Belmont Ridge Road Pardon Our Dust meeting
1. Route 659 (Belmont Ridge Road)
Reconstruct to 4-Lanes Project
Pardon Our Dust Meeting
Belmont Station Elementary School
October 27, 2016
2. 2
Northern Virginia Transportation Authority
Loudoun County
Virginia Department of Transportation
Dewberry Consultants, LLC
Shirley Contracting Company
The Project Team
3. 3
Objectives
Project Location
Project Purpose and Need
Provide an Overview of Design Features
Describe Construction Sequence
Discuss the Project Schedule
Answer Your Questions
5. • Improve traffic safety
through improvements to
roadway geometry,
operations, and grade
separation of W&OD
• Improve capacity &
reduce congestion
• Enhance Connectivity of
Regional Multimodal
Transportation Network
• Complete 4 lane roadway
section from Route 7 to
the Dulles Greenway 5
Project Purpose and Need
6. 6
Major Design Features
Typical Section
Four lane divided roadway
26’ Wide Grass Median
10’ Wide Shared Use Path on Both Sides
of the Road
11. 11
• Wall 1: Hay Rd. to 876’ North, Aprox.13’ Tall
Scheduled to complete by end of 2017.
Major Design Features
Noise Barriers
12. 12
• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF,
Approx. 13’ Tall, and Scheduled to complete by end of 2017.
Major Design Features
Noise Barriers
13. 13
• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF,
Approx. 13’ Tall, and Scheduled to complete by end of 2017.
Major Design Features
Noise Barriers
14. 14
•Wall 3: Chesterton
St. to 384’ North,
Aprox.13’ Tall
Scheduled to be
complete by end
of 2017.
Major Design Features
Noise Barriers
15. 15
• Concrete Posts and
Concrete Panels
•Panels:
Ashlar Stone Pattern
with a 12 Inch Tall
Coping on the Top
Stained Color Hopsac
Major Design Features
Noise Barriers
16. 16
Project Metrics
Total Project Budget: $61 Million
Construction Contract Value: $45.5 Million
Project Length: 1.9 Miles
Right-of-Way Acquisition: 26 Parcels
Adjustments to 5 Utilities
Project Duration: 39 months
17. 17
Construction Metrics
Communications 13,000 LF Line
Relocations
Overhead Power 9,000 LF
Gas Line 7,000 LF Relocations
36” Water Main: 10,000 LF
Earth Moving: 125,000 CY
(15,500 Truck Loads)
Storm Drainage: 14,200 LF Pipe
155 Drainage Structures
Pavement Stone: 45,000 Tons
Asphalt Pavement: 80,000 Tons
Noise Barrier: 47,000 SF
Pavement Markings: 130,000 LF
18. 18
September 2015 Notice To Proceed
October 2015 - July 2016 Complete Design / Permitting
Summer 2016 - Winter 2016 Right of Way Acquisition
Fall 2016 - Winter 2017 Utility Relocations
October 31, 2017 Grade Separation Complete
Fall 2016 - Winter 2017 Stage 1 Construction
Winter 2017 - Fall 2018 Stage 2 Construction
Winter 2018 Stage 3 / Complete Project
Project Schedule
19. Addressing Your Concerns…
Regarding Construction
19
A majority of the construction operations will be on
weekdays during normal daytime hours, generally 6:00 am to
6:00 pm.
Weekends will be utilized as make-up day due to weather.
Flagging operations to a single lane will be performed to
place safety measures and equipment access.
Nighttime operations will result in noise impacts.
Notices will be distributed to email distribution list and
directly to fire, rescue, and school personnel.
VDOT to send press releases for major traffic shifts.
Speed limit will be reduced from 45 mph to 40 mph during
construction.