SlideShare a Scribd company logo
19th IABSE Congress Stockholm, 21-23 September 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
1
Strengthening and Reconstruction of the Hugo Treffner Gymnasium
building in Tartu, Estonia
Kari Avellan, Erika Belopotocanova
KAREG Consulting Engineers, Helsinki, Finland
Contact: kari.avellan@kareg.com
Abstract
Strengthening and reconstruction of Hugo Treffner Gymnasium building was carried out from
1994 to 1997 in four stages. The mandate of KAREG Consulting Engineers entailed designs of
temporary and permanent structures as well as development of a monitoring system and
examining the condition of the structure. The foundations on the yard side walls were placed two
meter higher than the remaining of foundations of the structure. As a consequence, the above
mentioned findings led to forming cracks and brought about the walls of the building to incline.
The project involved corner walls and interior walls stabilization, exterior walls strengthening and
a new basement area construction. A new reinforced slab was poured, designed using the yield
line theory analysis. The use of the selected strengthening options and technique for structural
intervention of the walls was found to be a suitable technique to achieve the desired objective.
Keywords: strengthening; structural intervention; stabilisation; foundations; piles; cracks;
settlement; walls; concrete slab.
1 Introduction
Hugo Treffner Gymnasium (HTG) is a secondary
school located in Tartu, Estonia with special
emphasis on science education. Founded by a
renowned scholar Hugo Treffner, it was the only
large secondary school in 19th century in Estonia
with dominantly Estonian students and no age
restrictions. During the Estonian national awakening
(1850 – 1918) the school greatly contributed to the
number of Estonian intellectuals. In November 2011
HTG became the partner school of UNESCO.
Today, HTG is a modern and comfortable
educational institution and a leading co-educational
public school for students of age 16 to 19 (Figure 1).
Figure 1. Hugo Treffner Gymnasium today.
1.1 Hugo Treffner Gymnasium building
The building has served as a school for centuries.
Founded in 1883, HTG boasts a combination of a
19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
2
historic building and modern facilities in the heart
of Tartu.
In the course of extensive restoration work the
gymnasium has retained its historic aura (Figure
2). The majority of original details have been
successfully preserved, e.g. wooden ceiling beams
in the common room, or ceiling paintings in the
classroom on the street level 1.
Figure 2. HTG. Basement library and study.
Nowadays HTG building consists of four parts built
at different times. The building on Munga 12 is the
oldest part of the HTG building ensemble. It was
used as a schoolhouse since 1804, and it is
certainly one of the most eye-catching buildings in
the historical Jaani quarter of Tartu (Figure 3).
Figure 3. HTG building and Jaani Church.
The house by Rüütli Street was specifically
renovated for the school in 1830 by architect
G.F.W. Geist. An interesting fact is that this part of
the building complex is locally known and called
“the Princess House” as in 1784 it belonged to
Hedwig E. Biron, the Princess of Courland.
2 Mandate and scope of work
Strengthening the foundations and deteriorated
walls required considerable expertise in this
project.
The leading authority in this project was the city of
Tartu, represented by Mr. H. Jogi. The work was
performed as a joint venture of Stinger As and
KAREG Consulting Engineers in four stages during;
1994 – 1995, 1995 – 1996, 1997 and in 1999
(Figure 4).
Figure 4. HTG. Project stages. Layout.
The mandate of KAREG Consulting Engineers was
for the design-build, project and technical
management. It entailed structural and
geotechnical designs of temporary and permanent
structures as well as designing a monitoring
system, undergoing geotechnical investigation of
the site and examining the condition of the
structure. The designs were implemented for the
foundation work as well as for the concrete
structures from the basement up to the first floor.
A project of such complex proportions as this
requires diligent approach and sensitive time-
19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
3
management on site. It was crucial to oversee
operations on a day-to-day basis to ensure that
work is done safely, on time and to the right
quality standards. At times there were several
project stages ongoing simultaneously 2.
3 Site condition and investigation
A series of ground and site investigations was
performed by KAREG Consulting Engineers to
obtain information on the physical properties of
ground surrounding the site to design earthworks
and strengthening for the structure and for repair
of distress to earthworks and the structure caused
by subsurface conditions.
There were several unexpected findings during
the site investigation. A major revelation from the
results of the performed pit tests was the fact that
the old foundations of the house laid directly on
soil that consists mostly of silty clay and silt. The
uneven settlement of substrata was caused by the
