Design & Build- Free Trade Warehousing Zone at JNPT,
Mumbai
Weekly Progress Report
12-Dec-2022 to 18-Dec-2022 (Week No-112)
L&T Construction| 3
Sensitivity: LNT Construction Internal Use
Contents
1 General Details
2 EHS Report
3 Overall Progress
4 Schedule Progress Update
5 Agency approvals
6 Finishing Schedule
7 Statutory approvals
8 Progress Report Pictorial View
9 Methodology/Risk assessment approval summary
10 Material / Agency Approval Summary
11 Resource Report
12 Quality report
13 Document submission status/Input required- Client
14 List of Action points among DP World and JNPT SEZ Team
15 Photographic report
16 Insurance Details
L&T Construction| 4
Sensitivity: LNT Construction Internal Use
General Details
Name of Employer M/s Nhava Sheva Business Park Pvt. Ltd.
Name of Design Consultant M/s C R Narayan Rao Pvt. Ltd.
Name of the Contractor M/s Larsen & Toubro Ltd.
Name of Project Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
Project Start Date 20th Oct 20
Scheduled End Date
Phase 1- 19th Dec 2021
Phase 2- 19th Apr 2022
No. of Days of Contract 546 Days
Scope of Work Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
L&T Construction| 5
Sensitivity: LNT Construction Internal Use
EHS Report- Photographs
PEP talk about Electrical Safety PEP talk about Electrical Hazard
L&T Construction| 6
Sensitivity: LNT Construction Internal Use
EHS Report
Sl. No. Description This week Total
1 No. of Manhours Worked 20808 4553544
2 No. of accidents reported - 1
3 No. of near misses - 6
4 Lost time injury (LTI) - 1
5 Safety Observation 2 294
6 Safety Induction 13 7612
7 Training / Awareness Session. 2 197
8 Mass Toolbox Talks conducted 2 366
9 No. of safety site walks conducted 1 104
L&T Construction| 7
Sensitivity: LNT Construction Internal Use
Balance Activity Main Work
Task Name Remarks
•Phase -2
•Warehouse -3
• Office -1 Completed
• Office -2 Completed
• Office -3 Completed
• Bulk Storage Area Deep Cleaning in Progress in balance area , De- Snagging ongoing
•WareHouse-4
• Office Completed
•Toilet Completed
•Bulk Storage Area Completed
•WareHouse-5
• Office -1 Final Coat Painting Ongoing
• Office -2 Snagging Ongoing
• Office -3 Snagging Ongoing
• Bulk Storage Area Snagging Ongoing
L&T Construction| 8
Sensitivity: LNT Construction Internal Use
Balance Activity Main Work
Task Name Remarks
• WareHouse-6
•Office Area-2
Completed
•Office Area-3
•Office Area-1
• Bulk Storage Area Cleaning in Progress, De snagging ongoing
•External Work
•Road Area
WMM Completed
Paver Block Completed
Grass Crete Almost Completed b/w WH-03 & WH-05
Boundary Wall (Type-2) Final coat paint pending
Boundary Wall (Type-3) 50 m post & mesh fixing pending
L&T Construction| 9
Sensitivity: LNT Construction Internal Use
Admin Interior Work
Task Name Remarks
•Admin (GF)
Painting – Final Coat
Carpet laying & aluminum skirting
Granite on ledge wall fixing- Completed
Flooring in Reception area – Lift lobby floor tile pending
Toilet Cubical installation- Completed
MEP accessories in Toilet- Ongoing
•Admin (FF)
Painting – Final Coat
Carpet laying & aluminum skirting
Granite on ledge wall fixing -Finishing ongoing
Toilet Cubical installation- Completed
MEP accessories in Toilet
L&T Construction| 10
Sensitivity: LNT Construction Internal Use
Admin Interior Work
Task Name Remarks
•Admin (SF)
Painting
Carpet laying & aluminum skirting
Granite on ledge wall fixing - Finishing ongoing
Toilet Cubical installation- Completed
MEP accessories in Toilet
Terrace
Granite Counter
Painting
L&T Construction| 12
Sensitivity: LNT Construction Internal Use
Progress Report Pictorial View
Subgrade
GSB
DLC
Flooring
W-3
W-2
W-1
WMM
W-3
SUB.
W-6
Paver Block
DBM
Parking
UG
BC
W-6
Grass Crete
PQC
W-4
W-5
W-4
L&T Construction| 24
Sensitivity: LNT Construction Internal Use
Finishing schedule
Sl No. Items Sample submission date Actual Submitted Remarks
1
Tile
Flooring- Polished Vitrified Tiles 30-09-2021 09-09-2021
Approved on date 25-
11-2021
2 Flooring- Matt Finish ceramic Tile 30-09-2021 09-09-2021
3 Dado - Glazed ceramic Tiles 30-09-2021 09-09-2021
4
Stone
Granite 30-09-2021 08-11-2021
Approved on date 14-
12-21
Kota Stone 30-09-2021 08-11-2021
5
6
Paint
External 03-11-2021 09-09-2021
Approved
7 Internal 03-11-2021 09-09-2021
8 Window 10-02-2022 Shop drawing
approved
9 False ceiling 10-02-2022 Approved
10 ACP 01-02-2022 Sample approved
11 Glazing 04-02-2022 Sample approved
12 Furniture 10-02-2022 Approved
13 Toilet Cubical 15-02-2022
14 Light Fixtures 25-12-2021 Approved
15 Light & Switch socket 29-01-2022 Approved
16 Plumbing Fixtures 10-12-2021 Approved
L&T Construction| 25
Sensitivity: LNT Construction Internal Use
Statutory approvals
Task Name Duration Start Finish Actual Start Actual Finish Remarks
Development permission / building
permission post completion of
detailed design
60 days 23-01-2021 05-04-2021 23-01-2021 04-06-21
Fire NOC- Pre approval 30 days 17-02-2021 23-03-2021 17-02-2021 15-03-2021
Fire NOC Final Approval 05 days 08-02-2022 12-02-2022 - -
Application
Approved
Lift Approvals – pre-installation &
post-installation
