SlideShare a Scribd company logo
1 of 12
Custer Ave CSO Relief Project
Design and Construction Data
City of Atlanta Department of Watershed Management
72 Marietta Street
Atlanta, GA 30303
BGR Joint Venture
December 1, 2012
Prepared By Adam Carducci
Reviewed By Joe Crooms, P.E.
RohadFox Construction Services
Project Monthly Work Schedule of Events
SITE 32
Week 1. 12/3/12 – 12/7/12
 Grade and form side walk on the north east connecting to existing side walk along Hill Street.
 Remove existing side walk along the west side of Hill St.
 Cut sidewalk and install 3” wide trench drain with steel top and inlet deflectors.
 Install new 6’ wide sidewalk along with place concrete for transition side walk.
 Place concrete for inlet channel embedded with river cobble.
 Place 4” mulch layer at Flat Bottom Bio-Retention area.
 Five working days.
Week 2. 12/10/12 – 12/14/12
 Import soil for embankment areas as needed fine grade to establish 4/1 slope.
 Remove site spoils clean north Bio-Retention area , haul off as needed.
 Hydro Seed remainder of Bio-Retention area.
 Adjust manhole casting structure to elevation 963.43 or as directed.
 Begin removal of existing granite curb.
 Saw cut pavement at the spring line of Cherokee and Kelly Road.
 Saw cut asphalt pavement per area defined on plan on Cherokee St.
 Begin pavement removal on north side of existing pavement working south.
 Five working days.
Week 3. 12/17/12 – 12/21/12
 Continue to remove and haul remainder of concrete pavement on Kelly St.
 Remove existing catch basins and storm pipe to existing junction Box, properly seal connection point.
 Place GAB stone material along abandoned trench line, compaction testing per direction of Contract Manager.
 Begin subgrade condition process; excavating to sub grade elevation grading north of existing junction box.
 Fill areas as needed to raise slope elevation south of existing junction box.
 Begin to cut or fill for areas under the proposed curb on east and west sides.
 Crew would need to establish a stone access road for residence to homes.
 Five working days.
Week 4. 12/24/12 – 12/28/12
 Holiday observance for 12/24 – 12/25 (or remainder of week per City of Atlanta staff availability) .
 Establish line and grade for proposed curbs.
 Place stone base under proposed curb and gutter along with forms placed tied into areas per plan.
 Place concrete if available for new concrete curb and gutter.
 Adjust existing junction box as needed.
 Remove residential concrete driveways , saw cut transitional sidewalk for resident on the north side.
 Place stone access for residential drive approaches.
 Three working days.
Week 5. 12/31/12 - 1/4/13
 Holiday observance for days 12/31/12 – 1/1/13.
 Continue with proposed concrete pavement subgrade condition work.
 Place first 6” lift of graded aggregate base course on Kelly St.
 Begin full depth asphalt pavement removal on Cherokee St.
 Place first 6 “ lift of graded aggregate base on Cherokee St.
 Compaction testing per direction of City of Atlanta Contract Manager.
 Asphalt mix design review sent in for City of Atlanta approval.
 Three working days.
Week 6. 1/7/13 – 1/11/13
 Place final 6” graded aggregate base course for Kelly street.
 Fine grade compaction testing per direction of City of Atlanta Contract Manager.
 Place new 26’ wide concrete roadway per Fulton County Detail (use of high early mix encouraged).
 Seven day cure process (if applicable).
 Saw cut contraction joints as needed.
 Place concrete for residential drive approaches.
 Five working days.
Week 7. 1/14/13 – 1/18/13
 Final 6” layer of graded aggregate base course for Cherokee St.
 Compaction testing for graded aggregate base course per direction of City of Atlanta Contract Manager.
 Adjust manhole on Cherokee St. if needed.
 Place base course asphalt material on Cherokee St.
 Place level course of asphalt on Cherokee St.
 Place surface course per approval of City of Atlanta Contract Manager (cold weather limits).
 Restoration of north area begins, removal of tree protection on north end of Bio-Retention area.
 Placing topsoil behind curb areas, seed or sod as directed.
 Five working days.
Week 8. 1/21/13 – 1/25/12
 Final clean up.
 Removal debris and tree protection.
 Equipment removal.
 Projected Completion date 1/22/13.
 Two working days.
Contact Information
Adam Carducci
Field Engineer
ROHADFOX - RCCSC
171 17th Street NW, Suite 1625
Atlanta, GA 30363
[P] 404.880.9888
[M] 404.849.4009
[F] 404.880.9911
a.carducci@rccsc.net
www.rccsc.net
Joe Crooms, P. E.
Project Manager
ROHADFOX - RCCSC
Program Management, Construction
Management
171 17th Street NW, Suite 1625
Atlanta, GA 30363
[P] 404.880.9888
[M] 404.771.9007
[F] 404.880.9911
joe.crooms@rccsc.net
www.rccsc.net

More Related Content

What's hot

Geotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILLGeotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILLDr. Malek Smadi
 
ATT_1442257750728_matt resume
ATT_1442257750728_matt resumeATT_1442257750728_matt resume
ATT_1442257750728_matt resumeCharles Roberts
 
Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation VDOT Northern Virginia
 
How to Get the Most Out of Your Geotechnical Engineer
How to Get the Most Out of Your Geotechnical EngineerHow to Get the Most Out of Your Geotechnical Engineer
How to Get the Most Out of Your Geotechnical Engineerjbreedlove
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectFairfax County
 
9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration Project9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration ProjectFairfax County
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
 
MacDonald Dan Oct 1 2014 [1130 am Session A] TAC 2014 Montreal [Compat...
MacDonald Dan   Oct 1  2014 [1130 am  Session A]   TAC 2014  Montreal [Compat...MacDonald Dan   Oct 1  2014 [1130 am  Session A]   TAC 2014  Montreal [Compat...
MacDonald Dan Oct 1 2014 [1130 am Session A] TAC 2014 Montreal [Compat...Dan MacDonald, P.Eng.
 
Gen geot cs_uva_15.1
Gen geot cs_uva_15.1Gen geot cs_uva_15.1
Gen geot cs_uva_15.1Tensar
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County
 
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement ProjectGlenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement ProjectFairfax County
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingVDOT Northern Virginia
 
2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKSTimothy Antos
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
 
2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2Ismael Vazquez, LSIT
 
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement Project
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFranklin Park and Chesterbrook Neighborhood Stormwater Improvement Project
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFairfax County
 

What's hot (20)

Geotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILLGeotechnical report by Dr. Malek Samdi of GEOTILL
Geotechnical report by Dr. Malek Samdi of GEOTILL
 
ATT_1442257750728_matt resume
ATT_1442257750728_matt resumeATT_1442257750728_matt resume
ATT_1442257750728_matt resume
 
Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation
 
Resume Jun 2015
Resume Jun 2015Resume Jun 2015
Resume Jun 2015
 
How to Get the Most Out of Your Geotechnical Engineer
How to Get the Most Out of Your Geotechnical EngineerHow to Get the Most Out of Your Geotechnical Engineer
How to Get the Most Out of Your Geotechnical Engineer
 
Lindsay Minck 2015
Lindsay Minck 2015Lindsay Minck 2015
Lindsay Minck 2015
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation Project
 
9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration Project9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration Project
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main Project
 
MacDonald Dan Oct 1 2014 [1130 am Session A] TAC 2014 Montreal [Compat...
MacDonald Dan   Oct 1  2014 [1130 am  Session A]   TAC 2014  Montreal [Compat...MacDonald Dan   Oct 1  2014 [1130 am  Session A]   TAC 2014  Montreal [Compat...
MacDonald Dan Oct 1 2014 [1130 am Session A] TAC 2014 Montreal [Compat...
 
