Contents
• Introduction to PCF
• The Challenge of Project Reporting
• Spreadsheets – the “obvious” solution – Errors and Risks
• QEI Management Reporting – Example Reports and Case Studies
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo
• Common Challenges & Manage Risk
• Your Main Link for Performance Measurement-Control
Accounts
• Data Integration throughout the cost management lifecycle Requirements
• Special Focus:Cost & Schedule Integration
• Methods for Transferring Data
• A Little about ARES Software and PRISMG2
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo
Case Studies:
To illustrate the process, we draw on Supertech’s participation in the development and maintenance of a number of industry projects such as:
Jindal Steel and Power’s (JSPL) 12.5 MTA Steel Plant Project Control System. http://www.jindalsteelpower.com/ facilities/domestic/orissa/angul.aspx We consider this to be a Large Industrial Project (Mega Project).
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo
Over recent decades there has been very substantial development in project-related software covering the main elements of estimating/budgeting, planning/scheduling and progress measurement. Whilst this has many obvious advantages the need for the users of such software to be thoroughly grounded in the basic methodologies, as well understanding the specifics of the data bases and calculations carried out by the software, are considered to be essential to avoid possible misuse which could negatively affect the project outcome. Focussing on the estimating function, the applicable “fundamentals” are described in the context of a training course which has been designed to meet this need.
Project Controls Expo - 31st Oct 2012 - Accurate Management Reports on 1me, e...Project Controls Expo
Contents
• Introduction to PCF
• The Challenge of Project Reporting
• Spreadsheets – the “obvious” solution – Errors and Risks
• QEI Management Reporting – Example Reports and Case Studies
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo
• Common Challenges & Manage Risk
• Your Main Link for Performance Measurement-Control
Accounts
• Data Integration throughout the cost management lifecycle Requirements
• Special Focus:Cost & Schedule Integration
• Methods for Transferring Data
• A Little about ARES Software and PRISMG2
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo
Case Studies:
To illustrate the process, we draw on Supertech’s participation in the development and maintenance of a number of industry projects such as:
Jindal Steel and Power’s (JSPL) 12.5 MTA Steel Plant Project Control System. http://www.jindalsteelpower.com/ facilities/domestic/orissa/angul.aspx We consider this to be a Large Industrial Project (Mega Project).
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo
Over recent decades there has been very substantial development in project-related software covering the main elements of estimating/budgeting, planning/scheduling and progress measurement. Whilst this has many obvious advantages the need for the users of such software to be thoroughly grounded in the basic methodologies, as well understanding the specifics of the data bases and calculations carried out by the software, are considered to be essential to avoid possible misuse which could negatively affect the project outcome. Focussing on the estimating function, the applicable “fundamentals” are described in the context of a training course which has been designed to meet this need.
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...Project Controls Expo
Agenda
- What is Cost Engineering?
- Cost Estimating
- Cost Control
- Challenges of the Modern Cost Engineer
- Achieving an Integrated Work Process through a Holistic Mindset
A project promoter or developer has an option to give single contract on turnkey basis on single contractor or to source project packages/components from several suppliers. Advantages of an EPC single contract are highlighted in this presentation.
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Expo
Project Controls Technician Apprentice - Joining the puzzle together by Shane Forth - Director of PMO for Costain Natural Resources, UK
Anil Godhawale - Programme Director for Project Controls Institute, UK
Catherine Lambert - Product Development Manager for ECITB, UK at at Project Controls Expo 2017, Arsenal Stadium, London
Learn about challenges and solutions for implementing a transformational project based on real integration examples (cases).In any Project Controls (TCM framework, EVMS) implementation: technology, systems/processes, and people are involved. This presentation provides an understanding of integrating two of the essential knowledge areas: cost and schedule. See real examples of integrations explaining frameworks, models, best practices, bodies of knowledge, and standards. Analyze the outcome, challenges, and alternatives.
Intergen Energy Ltd.
Services
In addition to EPC-LSTK / EPCM, PMC and Reimbursable Services projects, we are also in a position to undertake specialised value-added services for your chemical projects covering various phases of the project cycle. In line with our project implementation philosophy, we assign trained specialists – be it for a Detailed Feasibility Report of an upcoming project, an Asset Evaluation assignment for a planned business acquisition, an Inspection / Expediting assignment for critical equipment at the Vendor’s shop floor, Supervision of Construction / Commissioning activity at your site or Project Management Consultancy services for your valuable project.