109 days 06-10-2021 14-02-2022 - -
Pre Installation 30 days 06-10-2021 11-11-2021 17-02-2021 15-03-2021
Post Installation 9 days 04-02-2022 14-02-2022 - -
CEIG Approval 30 days 02-12-2021 31-12-2021 - -
Application
Approved
Approvals for Chimney 30 days 12-06-2021 30-09-2021 - -
L&T Construction| 26
Sensitivity: LNT Construction Internal Use
Methodology Approval Summary
Sl
.No.
Description Reference No.
R0 R1 R2
Submitted
Date
Returned
date
Status
Submitted
Date
Returned
date
Status
Submitted
Date
Returned
date
Status
1
Method Statement for
Rectification of RCC
Bulging
LT/B&F/NSBP/MS-15 27-07-2021 28-07-2021 Approved
2
Pile Dynamic, Pull-
Out Load, Lateral Pile
Load, Pile Integrity
Test
LT/B&F/NSBP/MS-
16,17,18&19
05-08-2021 Approved
3
Method Statement for
Masonry work
LT/B&F/NSBP/MS/20 30-11-2022 03-12-2021 Approved
4
Method Statement for
Plastering work
LT/B&F/NSBP/MS/21 6-12-2021 06-12-2021 Approved
5 Flooring Work LT/B&F/NSBP/MS/22 Resubmitted Resubmitted 05-01-22 08-01-22 Approved
6
Construction
Methodology for
Water Proofing
LT/B&F/NSBP/MS/23 26-10-2021 28-10-2021 Resubmitted 22-11-2021 Approved
7
Profiling and fixing of
roof sheeting & wall cl
adding
LT/B&F/NSBP/MS/PEB/05 - - Resubmitted 06-01-22
8
Method Statement for
Paining work
LT/B&F/NSBP/MS/24 24-01-22 10-02-22 Approved
9 Tiling work LT/B&F/NSBP/MS/25 19-02-22 - Approved
10 MS Grill LT/B&F/NSBP/MS/ 16-02-22 - Submitted
11 DBM & BC work LT/B&F/NSBP/MS/ 16-02-22 - Submitted
12 False ceiling LT/B&F/NSBP/MS/ 16-02-22 - Submitted
L&T Construction| 27
Sensitivity: LNT Construction Internal Use
Material/Agency Approval Summary
Sl .No. Description Submitted Date Status
1 Weigh Bridge, M/s Essae 25-08-2021 M/s Essae approved
2
Tile (Somany & Kajaria) & Paint (Berger & Asian Paints)
shade
09-09-2021 Sample Approved
3 Swellable Water bar (Make-Fosroc) 11-09-2021 Source Approved
4 Flooring Agency 09-11-2021 M/s BGSB Approved
5 Granite Stone Sample 08-11-2021 Approved
6 Sheeting Profile Sample 22-11-2021 Approved
7 HVAC Fan (Make M/s Kruger) 23-12-2021 Approved on 07-01-2022
8 Glazing and ACP works 24-12-2021 M/s Alu/MS approved on 01-02-2022
9 Hollow sections make for PEB elements (M/s Apollo) 03-01-2022 Approved
10
Sectional Door, Rolling shutter, Dock leveler & Shelter
(Make- M/s Gandhi)
19-01-2022 Approved on 01-02-2022
11 Make of Fire Door (M/s Radiant) 22-01-2022 Approved
12 DB (Make M/s ABB) 01-02-2022 Approved on 06-02-2022
13 Paver Block (Make M/s JM Mhatre) 27-01-2022 Approved on 08-03-2022
19 Flush Door Laminate Shade Card 19-02-2022 Approved
14 Glazing - Aluminium Colour Shade 19-02-2022 Approved
15 Modular Furniture for Warehouse Office 24-02-2022 Approved
16 Sample of Steel & Fire doors 04-03-2022 Approved
17 Glass Processing Unit for Glazing works (M/s FG Glass) 21-03-2022 Profile submitted
18 Sample for Admin Building 07-05-2022 Approved
L&T Construction| 28
Sensitivity: LNT Construction Internal Use
Resource Report
Manpower
Staff Description Nos. Remark
Project Management &
Planning
03 -
Account & Admin 01 -
EHS 01 -
QA/QC 01 -
P&M 01 -
Execution-Civil & PEB 09 -
Execution-MEP 05 -
Total- 21 Nos.
Workmen Description Nos. Remark
Driver/Operator 12 -
Workmen & Helper 215 -
Workmen (Temp. Works) 5 -
Supervisor & Others 28 -
Total- 260 Nos.
Machinery
Type Nos.
Backhoe loader 01
Grader 00
Roller 01
Tractor 03
Boom lift 05
Scissor Lift 00
Trailer 01
F-15 01
L&T Construction| 29
Sensitivity: LNT Construction Internal Use
IGBC Critical Client Points
S No Description Remarks
1 Landscape Drawing AutoCAD format with the mentioned area marked – Tree Area, Shrub Area, Total Landscape
Area, Lawn (Turf) Area, and Number of Trees. Plant & Trees Species to be specified.
2 Tkm calculation Sheet to satisfy Case A & Case B mentioned in via Email
3 MHE vehicles Invoice (Fork lift + Pallet Truck + Reach Truck) till date.
4 MHE vehicles and charging point photos (With signage)
5 Golf cart Invoice
6 Golf Cart calculation ensuring 5% of occupants (excluding visitors) are catered
7
Declaration mentioning
Organise atleast two outreach/ educational programmes in a year on eco-friendly practices/ green initiatives.
The outreach/ educational programmes can include, but not limited to, clean & green, water conservation, energy
conservation, waste segregation & recycling, use bio-degradable plastic/ avoid single use plastic, air pollution, world
green building week and earth hour
8
Declaration mentioning
Atleast 75 % of the fleet (road fleet) complies with BS IV or latest emissions norms.
(And)
Entire fleet (road fleet) of the service provider will be periodically serviced to ensure efficient vehicle performance.
(And)
Awareness programmes will be organised periodically, by the service provider, to train the drivers on vehicle maintenance
and driving etiquette.
L&T Construction| 30
Sensitivity: LNT Construction Internal Use
IGBC Critical Client Points
S No Description Remarks
9 Provide Posters with education material for drivers shall be placed in drivers’ dormitories or resting areas (vehicle
maintenance and driving etiquette)