ground water level decrease due to
industrialization.
Another important outcome of subsurface
exploration was the fact that the foundations of
the yard side walls were placed two meter higher
than the remaining of foundations of the structure
(Figure 6).
As a consequence, the above mentioned findings
led to forming cracks and brought about the walls
to incline.
For that reason, before actual foundation
strengthening could be safely initiated, stabilizing
the exterior walls by temporary shoring using
heavy timber struts needed to be performed in
order to retain and support the structural stability
of the building (Figure 5).
4 Foundations strengthening
Underpinning, as a process of strengthening
existing foundations, is chosen and done for
several purposes. In this project of stabilizing,
strengthening and reconstruction of HTG building,
underpinning was necessary for the following
reasons:
Figure 5. Shored exterior inclined wall.
 To strengthen existing foundations and walls
that have suffered from cracks, deterioration,
and settlements
 To deepen a part of the existing foundations
Underpinning by piling in pits was accomplished
by extending the foundations in depth so they rest
on a more supportive soil stratum.
4.1 Project overview
The selected strengthening methods were
deemed appropriate and reflected the condition
of the substructure and superstructure. Factors
such as the unstable and degrading basement
walls, uneven settlements, cracks or inclined walls
were carefully analysed and taken into
consideration.
The phases of strengthening combined different
ways and manners of using jack piles as structural
members (Figure 6).
Figure 6. Building section. Phases of project.
19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
4
The project entailed the following phases and
stages: strengthening foundations by piling in pits,
corner walls and interior walls strengthening and
stabilization, exterior walls strengthening using
piles jacked through openings and cantilever steel
beams, new basement area construction using
jacked piles as soldier piles and reconstruction,
stabilization and expansion of interior premises of
the building 2.
5 Phases and stages of
strengthening, stabilization and
reconstruction of building
Preserving a structure of great historic importance
by strengthening its foundations and stabilizing
the walls requires significant expertise, know-how
and suitable selection of strengthening methods.
Due to uneven settlement of the structure and
overall fragile, understrength condition of the
degrading walls, strengthening by piling using
drilled spiral piles and jacked piles was deemed as
the most appropriate, economic, quick and least
invasive method.
Jacked piles consisted of sections of 1 m long
pipes. Every added part was spliced after the
previous part was jacked down. The piles had
closed toes and once embedded in soil they were
filled with concrete.
The first section of the drilled spiral pile was 1 m
long and had a spliced spiral = 25 mm x 10 mm.
The spiral piles were embedded into the soil by
twirling.
Each pile was pre-stressed in accordance with the
end jacking procedure. Drilled spiral piles were
used first as temporary tension piles and
afterwards as permanent compression piles.
5.1 Strengthening of foundations, corner
walls and interior walls
This stage of work consisted of excavation pits
beneath old foundations, reinstalling steel packing
plates with concrete beneath old foundations and
establishing a temporary support until the bound
was strong enough to keep the steel plate in its
position. Therefore the position of the first piling
pits was selected in the manner so that the
immediate wall over it could structurally work as
an arch.
Before digging works could start in this section of
the building, it was necessary to anchor the corner
walls of Jaani and Lübeck Street by horizontal
anchors in both directions.
That was achieved by installation of tension rods
of ø = 20 mm on each side of the corner walls in a
height about 4.5 m from the bottom end of the
old foundations.
The allowable load was 350 kN. Every pile was
pre-tested by end jacking procedure.
Strengthening of the interior walls was executed
using needle beams and two jacked piles. First,
two intersecting holes of ø = 300 mm were bored
in order to install universal beams. Afterwards,
the piles were jacked under needle beams. This
technique required two jacks working
simultaneously.
5.2 Exterior wall strengthening using piles
jacked through openings and cantilever
steel beams
This phase of the project was carried out on the
exterior wall opposite Jaani Church. The below
described method was selected as most
appropriate and economic taking into
consideration the unstable condition of the wall.
Works started by boring two intersecting holes of
ø = 400 mm into the wall and erecting pre-spliced
channels with partly up and down welded steel
plates. The following step was to pour and
reinforce a concrete slab of 600 mm thickness
having the channels in the concrete and living
space between the channels for jacking the piles.
The slab was designed as a two-way slab
supported by needle beams. There were four
