Strengthening and reconstruction of Hugo Treffner Gymnasium building was carried out from 1994 to 1997 in four stages. The mandate of KAREG Consulting Engineers entailed designs of temporary and permanent structures as well as development of a monitoring system and examining the condition of the structure. The foundations on the yard side walls were placed two meter higher than the remaining of foundations of the structure. As a consequence, the above mentioned findings led to forming cracks and brought about the walls of the building to incline. The project involved corner walls and interior walls stabilization, exterior walls strengthening and a new basement area construction. A new reinforced slab was poured, designed using the yield line theory analysis. The use of the selected strengthening options and technique for structural intervention of the walls was found to be a suitable technique to achieve the desired objective.
The Heydar Aliyev Cultural Centre in Baku, Azerbaijan was designed by Zaha Hadid Architects. It uses a combination of a concrete structure and space frame system to achieve large column-free interior spaces under its curved exterior. The space frame enabled construction of the free-form structure and uses vertical elements absorbed by the envelope. Reinforced concrete is used for shear walls and foundations, while the space frame, concrete, and glass fiber reinforced polyester and concrete panels create the distinctive curved surface.
This document summarizes the structural design and materials used in the Heydar Aliyev Culture Center in Baku, Azerbaijan. It describes how the main building uses reinforced concrete and a composite steel frame. The roof structure is a unique space frame design made of steel. High-performance materials like glass and stone were used for the curtain walls, interior and exterior solid skin panels to meet architectural and technical requirements.
The document discusses the Shard building project in London. It describes the Shard as the tallest building in Western Europe at 310 meters tall. BASF provided admixtures to help with a record-breaking concrete pour of 15,000 cubic meters for the basement levels. Their product MasterGlenium SKY 569 accelerated curing to allow for fast-track construction, meeting the goals of quality finish and on-schedule completion. The concrete pour was completed ahead of schedule, placing over 5,000 cubic meters in under 36 hours.
Understand environmental issues due to building materials and the energy consumption in manufacturing building materials and the alternative building technologies which are followed in present construction field.
The document provides information about the Shard, the tallest building in the UK. It discusses its construction, which involved a steel structure up to level 40, then a post-tensioned concrete frame up to level 69, topped by a steel-framed spire. Modular construction techniques were used to minimize risks during assembly of the steelwork sections. The building employs various energy efficient technologies and materials to reduce its environmental impact.
The document provides information on the typical stages of construction for a building project, including conception of the scheme, site investigation, designs, drawings and estimating, preparation of specifications, procurement of materials, supervision, and preparation of a time schedule. It discusses the stages in more detail, including site clearance, demarcation, positioning of the central coordinate, surveying and layout. It also describes the sequences and procedures for substructure elements like foundations (shallow and deep), grade beams, and superstructure elements like columns, beams and slabs, brickwork, and finishing work. Reinforcement practices and requirements for concrete mixing are also outlined.
This document summarizes a presentation by Raymond Wong on prefabricated construction systems used in Hong Kong. It describes how prefabrication has been used in public housing projects since the 1970s, with improvements over time such as introducing in-situ joined facades. It also discusses use of prefabrication in other building types like schools, government quarters, and special buildings. Recent developments show increasing use of prefabricated facades, walls, and structural elements in residential and commercial buildings. Future trends may include more modular and composite prefabricated elements for medium-rise buildings. Constraints include coordination challenges and limited work space in Hong Kong's dense urban environment.
This document describes a project to construct a temporary bus shelter made of bamboo and other recycled materials. It discusses the design process including initial designs, final drawings and photos. The construction process is explained through sequences and progress photos. Key materials used are bamboo for the structure, plywood for subflooring and nipa palm thatching for the roof. Different types of joints and connections used in the structure are illustrated such as notching, nailing and lashing techniques. Load distribution diagrams show how stress is transferred through the curved structure. The conclusion reflects on lessons learned regarding bamboo properties, construction skills and considering strength, stiffness and stability in skeletal structures.
The Heydar Aliyev Cultural Centre in Baku, Azerbaijan was designed by Zaha Hadid Architects. It uses a combination of a concrete structure and space frame system to achieve large column-free interior spaces under its curved exterior. The space frame enabled construction of the free-form structure and uses vertical elements absorbed by the envelope. Reinforced concrete is used for shear walls and foundations, while the space frame, concrete, and glass fiber reinforced polyester and concrete panels create the distinctive curved surface.
This document summarizes the structural design and materials used in the Heydar Aliyev Culture Center in Baku, Azerbaijan. It describes how the main building uses reinforced concrete and a composite steel frame. The roof structure is a unique space frame design made of steel. High-performance materials like glass and stone were used for the curtain walls, interior and exterior solid skin panels to meet architectural and technical requirements.
The document discusses the Shard building project in London. It describes the Shard as the tallest building in Western Europe at 310 meters tall. BASF provided admixtures to help with a record-breaking concrete pour of 15,000 cubic meters for the basement levels. Their product MasterGlenium SKY 569 accelerated curing to allow for fast-track construction, meeting the goals of quality finish and on-schedule completion. The concrete pour was completed ahead of schedule, placing over 5,000 cubic meters in under 36 hours.
Understand environmental issues due to building materials and the energy consumption in manufacturing building materials and the alternative building technologies which are followed in present construction field.
The document provides information about the Shard, the tallest building in the UK. It discusses its construction, which involved a steel structure up to level 40, then a post-tensioned concrete frame up to level 69, topped by a steel-framed spire. Modular construction techniques were used to minimize risks during assembly of the steelwork sections. The building employs various energy efficient technologies and materials to reduce its environmental impact.
The document provides information on the typical stages of construction for a building project, including conception of the scheme, site investigation, designs, drawings and estimating, preparation of specifications, procurement of materials, supervision, and preparation of a time schedule. It discusses the stages in more detail, including site clearance, demarcation, positioning of the central coordinate, surveying and layout. It also describes the sequences and procedures for substructure elements like foundations (shallow and deep), grade beams, and superstructure elements like columns, beams and slabs, brickwork, and finishing work. Reinforcement practices and requirements for concrete mixing are also outlined.