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM gives an early indication that either project is delayed or not and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work.
This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the Primavera P6 software is used to deals with the project monitoring process of a seven-storeyed (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.
Earned Value Management involves more that just cost and schedule. Six Business Systems, including EVM, are the basis of credible program performance management.
Here's a suggestion of how to "connect the dots."
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...Project Controls Expo
Agenda
- What is Cost Engineering?
- Cost Estimating
- Cost Control
- Challenges of the Modern Cost Engineer
- Achieving an Integrated Work Process through a Holistic Mindset
A project promoter or developer has an option to give single contract on turnkey basis on single contractor or to source project packages/components from several suppliers. Advantages of an EPC single contract are highlighted in this presentation.
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Expo
Project Controls Technician Apprentice - Joining the puzzle together by Shane Forth - Director of PMO for Costain Natural Resources, UK
Anil Godhawale - Programme Director for Project Controls Institute, UK
Catherine Lambert - Product Development Manager for ECITB, UK at at Project Controls Expo 2017, Arsenal Stadium, London
Learn about challenges and solutions for implementing a transformational project based on real integration examples (cases).In any Project Controls (TCM framework, EVMS) implementation: technology, systems/processes, and people are involved. This presentation provides an understanding of integrating two of the essential knowledge areas: cost and schedule. See real examples of integrations explaining frameworks, models, best practices, bodies of knowledge, and standards. Analyze the outcome, challenges, and alternatives.
Intergen Energy Ltd.
Services
In addition to EPC-LSTK / EPCM, PMC and Reimbursable Services projects, we are also in a position to undertake specialised value-added services for your chemical projects covering various phases of the project cycle. In line with our project implementation philosophy, we assign trained specialists – be it for a Detailed Feasibility Report of an upcoming project, an Asset Evaluation assignment for a planned business acquisition, an Inspection / Expediting assignment for critical equipment at the Vendor’s shop floor, Supervision of Construction / Commissioning activity at your site or Project Management Consultancy services for your valuable project.
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
Most of the construction projects are exposed to time and cost overruns due to various factors and this is a major problem. As a solution to this, the Earned Value Management (EVM) method is considered. EVM is a powerful and well-known method used in monitoring and controlling the project. EVM gives an early indication that either project is delayed or not and the project is either over budget or under budget at any particular day by tracking it. Thus, it helps to improve the management control system of a construction project, to detect and control the problems in potential risk areas and to suggest the importance and purpose of monitoring the construction work.
This paper explains the main parameters of the EVM system involved in the calculation of time and cost for construction projects. In this study, the Primavera P6 software is used to deals with the project monitoring process of a seven-storeyed (G+6) faculty building whose construction is in progress at Istanbul, Turkey. A comparison between the planned progress of construction activities and actual progress is performed and the analysis results are interpreted. This case study justifies the benefits of using EVM for project cash flow analysis and forecasting.
Earned Value Management involves more that just cost and schedule. Six Business Systems, including EVM, are the basis of credible program performance management.
Here's a suggestion of how to "connect the dots."
The synergy between benefits management and change management, workshop 2, Neil White, Parag Gogate, London, 23 June 2016
The APM Benefits Summit 2016
APM Benefits Management SIG
INTERNATIONAL SKILL DEVELOPMENT TRAINING INSTITUTIONS
TRAINING & DEVELOPMENT with PLACEMENT SERVICES
Soft Skills Training - 180 Programs
Management Skills Training- 140 Programs
Technical Skills Training- 80 Programs
Employability & Up Skills Training - 120 Programs
International Skills Development Training - 60 Programs
NSDC QP Training - 45 Programs
IT Training Programs – 25
English Language for all levels
Skill Development 350 Programs
Rural Development Programs
Entrepreneur Development Programs
Women Development Programs
Sectors Skill Oriented Training 75 Programs
NSQF / OSQP – 120 Programs
On-Job Training 60 Programs
HR Professional Skills Training 35 Programs
Social Media Networking Programs
SEO /SMO Training Programs
Operations & Administration Job Specific Programs
HSE Professionals Skills 70 Programs
Quality Professional 12 Programs
Compliance Professionals 15 Programs
Train the Trainer Domain Specific 15 Programs
PMP, CCE, LEED, CMA, FIDIC, PgMP, RMP, PSP, SP, CCP, CIC, CPA, CFPS, CSCM, CMQ, CFM, FRM, CPCM, CPHQ, SIX SIGMA
First Aid, Fire Safety, Scaffolding, Rigging & Slinging, Confined Spaces, Construction Safety, Good Manufacturing Practices, Slip - Trip - Fall Protection, Welding Safety, Carpenter & Painter Safety, Work Place Safety, Behavioral Safety, Work @ Heat & Height Safety, Crane Safety, Road Safety, General Health & Safety Environment, Electrical Safety, Mechanical Safety, Chemicals Safety, Food Safety, Logistics Safety, Ware Housing Safety, Safety Culture, Safety Policy, Safety Principles, Safety Consultancy,
any Interested aspirants may contact us
9176733557 / 044-24311557
info@anytraininganywhere.com
www.anytraininganywhere.com
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo
BMT Hi-Q Sigma Overview
• A professional services company compromising of 120 consultants across offices in Bath, Basingstoke and London.
