SlideShare a Scribd company logo
1 of 7
STRAYER BUS 375 Final Exam Part 1 (2 Set) NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/bus-375-
strayer/bus-375-final-exam-part-1-2-set-new
For more classes visit
http://www.assignmentcloud.com
• Question 1 Most of the scheduling methods
available today require the project manager to
classify the project as either _______ constrained or
______ constrained.
• Question 2 In reviewing the status of her project
with top management, Shirley was told that there
are only two programmers that she can use for her
project. Her project is classified as __________
constrained.
• Question 3 Gene is trying to order the concrete
needed to continue his project. However, the
supplier will not be able to deliver it until next
week. This is an example of what kind of resource
constraint?
• Question 4 Resources are adequate, but demand
varies widely over the life of the project. Delaying
noncritical activities to lower peak demand on
resources is known as resource
• Question 5 All resource leveling techniques
involve
• Question 6 When a company will reduce the
number of projects they have to manage internally
to only core projects and send noncritical projects
to contractors and consulting firms this is called
• Question 7 Tony has realized that two activities
in his project cannot be done at the same time
because not enough resources are available.
Activity 3 is critical and has a duration of 5 days.
Activity 4 has 2 days of slack and a duration of 2
days. How will he decide which activity should be
scheduled first?
• Question 8 Which of the following is NOT a
potential consequence of failing to identify limited
resources before project implementation?
• Question 9 In a Project Cost-Duration Graph,
total project costs are a sum of
• Question 1 0 The direct cost for completing an
activity in the shortest time it can realistically be
completed in is called its __________ cost.
• Question 11 Which of the following projects
would be least benefited if additional resources
were added?
• Question 12 It is going to cost $80,000 a day
simply to house and feed a construction crew in
the farthest reaches of northern Alaska. This
would be an example of a situation requiring
reducing the project duration due to
• Question 13 Which of the following is NOT
considered a project indirect cost?
• Question 14 When reducing project duration, the
duration for a project that is optimal is at the point
where
• Question 15 Before crashing, direct costs for an
activity represent normal costs, which typically
mean low-cost, efficient methods for completing
the activity in a(n) ________ amount of time.
• Question 16 The shortest possible time an
activity can be completed realistically is called
___¬¬¬_____ time.
• Question 17 The attempt to recognize and
manage potential and unforeseen trouble spots
that may occur when a project is implemented is
known as
• Question 18 The cost impact of a risk event
occurring as a project proceeds through its life
cycle tends to
• Question 19 An uncertain event or condition
that, if it occurs, has a positive or negative effect on
project objectives is termed a
• Question 20 Organizations use __________ in
conjunction with work breakdown structures to
help management teams identify and eventually
analyze risk.
• Question 21 Which of the following is NOT one of
the steps in the risk management process?
• Question 22 The risk management tool that is
divided into three color-coded zones representing
major, moderate, and minor risks is the risk
• Question 23 _______________ focuses on how to
respond to events that have a positive impact on a
project.
• Question 24 Risks that can result in a system or
process that will not work are known as
• Question 25 Tools such as a risk assessment
form and a risk severity matrix are used to
Set 2
• Question 1 Ed is looking over the actual results
of projects and comparing them to what was
estimated. He notices that the projects that took
six months or longer to complete were noticeably
more off the estimates. Which of the following
factors is he recognizing?
• Question 2 The salary of the project manager
would be an example of what type of cost found in
a project?
• Question 3 Which of the following does NOT help
describe a bottom-up estimating approach?
• Question 4 Which of the following would best
represent direct project costs?
• Question 5 Accounting would be an example of
which of the following costs typically found in a
project?
• Question 6 Which of the following is a good
condition for top-down estimating?
• Question 7 Which of the following methods is
NOT considered a top-down approach to
estimating project time and cost?
• Question 8 Which of the following top-down
methods is used when projects closely follow past
projects in regard to features and costs of those
features, and result in costs being assigned by
percentages to major segments of the project?
• Question 9 What is the relationship between
organizational culture and estimating?
• Question 10 Refining estimates may be
necessary for a number of reasons. For example,
people working on prototype development
needing time to interact with the design engineers
after the design is completed is a good example of
• Question 11 Which of the following describes the
consensus method?
• Question 12 Rob is responsible for estimating a
work package that has a significant amount of
uncertainty associated with the time and cost to
complete. Due to the uncertainty involved he will
be making a low, an average and a high estimate.
Rob is using which estimating approach?
• Question 13 Companies are using which of the
following for improving the estimating process for
future projects?
• Question 14 Tom is responsible for ordering
hardware for a custom home his company is
building. The contractor installing the hardware is
scheduled to start in 5 working days, but the
hardware is on backorder and will not arrive for
another 9 working days. Fortunately, Tom has 10
days of slack; however, he shares this slack with
the hardware installer. He will have to let the
contactor know that the hardware will be ready 4
days later than expected and that the slack for the
installer has been reduced by 4 days. Tom and the
installer share 10 days of
• Question 15 Which of the following correctly
calculates the late start for an activity?
• Question 16 System documentation cannot end
until three days after testing has started. This is an
example of which kind of lag?
• Question 17 If testing cannot be completed any
earlier than four days after the prototype has been
built, what type of lag exists?
• Question 18 Which of the following does NOT
help describe a project network?
• Question 19 Information to develop a project
network is collected from the
• Question 20 ________ activities are to be completed
immediately following a particular activity.
• Question 21 A(n) _________ activity has more than
one dependency arrow flowing from it.
• Question 22 The likelihood the original critical
path(s) will change once the project is initiated is
referred to as
• Question 23 A sequence of connected, dependent
activities is termed a(n)
• Question 24 The critical path in a project
network is the
• Question 25 Which of the following correctly
calculates the early finish for an activity?

