SITE MONITORING PROJECT
BCIT- ARCHITECTURAL AND BUILDIN TECHNOLOGY
BLDC 1050 – MATERIALS AND METHOD 1
PRESENTED TO: RAY WANG
PREPARED BY: ANTONELLA GENNUSA
STUDENT ID: A00991847
2
TABLE OF CONTENT
Project Summary…………………………………………………………………………………………………………………………… 3
Construction Site Plan…………………………………………………………………………………………………………………. 4
Project Description………………………………………………………………………………………………………………………. 5
SITE VISIT REPORT
Site Visit Report #1: Date: September 15/2016……………………………………………………………………..6
Site Visit Report #2: Date
Site Visit Report #3: Date
Site visit Report #4: Date
LIST OF FIGURES & ILLUSTRATIONS
SVR Photo 1.1: Photo from main entry to the site, hoarding and parking area in evidence..7
SVR Photo 1.2: Excavators during the site preparation works…………………………………………………..7
SVR Photo 1.3: Chute from truck and piles of gravel during the site preparation works……..7
SVR Photo 1.4: Protection of excavation wall, soil nail are drilled trough mesh face into the
earth……………………………………………………………………………………………………………………………………………………7
SVR Photo 2.1: Photo from above, shows cement and other materials…………………………….…….9
SVR Photo 2.3: Excavator at work, puddles of water in most of the site…………………………………9
SVR Photo 2.4: New bituminous asphalt in the parking vehicles…………………………………………..…9
SVR Photo 3.1: workers installing reinforcing steel ……………………………………………………………….11
SVR Photo 3.2: equipment on site…………………………………………………………………………………………….…11
SVR Photo 4.1: tower crane ………………………………………………………………………………………………….…..….13
SVR Photo 4.2: foundation details, dowel and concrete in foundation wall……………….….……13
SVR Photo 4.3: Concrete bucket …………………………………………………………………………………………….……13
3
PROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARY
PROJECT NAME:PROJECT NAME:PROJECT NAME:PROJECT NAME: Escala
SSSSUMMARYUMMARYUMMARYUMMARY:::: Escala Luxury is a huge complex featuring a 42 storey high-rise building whit
359 homes, and 4 storey low-rise building with 151 homes. Located in Brentwood,
neighborhood of Burnaby. This development has 520 total unit and over 15.000 square
feet of amenities. The site for Escala will be located at the corner of Gilmore Ave and
Douglas Road by Gilmore Station. Nearby parks include Wililngdon Heights Park.
START DAY:START DAY:START DAY:START DAY: Summer 2016
ESTIMATED COMPLETIONESTIMATED COMPLETIONESTIMATED COMPLETIONESTIMATED COMPLETION:::: Spring 2019
DEVELOPER:DEVELOPER:DEVELOPER:DEVELOPER: LM Escala Homes LP
LAWYERLAWYERLAWYERLAWYERSSSS:::: Terra Law Corporation
MARKETING & SALES MANAGERS:MARKETING & SALES MANAGERS:MARKETING & SALES MANAGERS:MARKETING & SALES MANAGERS: Escala Brentwood
CONSULTANT:CONSULTANT:CONSULTANT:CONSULTANT:
ARCHITECT:ARCHITECT:ARCHITECT:ARCHITECT: IBI Group Architects & Integra Architecture
DESIGNER:DESIGNER:DESIGNER:DESIGNER: The Mill
GENERAL CONTRACTOR:GENERAL CONTRACTOR:GENERAL CONTRACTOR:GENERAL CONTRACTOR: Ledingham McAllister
SUBCONTRACTORS INCLUDE:SUBCONTRACTORS INCLUDE:SUBCONTRACTORS INCLUDE:SUBCONTRACTORS INCLUDE:
EXCAVATINGEXCAVATINGEXCAVATINGEXCAVATING CONTRACTOR:CONTRACTOR:CONTRACTOR:CONTRACTOR: Whitewater.
FOUNDATION CONTRACTOR:FOUNDATION CONTRACTOR:FOUNDATION CONTRACTOR:FOUNDATION CONTRACTOR: Whitewater.
STEEL:STEEL:STEEL:STEEL: Dion custom
ELECTRICAL:ELECTRICAL:ELECTRICAL:ELECTRICAL: Chambers electric
4
SITE PLANSITE PLANSITE PLANSITE PLAN
N
5
PROJECT DESCRIPTIONPROJECT DESCRIPTIONPROJECT DESCRIPTIONPROJECT DESCRIPTION
Escala Luxury is a huge complex featuring a 42 storey high-rise building whit 359 homes,
and 4 storey low-rise building with 151 homes. Located in Brentwood, neighborhood of
Burnaby.
Protecting the site perimeter the area is surrounded by a high wood and metal hoarding,
many people work inside with the proper equipment (helmet, boots and jacket). There are