10 No smoking area photos with signage
11 Floor plans with waste bins
12 Organic Waste Composter with capacity of 160Kg/day to be installed (occupant number considered – 1650)
12
Install permanent educational signage in common areas of the park/ warehouse with green concepts such as Go Green,
Save Earth; Water is Precious, Save it; Turn off Lights, when not in use; Say no to Mixed Waste; Plant a Tree, Save the
Environment, etc
14
Undertaking for shuttle service connecting local public transit stops in the operating stage – Kindly reshare as the document
file got corrupted
15
Project Activity to be identified for Green activity beyond fence. Below are the IGBC recommended projects –
• RainWater Harvesting
• Sewage Treatment Plant
• Water Body
• Public Parks/Avenues
• Mass Plantation
• Renewable Energy
• Basic Facilities like – Provide at least four of the following : Bus Shelters, Street Lighting, Public toilets, Play area &
Sports kit, Tot-lot, Drinking water ATM or equipment, Organic waste management, other basic facilities
L&T Construction| 31
Sensitivity: LNT Construction Internal Use
Document submission status/Input required- Client
 Handover for Wh-1 & 2 – Taking Over Certificate issuance
 Disbursement of RAB-22 Main works
 Disbursement of RAB-2 Interior works
 EOT approval
 Road Marking details approval
 Column guard proposal confirmation
 View confirmation of cladding fixed over WH-1 & 2 wall along Grid 22
L&T Construction| 32
Sensitivity: LNT Construction Internal Use
List of Action points among DP World and JNPT SEZ Team
S.No Description Action by Target dt Completion dt Resolution Remarks
1 JNPT traffic island development( near to site) L&T Closed
2 Site Entry/exit cover expansion on the JNPT drain DPW L&T submitted the quate for works
3 Trailor movement to site from the JNPT road DPW/JNPT
Trailor entry/exit from JNPT road to decide and if required modification to
JNPT Median and road
4 Water connection tapping from JNPT Main header line L&T Application submitted to JNPT
5
JNPT RMU Metering panel specification to match by NSBP
new Metering panel
DPW/CRN/L&T
L&T will arrange for connection, Input required regarding specifications of
RMU, i.e. CT ratio
6 Building Plan approval- Phase-1 L&T 05-04-2021 01-06-2021 JNPT Already approved
7 Provisional Fire NOC- Phase-1 L&T 23-03-2021 17-03-2021 JNPT Already approved
8 Plinth Checking Phase-1 L&T JNPT
Plinth completion certificate received for Admin building, WH-1, WH-2 &
Substation.
9 Final Fire NOC - Phase-1 L&T 15-12-2021 JNPT Approval will be taken as per site condition
10 Occupancy Certificate - Phase-1 L&T 15-12-2021 JNPT Occupancy certificate will be with Plumbing certificate
11 Building Plan approval- Phase-2 L&T 19-06-2021 JNPT Approved
12 Provisional Fire NOC- Phase-2 L&T 13-05-2021 JNPT Provisional Fire NOC received
13 Plinth Checking Phase-2 L&T JNPT Approval will be taken as per site condition
14 CCOE/PESO approval L&T 13-07-2021 PESO Required towards the end of works
15 Final Fire NOC - Phase-2 L&T 14-04-2022 JNPT Demand note shared with M/ NSBP for payment
16 Occupancy Certificate - Phase-2 L&T 15-04-2022 JNPT
17 Approval from Airport Authority of India L&T AAI
18 Chief Electrical Inspector to Government (India) L&T 13-12-2021 CEIG
19 DISH approval L&T 15-04-2022 DISH N.A
20 Lift approval L&T 18-12-2021 PWD
L&T Construction| 33
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building
L&T Construction| 34
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building GF Reception Area Baffle Ceiling fixed Admin Building GF Custom Reception
L&T Construction| 35
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building all Revolving Chair received for
Workstation, Cabin & Reception
L&T Construction| 36
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building GF Dining Area
L&T Construction| 37
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building FF Engineering Room Admin Building SF Lobby Side Meeting Room
L&T Construction| 38
Sensitivity: LNT Construction Internal Use
Site Photographs
Admin Building SF Innovation Room Admin Building all EWC Fixture Fixed
L&T Construction| 39
Sensitivity: LNT Construction Internal Use
Site Photographs
Equipment Maintenance Building Municipal Solid Waste Collection Center
L&T Construction| 40
Sensitivity: LNT Construction Internal Use
Site Photographs
Mockup Kerb Stone Painting Mockup Ballard Fixed in WH-5
L&T Construction| 42
Sensitivity: LNT Construction Internal Use
Insurance Details
Sr.
No
Nature of Policy Policy No Validity Issued By Remarks
01 Marine Cargo 0865087494 31.03.2023
Tata AIG General
Insurance Co Ltd.
02
Plant and
Machinery
5011/R/150019780/03/000 31.03.2022
ICICI Lombard General
Insurance Co ltd.
03
Professional
Indemnity
5001002720P103233705 30.06.2022
United India Insurance
Co Ltd
04
Workman
compensation
411400/48/2022/44 30.03.2022
The Oriental Insurance
Company Limited
05
Commercial
general liability
5001002720P100653785 31.03.2023
United India Insurance
Co Ltd
L&T Construction| 43
Sensitivity: LNT Construction Internal Use
Thank you!