This document summarizes a presentation by Raymond Wong on prefabricated construction systems used in Hong Kong. It describes how prefabrication has been used in public housing projects since the 1970s, with improvements over time such as introducing in-situ joined facades. It also discusses use of prefabrication in other building types like schools, government quarters, and special buildings. Recent developments show increasing use of prefabricated facades, walls, and structural elements in residential and commercial buildings. Future trends may include more modular and composite prefabricated elements for medium-rise buildings. Constraints include coordination challenges and limited work space in Hong Kong's dense urban environment.
This document describes a project to construct a temporary bus shelter made of bamboo and other recycled materials. It discusses the design process including initial designs, final drawings and photos. The construction process is explained through sequences and progress photos. Key materials used are bamboo for the structure, plywood for subflooring and nipa palm thatching for the roof. Different types of joints and connections used in the structure are illustrated such as notching, nailing and lashing techniques. Load distribution diagrams show how stress is transferred through the curved structure. The conclusion reflects on lessons learned regarding bamboo properties, construction skills and considering strength, stiffness and stability in skeletal structures.
The document provides details on several heritage masonry projects completed by Yorkshire Masonry including:
1. Repairing a 60m chimney in Randwick including repointing bricks, replacing cracked bricks, and epoxy injecting render. Accessing the top required designing a lifting platform.
2. Repointing and repairing brick facades at the Walsh Bay Heritage Listed Mills over 6 months while new facades were constructed. Special shaped bricks were replaced.
3. Repointing and repairing a small chapel building at SCEGGS School, including doweling sandstone blocks and removing timber and metal plugs.
1) The document is a collection of notes on building construction written by Saqib Imran, a civil engineering student, to share knowledge with other students and engineers.
2) It covers topics like the key components of confined masonry buildings, the history and construction of the Taj Mahal, selection of stones for building construction, and how to build a stone wall.
3) The notes provide information on structural elements like masonry walls, confining elements, floors and roofs, foundations, as well as construction materials, processes, and techniques used to build important structures.
The Shard is a 310m tall skyscraper in London consisting of offices, hotels, apartments and retail space. It uses a combination of concrete and steel structures, with a concrete core providing stability. Over 54,000 cubic meters of concrete and 11,000 tons of structural steel were required. Complex transfer structures such as vierendeel trusses were needed to reduce column spacing as the building design transitioned between material types. Extensive analysis and testing was performed to ensure the tower could withstand the immense external and internal loads placed upon it.
The Heydar Aliyev Centre in Baku, Azerbaijan was designed to establish a continuous, fluid relationship between its surrounding plaza and interior spaces. This was achieved through a combination of a concrete structure and space frame system, which allowed for large column-free interior spaces. The building's skin, made of polyester-reinforced fibreglass panels, helps the structure appear homogenous. The design overcomes the challenges of the site's wind loads and seismic activity through these structural systems.
understand environmental issues due to building materials and the energy consumption in manufacturing building materials and the alternative building technologies which are followed in present construction field.
The document provides an overview of traditional architecture in Jordan, describing the main types and giving examples. It then discusses the rehabilitation of the Kan Zaman site, a 19th century complex converted into a tourist village. While the project saved the site from decay, the evaluation notes issues with reconstruction methods that did not respect the original architecture and used incompatible modern materials like Portland cement. Overall, the rehabilitation extended the site's life but did not fully comply with conservation standards.
The document discusses various modern construction technologies including concrete walls and floors, precast cladding panels, 3D volumetric modules, twin wall technology, flat slabs, thin joint masonry, insulating concrete formwork, and precast concrete foundations. These technologies aim to reduce costs and construction time while improving quality, through the use of prefabricated concrete elements constructed in a controlled factory environment and assembled on site.
Burj Al Arab is a luxury hotel located on an artificial island in Dubai. It is 321 meters tall and has 202 rooms. The hotel took over 6 years to construct at a cost of $650 million. Some key facts about its design and engineering include:
- It is supported by 230 concrete piles that are 40 meters long driven into the sandy soil below.
- The exterior is clad in glass and aluminum and is designed to resemble the sail of a dhow ship.
- The large atrium is spanned by trusses and enclosed by a lightweight fabric sail that is 161,000 square feet in area.
- Structurally, it relies on steel trusses and cross-bracing
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
Modern construction technologies provide advantages like faster construction, higher quality, environmental benefits, and ability to overcome lack of skilled workers. Technologies discussed include prefabricated buildings, tunnel formwork, jump formwork, reinforced soil, trenchless techniques, 3D printing, robotics, and more. While technologies increase speed and quality, some have limitations like limited architectural features, difficulty modifying structures, and higher initial costs. Overall, modern techniques can help qualify projects for sustainability and efficiency if the appropriate technology is selected for each project's unique requirements.
The document is a course outline for construction engineering that covers topics like foundation construction, masonry, reinforced concrete structures, and building components. It includes definitions of key terms like dead load, imposed load, and lateral load. It also summarizes different types of foundations like shallow foundations and deep pile foundations. Masonry construction techniques for brick, block, and stone are outlined. Reinforced concrete structures, joints, bonds, and arches are also summarized.
Building failures – General reasons – classification – Causes of
failures in RCC and Steel structures, Failure due to Fire, Wind and
Earthquakes.
Foundation failure – failures by alteration, improper maintenance,
overloading.
Retrofitting of structural components - beams, columns and slabs
This site visit report summarizes a student's visit to an ongoing construction project located in Antara Gapi, Hulu Selangor. The report describes the project details, observations made at the construction site, and the process of constructing pad footings. Photos from the site are included to illustrate various construction materials, techniques, and safety practices observed. The student concludes that the site visit provided valuable hands-on learning experiences about construction elements like pad footings that cannot be gained from a classroom. Communication between workers and proper safety protocols are also highlighted as important aspects of construction.
Al Hamra Firdous Tower is a 412.6m tall skyscraper located in Kuwait City, Kuwait. It has 77 floors of office and retail space, making it the tallest building in Kuwait. The unique twisting geometry was designed by Skidmore, Owings and Merrill to maximize views while minimizing solar heat gain. The solid south facade features limestone cladding to reduce solar radiation, while transparent north facades offer panoramic Gulf views. The tower's sculptural form reflects the local landscape and won several international architectural awards.
