The document discusses project planning and scheduling. It provides information about Stephen Jones, who will be speaking at a project controls expo. It then covers various project scheduling topics like the differences between planning and scheduling, network diagrams, dependencies, critical paths, Gantt charts, and resources. Sellafield, the largest nuclear site in Europe, is used as an example throughout.
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo
BMT Hi-Q Sigma Overview
• A professional services company compromising of 120 consultants across offices in Bath, Basingstoke and London.
• OperaJng across the Defence, JusJce, Energy and TransportaJon sectors.
• Achieved a turnover in 2011 of ~ £12M.
• As an employee benefit trust with no manufacturing or supply chain
interests, we provide truly imparJal advice, assistance.
• In the complex world which we know you face every day, our goal is simple and steadfast:
to bring clarity
INTERNATIONAL SKILL DEVELOPMENT TRAINING INSTITUTIONS
TRAINING & DEVELOPMENT with PLACEMENT SERVICES
Soft Skills Training - 180 Programs
Management Skills Training- 140 Programs
Technical Skills Training- 80 Programs
Employability & Up Skills Training - 120 Programs
International Skills Development Training - 60 Programs
NSDC QP Training - 45 Programs
IT Training Programs – 25
English Language for all levels
Skill Development 350 Programs
Rural Development Programs
Entrepreneur Development Programs
Women Development Programs
Sectors Skill Oriented Training 75 Programs
NSQF / OSQP – 120 Programs
On-Job Training 60 Programs
HR Professional Skills Training 35 Programs
Social Media Networking Programs
SEO /SMO Training Programs
Operations & Administration Job Specific Programs
HSE Professionals Skills 70 Programs
Quality Professional 12 Programs
Compliance Professionals 15 Programs
Train the Trainer Domain Specific 15 Programs
PMP, CCE, LEED, CMA, FIDIC, PgMP, RMP, PSP, SP, CCP, CIC, CPA, CFPS, CSCM, CMQ, CFM, FRM, CPCM, CPHQ, SIX SIGMA
First Aid, Fire Safety, Scaffolding, Rigging & Slinging, Confined Spaces, Construction Safety, Good Manufacturing Practices, Slip - Trip - Fall Protection, Welding Safety, Carpenter & Painter Safety, Work Place Safety, Behavioral Safety, Work @ Heat & Height Safety, Crane Safety, Road Safety, General Health & Safety Environment, Electrical Safety, Mechanical Safety, Chemicals Safety, Food Safety, Logistics Safety, Ware Housing Safety, Safety Culture, Safety Policy, Safety Principles, Safety Consultancy,
any Interested aspirants may contact us
9176733557 / 044-24311557
info@anytraininganywhere.com
www.anytraininganywhere.com
1 Day FIDIC Claims Workshop, 5 October 2015, Movenpick Hotel Ankara, TurkeyEkrem Kaya
In this one day workshop we focus on claims under FIDIC contracts: when they can be brought, how they must be brought, how they are assessed, and how they are resolved.
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo
• Common Challenges & Manage Risk
• Your Main Link for Performance Measurement-Control
Accounts
• Data Integration throughout the cost management lifecycle Requirements
• Special Focus:Cost & Schedule Integration
• Methods for Transferring Data
• A Little about ARES Software and PRISMG2
Critical Path Method (CPM) was developed in late 1950s and is used to identify task that are necessary for completion of project on time without delay.
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo
BMT Hi-Q Sigma Overview
• A professional services company compromising of 120 consultants across offices in Bath, Basingstoke and London.
• OperaJng across the Defence, JusJce, Energy and TransportaJon sectors.
• Achieved a turnover in 2011 of ~ £12M.
• As an employee benefit trust with no manufacturing or supply chain
interests, we provide truly imparJal advice, assistance.