ASCEMLSTPRESENTATION 05-06-03.PPT
ASCEMLSTPRESENTATION 05-06-03.PPTASCEMLSTPRESENTATION 05-06-03.PPT
ASCEMLSTPRESENTATION 05-06-03.PPT
 
Gen geot cs_uva_15.1
Gen geot cs_uva_15.1Gen geot cs_uva_15.1
Gen geot cs_uva_15.1
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016
 
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement ProjectGlenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement Project
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
 
2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
sariki profile
sariki profilesariki profile
sariki profile
 
2016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev22016-08-18-DCCR Presentation for DOT rev2
2016-08-18-DCCR Presentation for DOT rev2
 
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement Project
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFranklin Park and Chesterbrook Neighborhood Stormwater Improvement Project
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement Project
 

Viewers also liked

Presentation_LeedCD_245
Presentation_LeedCD_245Presentation_LeedCD_245
Presentation_LeedCD_245Adam Carducci
 
Project Presentation
Project PresentationProject Presentation
Project PresentationAdam Carducci
 
Simple Ball Project
Simple Ball ProjectSimple Ball Project
Simple Ball ProjectAhmad Khalid
 
Bremer story post-hoc analysis
Bremer story post-hoc analysisBremer story post-hoc analysis
Bremer story post-hoc analysismark gould
 
keyboard and mouse events
keyboard and mouse eventskeyboard and mouse events
keyboard and mouse eventsAhmad Khalid
 
JOE PONTILLAS FRANCIA
JOE PONTILLAS FRANCIAJOE PONTILLAS FRANCIA
JOE PONTILLAS FRANCIAjoe francia
 
Bremer Story (as in EQ website)
Bremer Story (as in EQ website)Bremer Story (as in EQ website)
Bremer Story (as in EQ website)mark gould
 
Script for ABC Ockhams Razor
Script for ABC Ockhams RazorScript for ABC Ockhams Razor
Script for ABC Ockhams Razormark gould
 
Unit_3_Self Marketing
Unit_3_Self MarketingUnit_3_Self Marketing
Unit_3_Self MarketingAdam Carducci
 
3G07_NEO衝突検知・警報システムのミッションデザイン
3G07_NEO衝突検知・警報システムのミッションデザイン3G07_NEO衝突検知・警報システムのミッションデザイン
3G07_NEO衝突検知・警報システムのミッションデザインAlessandro Takeshi Morita Gagliardi
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and TechniquesAdam Carducci
 

Viewers also liked (16)

Presentation_LeedCD_245
Presentation_LeedCD_245Presentation_LeedCD_245
Presentation_LeedCD_245
 
RESUME_2015
RESUME_2015RESUME_2015
RESUME_2015
 
Project Presentation
Project PresentationProject Presentation
Project Presentation
 
Simple Ball Project
Simple Ball ProjectSimple Ball Project
Simple Ball Project
 
Bremer story post-hoc analysis
Bremer story post-hoc analysisBremer story post-hoc analysis
Bremer story post-hoc analysis
 
keyboard and mouse events
keyboard and mouse eventskeyboard and mouse events
keyboard and mouse events
 
JOE PONTILLAS FRANCIA
JOE PONTILLAS FRANCIAJOE PONTILLAS FRANCIA
JOE PONTILLAS FRANCIA
 
Bremer Story (as in EQ website)
Bremer Story (as in EQ website)Bremer Story (as in EQ website)
Bremer Story (as in EQ website)
 
Python Games
Python GamesPython Games
Python Games
 
Script for ABC Ockhams Razor
Script for ABC Ockhams RazorScript for ABC Ockhams Razor
Script for ABC Ockhams Razor
 
Unit_3_Self Marketing
Unit_3_Self MarketingUnit_3_Self Marketing
Unit_3_Self Marketing
 
Presentation1
Presentation1Presentation1
Presentation1
 
South East Atlanta
South East AtlantaSouth East Atlanta
South East Atlanta
 
RESUME
RESUMERESUME
RESUME
 
3G07_NEO衝突検知・警報システムのミッションデザイン
3G07_NEO衝突検知・警報システムのミッションデザイン3G07_NEO衝突検知・警報システムのミッションデザイン
3G07_NEO衝突検知・警報システムのミッションデザイン
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 

