission lines
Transmission linesTransmission lines
Transmission lines
Zulfiqar Mangrio
 
Smart Gird
Smart GirdSmart Gird
Smart Gird
Zulfiqar Mangrio
 
Dc machine practical
Dc machine practical Dc machine practical
Dc machine practical
Zulfiqar Mangrio
 

More from Zulfiqar Mangrio (7)

Surface Geology and Subsurface Geology
Surface Geology and Subsurface GeologySurface Geology and Subsurface Geology
Surface Geology and Subsurface Geology
 
Seven c's of communication
Seven c's of communicationSeven c's of communication
Seven c's of communication
 
Slide Wire Dc potentiometer
Slide Wire Dc potentiometerSlide Wire Dc potentiometer
Slide Wire Dc potentiometer
 
Transmission lines
Transmission linesTransmission lines
Transmission lines
 
Smart Gird
Smart GirdSmart Gird
Smart Gird
 
Synchronous motor
Synchronous motorSynchronous motor
Synchronous motor
 
Dc machine practical
Dc machine practical Dc machine practical
Dc machine practical
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 

Substation equipment and its function 2

  • 1. Khairpur Mir`s Assignment of Power Distribution & Utilizations System SubmittedTo: Sir Irfan Ahmed SubmittedBy: Zulfiqar Mangrio (K-13EL-79) Topic:Substation equipment’s and its Function Department: Electrical Engineering Date: 28-Jan-2016
  • 2. K-13EL-37 Page 2 Substation equipment’s and its Function Distribution System The major function of distribution system is to provide power to individual consumer requirement. Supply of electric power to different consumers is done at low voltage level. Any Distribution of electric power is done by distribution networks. Distribution Substations distribute the power. As many equipment`s are used in substation which can lower the voltage level Control the whole system. Which are given below; Substation equipment’s 1. Power Transformer 2. Circuit Breaker 3. Disconnecting Switches & Isolator 4. Bus Bar 5. Current Transformer 6. Potential Transformer 7. Current Limiting Reactor 8. Shunt Reactor 9. Series Capacitor 10. Capacitor Voltage Transformer (CVT) 11. Coupling Capacitor Voltage Transformer (CCVT) 12. Shunt Capacitor 13. Grounding System 14. Lightning Arrester 15. Line Trap 16. Protective Relays 17. Station Batteries 1. Power Transformer A transformer is an electric static machine used to change the voltage and current without changing the frequency and power. The power transformer is different
  • 3. K-13EL-37 Page 3 from the distribution transformer because due to its high rating or it depends on the ratings. In case of a 220 KV or above KV level auto transformers are used. As in casethe of lower KV line such as less than 132KV line double winding transformers are used 2. Circuit Breaker The circuit breakers are used to control (Break) the circuit if any fault occurs in any of the Substation system. These circuit breaker breaks for a fault which can damage other equipment in the station. For any fault over the substation station we need to break the circuit it means that line current. This is done by automatically Circuit breaker by the help of relay. Some of the type of Circuit Breaker  Oil circuit breaker.  Air circuit breaker.  SF6 circuit breaker.  Vacuum circuit breaker
  • 4. K-13EL-37 Page 4 3. Disconnecting Switches & Isolator Isolator is a mechanical switch which can separate the part from circuit in the system when it is required. Electrical isolators separate a part of the system from rest for safe maintenance works. This isolator is to protect the transformer and the other equipment in the system. The isolator isolates or cut the circuit from the high voltage to the ground. It is protecting device. 4. Bus Bar A bus bars in electrical power distribution are the conductors which are made up of thick strips of copper or aluminum that conduct electricitywithin a switchboard, distribution board, substation, or other electrical apparatus. The bus is a line in which the incoming feeders come into and get into the instruments for further step up or step down. There may be double line in the bus so that if any fault occurs in the one the other can still have the current and the supply will not stop.