• In the complex world which we know you face every day, our goal is simple and steadfast:
to bring clarity
INTERNATIONAL SKILL DEVELOPMENT TRAINING INSTITUTIONS
TRAINING & DEVELOPMENT with PLACEMENT SERVICES
Soft Skills Training - 180 Programs
Management Skills Training- 140 Programs
Technical Skills Training- 80 Programs
Employability & Up Skills Training - 120 Programs
International Skills Development Training - 60 Programs
NSDC QP Training - 45 Programs
IT Training Programs – 25
English Language for all levels
Skill Development 350 Programs
Rural Development Programs
Entrepreneur Development Programs
Women Development Programs
Sectors Skill Oriented Training 75 Programs
NSQF / OSQP – 120 Programs
On-Job Training 60 Programs
HR Professional Skills Training 35 Programs
Social Media Networking Programs
SEO /SMO Training Programs
Operations & Administration Job Specific Programs
HSE Professionals Skills 70 Programs
Quality Professional 12 Programs
Compliance Professionals 15 Programs
Train the Trainer Domain Specific 15 Programs
PMP, CCE, LEED, CMA, FIDIC, PgMP, RMP, PSP, SP, CCP, CIC, CPA, CFPS, CSCM, CMQ, CFM, FRM, CPCM, CPHQ, SIX SIGMA
First Aid, Fire Safety, Scaffolding, Rigging & Slinging, Confined Spaces, Construction Safety, Good Manufacturing Practices, Slip - Trip - Fall Protection, Welding Safety, Carpenter & Painter Safety, Work Place Safety, Behavioral Safety, Work @ Heat & Height Safety, Crane Safety, Road Safety, General Health & Safety Environment, Electrical Safety, Mechanical Safety, Chemicals Safety, Food Safety, Logistics Safety, Ware Housing Safety, Safety Culture, Safety Policy, Safety Principles, Safety Consultancy,
any Interested aspirants may contact us
9176733557 / 044-24311557
info@anytraininganywhere.com
www.anytraininganywhere.com
1 Day FIDIC Claims Workshop, 5 October 2015, Movenpick Hotel Ankara, TurkeyEkrem Kaya
In this one day workshop we focus on claims under FIDIC contracts: when they can be brought, how they must be brought, how they are assessed, and how they are resolved.
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo
• Common Challenges & Manage Risk
• Your Main Link for Performance Measurement-Control
Accounts
• Data Integration throughout the cost management lifecycle Requirements
• Special Focus:Cost & Schedule Integration
• Methods for Transferring Data
• A Little about ARES Software and PRISMG2
Critical Path Method (CPM) was developed in late 1950s and is used to identify task that are necessary for completion of project on time without delay.
Project Controls Expo 18th Nov 2014 - "Using Agile and Earned Value" By Steph...Project Controls Expo
Over the last 15 years, Agile software development methods have been developed to deliver higher quality software, better and faster, whilst being able to react to changing (or poorly defined) client needs.
Earned Value Management (EVM) is a good practice approach used for the planning, management and control of projects and programmes. It measures cost and schedule against a baseline, to produce a simple set of metrics providing early warnings of performance issues, allowing for timely and appropriate adjustments.
There are some misconceptions that EVM techniques are too difficult to implement effectively on an Agile project.
National Grids Project Controls Journey – past, present and futureProject Controls Expo
National Grids Project Controls Journey – past, present and future By, Tim Fenemore - Head of Project Controls for National Grid, UK
Sanjay Lodhia - Head of Governance & Assurance for National Grid, UK
Tony Abiad - Head of Estimating & Cost for National Grid, UK
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs - Founder and CEO for ShapeDo, Israel" at Project Controls Expo 2017, Arsenal Stadium, London
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
Managing the risk of change by "Simon White - Risk Management Consultant for Trigo White Ltd, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior Consultant for QinetiQ, UK" & "Peter Tart - Senior Consultant for QinetiQ, UK at Project Controls Expo 2017, Arsenal Stadium, London
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston - Director of Project Controls for Costain Group PLC, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Founder for Basis PM, Texas, USA" at Project Controls Expo 2017, Arsenal Stadium, London
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Director for WSP, UK" & "Danny Vaughan - Head of Metrolink for TfGM, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
Governance and the art of decision making on Crossrail by "Walter Macharg - Head of Change Control and Cost Assurance for Crossrail, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partner, UK Head of Programme & Project Controls for Arcadis, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
Governance and Assurance for Nationally Significant Infrastructure Projects by "Terri Harrington"- Sponsorship Director - Complex Infrastructure Programme (CIP) for Highways England, UK at Project Controls Expo 2017, Arsenal Stadium, London
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
A review of whether interdependency exists in effective Project Control Methods and project performance by "Michael Halliday" Director for HKA, UK at Project Controls Expo 2017, Arsenal Stadium, London
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
A Source of Project Cost Integration by "David Hurren - Technical Director for RPCuk, UK Marie Trembacki - Associate Director for Faithful+Gould, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh Bhandari - Technical Principal - Project & Programme Controls for Mott MacDonald, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen - DEO Program Management for LA Metro, Los Angeles" at Project Controls Expo 2017, Arsenal Stadium, London
Acorn Recovery: Restore IT infra within minutesIP ServerOne
Introducing Acorn Recovery as a Service, a simple, fast, and secure managed disaster recovery (DRaaS) by IP ServerOne. A DR solution that helps restore your IT infra within minutes.