tension rods located above the channels (4 pieces
M36 grade 8.8 threatened rods) together with a
thick steel plate. The jack above the slab was
buckled against the steel plate by the piles. The
channels were then supported by the jacked pile
working as cantilever beams loaded by the old
wall. The counterweight was then made of the old
walls and partly of the new reinforced concrete
slab (Figure 7).
19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
5
Figure 7. Wall strengthening. Piles jacked through
openings.
5.2.1 Settlement measurement and values
Settlement during strengthening works was
monitored by leveling. Based on the
measurements, there was no noticeable
settlement recorded in this section of the building.
The measured settlement after strengthening
ranged between 2…4 mm. It was assumed that the
applied method of strengthening using pre-testing
and end-jacking yielded to such low settlement
values 2.
5.3 New basement area construction using
jacked piles as soldier piles
The foundations under the yard wall on axis 5
were laid 2 m higher than the other exterior walls
of the structure, therefore there was no
basement. The work was done by archeological
digging carried out in the interval manner.
Following the same principle, reinforced concrete
polings were poured 3.
Since the jacked piles used as soldier piles worked
structurally also as bended and compressed piles,
the allowable jacking force was only 250 kN per
pile.
Due to the earth pressure against the poured
polings between the soldier piles, the old wall and
some of the soldier piles had to be shored
horizontally against the old walls.
Finally, an insulated new reinforced concrete slab
was poured as a basement floor 4.
5.4 Reconstruction, stabilization and
expansion of interior premises
This phase of the project consisted of necessary
stages and steps of design, construction,
supervising and monitoring work towards making
large open areas both in the basement and on the
street level.
The process started off by safely removing partial
interior load-bearing walls in the basement. In this
area there were subsequently erected four drilled
spiral piles (1 – 4) that were embedded into the
soil by twirling (Figure 8).
Figure 8. Strengthening plan design. New
basement/open area.
The joints of the drilled spiral piles were spliced
together. Because of the lack of counterweight,
the two of the piles had first to work as tension
piles (1, 4) so that the remaining two (2, 3) could
be end-jacked. Once this process was completed,
the first set of the piles (1, 4) was end-jacked.
Finally, each of the four piles was checked by the
end-jack procedure. Only after this they were
filled with concrete.
19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
6
Figure 9. Street level. Piles 1 – 4 as temporary
shoring. New R/C beams.
In the basement area, a new concrete column was
constructed around the drilled spiral piles
incorporated inside the column as compressed
bars by bound. The column was positioned in the
middle of a new slab that was designed using the
yield line analysis for slabs and virtual work.
The slab together with the exterior walls it had
the function of a load-bearing member. The slab
and the old walls were then connected by dowels.
At the end, the reminding interior load-bearing
walls were removed.
Figure 10. HTG. New open area on the street level.
In the area on the street level (first floor), the
drilled spiral piles worked also as temporary
support during the process of pouring new
concrete beams around the middle wall. At the
final stage, the interior walls and the remaining
part of the middle wall were safely removed
(Figure 9).
This phase of the project resulted into creating
two large open areas; in the basement it was
about 95 m2
(below the slab), and on the street
level the open area was around 100 m2
(above the
slab). This outcome met the request of the client
and requirements of all safety precautions.
Nowadays the areas are used as a common room
for important school events and as the auditorium
(Figure 10).
6 Conclusions
 The strengthening scheme presented was an
economic and aesthetic solution to the
reconstruction of understrength foundations
and unstable walls of the building.
 Time management, minimal disruptions,
precise execution was not only an economic
and effective, but also inevitable factor in
order to follow technical specifications and
technological process that would lead the
project to successful completion.
 The use of the selected strengthening options
and technique for structural intervention of the
walls was found to be an appropriate
technique to achieve the desired objective and
at the same time being minimal invasive.
7 References
[1] Website. Hugo Treffneri Gümnaasium.
2016;http://www.htg.tartu.ee/.
[2] Avellan K., KAREG Consulting Engineers.
Internal archive. Helsinki: Finland; 1994-
1999.
[3] Ympäristöministeriö. Betonikrakenteen B4.
Ohjeet.Suomenrakentamismääräyskokoelm
a (Ministry of Environment, Concrete
structures B4, Guidelines. The National
Building Code of Finland. 2005; Finland. (in
Finnish).
[4] Johansen K.W. Pladeformler. Polyteknisk
forlag. 1968; Copenhagen; Denmark (in
Danish).