More Related Content

Similar to CONSTRUCTION PRESENTATION

G13 - Project Management.pptx
G13 - Project Management.pptxG13 - Project Management.pptx
G13 - Project Management.pptx
VatsalPancholi6
 
HKIS windows analysis delay-------------
HKIS windows analysis delay-------------HKIS windows analysis delay-------------
HKIS windows analysis delay-------------
engmts19861
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
JaiminTandel1
 
Engr.riyaz cv 02 11-15-2
Engr.riyaz cv 02 11-15-2Engr.riyaz cv 02 11-15-2
Engr.riyaz cv 02 11-15-2
Riyazuddin1985
 
Industrial Training Presentation Construction
Industrial Training Presentation ConstructionIndustrial Training Presentation Construction
Industrial Training Presentation Construction
KaranJayalakshman1
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
r66025007
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
Project assign 2
Project assign 2Project assign 2
Project assign 2
Moses Seriki
 
Summer training @ L&T
Summer training @ L&TSummer training @ L&T
Summer training @ L&Tams_5686
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
FaisalGulzar19
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
Rajabdeen Amjath
 
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptxDURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
kaustav_ju
 
243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 sMike Darwich
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Deck and Screen plans & Calculations
Deck and Screen plans & CalculationsDeck and Screen plans & Calculations
Deck and Screen plans & Calculations
Canberra Institute of technology
 