This document discusses prefabrication, systems building, and mixed/composite construction. It begins with an introduction and overview of prefabricated concrete, including terminology, materials, components, design requirements, joints, and manufacturing processes. It then covers systems building and mixed/composite construction, discussing formwork systems, structural schemes, and prefabricated structural units. The document provides details on various modular planning, construction elements, and techniques used in prefabricated and systems building projects.
The document discusses the functional requirements of buildings. It outlines several key principles for building planning including orientation, cross ventilation, damp proofing, and placement of walls and roofs. It also describes factors like comfort, durability, fire protection, insulation, and strength that must be considered in building design. Functional requirements include providing adequate light and ventilation while maintaining dimensional stability, durability, economy, and protection from fire, dampness, and termites.
This document discusses building bylaws and design loads for structures. It explains that building bylaws are regulations established by local authorities to prevent uncontrolled development and ensure safety. The objectives of bylaws are outlined, including disciplined growth, safety from hazards, efficient use of space, and occupant comfort. Specific bylaws like building frontage, open spaces, height limits are described. Design loads including dead, live, wind, snow, and earthquake loads are defined. Foundation types and superstructure components like columns, beams, floors, walls and roofs are also summarized.
The NTU Learning Hub in Singapore features an iconic architectural design of 12 pods containing 56 classrooms. UK designer Thomas Heatherwick conceived of the building, which features curved columns that grow outward as the building rises over eight stories. Engineering challenges included designing for stability with the irregular column angles. The structural engineer, T.Y. Lin International, developed an open column frame system using reinforced concrete and steel. Pigmented concrete was used in the structural elements for the first time in Singapore to achieve the desired architectural look.
The document provides details on several heritage masonry projects completed by Yorkshire Masonry including:
1. Repairing a 60m chimney in Randwick including repointing bricks, replacing cracked bricks, and epoxy injecting render. Accessing the top required designing a lifting platform.
2. Repointing and repairing brick facades at the Walsh Bay Heritage Listed Mills over 6 months while new facades were constructed. Special shaped bricks were replaced.
3. Repointing and repairing a small chapel building at SCEGGS School, including doweling sandstone blocks and removing timber and metal plugs.
1) The document is a collection of notes on building construction written by Saqib Imran, a civil engineering student, to share knowledge with other students and engineers.
2) It covers topics like the key components of confined masonry buildings, the history and construction of the Taj Mahal, selection of stones for building construction, and how to build a stone wall.
3) The notes provide information on structural elements like masonry walls, confining elements, floors and roofs, foundations, as well as construction materials, processes, and techniques used to build important structures.
The Shard is a 310m tall skyscraper in London consisting of offices, hotels, apartments and retail space. It uses a combination of concrete and steel structures, with a concrete core providing stability. Over 54,000 cubic meters of concrete and 11,000 tons of structural steel were required. Complex transfer structures such as vierendeel trusses were needed to reduce column spacing as the building design transitioned between material types. Extensive analysis and testing was performed to ensure the tower could withstand the immense external and internal loads placed upon it.
The Heydar Aliyev Centre in Baku, Azerbaijan was designed to establish a continuous, fluid relationship between its surrounding plaza and interior spaces. This was achieved through a combination of a concrete structure and space frame system, which allowed for large column-free interior spaces. The building's skin, made of polyester-reinforced fibreglass panels, helps the structure appear homogenous. The design overcomes the challenges of the site's wind loads and seismic activity through these structural systems.
understand environmental issues due to building materials and the energy consumption in manufacturing building materials and the alternative building technologies which are followed in present construction field.
The document provides an overview of traditional architecture in Jordan, describing the main types and giving examples. It then discusses the rehabilitation of the Kan Zaman site, a 19th century complex converted into a tourist village. While the project saved the site from decay, the evaluation notes issues with reconstruction methods that did not respect the original architecture and used incompatible modern materials like Portland cement. Overall, the rehabilitation extended the site's life but did not fully comply with conservation standards.
The document discusses various modern construction technologies including concrete walls and floors, precast cladding panels, 3D volumetric modules, twin wall technology, flat slabs, thin joint masonry, insulating concrete formwork, and precast concrete foundations. These technologies aim to reduce costs and construction time while improving quality, through the use of prefabricated concrete elements constructed in a controlled factory environment and assembled on site.
Burj Al Arab is a luxury hotel located on an artificial island in Dubai. It is 321 meters tall and has 202 rooms. The hotel took over 6 years to construct at a cost of $650 million. Some key facts about its design and engineering include:
- It is supported by 230 concrete piles that are 40 meters long driven into the sandy soil below.
- The exterior is clad in glass and aluminum and is designed to resemble the sail of a dhow ship.
- The large atrium is spanned by trusses and enclosed by a lightweight fabric sail that is 161,000 square feet in area.
- Structurally, it relies on steel trusses and cross-bracing
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
Modern construction technologies provide advantages like faster construction, higher quality, environmental benefits, and ability to overcome lack of skilled workers. Technologies discussed include prefabricated buildings, tunnel formwork, jump formwork, reinforced soil, trenchless techniques, 3D printing, robotics, and more. While technologies increase speed and quality, some have limitations like limited architectural features, difficulty modifying structures, and higher initial costs. Overall, modern techniques can help qualify projects for sustainability and efficiency if the appropriate technology is selected for each project's unique requirements.
The document is a course outline for construction engineering that covers topics like foundation construction, masonry, reinforced concrete structures, and building components. It includes definitions of key terms like dead load, imposed load, and lateral load. It also summarizes different types of foundations like shallow foundations and deep pile foundations. Masonry construction techniques for brick, block, and stone are outlined. Reinforced concrete structures, joints, bonds, and arches are also summarized.
Building failures – General reasons – classification – Causes of
failures in RCC and Steel structures, Failure due to Fire, Wind and
Earthquakes.
Foundation failure – failures by alteration, improper maintenance,
overloading.