More Related Content

What's hot

PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360Artonline Home
 
175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questionsNazakat Hussain
 
Risk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansRisk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansMohamed Saeed
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansMohamed Saeed
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answersMohamed Saeed
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkD10iT
 
Project Recovery
Project RecoveryProject Recovery
Project Recoverytrethard
 
Risk 4 simplelearn-exam3-ans
Risk 4 simplelearn-exam3-ansRisk 4 simplelearn-exam3-ans
Risk 4 simplelearn-exam3-ansMohamed Saeed
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and consPragnendra Rahevar
 

What's hot (16)

PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questions
 
Risk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansRisk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ans
 
Pmp full mock test – 200 questions
Pmp full mock test – 200 questionsPmp full mock test – 200 questions
Pmp full mock test – 200 questions
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ans
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
Project Recovery
Project RecoveryProject Recovery
Project Recovery
 
Risk 4 simplelearn-exam3-ans
Risk 4 simplelearn-exam3-ansRisk 4 simplelearn-exam3-ans
Risk 4 simplelearn-exam3-ans
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmp test 04
Pmp test 04Pmp test 04
Pmp test 04
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 

Similar to Strayer bus 375 final exam part 1

Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2eyavagal
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2nikig6806
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2eyavagal
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2eyavagal
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1nikig6806
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1eyavagal
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1eyavagal
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareSong Love
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsHomework Help Online
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsHomework Help Online
 
Liberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyLiberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyMatt Smith
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxIRESH3
 
Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studiesmeritweb
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
req engg (1).ppt
req engg (1).pptreq engg (1).ppt
req engg (1).pptWaniHBisen
 

Similar to Strayer bus 375 final exam part 1 (20)

Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
 
Bus 517 midterm
Bus 517 midtermBus 517 midterm
Bus 517 midterm
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questions
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questions
 
Bus 517 midterm exam 1 2
Bus 517 midterm exam 1 2Bus 517 midterm exam 1 2
Bus 517 midterm exam 1 2
 
Liberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyLiberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers key
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
Training presentation .pptx
Training presentation .pptxTraining presentation .pptx
Training presentation .pptx
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
 
Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
req engg (1).ppt
req engg (1).pptreq engg (1).ppt
req engg (1).ppt
 
15 Free PMP Exam Questions
15 Free PMP Exam Questions15 Free PMP Exam Questions
15 Free PMP Exam Questions
 

More from aaronabrahhaam

Ash edu 673 week 3 dq 2 new
Ash edu 673 week 3 dq 2 newAsh edu 673 week 3 dq 2 new
Ash edu 673 week 3 dq 2 newaaronabrahhaam
 
Ash edu 673 week 3 dq 1 new
Ash edu 673 week 3 dq 1 newAsh edu 673 week 3 dq 1 new
Ash edu 673 week 3 dq 1 newaaronabrahhaam
 
Ash edu 673 week 3 ccss
Ash edu 673 week 3 ccssAsh edu 673 week 3 ccss
Ash edu 673 week 3 ccssaaronabrahhaam
 
Ash edu 673 week 2 dq 1 new
Ash edu 673 week 2 dq 1 newAsh edu 673 week 2 dq 1 new
Ash edu 673 week 2 dq 1 newaaronabrahhaam
 
Ash edu 673 week 1 dq 1 new
Ash edu 673 week 1 dq 1 newAsh edu 673 week 1 dq 1 new
Ash edu 673 week 1 dq 1 newaaronabrahhaam
 
Stayer cis 513 week 10 term paper wireless deployment plan new
Stayer cis 513 week 10 term paper wireless deployment plan newStayer cis 513 week 10 term paper wireless deployment plan new
Stayer cis 513 week 10 term paper wireless deployment plan newaaronabrahhaam
 
Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...
Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...
Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...aaronabrahhaam
 
V grand canyon university nrs 429 v week 5 assignment clc new
V grand canyon university nrs 429 v week 5 assignment clc newV grand canyon university nrs 429 v week 5 assignment clc new
V grand canyon university nrs 429 v week 5 assignment clc newaaronabrahhaam
 
V grand canyon university nrs 429 v week 2 assignment health promotion among ...
V grand canyon university nrs 429 v week 2 assignment health promotion among ...V grand canyon university nrs 429 v week 2 assignment health promotion among ...
V grand canyon university nrs 429 v week 2 assignment health promotion among ...aaronabrahhaam
 
Strayer cis 517 week 9 assignment 6 voip part 4
Strayer cis 517 week 9 assignment 6 voip part 4Strayer cis 517 week 9 assignment 6 voip part 4
Strayer cis 517 week 9 assignment 6 voip part 4aaronabrahhaam
 
Strayer cis 517 week 6 assignment 4 voip part 2
Strayer cis 517 week 6 assignment 4 voip part 2Strayer cis 517 week 6 assignment 4 voip part 2
Strayer cis 517 week 6 assignment 4 voip part 2aaronabrahhaam
 
Devry acct 505 week 6 quiz segment reporting and relevant costs for decisions
Devry acct 505 week 6 quiz segment reporting and relevant costs for decisionsDevry acct 505 week 6 quiz segment reporting and relevant costs for decisions
Devry acct 505 week 6 quiz segment reporting and relevant costs for decisionsaaronabrahhaam
 
Devry acct 505 week 2 case 3
Devry acct 505 week 2 case 3Devry acct 505 week 2 case 3
Devry acct 505 week 2 case 3aaronabrahhaam
 
Devry psyc 110 final exam new
Devry psyc 110 final exam newDevry psyc 110 final exam new
Devry psyc 110 final exam newaaronabrahhaam
 
V grand canyon university nrs 440 v week 3 reflection paper new
V grand canyon university nrs 440 v week 3 reflection paper newV grand canyon university nrs 440 v week 3 reflection paper new
V grand canyon university nrs 440 v week 3 reflection paper newaaronabrahhaam
 
Strayer cis 375 week 2 assignment 1 multi
Strayer cis 375 week 2 assignment 1 multiStrayer cis 375 week 2 assignment 1 multi
Strayer cis 375 week 2 assignment 1 multiaaronabrahhaam
 
Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...
Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...
Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...aaronabrahhaam
 
Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...
Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...
Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...aaronabrahhaam
 
Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...
Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...
Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...aaronabrahhaam
 
Strayer pad 505 assignment 3 presenting the budget new
Strayer pad 505 assignment 3 presenting the budget newStrayer pad 505 assignment 3 presenting the budget new
Strayer pad 505 assignment 3 presenting the budget newaaronabrahhaam
 

More from aaronabrahhaam (20)

Ash edu 673 week 3 dq 2 new
Ash edu 673 week 3 dq 2 newAsh edu 673 week 3 dq 2 new
Ash edu 673 week 3 dq 2 new
 
Ash edu 673 week 3 dq 1 new
Ash edu 673 week 3 dq 1 newAsh edu 673 week 3 dq 1 new
Ash edu 673 week 3 dq 1 new
 
Ash edu 673 week 3 ccss
Ash edu 673 week 3 ccssAsh edu 673 week 3 ccss
Ash edu 673 week 3 ccss
 
Ash edu 673 week 2 dq 1 new
Ash edu 673 week 2 dq 1 newAsh edu 673 week 2 dq 1 new
Ash edu 673 week 2 dq 1 new
 
Ash edu 673 week 1 dq 1 new
Ash edu 673 week 1 dq 1 newAsh edu 673 week 1 dq 1 new
Ash edu 673 week 1 dq 1 new
 
Stayer cis 513 week 10 term paper wireless deployment plan new
Stayer cis 513 week 10 term paper wireless deployment plan newStayer cis 513 week 10 term paper wireless deployment plan new
Stayer cis 513 week 10 term paper wireless deployment plan new
 
Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...
Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...
Stayer cis 513 week 7 case study 2 security in bluetooth and other mobile dev...
 
V grand canyon university nrs 429 v week 5 assignment clc new
V grand canyon university nrs 429 v week 5 assignment clc newV grand canyon university nrs 429 v week 5 assignment clc new
V grand canyon university nrs 429 v week 5 assignment clc new
 
V grand canyon university nrs 429 v week 2 assignment health promotion among ...
V grand canyon university nrs 429 v week 2 assignment health promotion among ...V grand canyon university nrs 429 v week 2 assignment health promotion among ...
V grand canyon university nrs 429 v week 2 assignment health promotion among ...
 
Strayer cis 517 week 9 assignment 6 voip part 4
Strayer cis 517 week 9 assignment 6 voip part 4Strayer cis 517 week 9 assignment 6 voip part 4
Strayer cis 517 week 9 assignment 6 voip part 4
 
Strayer cis 517 week 6 assignment 4 voip part 2
Strayer cis 517 week 6 assignment 4 voip part 2Strayer cis 517 week 6 assignment 4 voip part 2
Strayer cis 517 week 6 assignment 4 voip part 2
 
Devry acct 505 week 6 quiz segment reporting and relevant costs for decisions
Devry acct 505 week 6 quiz segment reporting and relevant costs for decisionsDevry acct 505 week 6 quiz segment reporting and relevant costs for decisions
Devry acct 505 week 6 quiz segment reporting and relevant costs for decisions
 
Devry acct 505 week 2 case 3
Devry acct 505 week 2 case 3Devry acct 505 week 2 case 3
Devry acct 505 week 2 case 3
 
Devry psyc 110 final exam new
Devry psyc 110 final exam newDevry psyc 110 final exam new
Devry psyc 110 final exam new
 
V grand canyon university nrs 440 v week 3 reflection paper new
V grand canyon university nrs 440 v week 3 reflection paper newV grand canyon university nrs 440 v week 3 reflection paper new
V grand canyon university nrs 440 v week 3 reflection paper new
 
Strayer cis 375 week 2 assignment 1 multi
Strayer cis 375 week 2 assignment 1 multiStrayer cis 375 week 2 assignment 1 multi
Strayer cis 375 week 2 assignment 1 multi
 
Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...
Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...
Strayer hrm 562 week 8 assignment 2 proposal for organizational learning issu...
 
Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...
Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...
Strayer hrm 562 week 3 assignment 1 identifying the organizational learning i...
 
Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...
Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...
Chamberlain college of nursing nr 602 week 1 case study discussion initial vi...
 
Strayer pad 505 assignment 3 presenting the budget new
Strayer pad 505 assignment 3 presenting the budget newStrayer pad 505 assignment 3 presenting the budget new
Strayer pad 505 assignment 3 presenting the budget new
 

Recently uploaded

How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 

Recently uploaded (20)

Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 

Strayer bus 375 final exam part 1

  • 1. STRAYER BUS 375 Final Exam Part 1 (2 Set) NEW Check this A+ tutorial guideline at http://www.assignmentcloud.com/bus-375- strayer/bus-375-final-exam-part-1-2-set-new For more classes visit http://www.assignmentcloud.com • Question 1 Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained. • Question 2 In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project. Her project is classified as __________ constrained. • Question 3 Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint? • Question 4 Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on
  • 2. resources is known as resource • Question 5 All resource leveling techniques involve • Question 6 When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called • Question 7 Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first? • Question 8 Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation? • Question 9 In a Project Cost-Duration Graph, total project costs are a sum of • Question 1 0 The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost. • Question 11 Which of the following projects would be least benefited if additional resources were added? • Question 12 It is going to cost $80,000 a day simply to house and feed a construction crew in
  • 3. the farthest reaches of northern Alaska. This would be an example of a situation requiring reducing the project duration due to • Question 13 Which of the following is NOT considered a project indirect cost? • Question 14 When reducing project duration, the duration for a project that is optimal is at the point where • Question 15 Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time. • Question 16 The shortest possible time an activity can be completed realistically is called ___¬¬¬_____ time. • Question 17 The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as • Question 18 The cost impact of a risk event occurring as a project proceeds through its life cycle tends to • Question 19 An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a • Question 20 Organizations use __________ in conjunction with work breakdown structures to
  • 4. help management teams identify and eventually analyze risk. • Question 21 Which of the following is NOT one of the steps in the risk management process? • Question 22 The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk • Question 23 _______________ focuses on how to respond to events that have a positive impact on a project. • Question 24 Risks that can result in a system or process that will not work are known as • Question 25 Tools such as a risk assessment form and a risk severity matrix are used to Set 2 • Question 1 Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing? • Question 2 The salary of the project manager would be an example of what type of cost found in a project? • Question 3 Which of the following does NOT help describe a bottom-up estimating approach?
  • 5. • Question 4 Which of the following would best represent direct project costs? • Question 5 Accounting would be an example of which of the following costs typically found in a project? • Question 6 Which of the following is a good condition for top-down estimating? • Question 7 Which of the following methods is NOT considered a top-down approach to estimating project time and cost? • Question 8 Which of the following top-down methods is used when projects closely follow past projects in regard to features and costs of those features, and result in costs being assigned by percentages to major segments of the project? • Question 9 What is the relationship between organizational culture and estimating? • Question 10 Refining estimates may be necessary for a number of reasons. For example, people working on prototype development needing time to interact with the design engineers after the design is completed is a good example of • Question 11 Which of the following describes the consensus method? • Question 12 Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to
  • 6. complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach? • Question 13 Companies are using which of the following for improving the estimating process for future projects? • Question 14 Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of • Question 15 Which of the following correctly calculates the late start for an activity? • Question 16 System documentation cannot end until three days after testing has started. This is an example of which kind of lag? • Question 17 If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists? • Question 18 Which of the following does NOT
  • 7. help describe a project network? • Question 19 Information to develop a project network is collected from the • Question 20 ________ activities are to be completed immediately following a particular activity. • Question 21 A(n) _________ activity has more than one dependency arrow flowing from it. • Question 22 The likelihood the original critical path(s) will change once the project is initiated is referred to as • Question 23 A sequence of connected, dependent activities is termed a(n) • Question 24 The critical path in a project network is the • Question 25 Which of the following correctly calculates the early finish for an activity?