Similar to Site 32 Presentation

Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013 carsoncorporation
 
Washington County Road 4: Overlay with Geotextile Fabric
Washington County Road 4: Overlay with Geotextile FabricWashington County Road 4: Overlay with Geotextile Fabric
Washington County Road 4: Overlay with Geotextile FabricJill Reeves
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020Fairfax County
 
City of Salina-9th Street Curb & Gutter Project
City of Salina-9th Street Curb & Gutter ProjectCity of Salina-9th Street Curb & Gutter Project
City of Salina-9th Street Curb & Gutter ProjectCity of Salina
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Fairfax County
 
Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017
Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017
Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017Fairfax County
 
Celestain Jr Alfred_Refernce
Celestain Jr Alfred_RefernceCelestain Jr Alfred_Refernce
Celestain Jr Alfred_RefernceAlfred Celestain
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINTThomas Bryce
 
ABC in Alabama_2015 National ABC Conference Presentation
ABC in Alabama_2015 National ABC Conference PresentationABC in Alabama_2015 National ABC Conference Presentation
ABC in Alabama_2015 National ABC Conference PresentationDavid Tomley
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage ProjectAndrew Motycka
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentationknelischer
 
CPAC Meeting 9-22-03
CPAC Meeting 9-22-03CPAC Meeting 9-22-03
CPAC Meeting 9-22-03HartTWI
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16Don Dwyer
 
Foundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic RepairsFoundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic Repairsjamieram
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingVDOT Northern Virginia
 

Similar to Site 32 Presentation (20)

Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013
 
Washington County Road 4: Overlay with Geotextile Fabric
Washington County Road 4: Overlay with Geotextile FabricWashington County Road 4: Overlay with Geotextile Fabric
Washington County Road 4: Overlay with Geotextile Fabric
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020
 
City of Salina-9th Street Curb & Gutter Project
City of Salina-9th Street Curb & Gutter ProjectCity of Salina-9th Street Curb & Gutter Project
City of Salina-9th Street Curb & Gutter Project
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
 
Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017
Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017
Storm Pipe Relining (Cured-in-Place Pipe Lining) FY 2017
 
Celestain Jr Alfred_Refernce
Celestain Jr Alfred_RefernceCelestain Jr Alfred_Refernce
Celestain Jr Alfred_Refernce
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT
 
ABC in Alabama_2015 National ABC Conference Presentation
ABC in Alabama_2015 National ABC Conference PresentationABC in Alabama_2015 National ABC Conference Presentation
ABC in Alabama_2015 National ABC Conference Presentation
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage Project
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentation
 
CPAC Meeting 9-22-03
CPAC Meeting 9-22-03CPAC Meeting 9-22-03
CPAC Meeting 9-22-03
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16
 
Building Prothro Football Practice Fields
Building Prothro Football Practice FieldsBuilding Prothro Football Practice Fields
Building Prothro Football Practice Fields
 
Foundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic RepairsFoundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic Repairs
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 