Retrofitting of structural components - beams, columns and slabs
This site visit report summarizes a student's visit to an ongoing construction project located in Antara Gapi, Hulu Selangor. The report describes the project details, observations made at the construction site, and the process of constructing pad footings. Photos from the site are included to illustrate various construction materials, techniques, and safety practices observed. The student concludes that the site visit provided valuable hands-on learning experiences about construction elements like pad footings that cannot be gained from a classroom. Communication between workers and proper safety protocols are also highlighted as important aspects of construction.
Al Hamra Firdous Tower is a 412.6m tall skyscraper located in Kuwait City, Kuwait. It has 77 floors of office and retail space, making it the tallest building in Kuwait. The unique twisting geometry was designed by Skidmore, Owings and Merrill to maximize views while minimizing solar heat gain. The solid south facade features limestone cladding to reduce solar radiation, while transparent north facades offer panoramic Gulf views. The tower's sculptural form reflects the local landscape and won several international architectural awards.
This document discusses prefabrication, systems building, and mixed/composite construction. It begins with an introduction and overview of prefabricated concrete, including terminology, materials, components, design requirements, joints, and manufacturing processes. It then covers systems building and mixed/composite construction, discussing formwork systems, structural schemes, and prefabricated structural units. The document provides details on various modular planning, construction elements, and techniques used in prefabricated and systems building projects.
The document discusses the functional requirements of buildings. It outlines several key principles for building planning including orientation, cross ventilation, damp proofing, and placement of walls and roofs. It also describes factors like comfort, durability, fire protection, insulation, and strength that must be considered in building design. Functional requirements include providing adequate light and ventilation while maintaining dimensional stability, durability, economy, and protection from fire, dampness, and termites.
This document discusses building bylaws and design loads for structures. It explains that building bylaws are regulations established by local authorities to prevent uncontrolled development and ensure safety. The objectives of bylaws are outlined, including disciplined growth, safety from hazards, efficient use of space, and occupant comfort. Specific bylaws like building frontage, open spaces, height limits are described. Design loads including dead, live, wind, snow, and earthquake loads are defined. Foundation types and superstructure components like columns, beams, floors, walls and roofs are also summarized.
The NTU Learning Hub in Singapore features an iconic architectural design of 12 pods containing 56 classrooms. UK designer Thomas Heatherwick conceived of the building, which features curved columns that grow outward as the building rises over eight stories. Engineering challenges included designing for stability with the irregular column angles. The structural engineer, T.Y. Lin International, developed an open column frame system using reinforced concrete and steel. Pigmented concrete was used in the structural elements for the first time in Singapore to achieve the desired architectural look.
The document provides an overview of structural analysis and different structural systems used in architecture. It begins with a brief history of structural development from prehistoric times through modern steel structures. It then defines key structural concepts and requirements. The main structural systems discussed are wall-slab, post-lintel, and post-slab structures. Details are given on structural elements, load transfer methods, and case studies for each system. Advantages and disadvantages of wall-slab structures are also summarized.
The document provides a report from a site visit by a student to an ongoing construction project of 2-3 storey terrace houses. It includes an introduction to the project, objectives of the site visit, observations of construction materials and methods in use including piles, beams, columns, slabs and brickwork. Photos further describe the various components and construction stages witnessed. The student concludes it was a valuable learning experience that enhanced understanding of practical construction processes.
This document describes a 4-storey reinforced concrete test building with unreinforced masonry infill walls that will be used to test different seismic retrofit schemes. An analysis found the building has weak columns that are susceptible to sidesway collapse. The masonry infill provides much more shear strength than the bare concrete frame but at a smaller drift. Three retrofit schemes are proposed: 1) Replace masonry with damped bracing, 2) Jacket columns and some masonry with composite material to improve ductility, 3) Strengthen columns and add steel bracing. The effectiveness of each scheme will be tested using full-scale dynamic tests.
Behaviour of reinforced concrete frame with in fill walls under seismic loads...IAEME Publication
This document summarizes a study on the behavior of reinforced concrete frames with masonry infill walls under seismic loads. Five models of a 10-story reinforced concrete building were analyzed using ETABS software: a bare frame, a fully infilled frame, and frames with different infill wall configurations. The results show that infill walls increase the lateral stiffness and strength of the frame, reducing displacements and member forces. However, openings in infill walls decrease stiffness. A higher Young's modulus for the infill material further increases stiffness. The analysis provides insights into how the structural response is affected by infill wall properties.
first i need cover page and introductuon table of content and refrneces answer all questions
Instructions:
Engineering Essay on Construction Technology
Harvard Citation Style
10 pages
7 Sources
The document discusses refurbishment of buildings, describing it as altering an existing building to improve facilities and rearrange internal areas without changing the original function. It defines three types of refurbishment - minor, medium, and major - and provides details about their purposes, durations, and scope of works. It then discusses stages of refurbishment including building investigation and recommendations. The document concludes with a case study on the restoration and refurbishment of the Old City Hall in Penang, Malaysia, outlining defects addressed, work undertaken, and challenges overcome in the project.
A short and elaborate Case Study on Metropol Parasol located at Seville (Spain) for the course of Urban Design from students of 7th Semester Architecture at VNIT, Nagpur (August- December 2016)
The document provides details about the proposed Learning Centre for All project in Klang, Malaysia. It includes an introduction to the site context and existing conditions on Jalan Besar. Plans and drawings at 1:100 scale are presented for the ground, first, second, and third floors. Precedent studies are analyzed for a masonry screen facade, corrugated metal cladding facade, and structural steel system. These precedents provide advantages and disadvantages as well as lessons that can be applied to the design of the Learning Centre.
This document outlines an assignment for a construction solutions project for a Sentul community library. It includes building plans, precedent studies on façade, roof, and structure materials and systems. For the façade, two precedent studies are examined: a documentation center in Germany with a corten steel skin, and a house in Vietnam with precast concrete pattern blocks. A cultural center in Azerbaijan with a GFRP space frame roof system is analyzed. Two structure precedent studies look at a composite steel deck floor system and cold-formed steel framing. Detailed sectional perspectives and references are also provided.
The project "Brick-topia" was a thin-tile vaulted pavilion built with traditional construction techniques and computational design tools. It had a budget of 3000 euros and only 7 weeks to design, plan construction, and build. The pavilion used traditional Catalan vaulting techniques with thin bricks for the first layer laid without centering. Computational form-finding and structural analysis were used to design the free-form vaulted shape. Construction involved developing a novel lightweight falsework system using scaffolding, cardboard, wire and steel rods to support the vault during construction without exceeding the tight budget and schedule.