0x01 - Newton's Third Law: Static vs. Dynamic AbusersOWASP Beja
f you offer a service on the web, odds are that someone will abuse it. Be it an API, a SaaS, a PaaS, or even a static website, someone somewhere will try to figure out a way to use it to their own needs. In this talk we'll compare measures that are effective against static attackers and how to battle a dynamic attacker who adapts to your counter-measures.
About the Speaker
===============
Diogo Sousa, Engineering Manager @ Canonical
An opinionated individual with an interest in cryptography and its intersection with secure software development.
This presentation, created by Syed Faiz ul Hassan, explores the profound influence of media on public perception and behavior. It delves into the evolution of media from oral traditions to modern digital and social media platforms. Key topics include the role of media in information propagation, socialization, crisis awareness, globalization, and education. The presentation also examines media influence through agenda setting, propaganda, and manipulative techniques used by advertisers and marketers. Furthermore, it highlights the impact of surveillance enabled by media technologies on personal behavior and preferences. Through this comprehensive overview, the presentation aims to shed light on how media shapes collective consciousness and public opinion.
This presentation by Morris Kleiner (University of Minnesota), was made during the discussion “Competition and Regulation in Professions and Occupations” held at the Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found out at oe.cd/crps.
This presentation was uploaded with the author’s consent.
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Orkestra
UIIN Conference, Madrid, 27-29 May 2024
James Wilson, Orkestra and Deusto Business School
Emily Wise, Lund University
Madeline Smith, The Glasgow School of Art
Have you ever wondered how search works while visiting an e-commerce site, internal website, or searching through other types of online resources? Look no further than this informative session on the ways that taxonomies help end-users navigate the internet! Hear from taxonomists and other information professionals who have first-hand experience creating and working with taxonomies that aid in navigation, search, and discovery across a range of disciplines.
Eureka, I found it! - Special Libraries Association 2021 Presentation
Session B1 - Planning, Scheduling Monitoring and Control
1. Copyright @ 2011. All rights reserved
Planning, Scheduling Monitoring and Control
Project Controls Expo – 13th Oct 2015
Emirates Stadium, London
2. Copyright @ 2011. All rights reserved
About the Speaker
Stephen Jones
Chairman of the APM Planning, Monitoring and Control Specific
Interest Group. A Registered Project Professional, and a chartered
Electrical Engineer. Project Management experience comes from the
Nuclear Industry, currently Deputy Head of Project Management at
Sellafield Ltd.
3. Copyright @ 2011. All rights reserved
• Located in the County of
Cumbria, North West England
• Functional support capability is
provided by employees based
at Risley, Warrington
• Nuclear build started at
Sellafield in the late 1940’s
• Location of Calder Hall – The
world’s first commercial scale
Nuclear Power Station (1956-
2003)
Sellafield
Risley
Sellafield is the largest and most
complex Nuclear site in Europe
4. Copyright @ 2011. All rights reserved
250 active facilities on 1 ½ sq. miles / 700 acres
Operations include
Decommissioning
Nuclear fuel reprocessing
Nuclear waste management
Construction
Delivery of major projects
Total annual budget £1.9bn
Employs 10,000+ people
Recruits 64 Graduates and apprentices per year, 8 of which are my
direct reports.
Single largest Nuclear construction site
in the UK
5. Copyright @ 2011. All rights reserved
Topics
Planning Verses Scheduling
Network Diagrams
Dependencies
Critical Path
Gantt Charts
Resources
Levelling and Smoothing
Earned Value
6. Copyright @ 2011. All rights reserved
Latest Book from APM
https://www.apm.org.uk/Planning-Monitoring-Scheduling-Control
Available from
APM Website.
20% off today
at APM stand.