Similar to CONSTRUCTION PRESENTATION (20)

G13 - Project Management.pptx
G13 - Project Management.pptxG13 - Project Management.pptx
G13 - Project Management.pptx
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
HKIS windows analysis delay-------------
HKIS windows analysis delay-------------HKIS windows analysis delay-------------
HKIS windows analysis delay-------------
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
Engr.riyaz cv 02 11-15-2
Engr.riyaz cv 02 11-15-2Engr.riyaz cv 02 11-15-2
Engr.riyaz cv 02 11-15-2
 
Industrial Training Presentation Construction
Industrial Training Presentation ConstructionIndustrial Training Presentation Construction
Industrial Training Presentation Construction
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Project assign 2
Project assign 2Project assign 2
Project assign 2
 
Summer training @ L&T
Summer training @ L&TSummer training @ L&T
Summer training @ L&T
 
Masters s
Masters sMasters s
Masters s
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
Training PPT
Training PPTTraining PPT
Training PPT
 
chinthaka silva
chinthaka silvachinthaka silva
chinthaka silva
 
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptxDURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
 
243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Deck and Screen plans & Calculations
Deck and Screen plans & CalculationsDeck and Screen plans & Calculations
Deck and Screen plans & Calculations
 

Recently uploaded

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 

Recently uploaded (20)