  • 5. K-13EL-37 Page 5 5. Current Transformer A current transformer is defined as an instrument transformer in which the secondary current is substantially proportional to the primary current.Current transformers are used when the magnitude of AC currents exceeds the safe value of current of measuring instruments. Current transformers are basically used to take the readings of the currents entering the substation. This transformer steps down the current from 800 amps to 1 amp. This is done because we have no instrument for measuring of such a large current. The main use of this transformer is a. Distance Protection b. Backup Protection c. Measurement 6. Potential transformer The potential transformer usages a bus isolator care for itself. The main use of this transformer is to measure the voltage through the bus. This is done so as to get the detail information of the voltage passing through the bus to the apparatus. There are two main parts in it a. Measurement b. Protection
  • 6. K-13EL-37 Page 6 7. Current Limiting Reactor The Current limiting reactor is an electrical inductance made up of a number of turns of wire of low ohmic resistance and inserted in series with a line to limit the current that can flow under short circuit. 8. Shunt Reactor Shunt reactor is the absorption of reactive power in the case of Ferranti effect, and thus assembling the energy efficiency of the system. It is the most compact device normally used to compensate for reactive power transmission lines in high-voltage long and cable systems. Shunt reactor can be connected directly to the power line or to higher power transformer. It is used to improve and adjust the reactive power consumed reactor can also be a variable rating.
  • 7. K-13EL-37 Page 7 9. Series Capacitor • Increase power • Transmission capability • Improve system stability • Reduce system losses • Improve voltage profile • Optimize power flow between Parallel lines 10. Shunt Capacitor A capacitor bank is very essential equipment of an electrical power system. The energy required to run all the electrical devices are useful load power is the active power. It is expressed in active power KW or MW. The maximum load connected to the electric power system is essentially inductive in nature such as electric transformers, induction motors, synchronous motor, electric ovens, and fluorescent lighting are all inductive in nature. The current causes the capacitor to lead the effort; the capacitive reactance can be used to cancel the inductive reactance of the system.
  • 8. K-13EL-37 Page 8 11. Capacitor Voltage Transformer A capacitor voltage transformer (CVT) is a transformer used in power systems to stepping down high-voltage signals and providing additional low voltage signals either to measure or for the operation of the protective relay. In its simplest form, the device consists of three parts: two capacitors across the divided voltage signal, which is used to adjust the inductive device on the pace of supply and transformers, used to isolate and further stepped down the voltage of the devices or relay protective element. The voltage level of this transformer is measure voltage 200KV same as potential transformer. 12. Capacitance Coupled Voltage Transformer (CCVT) A capacitance Coupled voltage transformer (CCVT) is a same like CVT , which is used in power systems to step-down extra high voltage signals and provide low voltage signals either for measurement or to operate a protective relay. Mostly it is use EXTRA high voltage 500kv to sample the voltage for measurement purpose.
  • 9. K-13EL-37 Page 9 13. Grounding System To provide an earth mat for connecting neutral points, equipment body, support structures to the ground. For the safety of staff and to enable ground fault protection to provide a path to empty the land of neutral currents, errors, surge arresters, overhead shielding wire etc. with a safe step and touch potential possibilities. 14. Lightning Arrester Lightening arrestors are the instrument that are used in the incoming feeders so that to prevent the high voltage entering the main station. This high voltage is very unsafe from the equipment`s used in the substation. Even equipment are very expensive, so as to prevent any damage using lightning arresters. The lightning arresters do not let the lightning to fall on the substation. In the case of some lightning and lightning arresters