More Related Content

What's hot

Yorkshire Heritage References_new
Yorkshire Heritage References_newYorkshire Heritage References_new
Yorkshire Heritage References_new
Simon Nott
 
Building construction notes pdf
Building construction notes pdfBuilding construction notes pdf
Building construction notes pdf
Saqib Imran
 
Shard tower
Shard towerShard tower
Heydar Aliyev Centre
Heydar Aliyev CentreHeydar Aliyev Centre
Heydar Aliyev Centre
NADEEM AKHTAR
 
Alternative building materials m 5
Alternative building materials m 5Alternative building materials m 5
Alternative building materials m 5
Abhilash B L
 
Khhirbet abu jaber
Khhirbet abu jaber Khhirbet abu jaber
Khhirbet abu jaber
Dania Abdel-aziz
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
Shourya Puri
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
Rajat Nainwal
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
High rise building case study
High rise building case study High rise building case study
High rise building case study
VISHAKA BOTHRA
 
Heydar Aliyev Center Structural system and materials
Heydar Aliyev Center Structural system and materialsHeydar Aliyev Center Structural system and materials
Heydar Aliyev Center Structural system and materials
SasanSafar
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERING
Atiq Iqbal
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
VISHNU VIJAYAN
 
Site visit report
Site visit reportSite visit report
Site visit report
Jordon Wong
 
High Rise Structures case study - The Gherkin & Shanghai financial center.
High Rise Structures  case study - The Gherkin & Shanghai financial center.High Rise Structures  case study - The Gherkin & Shanghai financial center.
High Rise Structures case study - The Gherkin & Shanghai financial center.
Shabarinath R
 
Al Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, KuwaitAl Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, Kuwait
Sushil Kumar Gupta.
 
national building code
national building codenational building code
national building code
Ruhiya Garg
 
U boot technology
U boot technology U boot technology
U boot technology
akshayapriyadharshini
 
Part 3 ece
Part 3 ecePart 3 ece
Part 3 ece
Kaustubh Sane
 
Ece part 2
Ece part 2Ece part 2
Ece part 2
Kaustubh Sane
 

What's hot (20)

Yorkshire Heritage References_new
Yorkshire Heritage References_newYorkshire Heritage References_new
Yorkshire Heritage References_new
 
Building construction notes pdf
Building construction notes pdfBuilding construction notes pdf
Building construction notes pdf
 
Shard tower
Shard towerShard tower
Shard tower
 
Heydar Aliyev Centre
Heydar Aliyev CentreHeydar Aliyev Centre
Heydar Aliyev Centre
 
Alternative building materials m 5
Alternative building materials m 5Alternative building materials m 5
Alternative building materials m 5
 
Khhirbet abu jaber
Khhirbet abu jaber Khhirbet abu jaber
Khhirbet abu jaber
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
High rise building case study
High rise building case study High rise building case study
High rise building case study
 
Heydar Aliyev Center Structural system and materials
Heydar Aliyev Center Structural system and materialsHeydar Aliyev Center Structural system and materials
Heydar Aliyev Center Structural system and materials
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERING
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
 
Site visit report
Site visit reportSite visit report
Site visit report
 
High Rise Structures case study - The Gherkin & Shanghai financial center.
High Rise Structures  case study - The Gherkin & Shanghai financial center.High Rise Structures  case study - The Gherkin & Shanghai financial center.
High Rise Structures case study - The Gherkin & Shanghai financial center.
 