7. Copyright @ 2011. All rights reserved
Planning or Scheduling?
What is the difference between Planning
and Scheduling?
9. Copyright @ 2011. All rights reserved
Network Diagrams
Activity on Node Network
10. Copyright @ 2011. All rights reserved
Network Diagrams
Activity on Arrow Network
11. Copyright @ 2011. All rights reserved
Dependencies
Finish-to-Start (FS) relationship
Activity 2 cannot start until Activity 1 has finished
Activity
1
Activity
2
12. Copyright @ 2011. All rights reserved
Example
Can anyone give an example of two tasks with a
Finish-to-Start relationship?
For example. You cannot make a cup of tea, until
the kettle has boiled.
13. Copyright @ 2011. All rights reserved
Dependencies
Start-to-Start (SS) relationship
Activity 4 cannot start until Activity 3 has started
Activity
3
Activity
4
14. Copyright @ 2011. All rights reserved
Example
Can anyone give an example of two tasks with a
Start-to-Start relationship?
If activity 4 was lay pipeline, this can only start
once (activity 3) the sections of pipe have started
to arrive, it is not dependent on the delivery of the
pipes being complete.
15. Copyright @ 2011. All rights reserved
Dependencies
Finish-to-Finish (FF) relationship
Activity 6 cannot Finish until Activity 5 has
Finished
Activity
5
Activity
6
16. Copyright @ 2011. All rights reserved
Example
Can anyone give an example of two tasks with a
Finish-to-Finish relationship?
If activity 6 was planning application, and activity 5
was site surveys, then you can start the planning
application but it can not be completed until you
have all the survey information.
17. Copyright @ 2011. All rights reserved
Dependencies
Start-to-Finish (SF) relationship
This is rarely used. Activity 8 cannot finish until
activity 7 has started
Activity
7
Activity
8
18. Copyright @ 2011. All rights reserved
Example
Can anyone give an example of two tasks with a
Start-to-Finish relationship?
If activity 7 and activity 8 where stand-by and duty
pumps, the duty pump could not be stopped until
the stand-by pump had been started. It is difficult
to imagine planning to this level of detail,
therefore should be avoided.
19. Copyright @ 2011. All rights reserved
Lag and Lead
Lag
Activity 10 can only start 5 days after Activity 9
starts
Activity
9
Activity
10
+ 5
20. Copyright @ 2011. All rights reserved
Lag and Lead
Lead is a negative lag
Activity 12 can start 3 days before Activity 11
finishes
Activity
11
Activity
12
-3
21. Copyright @ 2011. All rights reserved
Creating a Network
All activities should have a predecessor and
successor
With the exception of the first and last
Predecessor Successor
22. Copyright @ 2011. All rights reserved
Example of Network
Design
Manufacture Test
Assemble
Purchase Test
23. Copyright @ 2011. All rights reserved
Exercise 1 – Draw the network
ID Predecessor Dur.
Activity 1 - 6
Activity 2 Activity 1 (Start-to-Start) 4
Activity 3 Activity 1 and Activity 2 7
Activity 4 Activity 3 (Start-to-Start) 4
Activity 5 Activity 2 9
Activity 6 Activity 4 (Finish-to-Finish) 5
Activity 7 Activity 3 + 3 Days Lag, and Activity 5 + 2 days Lag 5
Activity 8 Activity 6 + 3 Days Lag 2
Activity 9 Activity 6, and Activity 7, and Activity 8 (Finish-to-Finish) 4
25. Copyright @ 2011. All rights reserved
Which day does the project start?
Day One
Or
Day Zero
In all scheduling software Day zero does not exist.
For teaching purposed Day Zero is used, then
converted to Day One
The book acknowledges both, but Day one is correct
26. Copyright @ 2011. All rights reserved
Network Analysis
British Standard for the representation of a Network Node (BS4335)
Dur.EST EFT
ID Description
TFLST LFT
EST= Earliest Start
Dur. = Duration
EFT = Earliest Finish
LST = Latest Start
TF = Total Float
LFT = Latest Finish
27. Copyright @ 2011. All rights reserved
Earliest Start Time (EST)
The earliest time by which an activity can start EST
is equal to the EFT of preceding activities
EFT
Predecessor
EST
Activity
28. Copyright @ 2011. All rights reserved
Earliest Finish Time (EFT)
The earliest time by which an activity can finish
EFT = EST + Duration
Dur.EST EFT
Activity
29. Copyright @ 2011. All rights reserved
Latest Start Time (LST)
The latest time by which an activity can start
LST = LFT - Duration
Dur.