several workers who manage the traffic at the entrance. All the signs around the site are
properly installed.
The site has a large parking for vehicles and a long ramp to reach the hearts of the
excavation.
Storage and offices are located beside the site.
ITEMS OF WORK: gravel, structural steel, excavators, concrete, chute from truck, lumber,
garbage, signs, fence, pump.
The workers are still working on the foundations while the works for protecting the
excavation walls are complited, the new building will be finished in 2019.
6
SITE VISIT REPORTER #1SITE VISIT REPORTER #1SITE VISIT REPORTER #1SITE VISIT REPORTER #1 :::: September 15/2106 (2.50 p.m)September 15/2106 (2.50 p.m)September 15/2106 (2.50 p.m)September 15/2106 (2.50 p.m)
SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C
EXSISTING CONDITION: Sunny
SITE REPORTER: Antonella Gennusa
EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, chute from truck,
lumber, garbage, signs, fence, pump, bobcats.
DIVISION 1: GENERAL REQUIREMENTS:
As shown in the photo 1.1 the main entrance area is also parking for all vehicles, while
the secondary entrance area (on Gilmore avenue) is used for material deposit such as:
wood, steel and generators.
Offices and other deposits are located outside the site construction.
DIVISION 2_EXISTING CONDITION:
Since the first visit it can be observed that the excavation work is about to be completed
(photo 1.2) and that the excavation walls have been reinforced with soil nails similar to
soil anchors (photo 1.4) and a layer of shootcrete and mesh. The climate of these days
allows workers to work quietly.
At this stage of the work is not yet installed any cranes.
DIVISION 3_CONCRETE:
At this preliminary stage has not been set yet any formwork or reinforcing steel, workers
are still preparing and leveling the surface.
The holes of the construction site are filled with sands or concrete (photo 1.3).
DIVISION 31_EARTHWORK:
The site has been prepared for the next step.
Within the area ESC tanks have been installed. Protecting the site perimeter the area is
surrounded by a high wood and metal hoarding, all the signs around the site are properly
installed. The site has a large parking for vehicles and a long ramp to reach the hearts of
the excavation.
Protecting excavation walls soil nails have been installed and capped and after a layer of
shootcrete has been spryed.
SITE ISSUE:
The work is delyead because a small design error fortunately recovered in time.
7
PHOTO 1 .1 photo from main entry to the site, hoarding and parking area in evidence.
PHOTO 3 .2 Excavators during the site preparation
works.
PHOTO 2 .3 Chute from truck and piles of gravel
during the site preparation works
PHOTO 4 .3 Protection of excavation wall, soil nails are drilled trough
mesh face into the earth.
8
SITE VISIT REPORTER #2SITE VISIT REPORTER #2SITE VISIT REPORTER #2SITE VISIT REPORTER #2 : October 19/2106 (3.00 p.m): October 19/2106 (3.00 p.m): October 19/2106 (3.00 p.m): October 19/2106 (3.00 p.m)
SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C
EXSISTING CONDITION: Overcast
SITE REPORTER: Antonella Gennusa
EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, lumber, garbage, signs,
fence, pump, cement.
SUMMARY OF WORK SINCE PREVIOUS VISIT:
DIVISION 2/31_SITE WORK:
As shown in photo 2.3, since the first visit, the same areas are still in the excavation
process. Unlike the first visit it rained a lot that week, so the process is slowed.
SUMMARY OF WORK IN PROGRESS:
DIVISION 2/31_SITE WORK:
As shown in photo 2.1 and 2.3 after the rain of these days the water is pumped out
excavation, to provide a dry working area. A pumps system is installed all around.
Photo 2.4 shows the new bituminous paving long the vehicle parking and main entrance.
Most of the piles are covered with plastic sheet, to protect them from rotting.