Seismic Analysis on Bare Frame, Infilled Frame and Soft Story RC Framed Build...IRJET Journal
This document analyzes the seismic behavior of reinforced concrete (RC) framed buildings with different configurations through computer modeling and simulation. It compares the seismic performance of a bare frame building, an infilled frame building where the spaces between columns and beams are filled with masonry, a building with an open ground floor ("soft story"), and a building with open ground and first floors. The analysis found that the infilled frame performed best, with the highest base shear, natural frequency, and lowest story drift and time period. The bare frame performed worst. The soft story and two-story open configurations performed better than the bare frame but worse than the infilled frame. Infilled frames are therefore most effective at resisting earthquake forces compared to other
Building Technology I : Project 2 : Construction SolutionsJing Fan Koh
This document provides an overview of a project proposal for a performing arts centre in Kajang Old Town, Malaysia. It includes an introduction to the site context and design brief. Precedent studies are presented on the structural system of steel frame, composite floor system, and metal deck roof with mineral wool. Details are given on the materials and construction processes for each system. The intention of the design is to encourage users to engage with the historical and cultural context of the area through the building and public spaces.
This document provides details on the design of a community library project in Medan Pasar, Kuala Lumpur. It includes precedent studies on roof, facade, and structural systems to inform the design. Two facade design schemes are presented - a kinetic aluminium plate facade and a perforated masonry wall. Sectional perspectives of the roof and ground levels illustrate construction details.
This document outlines the details of a course on Advanced Construction Technology. The course aims to teach students the latest construction techniques applied to substructure and superstructure. It covers 6 modules that will provide knowledge on techniques like box jacking, pipe jacking, ground improvement methods, dredging systems, and rehabilitation/strengthening techniques. On completing the course, students will gain expertise in evaluating construction procedures, understanding various construction stages, and applying new construction technologies to special structures.
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...ijtsrd
The use of geo textiles in MSE walls started after the beneficial effect of reinforcement with geo textiles was noticed in highway embankments over weak sub grades. The first geo textile reinforced wall was constructed in France in 1971, and the first structure of this type in the United States was constructed in 1974. Since about 1980, the use of geo textiles in reinforced soil has increased significantly. The first wall to use this technology in the United States was built in 1972 on California State Highway 39, north east of Los Angeles. In the last 25 years, more than 23,000 Reinforced Earth structures representing over 70 million m2 750 million ft2 of wall facing have been completed in 37 countries. More than 8,000 walls have been built in the United States since 1972. The highest wall constructed in the United States was of height 30 meters 98 feet Sami Raj Sahu | Deeksha Shrotriya | Abhay Kumar Jha "Study of Reinforced Retaining Wall Over Predictable Considering Different Heights" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-6 , October 2021, URL: https://www.ijtsrd.com/papers/ijtsrd47578.pdf Paper URL : https://www.ijtsrd.com/engineering/civil-engineering/47578/study-of-reinforced-retaining-wall-over-predictable-considering-different-heights/sami-raj-sahu
The document summarizes the structural design experience of reinforced concrete tall buildings designed by Dar Al-Handasah Consultants over the past 12 years. It discusses key aspects of structural design including:
1) The buildings ranged in height from 80m to 590m and consisted of foundations, basements, podiums, towers, and tower tops, primarily constructed of reinforced concrete.
2) A relationship between required concrete volume and number of floors (Dar's Formula) is presented to estimate concrete needs based on height.
3) Comparisons are made between reinforced concrete and steel tall buildings, finding that concrete buildings are less sensitive to increases in height.
4) Long-term differential shortening,
This document summarizes the structural design experience of reinforced concrete tall buildings designed by Dar Al-Handasah Consultants over the past 12 years. It discusses how developments in concrete technology over the 20th century enabled increasingly taller buildings, like the Petronas Towers and Burj Dubai. The document outlines key features of the 45 mixed-use towers designed by Dar Al-Handasah, which range from 80-590 meters tall. It establishes a relationship between required concrete volume and number of floors, and proposes a formula to estimate total construction cost based on height. Lessons learned from structural modeling and monitoring of these tall buildings are also reviewed.
1. Structures in Kobe built since 1981 that were designed to strict seismic codes mostly withstood the 1995 Kobe earthquake, while newly built ductile-frame high-rise buildings were generally undamaged.
2. Modern earthquake engineering aims to create earthquake-resistant designs and construction techniques to build all types of structures, using state-of-the-art technology, materials science, and testing.
3. Key strategies for earthquake-resistant design include base isolation, increasing damping, and using devices like viscous and friction dampers to absorb seismic energy.
Similar to Strengthening and Reconstruction of the Hugo Treffner Gymnasium building in Tartu, Estonia (20)
Applications of artificial Intelligence in Mechanical Engineering.pdfAtif Razi
Historically, mechanical engineering has relied heavily on human expertise and empirical methods to solve complex problems. With the introduction of computer-aided design (CAD) and finite element analysis (FEA), the field took its first steps towards digitization. These tools allowed engineers to simulate and analyze mechanical systems with greater accuracy and efficiency. However, the sheer volume of data generated by modern engineering systems and the increasing complexity of these systems have necessitated more advanced analytical tools, paving the way for AI.
AI offers the capability to process vast amounts of data, identify patterns, and make predictions with a level of speed and accuracy unattainable by traditional methods. This has profound implications for mechanical engineering, enabling more efficient design processes, predictive maintenance strategies, and optimized manufacturing operations. AI-driven tools can learn from historical data, adapt to new information, and continuously improve their performance, making them invaluable in tackling the multifaceted challenges of modern mechanical engineering.
artificial intelligence and data science contents.pptxGauravCar
What is artificial intelligence? Artificial intelligence is the ability of a computer or computer-controlled robot to perform tasks that are commonly associated with the intellectual processes characteristic of humans, such as the ability to reason.
› ...