Activity
LST LFT
30. Copyright @ 2011. All rights reserved
Latest Finish Time (LFT)
The latest time by which an activity can finish LFT
is equal to the LST of succeeding activities
Activity
LFT
Successor
LST
31. Copyright @ 2011. All rights reserved
Forward Pass
Early Finish = Early Start + Duration
Assumes Finish to Start links with no lag
8
Activity A
6
Activity B
7
Activity C
Dur.EST EFT
ID Description
TFLST LFT
210 8 8 14 14
8 + 6 = 140 + 8 = 8 14 + 7 = 21
32. Copyright @ 2011. All rights reserved
If there are multiple Predecessors?
Big Steps Forward
80 8
Activity A
2
Activity C
100
Activity B
1010
Dur.EST EFT
ID Description
TFLST LFT
33. Copyright @ 2011. All rights reserved
Backward Pass
Late Start = Late Finish – Duration
Assumes Finish to Start links with no lag
68 14
Activity B
80 8
Activity A
714 21
Activity C
0 2114148
8 - 8 = 0 14 - 6 = 8 21 - 7 = 14
8
Dur.EST EFT
ID Description
TFLST LFT
34. Copyright @ 2011. All rights reserved
If there a multiple Successors?
Little Steps Back
80 8
Activity A
00
48 12
Activity B
08 12
18 9
Activity C
311 12
8
Dur.EST EFT
ID Description
TFLST LFT
35. Copyright @ 2011. All rights reserved
Total Float – also known as Slack
Float is amount of time an activity can be
delayed (or extended) without affecting the
total project duration, i.e. the end date.
36. Copyright @ 2011. All rights reserved
Calculating Float
Total Float = Late Finish – Early Finish
Assumes Finish to Start links with no lag
80 8
Activity A
0 8
68 14
Activity B
8 14
714 21
Activity C
14 2100 0
8 - 8 = 0 14 - 14 = 0 21 - 21 = 0
Dur.EST EFT
ID Description
TFLST LFT
37. Copyright @ 2011. All rights reserved
Free Float
The amount of time an activity can be delayed or
extended without delaying the start of the next or
succeeding activity
less less
Early
Finish
Time
Early
Start
Time
Duration
38. Copyright @ 2011. All rights reserved
Critical Path
The critical path is the path through activities with
minimum float. This is normally zero float
It is the longest route through the activity network
There may be more than one critical path
Any delays in critical activities will cause the
project to be delayed
39. Copyright @ 2011. All rights reserved
6
Critical Path Example
1. Get
Dressed
2. Fill
Kettle
3. Boil
Water
4. Make
Tea
5. Get
Milk
6. Pour
Milk
7. Cook
Toast
8. Butter
Toast
9. Pour
Tea
10. Eat
Breakfast
5 1 6 2 1 5
3 1
1 1
0 5
5 8 8 9
5 6 6 7
5 6 12 12 14 14 15 15 20
0 5 5 6 6 12 12 14 14 15 15 20
15141411
14131312
0 0 0 0 0 0
6 6
7 7
44. Copyright @ 2011. All rights reserved
Gantt Charts
A Gantt Chart is a simple form of Bar Chart
Bar length indicates duration
Tasks are usually positioned at earliest dates
showing any float at the end
Shown with or without logic connections
Can be rolled up into summary tasks and can show
milestones
45. Copyright @ 2011. All rights reserved
6
12
6
15
9
7
6 7 13 15 16
6 7 13 15 16
1413
1
1 6
Getting Up Example
1. Get
Dressed
2. Fill
Kettle
3. Boil
Water
4. Make
Tea
5. Get
Milk
6. Pour
Milk
7. Cook
Toast
8. Butter
Toast
9. Pour
Tea
10. Eat
Breakfast
5 1 6 2 1 5
3 1
1 1
5
8 9
6 7
12 14 15 20
5 6 12 14 15 20
1514
1413
0 0 0 0 0 0
6 6
7 7
46. Copyright @ 2011. All rights reserved
Getting Up Gantt
1 201918172 3 4 5 6 7 8 9 10111213 151614
Minutes
ActivityLabel
1 Get Dressed
2 Fill Kettle
3 Boil Water
4 Make Tea
9 Pour Tea
5 Get Milk
7 Cook Toast
10 Eat Breakfast
6 Pour Milk
8 Butter Toast
48. Copyright @ 2011. All rights reserved
Gantt Chart with Critical Path
49. Copyright @ 2011. All rights reserved
Summary Bars
Summary Bar or Hammock
Expand and contract linked activities
50. Copyright @ 2011. All rights reserved
Constraints
Types of Date Constraint