DIVISION 3_CONCRETE:
At this stage has not been set yet any formwork or reinforcing steel, workers are still
preparing and leveling the surface.
SITE ISSUE:
The work is still delayed, the site is messier compared with the last visit. Some materials
are spread around.
Another serious problem is the massive presence of water on site caused by the heavy
rains in recent days, pumps are operating all day to keep the water out from the
excavation to provide a dry working area (panoramic view 2.1).
9
PHOTO 2 .1 From above, shows cement and
other materials.
PHOTO 2.3 Excavator at work, puddles of water in most of the site.
PHOTO 2.4 New bituminous asphalt in the parking vehicles
10
SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #3333 :::: NovemberNovemberNovemberNovember 1111/2106 (/2106 (/2106 (/2106 (2:2:2:2:00 p.m)00 p.m)00 p.m)00 p.m)
SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C
EXSISTING CONDITION: Cloudy
SITE REPORTER: Antonella Gennusa
EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, lumber, garbage, signs,
fence, pump, cement, concrete bucket.
SUMMARY OF WORK SINCE PREVIOUS VISIT:
DIVISION 2/31_SITE WORK:
As shown in photo 3.1, since the first visit, the same areas are still in the excavation
process. Few of rocks have been removed from the site. But there are still some smaller
rocks left at the site.
SUMMARY OF WORK IN PROGRESS:
DIVISION 2/31_SITE WORK:
As shown in picture 3.1, crew were excavating one specified area to install the crane. They
excavated the site, add the plastic white material. The next step would be to add the
grade on top of the plastic material,( reinforcing steel).
DIVISION 3_CONCRETE:
The process of the concrete is still on going. But due to the heavy rain, there was delay in
schedule for shotcrete the walls.
SITE ISSUE:
The day I went to report on the site, I talked to contractor. Due to the heavy rain fall
during October, the dewatering process is not going very well. The crew had to repeat the
process multiple times in order to have a dry site to work on. The rain had great effect on
the schedule and it causes delay.
11
PHOTO 3.1 workers installing reinforcing steel
PHOTO 3.2 equipment on site
12
SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #4444 :::: NovemberNovemberNovemberNovember 14141414/2106 (/2106 (/2106 (/2106 (1111::::15151515 p.m)p.m)p.m)p.m)
SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C
EXSISTING CONDITION: Sunny
SITE REPORTER: Antonella Gennusa
EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, lumber, garbage, signs,
fence, pump, cement, concrete bucket, tower crane.
SUMMARY OF WORK SINCE PREVIOUS VISIT:
Past few weeks, the crew were excavating the specified area to install the crane. Now the
crane has been fully installed and it’s been using to lift heavy materials, such as concrete
bucket. (photo 4.1)
SUMMARY OF WORK IN PROGRESS:
DIVISION 2/31_SITE WORK:
The excavation process is going on. A ramp has been made for the crew to have easy
access to the site. As well as temporary stairs have been installed on the site. After the
ramp is moved, the heavy equipment will be lifted from the site. (photo 4.3)
DIVISION 3_CONCRETE:
Crew were building the part of foundation. Required excavation has been done. And they
were in middle of installing reinforcements to the concrete. The reinforcement concrete
provide the required strength for foundation. As shown in the picture, the dwell has been
installed on the site. The concrete has been poured on the walls. (photo 4.2)
SITE ISSUE:
One safety issues that I had noticed, was that one of the crew on the site was not wearing
protection, such as his helmet.
13
PHOTO 4.1 tower crane
PHOTO 4.2 foundation details, dowel and concrete in foundation wall
PHOTO 4.2 Concrete bucket