• OperaJng across the Defence, JusJce, Energy and TransportaJon sectors.
• Achieved a turnover in 2011 of ~ £12M.
• As an employee benefit trust with no manufacturing or supply chain
interests, we provide truly imparJal advice, assistance.
• In the complex world which we know you face every day, our goal is simple and steadfast:
to bring clarity
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...Project Controls Expo
ARES PRISM - Integrating Project & Portfolio Management by "Lateef Daly"- Director of Operations, Europe & Middle East for ARES PRISM, UK at Project Controls Expo 2017, Arsenal Stadium, London
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
A Source of Project Cost Integration by "David Hurren - Technical Director for RPCuk, UK Marie Trembacki - Associate Director for Faithful+Gould, UK" at Project Controls Expo 2017, Arsenal Stadium, London
PIDX Spring 2011 Using Predictive Analytics to Accelerate eCatalog Creation...tpmorgan1
Presentation by Tim Morgan, Sullexis, at the PIDX Spring 2011 conference in Houston TX. The presentation is a Case Study that addressings the complexities of creating and maintaining electronic pricesheets for P2P initiatives, and how Predictive Analytics can be used to accelerate the process and lower cost.
Improving forecasting to optimise programme and project decisions by "Chris B...Project Controls Expo
Improving forecasting to optimise programme and project decisions by Chris Beach - Strategy Director for Amec Foster Wheeler, UK at Project Controls Expo 2017, Arsenal Stadium, London
USUGM 2014 - Zhenbin Li (Boehringer Ingelheim): Challenges and Approach in Mi...ChemAxon
Chemistry infrastructure serves as a backbone of pharmaceutical discovery informatics. In last two year, we have implemented and migrated most of our applications and systems using ChemAxon technology as our core chemistry infrastructure platform. During this evolutional migration, we encountered challenges in legacy systems, technology adaption, and data curation. An effective organization and business engagement are crucial for the success.
National Grids Project Controls Journey – past, present and futureProject Controls Expo
National Grids Project Controls Journey – past, present and future By, Tim Fenemore - Head of Project Controls for National Grid, UK
Sanjay Lodhia - Head of Governance & Assurance for National Grid, UK
Tony Abiad - Head of Estimating & Cost for National Grid, UK
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs - Founder and CEO for ShapeDo, Israel" at Project Controls Expo 2017, Arsenal Stadium, London
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
Managing the risk of change by "Simon White - Risk Management Consultant for Trigo White Ltd, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior Consultant for QinetiQ, UK" & "Peter Tart - Senior Consultant for QinetiQ, UK at Project Controls Expo 2017, Arsenal Stadium, London
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston - Director of Project Controls for Costain Group PLC, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Founder for Basis PM, Texas, USA" at Project Controls Expo 2017, Arsenal Stadium, London
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Director for WSP, UK" & "Danny Vaughan - Head of Metrolink for TfGM, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
Governance and the art of decision making on Crossrail by "Walter Macharg - Head of Change Control and Cost Assurance for Crossrail, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partner, UK Head of Programme & Project Controls for Arcadis, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
Governance and Assurance for Nationally Significant Infrastructure Projects by "Terri Harrington"- Sponsorship Director - Complex Infrastructure Programme (CIP) for Highways England, UK at Project Controls Expo 2017, Arsenal Stadium, London
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
A review of whether interdependency exists in effective Project Control Methods and project performance by "Michael Halliday" Director for HKA, UK at Project Controls Expo 2017, Arsenal Stadium, London
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh Bhandari - Technical Principal - Project & Programme Controls for Mott MacDonald, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen - DEO Program Management for LA Metro, Los Angeles" at Project Controls Expo 2017, Arsenal Stadium, London
Enterprise Project Management Solutions - Install and train, job done? by "Da...Project Controls Expo
Enterprise Project Management Solutions - Install and train, job done? by "David Dunning - Chairman for CPS, UK" at Project Controls Expo 2017, Arsenal Stadium, London
The Future of Project Controls: Improve project performance using Big Data by...Project Controls Expo
The Future of Project Controls: Improve project performance using Big Data by "Martin Van Vliet " - Business Director for Cost Engineering BV, Netherlands at Project Controls Expo 2017, Arsenal Stadium, London
0x01 - Newton's Third Law: Static vs. Dynamic AbusersOWASP Beja
f you offer a service on the web, odds are that someone will abuse it. Be it an API, a SaaS, a PaaS, or even a static website, someone somewhere will try to figure out a way to use it to their own needs. In this talk we'll compare measures that are effective against static attackers and how to battle a dynamic attacker who adapts to your counter-measures.