Artificial intelligence (AI) | Definitio
Software Engineering and Project Management - Introduction, Modeling Concepts...Prakhyath Rai
Introduction, Modeling Concepts and Class Modeling: What is Object orientation? What is OO development? OO Themes; Evidence for usefulness of OO development; OO modeling history. Modeling
as Design technique: Modeling, abstraction, The Three models. Class Modeling: Object and Class Concept, Link and associations concepts, Generalization and Inheritance, A sample class model, Navigation of class models, and UML diagrams
Building the Analysis Models: Requirement Analysis, Analysis Model Approaches, Data modeling Concepts, Object Oriented Analysis, Scenario-Based Modeling, Flow-Oriented Modeling, class Based Modeling, Creating a Behavioral Model.
Null Bangalore | Pentesters Approach to AWS IAMDivyanshu
#Abstract:
- Learn more about the real-world methods for auditing AWS IAM (Identity and Access Management) as a pentester. So let us proceed with a brief discussion of IAM as well as some typical misconfigurations and their potential exploits in order to reinforce the understanding of IAM security best practices.
- Gain actionable insights into AWS IAM policies and roles, using hands on approach.
#Prerequisites:
- Basic understanding of AWS services and architecture
- Familiarity with cloud security concepts
- Experience using the AWS Management Console or AWS CLI.
- For hands on lab create account on [killercoda.com](https://killercoda.com/cloudsecurity-scenario/)
# Scenario Covered:
- Basics of IAM in AWS
- Implementing IAM Policies with Least Privilege to Manage S3 Bucket
- Objective: Create an S3 bucket with least privilege IAM policy and validate access.
- Steps:
- Create S3 bucket.
- Attach least privilege policy to IAM user.
- Validate access.
- Exploiting IAM PassRole Misconfiguration
-Allows a user to pass a specific IAM role to an AWS service (ec2), typically used for service access delegation. Then exploit PassRole Misconfiguration granting unauthorized access to sensitive resources.
- Objective: Demonstrate how a PassRole misconfiguration can grant unauthorized access.
- Steps:
- Allow user to pass IAM role to EC2.
- Exploit misconfiguration for unauthorized access.
- Access sensitive resources.
- Exploiting IAM AssumeRole Misconfiguration with Overly Permissive Role
- An overly permissive IAM role configuration can lead to privilege escalation by creating a role with administrative privileges and allow a user to assume this role.
- Objective: Show how overly permissive IAM roles can lead to privilege escalation.
- Steps:
- Create role with administrative privileges.
- Allow user to assume the role.
- Perform administrative actions.
- Differentiation between PassRole vs AssumeRole
Try at [killercoda.com](https://killercoda.com/cloudsecurity-scenario/)
Batteries -Introduction – Types of Batteries – discharging and charging of battery - characteristics of battery –battery rating- various tests on battery- – Primary battery: silver button cell- Secondary battery :Ni-Cd battery-modern battery: lithium ion battery-maintenance of batteries-choices of batteries for electric vehicle applications.
Fuel Cells: Introduction- importance and classification of fuel cells - description, principle, components, applications of fuel cells: H2-O2 fuel cell, alkaline fuel cell, molten carbonate fuel cell and direct methanol fuel cells.
Comparative analysis between traditional aquaponics and reconstructed aquapon...bijceesjournal
The aquaponic system of planting is a method that does not require soil usage. It is a method that only needs water, fish, lava rocks (a substitute for soil), and plants. Aquaponic systems are sustainable and environmentally friendly. Its use not only helps to plant in small spaces but also helps reduce artificial chemical use and minimizes excess water use, as aquaponics consumes 90% less water than soil-based gardening. The study applied a descriptive and experimental design to assess and compare conventional and reconstructed aquaponic methods for reproducing tomatoes. The researchers created an observation checklist to determine the significant factors of the study. The study aims to determine the significant difference between traditional aquaponics and reconstructed aquaponics systems propagating tomatoes in terms of height, weight, girth, and number of fruits. The reconstructed aquaponics system’s higher growth yield results in a much more nourished crop than the traditional aquaponics system. It is superior in its number of fruits, height, weight, and girth measurement. Moreover, the reconstructed aquaponics system is proven to eliminate all the hindrances present in the traditional aquaponics system, which are overcrowding of fish, algae growth, pest problems, contaminated water, and dead fish.
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...IJECEIAES
Medical image analysis has witnessed significant advancements with deep learning techniques. In the domain of brain tumor segmentation, the ability to
precisely delineate tumor boundaries from magnetic resonance imaging (MRI)
scans holds profound implications for diagnosis. This study presents an ensemble convolutional neural network (CNN) with transfer learning, integrating
the state-of-the-art Deeplabv3+ architecture with the ResNet18 backbone. The
model is rigorously trained and evaluated, exhibiting remarkable performance
metrics, including an impressive global accuracy of 99.286%, a high-class accuracy of 82.191%, a mean intersection over union (IoU) of 79.900%, a weighted
IoU of 98.620%, and a Boundary F1 (BF) score of 83.303%. Notably, a detailed comparative analysis with existing methods showcases the superiority of
our proposed model. These findings underscore the model’s competence in precise brain tumor localization, underscoring its potential to revolutionize medical
image analysis and enhance healthcare outcomes. This research paves the way
for future exploration and optimization of advanced CNN models in medical
imaging, emphasizing addressing false positives and resource efficiency.
Strengthening and Reconstruction of the Hugo Treffner Gymnasium building in Tartu, Estonia
1. 19th IABSE Congress Stockholm, 21-23 September 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
1
Strengthening and Reconstruction of the Hugo Treffner Gymnasium
building in Tartu, Estonia
Kari Avellan, Erika Belopotocanova
KAREG Consulting Engineers, Helsinki, Finland
Contact: kari.avellan@kareg.com
Abstract
Strengthening and reconstruction of Hugo Treffner Gymnasium building was carried out from
1994 to 1997 in four stages. The mandate of KAREG Consulting Engineers entailed designs of
temporary and permanent structures as well as development of a monitoring system and
examining the condition of the structure. The foundations on the yard side walls were placed two
meter higher than the remaining of foundations of the structure. As a consequence, the above
mentioned findings led to forming cracks and brought about the walls of the building to incline.