Site 32 Presentation

  • 1. Custer Ave CSO Relief Project Design and Construction Data City of Atlanta Department of Watershed Management 72 Marietta Street Atlanta, GA 30303 BGR Joint Venture December 1, 2012 Prepared By Adam Carducci Reviewed By Joe Crooms, P.E. RohadFox Construction Services Project Monthly Work Schedule of Events SITE 32
  • 2.
  • 3.
  • 4. Week 1. 12/3/12 – 12/7/12  Grade and form side walk on the north east connecting to existing side walk along Hill Street.  Remove existing side walk along the west side of Hill St.  Cut sidewalk and install 3” wide trench drain with steel top and inlet deflectors.  Install new 6’ wide sidewalk along with place concrete for transition side walk.  Place concrete for inlet channel embedded with river cobble.  Place 4” mulch layer at Flat Bottom Bio-Retention area.  Five working days.
  • 5. Week 2. 12/10/12 – 12/14/12  Import soil for embankment areas as needed fine grade to establish 4/1 slope.  Remove site spoils clean north Bio-Retention area , haul off as needed.  Hydro Seed remainder of Bio-Retention area.  Adjust manhole casting structure to elevation 963.43 or as directed.  Begin removal of existing granite curb.  Saw cut pavement at the spring line of Cherokee and Kelly Road.  Saw cut asphalt pavement per area defined on plan on Cherokee St.  Begin pavement removal on north side of existing pavement working south.  Five working days.
  • 6. Week 3. 12/17/12 – 12/21/12  Continue to remove and haul remainder of concrete pavement on Kelly St.  Remove existing catch basins and storm pipe to existing junction Box, properly seal connection point.  Place GAB stone material along abandoned trench line, compaction testing per direction of Contract Manager.  Begin subgrade condition process; excavating to sub grade elevation grading north of existing junction box.  Fill areas as needed to raise slope elevation south of existing junction box.  Begin to cut or fill for areas under the proposed curb on east and west sides.  Crew would need to establish a stone access road for residence to homes.  Five working days.
  • 7. Week 4. 12/24/12 – 12/28/12  Holiday observance for 12/24 – 12/25 (or remainder of week per City of Atlanta staff availability) .  Establish line and grade for proposed curbs.  Place stone base under proposed curb and gutter along with forms placed tied into areas per plan.  Place concrete if available for new concrete curb and gutter.  Adjust existing junction box as needed.  Remove residential concrete driveways , saw cut transitional sidewalk for resident on the north side.  Place stone access for residential drive approaches.  Three working days.
  • 8. Week 5. 12/31/12 - 1/4/13  Holiday observance for days 12/31/12 – 1/1/13.  Continue with proposed concrete pavement subgrade condition work.  Place first 6” lift of graded aggregate base course on Kelly St.  Begin full depth asphalt pavement removal on Cherokee St.  Place first 6 “ lift of graded aggregate base on Cherokee St.  Compaction testing per direction of City of Atlanta Contract Manager.  Asphalt mix design review sent in for City of Atlanta approval.  Three working days.
  • 9. Week 6. 1/7/13 – 1/11/13  Place final 6” graded aggregate base course for Kelly street.  Fine grade compaction testing per direction of City of Atlanta Contract Manager.  Place new 26’ wide concrete roadway per Fulton County Detail (use of high early mix encouraged).  Seven day cure process (if applicable).  Saw cut contraction joints as needed.  Place concrete for residential drive approaches.  Five working days.
  • 10. Week 7. 1/14/13 – 1/18/13  Final 6” layer of graded aggregate base course for Cherokee St.  Compaction testing for graded aggregate base course per direction of City of Atlanta Contract Manager.  Adjust manhole on Cherokee St. if needed.  Place base course asphalt material on Cherokee St.  Place level course of asphalt on Cherokee St.  Place surface course per approval of City of Atlanta Contract Manager (cold weather limits).  Restoration of north area begins, removal of tree protection on north end of Bio-Retention area.  Placing topsoil behind curb areas, seed or sod as directed.  Five working days.
  • 11. Week 8. 1/21/13 – 1/25/12  Final clean up.  Removal debris and tree protection.  Equipment removal.  Projected Completion date 1/22/13.  Two working days.
  • 12. Contact Information Adam Carducci Field Engineer ROHADFOX - RCCSC 171 17th Street NW, Suite 1625 Atlanta, GA 30363 [P] 404.880.9888 [M] 404.849.4009 [F] 404.880.9911 a.carducci@rccsc.net www.rccsc.net Joe Crooms, P. E. Project Manager ROHADFOX - RCCSC Program Management, Construction Management 171 17th Street NW, Suite 1625 Atlanta, GA 30363 [P] 404.880.9888 [M] 404.771.9007 [F] 404.880.9911 joe.crooms@rccsc.net www.rccsc.net