Al Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, KuwaitAl Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, Kuwait
 
national building code
national building codenational building code
national building code
 
U boot technology
U boot technology U boot technology
U boot technology
 
Part 3 ece
Part 3 ecePart 3 ece
Part 3 ece
 
Ece part 2
Ece part 2Ece part 2
Ece part 2
 

Similar to Strengthening and Reconstruction of the Hugo Treffner Gymnasium building in Tartu, Estonia

Southeast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning HubSoutheast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning Hub
T.Y. Lin International
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
BirukYared3
 
structure analysis by PUC GRP 3
structure analysis by PUC GRP 3structure analysis by PUC GRP 3
structure analysis by PUC GRP 3
promitchowdhury1
 
Site report
Site reportSite report
Site report
Penny3688
 
2327
23272327
Behaviour of reinforced concrete frame with in fill walls under seismic loads...
Behaviour of reinforced concrete frame with in fill walls under seismic loads...Behaviour of reinforced concrete frame with in fill walls under seismic loads...
Behaviour of reinforced concrete frame with in fill walls under seismic loads...
IAEME Publication
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample Harvard
Writers Per Hour
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
taufiqahmad_87
 
Case Study: Metropol Parasol, Seville (Spain)
Case Study: Metropol Parasol, Seville (Spain)Case Study: Metropol Parasol, Seville (Spain)
Case Study: Metropol Parasol, Seville (Spain)
Prasad Thanthratey
 
Construction solutions
Construction solutionsConstruction solutions
Construction solutions
kennett2203
 
BUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTBUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORT
JoyeeLee0131
 
‘‘Brick-topia’’, the thin-tile vaulted pavilion
‘‘Brick-topia’’, the thin-tile vaulted pavilion‘‘Brick-topia’’, the thin-tile vaulted pavilion
‘‘Brick-topia’’, the thin-tile vaulted pavilion
Anupama Krishnan
 
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...
IRJET Journal
 
Building Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction SolutionsBuilding Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction Solutions
Jing Fan Koh
 
PROJECT 2: CONSTRUCTION SOLUTIONS
PROJECT 2: CONSTRUCTION SOLUTIONSPROJECT 2: CONSTRUCTION SOLUTIONS
PROJECT 2: CONSTRUCTION SOLUTIONS
Nik Ahmad Munawwar Nik Din
 
Mod. 1.pptx
Mod. 1.pptxMod. 1.pptx
Mod. 1.pptx
MrinmayeeGanage1
 
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
ijtsrd
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
hlksd
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
Bian Bian
 
earthquake resistant design
earthquake resistant designearthquake resistant design
earthquake resistant design
Aditya Sanyal
 

Similar to Strengthening and Reconstruction of the Hugo Treffner Gymnasium building in Tartu, Estonia (20)

Southeast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning HubSoutheast Asia Construction - NTU Learning Hub
Southeast Asia Construction - NTU Learning Hub
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
structure analysis by PUC GRP 3
structure analysis by PUC GRP 3structure analysis by PUC GRP 3
structure analysis by PUC GRP 3
 
Site report
Site reportSite report
Site report
 
2327
23272327
2327
 
Behaviour of reinforced concrete frame with in fill walls under seismic loads...
Behaviour of reinforced concrete frame with in fill walls under seismic loads...Behaviour of reinforced concrete frame with in fill walls under seismic loads...
Behaviour of reinforced concrete frame with in fill walls under seismic loads...
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample Harvard
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
Case Study: Metropol Parasol, Seville (Spain)
Case Study: Metropol Parasol, Seville (Spain)Case Study: Metropol Parasol, Seville (Spain)
Case Study: Metropol Parasol, Seville (Spain)
 
Construction solutions
Construction solutionsConstruction solutions
Construction solutions
 
BUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTBUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORT
 
‘‘Brick-topia’’, the thin-tile vaulted pavilion
‘‘Brick-topia’’, the thin-tile vaulted pavilion‘‘Brick-topia’’, the thin-tile vaulted pavilion
‘‘Brick-topia’’, the thin-tile vaulted pavilion
 
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...
 
Building Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction SolutionsBuilding Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction Solutions
 
PROJECT 2: CONSTRUCTION SOLUTIONS
PROJECT 2: CONSTRUCTION SOLUTIONSPROJECT 2: CONSTRUCTION SOLUTIONS
PROJECT 2: CONSTRUCTION SOLUTIONS
 
Mod. 1.pptx
Mod. 1.pptxMod. 1.pptx
Mod. 1.pptx
 
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
 
earthquake resistant design
earthquake resistant designearthquake resistant design
earthquake resistant design
 

Recently uploaded

Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 

Recently uploaded (20)

Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 

Strengthening and Reconstruction of the Hugo Treffner Gymnasium building in Tartu, Estonia