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

CONSTRUCTION PRESENTATION

  • 1. L&T Construction| 1 Sensitivity: LNT Construction Internal Use Design & Build- Free Trade Warehousing Zone at JNPT, Mumbai
  • 2. L&T Construction| 2 Sensitivity: LNT Construction Internal Use Design & Build- Free Trade Warehousing Zone at JNPT, Mumbai Weekly Progress Report 12-Dec-2022 to 18-Dec-2022 (Week No-112)
  • 3. L&T Construction| 3 Sensitivity: LNT Construction Internal Use Contents 1 General Details 2 EHS Report 3 Overall Progress 4 Schedule Progress Update 5 Agency approvals 6 Finishing Schedule 7 Statutory approvals 8 Progress Report Pictorial View 9 Methodology/Risk assessment approval summary 10 Material / Agency Approval Summary 11 Resource Report 12 Quality report 13 Document submission status/Input required- Client 14 List of Action points among DP World and JNPT SEZ Team 15 Photographic report 16 Insurance Details
  • 4. L&T Construction| 4 Sensitivity: LNT Construction Internal Use General Details Name of Employer M/s Nhava Sheva Business Park Pvt. Ltd. Name of Design Consultant M/s C R Narayan Rao Pvt. Ltd. Name of the Contractor M/s Larsen & Toubro Ltd. Name of Project Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai Project Start Date 20th Oct 20 Scheduled End Date Phase 1- 19th Dec 2021 Phase 2- 19th Apr 2022 No. of Days of Contract 546 Days Scope of Work Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
  • 5. L&T Construction| 5 Sensitivity: LNT Construction Internal Use EHS Report- Photographs PEP talk about Electrical Safety PEP talk about Electrical Hazard
  • 6. L&T Construction| 6 Sensitivity: LNT Construction Internal Use EHS Report Sl. No. Description This week Total 1 No. of Manhours Worked 20808 4553544 2 No. of accidents reported - 1 3 No. of near misses - 6 4 Lost time injury (LTI) - 1 5 Safety Observation 2 294 6 Safety Induction 13 7612 7 Training / Awareness Session. 2 197 8 Mass Toolbox Talks conducted 2 366 9 No. of safety site walks conducted 1 104
  • 7. L&T Construction| 7 Sensitivity: LNT Construction Internal Use Balance Activity Main Work Task Name Remarks •Phase -2 •Warehouse -3 • Office -1 Completed • Office -2 Completed • Office -3 Completed • Bulk Storage Area Deep Cleaning in Progress in balance area , De- Snagging ongoing •WareHouse-4 • Office Completed •Toilet Completed •Bulk Storage Area Completed •WareHouse-5 • Office -1 Final Coat Painting Ongoing • Office -2 Snagging Ongoing • Office -3 Snagging Ongoing • Bulk Storage Area Snagging Ongoing
  • 8. L&T Construction| 8 Sensitivity: LNT Construction Internal Use Balance Activity Main Work Task Name Remarks • WareHouse-6 •Office Area-2 Completed •Office Area-3 •Office Area-1 • Bulk Storage Area Cleaning in Progress, De snagging ongoing •External Work •Road Area WMM Completed Paver Block Completed Grass Crete Almost Completed b/w WH-03 & WH-05 Boundary Wall (Type-2) Final coat paint pending Boundary Wall (Type-3) 50 m post & mesh fixing pending
  • 9. L&T Construction| 9 Sensitivity: LNT Construction Internal Use Admin Interior Work Task Name Remarks •Admin (GF) Painting – Final Coat Carpet laying & aluminum skirting Granite on ledge wall fixing- Completed Flooring in Reception area – Lift lobby floor tile pending Toilet Cubical installation- Completed MEP accessories in Toilet- Ongoing •Admin (FF) Painting – Final Coat Carpet laying & aluminum skirting Granite on ledge wall fixing -Finishing ongoing Toilet Cubical installation- Completed MEP accessories in Toilet
  • 10. L&T Construction| 10 Sensitivity: LNT Construction Internal Use Admin Interior Work Task Name Remarks •Admin (SF) Painting Carpet laying & aluminum skirting Granite on ledge wall fixing - Finishing ongoing Toilet Cubical installation- Completed MEP accessories in Toilet Terrace Granite Counter Painting
  • 11. L&T Construction| 12 Sensitivity: LNT Construction Internal Use Progress Report Pictorial View Subgrade GSB DLC Flooring W-3 W-2 W-1 WMM W-3 SUB. W-6 Paver Block DBM Parking UG BC W-6 Grass Crete PQC W-4 W-5 W-4
  • 12. L&T Construction| 24 Sensitivity: LNT Construction Internal Use Finishing schedule Sl No. Items Sample submission date Actual Submitted Remarks 1 Tile Flooring- Polished Vitrified Tiles 30-09-2021 09-09-2021 Approved on date 25- 11-2021 2 Flooring- Matt Finish ceramic Tile 30-09-2021 09-09-2021 3 Dado - Glazed ceramic Tiles 30-09-2021 09-09-2021 4 Stone Granite 30-09-2021 08-11-2021 Approved on date 14- 12-21 Kota Stone 30-09-2021 08-11-2021 5 6 Paint External 03-11-2021 09-09-2021 Approved 7 Internal 03-11-2021 09-09-2021 8 Window 10-02-2022 Shop drawing approved 9 False ceiling 10-02-2022 Approved 10 ACP 01-02-2022 Sample approved 11 Glazing 04-02-2022 Sample approved 12 Furniture 10-02-2022 Approved 13 Toilet Cubical 15-02-2022 14 Light Fixtures 25-12-2021 Approved 15 Light & Switch socket 29-01-2022 Approved 16 Plumbing Fixtures 10-12-2021 Approved