  • 10. K-13EL-37 Page 10 drag and ground it to the ground. 15. Line Trap A line trap also called wave trap free parallel resonant circuit, connected series with high voltage transmission power lines to provide high frequency (40 kHz to 1000 kHz) carrier signals of power line communication purpose. 16. Protective Relays Protectionrelays used to detect defective or device lines and to isolate the defective equipment. Relays are also used to detect abnormal operating conditions or undesirable from those caused by damaged equipment and either a warning or isolate the equipment. Protectionrelays are used in electrical system protection by causing defective device or lines to be separate or disconnect the equipment and to maintain continuity of service to the rest of the system.
  • 11. K-13EL-37 Page 11 18. Station Batteries Batteries are supply the direct current to the relays for control purpose, as well as store the energy so use for the when there is no power in the substation it means that all the system is open or any fault condition. These are connected in series to increase the voltage level. Another Apparatus  Protection system To provide alarm or automatic tripping of faulty part from healthy part and also to minimize damage to faulty equipment and associated system  Control cable It provide supply to various auxiliary equipment’s and machines.  Auxiliary standby power system For supplying starting power, standby power for auxiliaries.  Firefighting system
  • 12. K-13EL-37 Page 12 To sense the occurrence of fire by sensors and to initiate water spray, to disconnect power supply to affected region to pin point location of fire by indication in control room. How to Determine the Primary current and secondary current in transformer? As the input voltage is 11kv, output phase voltage is 220v and rated as; 1. TransformerRated At 50 KVA (a) Primary Current: As we know that Power transformer’s Primary winding connected in Delta Connection, So, IL =√3 x Ip VL = Vp Now, Apparent power is; S = V.I => I = S/V IPrimary = 5000 11000 IPrimary =4.545 A (b) Secondary Current:
  • 13. K-13EL-37 Page 13 The Secondaryof the Power transformer winding are connected in Delta or Wye. So, IL = IP VL =√3 x Vp As Output Voltages are 220 V S = V.I => I = S/V ISec = 5000 220 ISec = 227.27 A 2. Transformerrated At 100KVA (a) .Primary Current: As we know that Power transformer’s Primary winding connected in Delta Connection, So, By Using Apparent power Formula, we get; S = V.I => I = S/V IPrimary = 100 ,000 11000 IPrimary =9.090 A (b) Secondary Current: So, Using apparent power formula, we get; IL = IP VL =√3 x Vp As Output Voltages are 220 V
  • 14. K-13EL-37 Page 14 S = V.I => I = S/V ISec = 100,000 220 ISec = 454.54 A 3. TransformerRated At 200 KVA (a) Primary Current: As we know that Power transformer’s Primary winding connected in Delta Connection, So, By Using Apparent power Formula, we get; S = V.I => I = S/V IPrimary = 200 ,000 11000 IPrimary = 18.181 A (b) Secondary Current: So, Using apparent power formula, we get; IL = IP VL =√3 x Vp As Output Voltages are 220 V S = V.I=> I = S/V ISec = 200,000 220 ISec = 909.09 A
  • 15. K-13EL-37 Page 15 4. TransformerRated At 400 KVA (a) Primary Current: As we know that Power transformer’s Primary winding connected in Delta Connection, So, By Using Apparent power Formula, we get; S = V.I => I = S/V IPrimary = 400 ,000 11000 IPrimary = 36.36 A (b) Secondary Current: So, Using apparent power formula, we get; IL = IP VL =√3 x Vp As Output Voltages are 220 V S = V.I => I = S/V ISec = 400,000 220 ISec =1818.18 A 5. TransformerRated At 630 KVA (a) Primary Current:
  • 16. K-13EL-37 Page 16 As we know that Power transformer’s Primary winding connected in Delta Connection, So, By Using Apparent power Formula, we get; S = V.I => I = S/V IPrimary = 630 ,000 11000 IPrimary = 57.27 A (b) Secondary Current: So, Using apparent power formula, we get; IL = IP VL =√3 x Vp As Output Voltages are 220 V S = V.I=> I = S/V ISec = 630,000 220 ISec = 2863.63 A Bus Scheme`s Used in Pakistan
  • 17. K-13EL-37 Page 17 I) breaker and Half scheme: II) Siemens GIS substation with Main & Transfer bus scheme (2 BB)