About the Speaker
===============
Diogo Sousa, Engineering Manager @ Canonical
An opinionated individual with an interest in cryptography and its intersection with secure software development.
This presentation, created by Syed Faiz ul Hassan, explores the profound influence of media on public perception and behavior. It delves into the evolution of media from oral traditions to modern digital and social media platforms. Key topics include the role of media in information propagation, socialization, crisis awareness, globalization, and education. The presentation also examines media influence through agenda setting, propaganda, and manipulative techniques used by advertisers and marketers. Furthermore, it highlights the impact of surveillance enabled by media technologies on personal behavior and preferences. Through this comprehensive overview, the presentation aims to shed light on how media shapes collective consciousness and public opinion.
Acorn Recovery: Restore IT infra within minutesIP ServerOne
Introducing Acorn Recovery as a Service, a simple, fast, and secure managed disaster recovery (DRaaS) by IP ServerOne. A DR solution that helps restore your IT infra within minutes.
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Orkestra
UIIN Conference, Madrid, 27-29 May 2024
James Wilson, Orkestra and Deusto Business School
Emily Wise, Lund University
Madeline Smith, The Glasgow School of Art
Have you ever wondered how search works while visiting an e-commerce site, internal website, or searching through other types of online resources? Look no further than this informative session on the ways that taxonomies help end-users navigate the internet! Hear from taxonomists and other information professionals who have first-hand experience creating and working with taxonomies that aid in navigation, search, and discovery across a range of disciplines.
This presentation by Morris Kleiner (University of Minnesota), was made during the discussion “Competition and Regulation in Professions and Occupations” held at the Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found out at oe.cd/crps.
This presentation was uploaded with the author’s consent.
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Session T7 - Total Cost Management - The synergy between Cost Estimating and Project Controls
1. Copyright @ 2011. All rights reserved
Total Cost Management
The synergy between Cost Estimating and
Project Controls
Project Controls Expo – 13th Oct 2015
Emirates Stadium, London
2. Copyright @ 2011. All rights reserved
About the Speaker
Aafje Jansen-Romijn, Managing Director at Cost Engineering Consultancy B.V.
Professional career:
1990-1998 Dow Chemical - Project Controls department
1998-2000 Stork Comprimo
2000-2001 Jacobs Engineering
2001- present Cost Engineering Consultancy B.V.
CCP, CEP by the AACE International standards.
Comprehensive experience in cost engineering and cost estimating solutions in
wide variety of industries.
3. Copyright @ 2011. All rights reserved
Bulk storage
Construction industry
EPC(M)
Food and Nutrition
Government
Offshore
Oil & Gas industry
Heavy industry
Pharmaceutical industry
Petro-/chemical industry
Power industry
Mining & Minerals
References
4. Copyright @ 2011. All rights reserved
Project experience
One of the most important tools for an estimator is experience
Desire to improve capital cost estimating systems, tools,
methodologies and practices.
Data collection of project cost, schedule and scope information
required in a structured format
Missing feedback loop during the execution phase in order to validate
and/or improve their estimating data.
