SlideShare a Scribd company logo
1 of 20
Route 659 (Belmont Ridge Road)
Reconstruct to 4-Lanes Project
Pardon Our Dust Meeting
Belmont Station Elementary School
October 27, 2016
2
 Northern Virginia Transportation Authority
 Loudoun County
 Virginia Department of Transportation
 Dewberry Consultants, LLC
 Shirley Contracting Company
The Project Team
3
Objectives
 Project Location
 Project Purpose and Need
 Provide an Overview of Design Features
Describe Construction Sequence
Discuss the Project Schedule
Answer Your Questions
Project Location
4
North
South
West East
• Improve traffic safety
through improvements to
roadway geometry,
operations, and grade
separation of W&OD
• Improve capacity &
reduce congestion
• Enhance Connectivity of
Regional Multimodal
Transportation Network
• Complete 4 lane roadway
section from Route 7 to
the Dulles Greenway 5
Project Purpose and Need
6
Major Design Features
Typical Section
 Four lane divided roadway
 26’ Wide Grass Median
 10’ Wide Shared Use Path on Both Sides
of the Road
7
Construction Sequence
Stages 1, 2 & 3
8
Bridge Construction Sequence
Stages 1 & 2
9
Major Design Features
Grade Separated Interchange Over
W&OD Trail
10
Major Design Features
W&OD Trail Parking Facility
11
• Wall 1: Hay Rd. to 876’ North, Aprox.13’ Tall
Scheduled to complete by end of 2017.
Major Design Features
Noise Barriers
12
• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF,
Approx. 13’ Tall, and Scheduled to complete by end of 2017.
Major Design Features
Noise Barriers
13
• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF,
Approx. 13’ Tall, and Scheduled to complete by end of 2017.
Major Design Features
Noise Barriers
14
•Wall 3: Chesterton
St. to 384’ North,
Aprox.13’ Tall
Scheduled to be
complete by end
of 2017.
Major Design Features
Noise Barriers
15
• Concrete Posts and
Concrete Panels
•Panels:
Ashlar Stone Pattern
with a 12 Inch Tall
Coping on the Top
Stained Color Hopsac
Major Design Features
Noise Barriers
16
Project Metrics
Total Project Budget: $61 Million
Construction Contract Value: $45.5 Million
Project Length: 1.9 Miles
Right-of-Way Acquisition: 26 Parcels
Adjustments to 5 Utilities
Project Duration: 39 months
17
Construction Metrics
 Communications 13,000 LF Line
Relocations
 Overhead Power 9,000 LF
 Gas Line 7,000 LF Relocations
 36” Water Main: 10,000 LF
 Earth Moving: 125,000 CY
(15,500 Truck Loads)
 Storm Drainage: 14,200 LF Pipe
155 Drainage Structures
 Pavement Stone: 45,000 Tons
 Asphalt Pavement: 80,000 Tons
 Noise Barrier: 47,000 SF
 Pavement Markings: 130,000 LF
18
September 2015 Notice To Proceed
October 2015 - July 2016 Complete Design / Permitting
Summer 2016 - Winter 2016 Right of Way Acquisition
Fall 2016 - Winter 2017 Utility Relocations
October 31, 2017 Grade Separation Complete
Fall 2016 - Winter 2017 Stage 1 Construction
Winter 2017 - Fall 2018 Stage 2 Construction
Winter 2018 Stage 3 / Complete Project
Project Schedule
Addressing Your Concerns…
Regarding Construction
19
 A majority of the construction operations will be on
weekdays during normal daytime hours, generally 6:00 am to
6:00 pm.
 Weekends will be utilized as make-up day due to weather.
 Flagging operations to a single lane will be performed to
place safety measures and equipment access.
 Nighttime operations will result in noise impacts.
 Notices will be distributed to email distribution list and
directly to fire, rescue, and school personnel.
 VDOT to send press releases for major traffic shifts.
 Speed limit will be reduced from 45 mph to 40 mph during
construction.
20
http://www.virginiadot.org/projects/northernvirginia/belmont
_ridge_road_widening.asp
(this webpage will be updated throughout the project development)
Or Google: “Belmont Ridge Road Widening”
Questions and Answers
For More Information About Route
659 Widening Project:

More Related Content

What's hot

Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk Fairfax County
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Crosstown TO
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationFairfax County
 

What's hot (20)

Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
 

Similar to Belmont Ridge Road Pardon Our Dust meeting

Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016Pont Samuel-De Champlain Bridge
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Pont Samuel-De Champlain Bridge
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Fairfax County
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentationZiad el-Balbisi
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
 
Project Induction Program 11.02.2016
Project Induction Program 11.02.2016Project Induction Program 11.02.2016
Project Induction Program 11.02.2016Lasantha Perera
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Pont Samuel-De Champlain Bridge
 

Similar to Belmont Ridge Road Pardon Our Dust meeting (20)

Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Four Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force PresentationFour Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force Presentation
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Public Information Meeting - Verdu - May 25, 2016
Public Information Meeting - Verdu - May 25, 2016Public Information Meeting - Verdu - May 25, 2016
Public Information Meeting - Verdu - May 25, 2016
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentation
 
Center Road sidewalk
Center Road sidewalkCenter Road sidewalk
Center Road sidewalk
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Project Induction Program 11.02.2016
Project Induction Program 11.02.2016Project Induction Program 11.02.2016
Project Induction Program 11.02.2016
 
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
 
ORahman-Resume
ORahman-ResumeORahman-Resume
ORahman-Resume
 
Wellborn Community Plan
Wellborn Community PlanWellborn Community Plan
Wellborn Community Plan
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016
 