More Related Content

What's hot

Construction Documents Fall 2014
Construction Documents Fall 2014Construction Documents Fall 2014
Construction Documents Fall 2014
Martin Pauly
 
Item # 5 - 301 Encino Significance & Compatibility
Item # 5 - 301 Encino Significance & CompatibilityItem # 5 - 301 Encino Significance & Compatibility
Item # 5 - 301 Encino Significance & Compatibility
ahcitycouncil
 
Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Project management project 1 report (pr architects)
Project management project 1 report (pr architects)
Jannah Jailani
 
Portfolio.pdf 1
Portfolio.pdf 1Portfolio.pdf 1
Portfolio.pdf 1
NIcholas Casertano
 
Town planning report northroad 20121210 a
Town planning report northroad 20121210 aTown planning report northroad 20121210 a
Town planning report northroad 20121210 a
Anne Kim
 
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-inRenovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
Anthony Boyko
 
502 north market
502 north market502 north market
502 north market
James Richardson
 
ICI - Final Project - Brief Report
ICI - Final Project - Brief ReportICI - Final Project - Brief Report
ICI - Final Project - Brief Report
Yung Kai
 
Salt Lake Costume Project (1701 S 1100 E)
Salt Lake Costume Project (1701 S 1100 E)Salt Lake Costume Project (1701 S 1100 E)
Salt Lake Costume Project (1701 S 1100 E)
ELPCO East Liberty Park Comm. Organization
 
Item # 4 - 820 Cambridge Compatibility
Item # 4 - 820 Cambridge Compatibility Item # 4 - 820 Cambridge Compatibility
Item # 4 - 820 Cambridge Compatibility
ahcitycouncil
 
Ongoing & Suspended Projects as of September 2011
Ongoing & Suspended Projects as of September 2011Ongoing & Suspended Projects as of September 2011
Ongoing & Suspended Projects as of September 2011
cmogsc
 
D18cl124 internship_report
D18cl124 internship_reportD18cl124 internship_report
D18cl124 internship_report
CHARUSSAT UNIVERSITY
 
TechTown 1st Floor Renovation
TechTown 1st Floor RenovationTechTown 1st Floor Renovation
TechTown 1st Floor Renovation
Christopher Bruner
 
CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013
tboyko
 
One House Project Drawing
One House Project DrawingOne House Project Drawing
One House Project Drawing
Hassankhosa
 
Lowe's Carmel, IN
Lowe's   Carmel, INLowe's   Carmel, IN
Lowe's Carmel, IN
Djuan Jackson, NOMA, CDT
 
Titan Engineers PC - Statement of Qualifications
Titan Engineers PC - Statement of QualificationsTitan Engineers PC - Statement of Qualifications
Titan Engineers PC - Statement of Qualifications
Nicholas Wong PE
 
Item # 8 - 203 E. Edgewood
Item # 8 - 203 E. EdgewoodItem # 8 - 203 E. Edgewood
Item # 8 - 203 E. Edgewood
ahcitycouncil
 
Introduction of basic housing & Planning -A Live case Study
Introduction of basic housing & Planning -A Live case StudyIntroduction of basic housing & Planning -A Live case Study
Introduction of basic housing & Planning -A Live case Study
Government Polytecnic For Girls< Ahmedabad
 

What's hot (19)

Construction Documents Fall 2014
Construction Documents Fall 2014Construction Documents Fall 2014
Construction Documents Fall 2014
 
Item # 5 - 301 Encino Significance & Compatibility
Item # 5 - 301 Encino Significance & CompatibilityItem # 5 - 301 Encino Significance & Compatibility
Item # 5 - 301 Encino Significance & Compatibility
 
Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Project management project 1 report (pr architects)
Project management project 1 report (pr architects)
 
Portfolio.pdf 1
Portfolio.pdf 1Portfolio.pdf 1
Portfolio.pdf 1
 
Town planning report northroad 20121210 a
Town planning report northroad 20121210 aTown planning report northroad 20121210 a
Town planning report northroad 20121210 a
 
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-inRenovator's Presentation for Orderline Duplex Simplifed for linked-in
Renovator's Presentation for Orderline Duplex Simplifed for linked-in
 
502 north market
502 north market502 north market
502 north market
 
ICI - Final Project - Brief Report
ICI - Final Project - Brief ReportICI - Final Project - Brief Report
ICI - Final Project - Brief Report
 
Salt Lake Costume Project (1701 S 1100 E)
Salt Lake Costume Project (1701 S 1100 E)Salt Lake Costume Project (1701 S 1100 E)
Salt Lake Costume Project (1701 S 1100 E)
 
Item # 4 - 820 Cambridge Compatibility
Item # 4 - 820 Cambridge Compatibility Item # 4 - 820 Cambridge Compatibility
Item # 4 - 820 Cambridge Compatibility
 
Ongoing & Suspended Projects as of September 2011
Ongoing & Suspended Projects as of September 2011Ongoing & Suspended Projects as of September 2011
Ongoing & Suspended Projects as of September 2011
 
D18cl124 internship_report
D18cl124 internship_reportD18cl124 internship_report
D18cl124 internship_report
 
TechTown 1st Floor Renovation
TechTown 1st Floor RenovationTechTown 1st Floor Renovation
TechTown 1st Floor Renovation
 
CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013CDECA Toronto Chapter Presentation Feb 5, 2013
CDECA Toronto Chapter Presentation Feb 5, 2013
 
One House Project Drawing
One House Project DrawingOne House Project Drawing
One House Project Drawing
 
Lowe's Carmel, IN
Lowe's   Carmel, INLowe's   Carmel, IN
Lowe's Carmel, IN
 
Titan Engineers PC - Statement of Qualifications
Titan Engineers PC - Statement of QualificationsTitan Engineers PC - Statement of Qualifications
Titan Engineers PC - Statement of Qualifications
 
Item # 8 - 203 E. Edgewood
Item # 8 - 203 E. EdgewoodItem # 8 - 203 E. Edgewood
Item # 8 - 203 E. Edgewood
 
Introduction of basic housing & Planning -A Live case Study
Introduction of basic housing & Planning -A Live case StudyIntroduction of basic housing & Planning -A Live case Study
Introduction of basic housing & Planning -A Live case Study
 

Similar to site monitoring project

Building Technology 2
Building Technology 2Building Technology 2
Building Technology 2
nadiacbass
 
Cp 2 AssignmentV2 15092015
Cp 2 AssignmentV2    15092015Cp 2 AssignmentV2    15092015
Cp 2 AssignmentV2 15092015
Praveen Premkumar
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
cyberyogi07
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
JaiminTandel1
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
Clement Seong
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
Bolin Loong
 
Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011
cmogsc
 
Field visit report 2019
Field visit report 2019Field visit report 2019
Field visit report 2019
Nirob Ahmed
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
Benoit Latapie
 
Phase of Building
Phase of BuildingPhase of Building
Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010
Stephen Bolduc
 
LINKS CAFE - Online publishing version
LINKS CAFE  -  Online publishing versionLINKS CAFE  -  Online publishing version
LINKS CAFE - Online publishing version
M. A. Architect
 
21dj0036 plan.pdf
21dj0036 plan.pdf21dj0036 plan.pdf
21dj0036 plan.pdf
Quote5
 
ICI FINAL REPORT
ICI FINAL REPORTICI FINAL REPORT
ICI FINAL REPORT
Clement Seong
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
Sheau Hui Tan
 
pheonix
pheonixpheonix
Item # 5 - 119 Grant (Compatibility Only)
Item # 5 - 119 Grant (Compatibility Only)Item # 5 - 119 Grant (Compatibility Only)
Item # 5 - 119 Grant (Compatibility Only)
ahcitycouncil
 
01 jt twisting super tower final project
01 jt   twisting super tower final project01 jt   twisting super tower final project
01 jt twisting super tower final project
limaperu0101
 
01 jt twisting super tower final project
01 jt   twisting super tower final project01 jt   twisting super tower final project
01 jt twisting super tower final project
limaperu0101
 
Niand work profile
Niand work profileNiand work profile
Niand work profile
Dr. Ninad Dhawle
 

Similar to site monitoring project (20)

Building Technology 2
Building Technology 2Building Technology 2
Building Technology 2
 
Cp 2 AssignmentV2 15092015
Cp 2 AssignmentV2    15092015Cp 2 AssignmentV2    15092015
Cp 2 AssignmentV2 15092015
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011
 
Field visit report 2019
Field visit report 2019Field visit report 2019
Field visit report 2019
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
 
Phase of Building
Phase of BuildingPhase of Building
Phase of Building
 
Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010Bangor Waterfront Park Plans by Shadley 12-2010
Bangor Waterfront Park Plans by Shadley 12-2010
 
LINKS CAFE - Online publishing version
LINKS CAFE  -  Online publishing versionLINKS CAFE  -  Online publishing version
LINKS CAFE - Online publishing version
 
21dj0036 plan.pdf
21dj0036 plan.pdf21dj0036 plan.pdf
21dj0036 plan.pdf
 
ICI FINAL REPORT
ICI FINAL REPORTICI FINAL REPORT
ICI FINAL REPORT
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
pheonix
pheonixpheonix
pheonix
 
Item # 5 - 119 Grant (Compatibility Only)
Item # 5 - 119 Grant (Compatibility Only)Item # 5 - 119 Grant (Compatibility Only)
Item # 5 - 119 Grant (Compatibility Only)
 
01 jt twisting super tower final project
01 jt   twisting super tower final project01 jt   twisting super tower final project
01 jt twisting super tower final project
 
01 jt twisting super tower final project
01 jt   twisting super tower final project01 jt   twisting super tower final project
01 jt twisting super tower final project
 
Niand work profile
Niand work profileNiand work profile
Niand work profile
 

site monitoring project

  • 1. 1 SITE MONITORING PROJECT BCIT- ARCHITECTURAL AND BUILDIN TECHNOLOGY BLDC 1050 – MATERIALS AND METHOD 1 PRESENTED TO: RAY WANG PREPARED BY: ANTONELLA GENNUSA STUDENT ID: A00991847
  • 2. 2 TABLE OF CONTENT Project Summary…………………………………………………………………………………………………………………………… 3 Construction Site Plan…………………………………………………………………………………………………………………. 4 Project Description………………………………………………………………………………………………………………………. 5 SITE VISIT REPORT Site Visit Report #1: Date: September 15/2016……………………………………………………………………..6 Site Visit Report #2: Date Site Visit Report #3: Date Site visit Report #4: Date LIST OF FIGURES & ILLUSTRATIONS SVR Photo 1.1: Photo from main entry to the site, hoarding and parking area in evidence..7 SVR Photo 1.2: Excavators during the site preparation works…………………………………………………..7 SVR Photo 1.3: Chute from truck and piles of gravel during the site preparation works……..7 SVR Photo 1.4: Protection of excavation wall, soil nail are drilled trough mesh face into the earth……………………………………………………………………………………………………………………………………………………7 SVR Photo 2.1: Photo from above, shows cement and other materials…………………………….…….9 SVR Photo 2.3: Excavator at work, puddles of water in most of the site…………………………………9 SVR Photo 2.4: New bituminous asphalt in the parking vehicles…………………………………………..…9 SVR Photo 3.1: workers installing reinforcing steel ……………………………………………………………….11 SVR Photo 3.2: equipment on site…………………………………………………………………………………………….…11 SVR Photo 4.1: tower crane ………………………………………………………………………………………………….…..….13 SVR Photo 4.2: foundation details, dowel and concrete in foundation wall……………….….……13 SVR Photo 4.3: Concrete bucket …………………………………………………………………………………………….……13
  • 3. 3 PROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARY PROJECT NAME:PROJECT NAME:PROJECT NAME:PROJECT NAME: Escala SSSSUMMARYUMMARYUMMARYUMMARY:::: Escala Luxury is a huge complex featuring a 42 storey high-rise building whit 359 homes, and 4 storey low-rise building with 151 homes. Located in Brentwood, neighborhood of Burnaby. This development has 520 total unit and over 15.000 square feet of amenities. The site for Escala will be located at the corner of Gilmore Ave and Douglas Road by Gilmore Station. Nearby parks include Wililngdon Heights Park. START DAY:START DAY:START DAY:START DAY: Summer 2016 ESTIMATED COMPLETIONESTIMATED COMPLETIONESTIMATED COMPLETIONESTIMATED COMPLETION:::: Spring 2019 DEVELOPER:DEVELOPER:DEVELOPER:DEVELOPER: LM Escala Homes LP LAWYERLAWYERLAWYERLAWYERSSSS:::: Terra Law Corporation MARKETING & SALES MANAGERS:MARKETING & SALES MANAGERS:MARKETING & SALES MANAGERS:MARKETING & SALES MANAGERS: Escala Brentwood CONSULTANT:CONSULTANT:CONSULTANT:CONSULTANT: ARCHITECT:ARCHITECT:ARCHITECT:ARCHITECT: IBI Group Architects & Integra Architecture DESIGNER:DESIGNER:DESIGNER:DESIGNER: The Mill GENERAL CONTRACTOR:GENERAL CONTRACTOR:GENERAL CONTRACTOR:GENERAL CONTRACTOR: Ledingham McAllister SUBCONTRACTORS INCLUDE:SUBCONTRACTORS INCLUDE:SUBCONTRACTORS INCLUDE:SUBCONTRACTORS INCLUDE: EXCAVATINGEXCAVATINGEXCAVATINGEXCAVATING CONTRACTOR:CONTRACTOR:CONTRACTOR:CONTRACTOR: Whitewater. FOUNDATION CONTRACTOR:FOUNDATION CONTRACTOR:FOUNDATION CONTRACTOR:FOUNDATION CONTRACTOR: Whitewater. STEEL:STEEL:STEEL:STEEL: Dion custom ELECTRICAL:ELECTRICAL:ELECTRICAL:ELECTRICAL: Chambers electric
  • 4. 4 SITE PLANSITE PLANSITE PLANSITE PLAN N