  • 1. 19th IABSE Congress Stockholm, 21-23 September 2016 Challenges in Design and Construction of an Innovative and Sustainable Built Environment 1 Strengthening and Reconstruction of the Hugo Treffner Gymnasium building in Tartu, Estonia Kari Avellan, Erika Belopotocanova KAREG Consulting Engineers, Helsinki, Finland Contact: kari.avellan@kareg.com Abstract Strengthening and reconstruction of Hugo Treffner Gymnasium building was carried out from 1994 to 1997 in four stages. The mandate of KAREG Consulting Engineers entailed designs of temporary and permanent structures as well as development of a monitoring system and examining the condition of the structure. The foundations on the yard side walls were placed two meter higher than the remaining of foundations of the structure. As a consequence, the above mentioned findings led to forming cracks and brought about the walls of the building to incline. The project involved corner walls and interior walls stabilization, exterior walls strengthening and a new basement area construction. A new reinforced slab was poured, designed using the yield line theory analysis. The use of the selected strengthening options and technique for structural intervention of the walls was found to be a suitable technique to achieve the desired objective. Keywords: strengthening; structural intervention; stabilisation; foundations; piles; cracks; settlement; walls; concrete slab. 1 Introduction Hugo Treffner Gymnasium (HTG) is a secondary school located in Tartu, Estonia with special emphasis on science education. Founded by a renowned scholar Hugo Treffner, it was the only large secondary school in 19th century in Estonia with dominantly Estonian students and no age restrictions. During the Estonian national awakening (1850 – 1918) the school greatly contributed to the number of Estonian intellectuals. In November 2011 HTG became the partner school of UNESCO. Today, HTG is a modern and comfortable educational institution and a leading co-educational public school for students of age 16 to 19 (Figure 1). Figure 1. Hugo Treffner Gymnasium today. 1.1 Hugo Treffner Gymnasium building The building has served as a school for centuries. Founded in 1883, HTG boasts a combination of a
  • 2. 19th IABSE Congress Stockholm 2016 Challenges in Design and Construction of an Innovative and Sustainable Built Environment 2 historic building and modern facilities in the heart of Tartu. In the course of extensive restoration work the gymnasium has retained its historic aura (Figure 2). The majority of original details have been successfully preserved, e.g. wooden ceiling beams in the common room, or ceiling paintings in the classroom on the street level 1. Figure 2. HTG. Basement library and study. Nowadays HTG building consists of four parts built at different times. The building on Munga 12 is the oldest part of the HTG building ensemble. It was used as a schoolhouse since 1804, and it is certainly one of the most eye-catching buildings in the historical Jaani quarter of Tartu (Figure 3). Figure 3. HTG building and Jaani Church. The house by Rüütli Street was specifically renovated for the school in 1830 by architect G.F.W. Geist. An interesting fact is that this part of the building complex is locally known and called “the Princess House” as in 1784 it belonged to Hedwig E. Biron, the Princess of Courland. 2 Mandate and scope of work Strengthening the foundations and deteriorated walls required considerable expertise in this project. The leading authority in this project was the city of Tartu, represented by Mr. H. Jogi. The work was performed as a joint venture of Stinger As and KAREG Consulting Engineers in four stages during; 1994 – 1995, 1995 – 1996, 1997 and in 1999 (Figure 4). Figure 4. HTG. Project stages. Layout. The mandate of KAREG Consulting Engineers was for the design-build, project and technical management. It entailed structural and geotechnical designs of temporary and permanent structures as well as designing a monitoring system, undergoing geotechnical investigation of the site and examining the condition of the structure. The designs were implemented for the foundation work as well as for the concrete structures from the basement up to the first floor. A project of such complex proportions as this requires diligent approach and sensitive time-
  • 3. 19th IABSE Congress Stockholm 2016 Challenges in Design and Construction of an Innovative and Sustainable Built Environment 3 management on site. It was crucial to oversee operations on a day-to-day basis to ensure that work is done safely, on time and to the right quality standards. At times there were several project stages ongoing simultaneously 2. 