Crosstown apwa presentation2016 04-19
Crosstown apwa presentation2016 04-19Crosstown apwa presentation2016 04-19
Crosstown apwa presentation2016 04-19
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017
 

More from VDOT Northern Virginia

2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow BriefingVDOT Northern Virginia
 
2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow Briefing2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow BriefingVDOT Northern Virginia
 
Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016VDOT Northern Virginia
 

More from VDOT Northern Virginia (7)

2019-2020 NWS Winter Outlook
2019-2020 NWS Winter Outlook2019-2020 NWS Winter Outlook
2019-2020 NWS Winter Outlook
 
2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing
 
2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow Briefing2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow Briefing
 
2018 NOVA Annual Snow Briefing
2018 NOVA Annual Snow Briefing2018 NOVA Annual Snow Briefing
2018 NOVA Annual Snow Briefing
 
Pikes Branch Stream Restoration
Pikes Branch Stream RestorationPikes Branch Stream Restoration
Pikes Branch Stream Restoration
 
2017-2018 VDOT NOVA Snow Briefing
2017-2018 VDOT NOVA Snow Briefing2017-2018 VDOT NOVA Snow Briefing
2017-2018 VDOT NOVA Snow Briefing
 
Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016
 

Recently uploaded

Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...Suhani Kapoor
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Fair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTFair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTaccounts329278
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Roomishabajaj13
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 

Recently uploaded (20)

Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Fair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTFair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CT
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 

Belmont Ridge Road Pardon Our Dust meeting

  • 1. Route 659 (Belmont Ridge Road) Reconstruct to 4-Lanes Project Pardon Our Dust Meeting Belmont Station Elementary School October 27, 2016
  • 2. 2  Northern Virginia Transportation Authority  Loudoun County  Virginia Department of Transportation  Dewberry Consultants, LLC  Shirley Contracting Company The Project Team
  • 3. 3 Objectives  Project Location  Project Purpose and Need  Provide an Overview of Design Features Describe Construction Sequence Discuss the Project Schedule Answer Your Questions
  • 5. • Improve traffic safety through improvements to roadway geometry, operations, and grade separation of W&OD • Improve capacity & reduce congestion • Enhance Connectivity of Regional Multimodal Transportation Network • Complete 4 lane roadway section from Route 7 to the Dulles Greenway 5 Project Purpose and Need
  • 6. 6 Major Design Features Typical Section  Four lane divided roadway  26’ Wide Grass Median  10’ Wide Shared Use Path on Both Sides of the Road
  • 9. 9 Major Design Features Grade Separated Interchange Over W&OD Trail
  • 10. 10 Major Design Features W&OD Trail Parking Facility
  • 11. 11 • Wall 1: Hay Rd. to 876’ North, Aprox.13’ Tall Scheduled to complete by end of 2017. Major Design Features Noise Barriers
  • 12. 12 • Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF, Approx. 13’ Tall, and Scheduled to complete by end of 2017. Major Design Features Noise Barriers
  • 13. 13 • Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF, Approx. 13’ Tall, and Scheduled to complete by end of 2017. Major Design Features Noise Barriers
  • 14. 14 •Wall 3: Chesterton St. to 384’ North, Aprox.13’ Tall Scheduled to be complete by end of 2017. Major Design Features Noise Barriers
  • 15. 15 • Concrete Posts and Concrete Panels •Panels: Ashlar Stone Pattern with a 12 Inch Tall Coping on the Top Stained Color Hopsac Major Design Features Noise Barriers
  • 16. 16 Project Metrics Total Project Budget: $61 Million Construction Contract Value: $45.5 Million Project Length: 1.9 Miles Right-of-Way Acquisition: 26 Parcels Adjustments to 5 Utilities Project Duration: 39 months
  • 17. 17 Construction Metrics  Communications 13,000 LF Line Relocations  Overhead Power 9,000 LF  Gas Line 7,000 LF Relocations  36” Water Main: 10,000 LF  Earth Moving: 125,000 CY (15,500 Truck Loads)  Storm Drainage: 14,200 LF Pipe 155 Drainage Structures  Pavement Stone: 45,000 Tons  Asphalt Pavement: 80,000 Tons  Noise Barrier: 47,000 SF  Pavement Markings: 130,000 LF
  • 18. 18 September 2015 Notice To Proceed October 2015 - July 2016 Complete Design / Permitting Summer 2016 - Winter 2016 Right of Way Acquisition Fall 2016 - Winter 2017 Utility Relocations October 31, 2017 Grade Separation Complete Fall 2016 - Winter 2017 Stage 1 Construction Winter 2017 - Fall 2018 Stage 2 Construction Winter 2018 Stage 3 / Complete Project Project Schedule
  • 19. Addressing Your Concerns… Regarding Construction 19  A majority of the construction operations will be on weekdays during normal daytime hours, generally 6:00 am to 6:00 pm.  Weekends will be utilized as make-up day due to weather.  Flagging operations to a single lane will be performed to place safety measures and equipment access.  Nighttime operations will result in noise impacts.  Notices will be distributed to email distribution list and directly to fire, rescue, and school personnel.  VDOT to send press releases for major traffic shifts.  Speed limit will be reduced from 45 mph to 40 mph during construction.
  • 20. 20 http://www.virginiadot.org/projects/northernvirginia/belmont _ridge_road_widening.asp (this webpage will be updated throughout the project development) Or Google: “Belmont Ridge Road Widening” Questions and Answers For More Information About Route 659 Widening Project: