SlideShare a Scribd company logo
1 of 33
Download to read offline
ACCELERATED BRIDGE CONSTRUCTION
Ross Clark Circle Bridge Slide
Dothan, Alabama
231 431
231
Ross Clark Circle (west side)
US 231
Built in 1950s
Divided Four Lane
Average Daily Traffic
o design – 5,000
o current > 40,000
o 20 year ≈ 73,000
Beaver Creek Culvert
3 BBL 10’(↔) x 6’ (↨)
155 ft long
20’ fill
Structurally Deficient
(severely cracked)
Opening has immersed
UTILITIES
WATER
SEWER
OVERHEAD
ELECTRIC
TELEPHONE /
CABLE
Exit End
Entry End
Contractor provides
engineered design
Temporary Shoring Boxes and Falsework
Temporary Shoring Boxes
Used to construct the
permanent bridge
abutment piles and cap
seats
Temporary Falsework
Used to construct the new bridge
superstructure adjacent to the
permanent structure location and
for support during the bridge slide
Temporary Falsework
Temporary Shoring Boxes
Cost effective
Used material that was
readily available to McInnis
Construction
Could be installed quickly at
the project site
Could be de-constructed
Could be re-used on future
projects
In order to ensure
proper geometry
controls and check
constructability, McInnis
Construction set up a
pre-fabrication site at
their home office to
verify the temporary
shoring box geometry
and fit-up, pick weights
and crane reach
requirements,
fabrication steps,
transportation
requirements, and de-
construction sequence
Pre-Fabrication Site
Thompson Engineering coordinated the AASHTO
LRFD design of the temporary shoring box with
McInnis Construction in order to optimize
construction means & methods.
Lay-Down Area
Construction activities
continued concurrently as
the shoring boxes were built
in the Lay-Down area.
A two phase traffic control was used to maintain traffic during
excavation and installation of the shoring boxes. The first phase
shifted traffic to the inside with excavation on the outside.
A plan note required existing traffic to be maintained
during peak hours, therefore McInnis Construction
installed the shoring boxes during the weekend
including nighttime work to minimize impacts to traffic.
To stay within the crane capacity
the upper lid and side sill plates
were erected separately.
Backfilling and approach roadway
asphalt being completed.
Corner piles and timber wingwalls
were installed to support the
approach roadway embankment.
Phase two traffic control
shifted traffic to the outside
while construction activities
were repeated on the inside.
Excavation continued on the
inside while traffic was
maintained on the outside.
Shoring boxes being erected
and set in the trench.
The last of the four shoring boxes
being set adjacent to traffic.
Inside
excavation.
Pile Driving Preparation
After the shoring
boxes were
installed, pile layout
and geometry
control checks were
made prior to pile
driving.
A similar inside/outside traffic control was used to
drive the piles after the upper lids of the shoring boxes
were removed.
Additional falsework piles were driven on the outside.
After the piles were
installed the abutment cap
seat was constructed.
Temporary Falsework
Temporary
falsework was
installed adjacent
to the new bridge
location to
support the new
superstructure in
preparation for
the bridge slide.
The BT-63 inch precast prestressed concrete
bulb-tee girders were erected adjacent to
the new bridge location on the falsework.
Shoring system needs to be wrapped with plastic or filter
blanket to stop intrusion of sand from backfilling around the
box.
Top sill plate on sidewalls needs reinforcement/stiffness for
when asphalt is placed adjacent to it. Sill plate deformation
caused the top lid to become extremely difficult to lift and
place during lane closure construction.
Shoring system was designed heavy for reusing
purposes. However, we need it to be lighter or have a larger
crane so we could set a more completed section during lane
closure construction.
Backfilling the shoring boxes after excavation took the
longest time. More ways to improve logistics on job site.
Prefabricating the boxes worked good. Need to improve on
the shipping dimensions and time to fabricate on the job
site.
Owner & Project
Designer: Alabama
Department of
Transportation
Contractor: McInnis
Construction
Construction Engineer:
Thompson Engineering
ABC in Alabama_2015 National ABC Conference Presentation

More Related Content

What's hot (20)

Steel structures
Steel structuresSteel structures
Steel structures
 
Truss Bridge Report
Truss Bridge ReportTruss Bridge Report
Truss Bridge Report
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridge
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridge
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
Building Structure Project 1 Report
Building Structure Project 1 ReportBuilding Structure Project 1 Report
Building Structure Project 1 Report
 
Bridge construction atlas
Bridge construction atlasBridge construction atlas
Bridge construction atlas
 
Steel structures failure
Steel structures failureSteel structures failure
Steel structures failure
 
Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
 
Metal structures
Metal  structures Metal  structures
Metal structures
 
Bridge
BridgeBridge
Bridge
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Bridges precast
Bridges precastBridges precast
Bridges precast
 
Ppt bridges & types
Ppt bridges & typesPpt bridges & types
Ppt bridges & types
 
Bridge facts
Bridge factsBridge facts
Bridge facts
 
Final report design of a pedestrian bridge - fall 2009
Final report   design of a pedestrian bridge - fall 2009Final report   design of a pedestrian bridge - fall 2009
Final report design of a pedestrian bridge - fall 2009
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its Types
 
Types of bridge(theory.explanation)
Types of bridge(theory.explanation)Types of bridge(theory.explanation)
Types of bridge(theory.explanation)
 
PPT On High level bridge
PPT On High level bridgePPT On High level bridge
PPT On High level bridge
 
Susppension bridges
Susppension bridges Susppension bridges
Susppension bridges
 

Viewers also liked

Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differencesscaffolddesign
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueSandeep Jain
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 

Viewers also liked (9)

Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differences
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Formwork
FormworkFormwork
Formwork
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
What is Big Data?
What is Big Data?What is Big Data?
What is Big Data?
 