3 Site condition and investigation A series of ground and site investigations was performed by KAREG Consulting Engineers to obtain information on the physical properties of ground surrounding the site to design earthworks and strengthening for the structure and for repair of distress to earthworks and the structure caused by subsurface conditions. There were several unexpected findings during the site investigation. A major revelation from the results of the performed pit tests was the fact that the old foundations of the house laid directly on soil that consists mostly of silty clay and silt. The uneven settlement of substrata was caused by the ground water level decrease due to industrialization. Another important outcome of subsurface exploration was the fact that the foundations of the yard side walls were placed two meter higher than the remaining of foundations of the structure (Figure 6). As a consequence, the above mentioned findings led to forming cracks and brought about the walls to incline. For that reason, before actual foundation strengthening could be safely initiated, stabilizing the exterior walls by temporary shoring using heavy timber struts needed to be performed in order to retain and support the structural stability of the building (Figure 5). 4 Foundations strengthening Underpinning, as a process of strengthening existing foundations, is chosen and done for several purposes. In this project of stabilizing, strengthening and reconstruction of HTG building, underpinning was necessary for the following reasons: Figure 5. Shored exterior inclined wall.  To strengthen existing foundations and walls that have suffered from cracks, deterioration, and settlements  To deepen a part of the existing foundations Underpinning by piling in pits was accomplished by extending the foundations in depth so they rest on a more supportive soil stratum. 4.1 Project overview The selected strengthening methods were deemed appropriate and reflected the condition of the substructure and superstructure. Factors such as the unstable and degrading basement walls, uneven settlements, cracks or inclined walls were carefully analysed and taken into consideration. The phases of strengthening combined different ways and manners of using jack piles as structural members (Figure 6). Figure 6. Building section. Phases of project.
  • 4. 19th IABSE Congress Stockholm 2016 Challenges in Design and Construction of an Innovative and Sustainable Built Environment 4 The project entailed the following phases and stages: strengthening foundations by piling in pits, corner walls and interior walls strengthening and stabilization, exterior walls strengthening using piles jacked through openings and cantilever steel beams, new basement area construction using jacked piles as soldier piles and reconstruction, stabilization and expansion of interior premises of the building 2. 5 Phases and stages of strengthening, stabilization and reconstruction of building Preserving a structure of great historic importance by strengthening its foundations and stabilizing the walls requires significant expertise, know-how and suitable selection of strengthening methods. Due to uneven settlement of the structure and overall fragile, understrength condition of the degrading walls, strengthening by piling using drilled spiral piles and jacked piles was deemed as the most appropriate, economic, quick and least invasive method. Jacked piles consisted of sections of 1 m long pipes. Every added part was spliced after the previous part was jacked down. The piles had closed toes and once embedded in soil they were filled with concrete. The first section of the drilled spiral pile was 1 m long and had a spliced spiral = 25 mm x 10 mm. The spiral piles were embedded into the soil by twirling. Each pile was pre-stressed in accordance with the end jacking procedure. Drilled spiral piles were used first as temporary tension piles and afterwards as permanent compression piles. 5.1 Strengthening of foundations, corner walls and interior walls This stage of work consisted of excavation pits beneath old foundations, reinstalling steel packing plates with concrete beneath old foundations and establishing a temporary support until the bound was strong enough to keep the steel plate in its position. Therefore the position of the first piling pits was selected in the manner so that the immediate wall over it could structurally work as an arch. Before digging works could start in this section of the building, it was necessary to anchor the corner walls of Jaani and Lübeck Street by horizontal anchors in both directions. That was achieved by installation of tension rods of ø = 20 mm on each side of the corner walls in a height about 4.5 m from the bottom end of the old foundations. The allowable load was 350 kN. Every pile was pre-tested by end jacking procedure. Strengthening of the interior walls was executed using needle beams and two jacked piles. First, two intersecting holes of ø = 300 mm were bored in order to install universal beams. Afterwards, the piles were jacked under needle beams. This technique required two jacks working simultaneously. 5.2 Exterior wall strengthening using piles jacked through openings and cantilever steel beams This phase of the project was carried out on the exterior wall opposite Jaani Church. The below described method was selected as most appropriate and economic taking into consideration the unstable condition of the wall. Works started by boring two intersecting holes of ø = 400 mm into the wall and erecting pre-spliced channels with partly up and down welded steel plates. The following step was to pour and reinforce a concrete slab of 600 mm thickness having the channels in the concrete and living space between the channels for jacking the piles. The slab was designed as a two-way slab supported by needle beams. There were four tension rods located above the channels (4 pieces M36 grade 8.8 threatened rods) together with a thick steel plate. The jack above the slab was buckled against the steel plate by the piles. The channels were then supported by the jacked pile working as cantilever beams loaded by the old wall. The counterweight was then made of the old walls and partly of the new reinforced concrete slab (Figure 7).