  • 13. L&T Construction| 25 Sensitivity: LNT Construction Internal Use Statutory approvals Task Name Duration Start Finish Actual Start Actual Finish Remarks Development permission / building permission post completion of detailed design 60 days 23-01-2021 05-04-2021 23-01-2021 04-06-21 Fire NOC- Pre approval 30 days 17-02-2021 23-03-2021 17-02-2021 15-03-2021 Fire NOC Final Approval 05 days 08-02-2022 12-02-2022 - - Application Approved Lift Approvals – pre-installation & post-installation 109 days 06-10-2021 14-02-2022 - - Pre Installation 30 days 06-10-2021 11-11-2021 17-02-2021 15-03-2021 Post Installation 9 days 04-02-2022 14-02-2022 - - CEIG Approval 30 days 02-12-2021 31-12-2021 - - Application Approved Approvals for Chimney 30 days 12-06-2021 30-09-2021 - -
  • 14. L&T Construction| 26 Sensitivity: LNT Construction Internal Use Methodology Approval Summary Sl .No. Description Reference No. R0 R1 R2 Submitted Date Returned date Status Submitted Date Returned date Status Submitted Date Returned date Status 1 Method Statement for Rectification of RCC Bulging LT/B&F/NSBP/MS-15 27-07-2021 28-07-2021 Approved 2 Pile Dynamic, Pull- Out Load, Lateral Pile Load, Pile Integrity Test LT/B&F/NSBP/MS- 16,17,18&19 05-08-2021 Approved 3 Method Statement for Masonry work LT/B&F/NSBP/MS/20 30-11-2022 03-12-2021 Approved 4 Method Statement for Plastering work LT/B&F/NSBP/MS/21 6-12-2021 06-12-2021 Approved 5 Flooring Work LT/B&F/NSBP/MS/22 Resubmitted Resubmitted 05-01-22 08-01-22 Approved 6 Construction Methodology for Water Proofing LT/B&F/NSBP/MS/23 26-10-2021 28-10-2021 Resubmitted 22-11-2021 Approved 7 Profiling and fixing of roof sheeting & wall cl adding LT/B&F/NSBP/MS/PEB/05 - - Resubmitted 06-01-22 8 Method Statement for Paining work LT/B&F/NSBP/MS/24 24-01-22 10-02-22 Approved 9 Tiling work LT/B&F/NSBP/MS/25 19-02-22 - Approved 10 MS Grill LT/B&F/NSBP/MS/ 16-02-22 - Submitted 11 DBM & BC work LT/B&F/NSBP/MS/ 16-02-22 - Submitted 12 False ceiling LT/B&F/NSBP/MS/ 16-02-22 - Submitted
  • 15. L&T Construction| 27 Sensitivity: LNT Construction Internal Use Material/Agency Approval Summary Sl .No. Description Submitted Date Status 1 Weigh Bridge, M/s Essae 25-08-2021 M/s Essae approved 2 Tile (Somany & Kajaria) & Paint (Berger & Asian Paints) shade 09-09-2021 Sample Approved 3 Swellable Water bar (Make-Fosroc) 11-09-2021 Source Approved 4 Flooring Agency 09-11-2021 M/s BGSB Approved 5 Granite Stone Sample 08-11-2021 Approved 6 Sheeting Profile Sample 22-11-2021 Approved 7 HVAC Fan (Make M/s Kruger) 23-12-2021 Approved on 07-01-2022 8 Glazing and ACP works 24-12-2021 M/s Alu/MS approved on 01-02-2022 9 Hollow sections make for PEB elements (M/s Apollo) 03-01-2022 Approved 10 Sectional Door, Rolling shutter, Dock leveler & Shelter (Make- M/s Gandhi) 19-01-2022 Approved on 01-02-2022 11 Make of Fire Door (M/s Radiant) 22-01-2022 Approved 12 DB (Make M/s ABB) 01-02-2022 Approved on 06-02-2022 13 Paver Block (Make M/s JM Mhatre) 27-01-2022 Approved on 08-03-2022 19 Flush Door Laminate Shade Card 19-02-2022 Approved 14 Glazing - Aluminium Colour Shade 19-02-2022 Approved 15 Modular Furniture for Warehouse Office 24-02-2022 Approved 16 Sample of Steel & Fire doors 04-03-2022 Approved 17 Glass Processing Unit for Glazing works (M/s FG Glass) 21-03-2022 Profile submitted 18 Sample for Admin Building 07-05-2022 Approved
  • 16. L&T Construction| 28 Sensitivity: LNT Construction Internal Use Resource Report Manpower Staff Description Nos. Remark Project Management & Planning 03 - Account & Admin 01 - EHS 01 - QA/QC 01 - P&M 01 - Execution-Civil & PEB 09 - Execution-MEP 05 - Total- 21 Nos. Workmen Description Nos. Remark Driver/Operator 12 - Workmen & Helper 215 - Workmen (Temp. Works) 5 - Supervisor & Others 28 - Total- 260 Nos. Machinery Type Nos. Backhoe loader 01 Grader 00 Roller 01 Tractor 03 Boom lift 05 Scissor Lift 00 Trailer 01 F-15 01
  • 17. L&T Construction| 29 Sensitivity: LNT Construction Internal Use IGBC Critical Client Points S No Description Remarks 1 Landscape Drawing AutoCAD format with the mentioned area marked – Tree Area, Shrub Area, Total Landscape Area, Lawn (Turf) Area, and Number of Trees. Plant & Trees Species to be specified. 2 Tkm calculation Sheet to satisfy Case A & Case B mentioned in via Email 3 MHE vehicles Invoice (Fork lift + Pallet Truck + Reach Truck) till date. 4 MHE vehicles and charging point photos (With signage) 5 Golf cart Invoice 6 Golf Cart calculation ensuring 5% of occupants (excluding visitors) are catered 7 Declaration mentioning Organise atleast two outreach/ educational programmes in a year on eco-friendly practices/ green initiatives. The outreach/ educational programmes can include, but not limited to, clean & green, water conservation, energy conservation, waste segregation & recycling, use bio-degradable plastic/ avoid single use plastic, air pollution, world green building week and earth hour 8 Declaration mentioning Atleast 75 % of the fleet (road fleet) complies with BS IV or latest emissions norms. (And) Entire fleet (road fleet) of the service provider will be periodically serviced to ensure efficient vehicle performance. (And) Awareness programmes will be organised periodically, by the service provider, to train the drivers on vehicle maintenance and driving etiquette.