5. Copyright @ 2011. All rights reserved
Broken feedback loop
Many reasons can be identified:
Disconnects exist between project management, estimating, planning
and cost control, due to a lack of understanding of each other’s need
which could disrupt a proper feedback cycle
The cost control baseline could lack the level of detail required to
evaluate for instance compensation events during execution
It could be induced by opting for lump-sum turnkey EPC contracts for the
majority of the projects, as engineering contractors are reluctant to
share information regarding hours, costs and key quantities
Companies have a need for a project historical retrieval and analysis system
6. Copyright @ 2011. All rights reserved
Synergy between Cost Estimating and
Project Controls
It is time to establish synergy between Cost Estimating and Project Controls
by working with pre-set visual performance indicators during project
execution.
Should start by setting up a proper baseline conforming to all
requirements of the stakeholders.
Monitor project cost and schedule performance during Project Cost
Control
Give improved forecasting information.
Meaningful ratios and statistics for your projects to aid estimate reviews,
providing estimating database feedback and calibration information.
9. Copyright @ 2011. All rights reserved
Estimating the cost baseline
Estimate classification
10. Copyright @ 2011. All rights reserved
Estimating the cost baseline
Breakdown Structures
11. Copyright @ 2011. All rights reserved
Estimating the cost baseline
Breakdown Structures
12. Copyright @ 2011. All rights reserved
Spending valuable time on things that
matter
Handling,
correcting,
checking, 65%
Forecasting &
Change
Management,
10%
Controlling; 25%
13. Copyright @ 2011. All rights reserved
Forecasting – the link with estimating
The link with estimating
Better integration
Keep the estimate alive
Involvement estimator during project controls
14. Copyright @ 2011. All rights reserved
Forecasting – the link with estimating
The link with estimating
Changes based upon proper
estimating
Visualize project
development
through time
16. Copyright @ 2011. All rights reserved
Project close-out
Information of interest:
Cost Factors – for early phase estimating
Hand factors
Lang factors
Characteristic values and metrics – concept studies
Realized hours – benchmarking estimating norms
17. Copyright @ 2011. All rights reserved
TIC
factor
Develop
characteristic
values / metrics
Project close-out
18. Copyright @ 2011. All rights reserved
Project close-out
What are important metrics?
Metrics used for quantitative estimating in order to determine the
expected project quantities without having to involve a full design team
to determine these quantities.
For example:
Length of pipe per main equipment item : 150 m pipe / eq.
Number of fittings per length of pipe : 0,6 fitting / m pipe
19. Copyright @ 2011. All rights reserved
Project close-out
The purpose of this focus on cost metrics is to extend to cost engineering
practices. By using these metrics and research findings, companies can
improve their project and business results.
These characteristic values will:
Support conceptual estimate
Support estimate reviews
Assess company performance against industry norms.
Support calibration and improvement of company tools and
databases.
Improve asset cost evaluation and concept development
22. Copyright @ 2011. All rights reserved
PT
FT
Project Structure - objects
Metrics
@ 4.5” pipe
@ 150 m pipe per equipment
@ 0,9 - 1,2 Control valve per equipment
@ 5.5 Field instruments per equipment
@ 3 lighting fixtures per equipment
Cost database aligned with metrics
Core metrics in estimating are often
key quantities
23. Copyright @ 2011. All rights reserved
Key quantities
Essential basis for metric development:
What is included in the metric – ISBL versus OSBL
Analyzing key quantities of projects
Develop useful characteristic values
No relation: Length of Electrical cable per meter pipe
Distinguish between different types of projects
Develop and maintain cost database inline with composites supporting
the characteristic values
27. Copyright @ 2011. All rights reserved
Project metrics
Database system for project historical retrieval and analysis system
Always actual metrics by using Estimate at Completion Quantities
Specify companies needs
Both project metrics and project controls EVM metrics
28. Copyright @ 2011. All rights reserved
Project metrics
Improving the Quality of Earned
Value information:
Credible
Timely
Significant
Analyzed (numbers don’t
speak analysts do)
29. Copyright @ 2011. All rights reserved
Earned Value Management
Example Reporting
30. Copyright @ 2011. All rights reserved
Total Cost Management
Create synergy between estimating and project controls
Align estimate requirements with project controls system
Embed metrics reporting into your organisation
Involve estimating during forecasting
Do not wait till project closure – you will be too late!