  • 5. 5 PROJECT DESCRIPTIONPROJECT DESCRIPTIONPROJECT DESCRIPTIONPROJECT DESCRIPTION Escala Luxury is a huge complex featuring a 42 storey high-rise building whit 359 homes, and 4 storey low-rise building with 151 homes. Located in Brentwood, neighborhood of Burnaby. Protecting the site perimeter the area is surrounded by a high wood and metal hoarding, many people work inside with the proper equipment (helmet, boots and jacket). There are several workers who manage the traffic at the entrance. All the signs around the site are properly installed. The site has a large parking for vehicles and a long ramp to reach the hearts of the excavation. Storage and offices are located beside the site. ITEMS OF WORK: gravel, structural steel, excavators, concrete, chute from truck, lumber, garbage, signs, fence, pump. The workers are still working on the foundations while the works for protecting the excavation walls are complited, the new building will be finished in 2019.
  • 6. 6 SITE VISIT REPORTER #1SITE VISIT REPORTER #1SITE VISIT REPORTER #1SITE VISIT REPORTER #1 :::: September 15/2106 (2.50 p.m)September 15/2106 (2.50 p.m)September 15/2106 (2.50 p.m)September 15/2106 (2.50 p.m) SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C EXSISTING CONDITION: Sunny SITE REPORTER: Antonella Gennusa EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, chute from truck, lumber, garbage, signs, fence, pump, bobcats. DIVISION 1: GENERAL REQUIREMENTS: As shown in the photo 1.1 the main entrance area is also parking for all vehicles, while the secondary entrance area (on Gilmore avenue) is used for material deposit such as: wood, steel and generators. Offices and other deposits are located outside the site construction. DIVISION 2_EXISTING CONDITION: Since the first visit it can be observed that the excavation work is about to be completed (photo 1.2) and that the excavation walls have been reinforced with soil nails similar to soil anchors (photo 1.4) and a layer of shootcrete and mesh. The climate of these days allows workers to work quietly. At this stage of the work is not yet installed any cranes. DIVISION 3_CONCRETE: At this preliminary stage has not been set yet any formwork or reinforcing steel, workers are still preparing and leveling the surface. The holes of the construction site are filled with sands or concrete (photo 1.3). DIVISION 31_EARTHWORK: The site has been prepared for the next step. Within the area ESC tanks have been installed. Protecting the site perimeter the area is surrounded by a high wood and metal hoarding, all the signs around the site are properly installed. The site has a large parking for vehicles and a long ramp to reach the hearts of the excavation. Protecting excavation walls soil nails have been installed and capped and after a layer of shootcrete has been spryed. SITE ISSUE: The work is delyead because a small design error fortunately recovered in time.
  • 7. 7 PHOTO 1 .1 photo from main entry to the site, hoarding and parking area in evidence. PHOTO 3 .2 Excavators during the site preparation works. PHOTO 2 .3 Chute from truck and piles of gravel during the site preparation works PHOTO 4 .3 Protection of excavation wall, soil nails are drilled trough mesh face into the earth.
  • 8. 8 SITE VISIT REPORTER #2SITE VISIT REPORTER #2SITE VISIT REPORTER #2SITE VISIT REPORTER #2 : October 19/2106 (3.00 p.m): October 19/2106 (3.00 p.m): October 19/2106 (3.00 p.m): October 19/2106 (3.00 p.m) SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C EXSISTING CONDITION: Overcast SITE REPORTER: Antonella Gennusa EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, lumber, garbage, signs, fence, pump, cement. SUMMARY OF WORK SINCE PREVIOUS VISIT: DIVISION 2/31_SITE WORK: As shown in photo 2.3, since the first visit, the same areas are still in the excavation process. Unlike the first visit it rained a lot that week, so the process is slowed. SUMMARY OF WORK IN PROGRESS: DIVISION 2/31_SITE WORK: As shown in photo 2.1 and 2.3 after the rain of these days the water is pumped out excavation, to provide a dry working area. A pumps system is installed all around. Photo 2.4 shows the new bituminous paving long the vehicle parking and main entrance. Most of the piles are covered with plastic sheet, to protect them from rotting. DIVISION 3_CONCRETE: At this stage has not been set yet any formwork or reinforcing steel, workers are still preparing and leveling the surface. SITE ISSUE: The work is still delayed, the site is messier compared with the last visit. Some materials are spread around. Another serious problem is the massive presence of water on site caused by the heavy rains in recent days, pumps are operating all day to keep the water out from the excavation to provide a dry working area (panoramic view 2.1).
  • 9. 9 PHOTO 2 .1 From above, shows cement and other materials. PHOTO 2.3 Excavator at work, puddles of water in most of the site. PHOTO 2.4 New bituminous asphalt in the parking vehicles
  • 10. 10 SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #3333 :::: NovemberNovemberNovemberNovember 1111/2106 (/2106 (/2106 (/2106 (2:2:2:2:00 p.m)00 p.m)00 p.m)00 p.m) SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C EXSISTING CONDITION: Cloudy SITE REPORTER: Antonella Gennusa EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, lumber, garbage, signs, fence, pump, cement, concrete bucket. SUMMARY OF WORK SINCE PREVIOUS VISIT: DIVISION 2/31_SITE WORK: As shown in photo 3.1, since the first visit, the same areas are still in the excavation process. Few of rocks have been removed from the site. But there are still some smaller rocks left at the site. SUMMARY OF WORK IN PROGRESS: DIVISION 2/31_SITE WORK: As shown in picture 3.1, crew were excavating one specified area to install the crane. They excavated the site, add the plastic white material. The next step would be to add the grade on top of the plastic material,( reinforcing steel). DIVISION 3_CONCRETE: The process of the concrete is still on going. But due to the heavy rain, there was delay in schedule for shotcrete the walls. SITE ISSUE: The day I went to report on the site, I talked to contractor. Due to the heavy rain fall during October, the dewatering process is not going very well. The crew had to repeat the process multiple times in order to have a dry site to work on. The rain had great effect on the schedule and it causes delay.
  • 11. 11 PHOTO 3.1 workers installing reinforcing steel PHOTO 3.2 equipment on site
  • 12. 12 SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #SITE VISIT REPORTER #4444 :::: NovemberNovemberNovemberNovember 14141414/2106 (/2106 (/2106 (/2106 (1111::::15151515 p.m)p.m)p.m)p.m) SITE LOCATION: 1710 Gilmore Ave, Burnaby, BC V5C EXSISTING CONDITION: Sunny SITE REPORTER: Antonella Gennusa EQUIPMENT ON SITE: Gravel, structural steel, excavators, concrete, lumber, garbage, signs, fence, pump, cement, concrete bucket, tower crane. SUMMARY OF WORK SINCE PREVIOUS VISIT: Past few weeks, the crew were excavating the specified area to install the crane. Now the crane has been fully installed and it’s been using to lift heavy materials, such as concrete bucket. (photo 4.1) SUMMARY OF WORK IN PROGRESS: DIVISION 2/31_SITE WORK: The excavation process is going on. A ramp has been made for the crew to have easy access to the site. As well as temporary stairs have been installed on the site. After the ramp is moved, the heavy equipment will be lifted from the site. (photo 4.3) DIVISION 3_CONCRETE: Crew were building the part of foundation. Required excavation has been done. And they were in middle of installing reinforcements to the concrete. The reinforcement concrete provide the required strength for foundation. As shown in the picture, the dwell has been installed on the site. The concrete has been poured on the walls. (photo 4.2) SITE ISSUE: One safety issues that I had noticed, was that one of the crew on the site was not wearing protection, such as his helmet.
  • 13. 13 PHOTO 4.1 tower crane PHOTO 4.2 foundation details, dowel and concrete in foundation wall PHOTO 4.2 Concrete bucket