The project involved corner walls and interior walls stabilization, exterior walls strengthening and
a new basement area construction. A new reinforced slab was poured, designed using the yield
line theory analysis. The use of the selected strengthening options and technique for structural
intervention of the walls was found to be a suitable technique to achieve the desired objective.
Keywords: strengthening; structural intervention; stabilisation; foundations; piles; cracks;
settlement; walls; concrete slab.
1 Introduction
Hugo Treffner Gymnasium (HTG) is a secondary
school located in Tartu, Estonia with special
emphasis on science education. Founded by a
renowned scholar Hugo Treffner, it was the only
large secondary school in 19th century in Estonia
with dominantly Estonian students and no age
restrictions. During the Estonian national awakening
(1850 – 1918) the school greatly contributed to the
number of Estonian intellectuals. In November 2011
HTG became the partner school of UNESCO.
Today, HTG is a modern and comfortable
educational institution and a leading co-educational
public school for students of age 16 to 19 (Figure 1).
Figure 1. Hugo Treffner Gymnasium today.
1.1 Hugo Treffner Gymnasium building
The building has served as a school for centuries.
Founded in 1883, HTG boasts a combination of a
2. 19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
2
historic building and modern facilities in the heart
of Tartu.
In the course of extensive restoration work the
gymnasium has retained its historic aura (Figure
2). The majority of original details have been
successfully preserved, e.g. wooden ceiling beams
in the common room, or ceiling paintings in the
classroom on the street level 1.
Figure 2. HTG. Basement library and study.
Nowadays HTG building consists of four parts built
at different times. The building on Munga 12 is the
oldest part of the HTG building ensemble. It was
used as a schoolhouse since 1804, and it is
certainly one of the most eye-catching buildings in
the historical Jaani quarter of Tartu (Figure 3).
Figure 3. HTG building and Jaani Church.
The house by Rüütli Street was specifically
renovated for the school in 1830 by architect
G.F.W. Geist. An interesting fact is that this part of
the building complex is locally known and called
“the Princess House” as in 1784 it belonged to
Hedwig E. Biron, the Princess of Courland.
2 Mandate and scope of work
Strengthening the foundations and deteriorated
walls required considerable expertise in this
project.
The leading authority in this project was the city of
Tartu, represented by Mr. H. Jogi. The work was
performed as a joint venture of Stinger As and
KAREG Consulting Engineers in four stages during;
1994 – 1995, 1995 – 1996, 1997 and in 1999
(Figure 4).
Figure 4. HTG. Project stages. Layout.
The mandate of KAREG Consulting Engineers was
for the design-build, project and technical
management. It entailed structural and
geotechnical designs of temporary and permanent
structures as well as designing a monitoring
system, undergoing geotechnical investigation of
the site and examining the condition of the
structure. The designs were implemented for the
foundation work as well as for the concrete
structures from the basement up to the first floor.
A project of such complex proportions as this
requires diligent approach and sensitive time-
3. 19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
3
management on site. It was crucial to oversee
operations on a day-to-day basis to ensure that
work is done safely, on time and to the right
quality standards. At times there were several
project stages ongoing simultaneously 2.
3 Site condition and investigation
A series of ground and site investigations was
performed by KAREG Consulting Engineers to
obtain information on the physical properties of
ground surrounding the site to design earthworks
and strengthening for the structure and for repair
of distress to earthworks and the structure caused
by subsurface conditions.
There were several unexpected findings during
the site investigation. A major revelation from the
results of the performed pit tests was the fact that
the old foundations of the house laid directly on
soil that consists mostly of silty clay and silt. The
uneven settlement of substrata was caused by the
ground water level decrease due to
industrialization.
Another important outcome of subsurface
exploration was the fact that the foundations of
the yard side walls were placed two meter higher
than the remaining of foundations of the structure
(Figure 6).
As a consequence, the above mentioned findings
led to forming cracks and brought about the walls
to incline.
For that reason, before actual foundation
strengthening could be safely initiated, stabilizing
the exterior walls by temporary shoring using
heavy timber struts needed to be performed in
order to retain and support the structural stability
of the building (Figure 5).
4 Foundations strengthening
Underpinning, as a process of strengthening
existing foundations, is chosen and done for
several purposes. In this project of stabilizing,
strengthening and reconstruction of HTG building,
underpinning was necessary for the following
reasons:
Figure 5. Shored exterior inclined wall.
To strengthen existing foundations and walls
that have suffered from cracks, deterioration,
and settlements
To deepen a part of the existing foundations
Underpinning by piling in pits was accomplished
by extending the foundations in depth so they rest
on a more supportive soil stratum.
4.1 Project overview
The selected strengthening methods were
deemed appropriate and reflected the condition
of the substructure and superstructure. Factors
such as the unstable and degrading basement
walls, uneven settlements, cracks or inclined walls
were carefully analysed and taken into
consideration.
The phases of strengthening combined different
ways and manners of using jack piles as structural
members (Figure 6).
Figure 6. Building section. Phases of project.
4. 19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
4
The project entailed the following phases and
stages: strengthening foundations by piling in pits,
corner walls and interior walls strengthening and
stabilization, exterior walls strengthening using
piles jacked through openings and cantilever steel
beams, new basement area construction using
jacked piles as soldier piles and reconstruction,
stabilization and expansion of interior premises of
the building 2.
5 Phases and stages of
strengthening, stabilization and
reconstruction of building
Preserving a structure of great historic importance
by strengthening its foundations and stabilizing
the walls requires significant expertise, know-how
and suitable selection of strengthening methods.
Due to uneven settlement of the structure and
overall fragile, understrength condition of the
degrading walls, strengthening by piling using
drilled spiral piles and jacked piles was deemed as
the most appropriate, economic, quick and least
invasive method.
Jacked piles consisted of sections of 1 m long
pipes. Every added part was spliced after the
previous part was jacked down. The piles had
closed toes and once embedded in soil they were
filled with concrete.
The first section of the drilled spiral pile was 1 m
long and had a spliced spiral = 25 mm x 10 mm.
The spiral piles were embedded into the soil by
twirling.
Each pile was pre-stressed in accordance with the
end jacking procedure. Drilled spiral piles were
used first as temporary tension piles and
afterwards as permanent compression piles.