  • 18. L&T Construction| 30 Sensitivity: LNT Construction Internal Use IGBC Critical Client Points S No Description Remarks 9 Provide Posters with education material for drivers shall be placed in drivers’ dormitories or resting areas (vehicle maintenance and driving etiquette) 10 No smoking area photos with signage 11 Floor plans with waste bins 12 Organic Waste Composter with capacity of 160Kg/day to be installed (occupant number considered – 1650) 12 Install permanent educational signage in common areas of the park/ warehouse with green concepts such as Go Green, Save Earth; Water is Precious, Save it; Turn off Lights, when not in use; Say no to Mixed Waste; Plant a Tree, Save the Environment, etc 14 Undertaking for shuttle service connecting local public transit stops in the operating stage – Kindly reshare as the document file got corrupted 15 Project Activity to be identified for Green activity beyond fence. Below are the IGBC recommended projects – • RainWater Harvesting • Sewage Treatment Plant • Water Body • Public Parks/Avenues • Mass Plantation • Renewable Energy • Basic Facilities like – Provide at least four of the following : Bus Shelters, Street Lighting, Public toilets, Play area & Sports kit, Tot-lot, Drinking water ATM or equipment, Organic waste management, other basic facilities
  • 19. L&T Construction| 31 Sensitivity: LNT Construction Internal Use Document submission status/Input required- Client  Handover for Wh-1 & 2 – Taking Over Certificate issuance  Disbursement of RAB-22 Main works  Disbursement of RAB-2 Interior works  EOT approval  Road Marking details approval  Column guard proposal confirmation  View confirmation of cladding fixed over WH-1 & 2 wall along Grid 22
  • 20. L&T Construction| 32 Sensitivity: LNT Construction Internal Use List of Action points among DP World and JNPT SEZ Team S.No Description Action by Target dt Completion dt Resolution Remarks 1 JNPT traffic island development( near to site) L&T Closed 2 Site Entry/exit cover expansion on the JNPT drain DPW L&T submitted the quate for works 3 Trailor movement to site from the JNPT road DPW/JNPT Trailor entry/exit from JNPT road to decide and if required modification to JNPT Median and road 4 Water connection tapping from JNPT Main header line L&T Application submitted to JNPT 5 JNPT RMU Metering panel specification to match by NSBP new Metering panel DPW/CRN/L&T L&T will arrange for connection, Input required regarding specifications of RMU, i.e. CT ratio 6 Building Plan approval- Phase-1 L&T 05-04-2021 01-06-2021 JNPT Already approved 7 Provisional Fire NOC- Phase-1 L&T 23-03-2021 17-03-2021 JNPT Already approved 8 Plinth Checking Phase-1 L&T JNPT Plinth completion certificate received for Admin building, WH-1, WH-2 & Substation. 9 Final Fire NOC - Phase-1 L&T 15-12-2021 JNPT Approval will be taken as per site condition 10 Occupancy Certificate - Phase-1 L&T 15-12-2021 JNPT Occupancy certificate will be with Plumbing certificate 11 Building Plan approval- Phase-2 L&T 19-06-2021 JNPT Approved 12 Provisional Fire NOC- Phase-2 L&T 13-05-2021 JNPT Provisional Fire NOC received 13 Plinth Checking Phase-2 L&T JNPT Approval will be taken as per site condition 14 CCOE/PESO approval L&T 13-07-2021 PESO Required towards the end of works 15 Final Fire NOC - Phase-2 L&T 14-04-2022 JNPT Demand note shared with M/ NSBP for payment 16 Occupancy Certificate - Phase-2 L&T 15-04-2022 JNPT 17 Approval from Airport Authority of India L&T AAI 18 Chief Electrical Inspector to Government (India) L&T 13-12-2021 CEIG 19 DISH approval L&T 15-04-2022 DISH N.A 20 Lift approval L&T 18-12-2021 PWD
  • 21. L&T Construction| 33 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building
  • 22. L&T Construction| 34 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building GF Reception Area Baffle Ceiling fixed Admin Building GF Custom Reception
  • 23. L&T Construction| 35 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building all Revolving Chair received for Workstation, Cabin & Reception
  • 24. L&T Construction| 36 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building GF Dining Area
  • 25. L&T Construction| 37 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building FF Engineering Room Admin Building SF Lobby Side Meeting Room
  • 26. L&T Construction| 38 Sensitivity: LNT Construction Internal Use Site Photographs Admin Building SF Innovation Room Admin Building all EWC Fixture Fixed
  • 27. L&T Construction| 39 Sensitivity: LNT Construction Internal Use Site Photographs Equipment Maintenance Building Municipal Solid Waste Collection Center
  • 28. L&T Construction| 40 Sensitivity: LNT Construction Internal Use Site Photographs Mockup Kerb Stone Painting Mockup Ballard Fixed in WH-5
  • 29. L&T Construction| 42 Sensitivity: LNT Construction Internal Use Insurance Details Sr. No Nature of Policy Policy No Validity Issued By Remarks 01 Marine Cargo 0865087494 31.03.2023 Tata AIG General Insurance Co Ltd. 02 Plant and Machinery 5011/R/150019780/03/000 31.03.2022 ICICI Lombard General Insurance Co ltd. 03 Professional Indemnity 5001002720P103233705 30.06.2022 United India Insurance Co Ltd 04 Workman compensation 411400/48/2022/44 30.03.2022 The Oriental Insurance Company Limited 05 Commercial general liability 5001002720P100653785 31.03.2023 United India Insurance Co Ltd
  • 30. L&T Construction| 43 Sensitivity: LNT Construction Internal Use Thank you!