Similar to ABC in Alabama_2015 National ABC Conference Presentation

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxLokeswarSaha1
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINALJoe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINALJoseph Kaufman
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxVinayak247538
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptxAnanthakumar75
 
Cable stay bridge construction
Cable stay bridge constructionCable stay bridge construction
Cable stay bridge constructionBalkrishan Kushwah
 

Similar to ABC in Alabama_2015 National ABC Conference Presentation (20)

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Metroppt
MetropptMetroppt
Metroppt
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINALJoe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
Joe Kaufman SEAoO Scholarship Report 2016 7 Pages Total - REVISED FINAL
 
07 soil-grout threadbar
07 soil-grout threadbar07 soil-grout threadbar
07 soil-grout threadbar
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
 
Cable stay bridge construction
Cable stay bridge constructionCable stay bridge construction
Cable stay bridge construction
 

ABC in Alabama_2015 National ABC Conference Presentation

  • 1. ACCELERATED BRIDGE CONSTRUCTION Ross Clark Circle Bridge Slide Dothan, Alabama
  • 2.
  • 4.
  • 5. Ross Clark Circle (west side) US 231 Built in 1950s Divided Four Lane Average Daily Traffic o design – 5,000 o current > 40,000 o 20 year ≈ 73,000
  • 6. Beaver Creek Culvert 3 BBL 10’(↔) x 6’ (↨) 155 ft long 20’ fill Structurally Deficient (severely cracked) Opening has immersed
  • 10.
  • 11.
  • 13. Temporary Shoring Boxes and Falsework Temporary Shoring Boxes Used to construct the permanent bridge abutment piles and cap seats Temporary Falsework Used to construct the new bridge superstructure adjacent to the permanent structure location and for support during the bridge slide
  • 15. Temporary Shoring Boxes Cost effective Used material that was readily available to McInnis Construction Could be installed quickly at the project site Could be de-constructed Could be re-used on future projects
  • 16. In order to ensure proper geometry controls and check constructability, McInnis Construction set up a pre-fabrication site at their home office to verify the temporary shoring box geometry and fit-up, pick weights and crane reach requirements, fabrication steps, transportation requirements, and de- construction sequence Pre-Fabrication Site Thompson Engineering coordinated the AASHTO LRFD design of the temporary shoring box with McInnis Construction in order to optimize construction means & methods.
  • 17. Lay-Down Area Construction activities continued concurrently as the shoring boxes were built in the Lay-Down area.
  • 18. A two phase traffic control was used to maintain traffic during excavation and installation of the shoring boxes. The first phase shifted traffic to the inside with excavation on the outside.
  • 19. A plan note required existing traffic to be maintained during peak hours, therefore McInnis Construction installed the shoring boxes during the weekend including nighttime work to minimize impacts to traffic.
  • 20. To stay within the crane capacity the upper lid and side sill plates were erected separately.
  • 21. Backfilling and approach roadway asphalt being completed.
  • 22. Corner piles and timber wingwalls were installed to support the approach roadway embankment. Phase two traffic control shifted traffic to the outside while construction activities were repeated on the inside.
  • 23. Excavation continued on the inside while traffic was maintained on the outside.
  • 24. Shoring boxes being erected and set in the trench.
  • 25. The last of the four shoring boxes being set adjacent to traffic. Inside excavation.
  • 26. Pile Driving Preparation After the shoring boxes were installed, pile layout and geometry control checks were made prior to pile driving.
  • 27. A similar inside/outside traffic control was used to drive the piles after the upper lids of the shoring boxes were removed. Additional falsework piles were driven on the outside.
  • 28. After the piles were installed the abutment cap seat was constructed.
  • 29. Temporary Falsework Temporary falsework was installed adjacent to the new bridge location to support the new superstructure in preparation for the bridge slide.
  • 30. The BT-63 inch precast prestressed concrete bulb-tee girders were erected adjacent to the new bridge location on the falsework.
  • 31. Shoring system needs to be wrapped with plastic or filter blanket to stop intrusion of sand from backfilling around the box. Top sill plate on sidewalls needs reinforcement/stiffness for when asphalt is placed adjacent to it. Sill plate deformation caused the top lid to become extremely difficult to lift and place during lane closure construction. Shoring system was designed heavy for reusing purposes. However, we need it to be lighter or have a larger crane so we could set a more completed section during lane closure construction. Backfilling the shoring boxes after excavation took the longest time. More ways to improve logistics on job site. Prefabricating the boxes worked good. Need to improve on the shipping dimensions and time to fabricate on the job site.
  • 32. Owner & Project Designer: Alabama Department of Transportation Contractor: McInnis Construction Construction Engineer: Thompson Engineering