5.1 Strengthening of foundations, corner
walls and interior walls
This stage of work consisted of excavation pits
beneath old foundations, reinstalling steel packing
plates with concrete beneath old foundations and
establishing a temporary support until the bound
was strong enough to keep the steel plate in its
position. Therefore the position of the first piling
pits was selected in the manner so that the
immediate wall over it could structurally work as
an arch.
Before digging works could start in this section of
the building, it was necessary to anchor the corner
walls of Jaani and Lübeck Street by horizontal
anchors in both directions.
That was achieved by installation of tension rods
of ø = 20 mm on each side of the corner walls in a
height about 4.5 m from the bottom end of the
old foundations.
The allowable load was 350 kN. Every pile was
pre-tested by end jacking procedure.
Strengthening of the interior walls was executed
using needle beams and two jacked piles. First,
two intersecting holes of ø = 300 mm were bored
in order to install universal beams. Afterwards,
the piles were jacked under needle beams. This
technique required two jacks working
simultaneously.
5.2 Exterior wall strengthening using piles
jacked through openings and cantilever
steel beams
This phase of the project was carried out on the
exterior wall opposite Jaani Church. The below
described method was selected as most
appropriate and economic taking into
consideration the unstable condition of the wall.
Works started by boring two intersecting holes of
ø = 400 mm into the wall and erecting pre-spliced
channels with partly up and down welded steel
plates. The following step was to pour and
reinforce a concrete slab of 600 mm thickness
having the channels in the concrete and living
space between the channels for jacking the piles.
The slab was designed as a two-way slab
supported by needle beams. There were four
tension rods located above the channels (4 pieces
M36 grade 8.8 threatened rods) together with a
thick steel plate. The jack above the slab was
buckled against the steel plate by the piles. The
channels were then supported by the jacked pile
working as cantilever beams loaded by the old
wall. The counterweight was then made of the old
walls and partly of the new reinforced concrete
slab (Figure 7).
5. 19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
5
Figure 7. Wall strengthening. Piles jacked through
openings.
5.2.1 Settlement measurement and values
Settlement during strengthening works was
monitored by leveling. Based on the
measurements, there was no noticeable
settlement recorded in this section of the building.
The measured settlement after strengthening
ranged between 2…4 mm. It was assumed that the
applied method of strengthening using pre-testing
and end-jacking yielded to such low settlement
values 2.
5.3 New basement area construction using
jacked piles as soldier piles
The foundations under the yard wall on axis 5
were laid 2 m higher than the other exterior walls
of the structure, therefore there was no
basement. The work was done by archeological
digging carried out in the interval manner.
Following the same principle, reinforced concrete
polings were poured 3.
Since the jacked piles used as soldier piles worked
structurally also as bended and compressed piles,
the allowable jacking force was only 250 kN per
pile.
Due to the earth pressure against the poured
polings between the soldier piles, the old wall and
some of the soldier piles had to be shored
horizontally against the old walls.
Finally, an insulated new reinforced concrete slab
was poured as a basement floor 4.
5.4 Reconstruction, stabilization and
expansion of interior premises
This phase of the project consisted of necessary
stages and steps of design, construction,
supervising and monitoring work towards making
large open areas both in the basement and on the
street level.
The process started off by safely removing partial
interior load-bearing walls in the basement. In this
area there were subsequently erected four drilled
spiral piles (1 – 4) that were embedded into the
soil by twirling (Figure 8).
Figure 8. Strengthening plan design. New
basement/open area.
The joints of the drilled spiral piles were spliced
together. Because of the lack of counterweight,
the two of the piles had first to work as tension
piles (1, 4) so that the remaining two (2, 3) could
be end-jacked. Once this process was completed,
the first set of the piles (1, 4) was end-jacked.
Finally, each of the four piles was checked by the
end-jack procedure. Only after this they were
filled with concrete.
6. 19th IABSE Congress Stockholm 2016
Challenges in Design and Construction of an Innovative and Sustainable Built Environment
6
Figure 9. Street level. Piles 1 – 4 as temporary
shoring. New R/C beams.
In the basement area, a new concrete column was
constructed around the drilled spiral piles
incorporated inside the column as compressed
bars by bound. The column was positioned in the
middle of a new slab that was designed using the
yield line analysis for slabs and virtual work.
The slab together with the exterior walls it had
the function of a load-bearing member. The slab
and the old walls were then connected by dowels.
At the end, the reminding interior load-bearing
walls were removed.
Figure 10. HTG. New open area on the street level.
In the area on the street level (first floor), the
drilled spiral piles worked also as temporary
support during the process of pouring new
concrete beams around the middle wall. At the
final stage, the interior walls and the remaining
part of the middle wall were safely removed
(Figure 9).
This phase of the project resulted into creating
two large open areas; in the basement it was
about 95 m2
(below the slab), and on the street
level the open area was around 100 m2
(above the
slab). This outcome met the request of the client
and requirements of all safety precautions.
Nowadays the areas are used as a common room
for important school events and as the auditorium
(Figure 10).
6 Conclusions
The strengthening scheme presented was an
economic and aesthetic solution to the
reconstruction of understrength foundations
and unstable walls of the building.
Time management, minimal disruptions,
precise execution was not only an economic
and effective, but also inevitable factor in
order to follow technical specifications and
technological process that would lead the
project to successful completion.
The use of the selected strengthening options
and technique for structural intervention of the
walls was found to be an appropriate
technique to achieve the desired objective and
at the same time being minimal invasive.
7 References
[1] Website. Hugo Treffneri Gümnaasium.
2016;http://www.htg.tartu.ee/.
[2] Avellan K., KAREG Consulting Engineers.
Internal archive. Helsinki: Finland; 1994-
1999.
[3] Ympäristöministeriö. Betonikrakenteen B4.
Ohjeet.Suomenrakentamismääräyskokoelm
a (Ministry of Environment, Concrete
structures B4, Guidelines. The National
Building Code of Finland. 2005; Finland. (in
Finnish).
[4] Johansen K.W. Pladeformler. Polyteknisk
forlag. 1968; Copenhagen; Denmark (in
Danish).