  • 5. 19th IABSE Congress Stockholm 2016 Challenges in Design and Construction of an Innovative and Sustainable Built Environment 5 Figure 7. Wall strengthening. Piles jacked through openings. 5.2.1 Settlement measurement and values Settlement during strengthening works was monitored by leveling. Based on the measurements, there was no noticeable settlement recorded in this section of the building. The measured settlement after strengthening ranged between 2…4 mm. It was assumed that the applied method of strengthening using pre-testing and end-jacking yielded to such low settlement values 2. 5.3 New basement area construction using jacked piles as soldier piles The foundations under the yard wall on axis 5 were laid 2 m higher than the other exterior walls of the structure, therefore there was no basement. The work was done by archeological digging carried out in the interval manner. Following the same principle, reinforced concrete polings were poured 3. Since the jacked piles used as soldier piles worked structurally also as bended and compressed piles, the allowable jacking force was only 250 kN per pile. Due to the earth pressure against the poured polings between the soldier piles, the old wall and some of the soldier piles had to be shored horizontally against the old walls. Finally, an insulated new reinforced concrete slab was poured as a basement floor 4. 5.4 Reconstruction, stabilization and expansion of interior premises This phase of the project consisted of necessary stages and steps of design, construction, supervising and monitoring work towards making large open areas both in the basement and on the street level. The process started off by safely removing partial interior load-bearing walls in the basement. In this area there were subsequently erected four drilled spiral piles (1 – 4) that were embedded into the soil by twirling (Figure 8). Figure 8. Strengthening plan design. New basement/open area. The joints of the drilled spiral piles were spliced together. Because of the lack of counterweight, the two of the piles had first to work as tension piles (1, 4) so that the remaining two (2, 3) could be end-jacked. Once this process was completed, the first set of the piles (1, 4) was end-jacked. Finally, each of the four piles was checked by the end-jack procedure. Only after this they were filled with concrete.
  • 6. 19th IABSE Congress Stockholm 2016 Challenges in Design and Construction of an Innovative and Sustainable Built Environment 6 Figure 9. Street level. Piles 1 – 4 as temporary shoring. New R/C beams. In the basement area, a new concrete column was constructed around the drilled spiral piles incorporated inside the column as compressed bars by bound. The column was positioned in the middle of a new slab that was designed using the yield line analysis for slabs and virtual work. The slab together with the exterior walls it had the function of a load-bearing member. The slab and the old walls were then connected by dowels. At the end, the reminding interior load-bearing walls were removed. Figure 10. HTG. New open area on the street level. In the area on the street level (first floor), the drilled spiral piles worked also as temporary support during the process of pouring new concrete beams around the middle wall. At the final stage, the interior walls and the remaining part of the middle wall were safely removed (Figure 9). This phase of the project resulted into creating two large open areas; in the basement it was about 95 m2 (below the slab), and on the street level the open area was around 100 m2 (above the slab). This outcome met the request of the client and requirements of all safety precautions. Nowadays the areas are used as a common room for important school events and as the auditorium (Figure 10). 6 Conclusions  The strengthening scheme presented was an economic and aesthetic solution to the reconstruction of understrength foundations and unstable walls of the building.  Time management, minimal disruptions, precise execution was not only an economic and effective, but also inevitable factor in order to follow technical specifications and technological process that would lead the project to successful completion.  The use of the selected strengthening options and technique for structural intervention of the walls was found to be an appropriate technique to achieve the desired objective and at the same time being minimal invasive. 7 References [1] Website. Hugo Treffneri Gümnaasium. 2016;http://www.htg.tartu.ee/. [2] Avellan K., KAREG Consulting Engineers. Internal archive. Helsinki: Finland; 1994- 1999. [3] Ympäristöministeriö. Betonikrakenteen B4. Ohjeet.Suomenrakentamismääräyskokoelm a (Ministry of Environment, Concrete structures B4, Guidelines. The National Building Code of Finland. 2005; Finland. (in Finnish). [4] Johansen K.W. Pladeformler. Polyteknisk forlag. 1968; Copenhagen; Denmark (in Danish).