Must Start on
Must Finish on
Start no later than
Finish no later than
Start no earlier than
Finish no earlier than
As Late As Possible
51. Copyright @ 2011. All rights reserved
Milestones
Milestones are shown as a diamond shape
Milestone are used to record the anticipated date
an activity
52. Copyright @ 2011. All rights reserved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 1
2 2
3 3
4 4
5 5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Period 1 Period 2 Period 3 Period 4 Period 5
Milestone Chart
A B C D E
Progress lines will remain straight until the completion dates are
reached. If work deviates from schedule, the progress line will
slope to show the revised estimated completion date
53. Copyright @ 2011. All rights reserved
Level of Effort
General support Activities
Project Manager
Planner
Scheduler
Level of effort should be used sparingly
These activities should be clearly identified
54. Copyright @ 2011. All rights reserved
Resources
This section will cover
Resource histogram
Levelling
Smoothing
55. Copyright @ 2011. All rights reserved
Resource
day
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
A 2 2 2 2
B 4 4 4 4 4 4
C 4 4 4 4 4
D 5 5 5
E 2 2 2 2 2
F 4 4 4 4 4
G 3 3 3
56. Copyright @ 2011. All rights reserved
Resource
12
11 F F F
10 F F F
9 F F F
8 C C C C C F F F F
7 C C C C C F E E E
6 C C C C C F E E E F
5 C C C C C F D D D F
4 B B B B B B D D D F
3 B B B B B B D D D F G G G
2 A A A A B B B B B B D D D E E G G G
1 A A A A B B B B B B D D D E E G G G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
day
57. Copyright @ 2011. All rights reserved
Exercise 3 – Gantt Charts
Using the network from Exercise 2
The following activities require the use of a certain numbers of carpenters:
Activity 01 3 Carpenters
Activity 03 3 Carpenters
Activity 04 4 Carpenters
Activity 05 7 Carpenters
Activity 06 6 Carpenters
(all other activities use zero carpenters)
Draw a Gantt Chart and the associate resource histogram
59. Copyright @ 2011. All rights reserved
Smoothing
Assuming Time is limited
It allows the activity to be arranged with their float
No Change to Project Duration
Over demand may not be removed requiring
additional resource
60. Copyright @ 2011. All rights reserved
12
11
10
9
8 C C C C C
7 C C C C C E E E F F F
6 C C C C C E E E F F F F F
5 C C C C C D D D F F F F F
4 B B B B B B D D D F F F F F
3 B B B B B B D D D F F G G G
2 A A A A B B B B B B D D D E E G G G
1 A A A A B B B B B B D D D E E G G G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Example of Smoothed Histogram
Assume only 6 resource at our disposal.
The start of activity F has been delayed.
61. Copyright @ 2011. All rights reserved
Levelling
Assumes resources are limited
It allows the activity start times to be delayed
Over demand is removed
Duration of the project may increase
62. Copyright @ 2011. All rights reserved
Example of Levelled Histogram
12
11
10
9
8
7
6 E E E E E
5 D D D E E E E E
4 B B B B B B C C C C C D D D F F F F F
3 B B B B B B C C C C C D D D F F F F F G G G
2 A A A A B B B B B B C C C C C D D D F F F F F G G G
1 A A A A B B B B B B C C C C C D D D F F F F F G G G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Assume only 6 resource at our disposal.
All over demand has been removed
63. Copyright @ 2011. All rights reserved
Exercise 4 – Smoothing
Using the network from Exercise 2
Assuming there are only 10 Carpenters available at any one time, smooth
the resources so the project is completed in the minimum time
Draw a Gantt Chart and the associate smoothed resource histogram
65. Copyright @ 2011. All rights reserved
Earned Value
Available on APM Website – free PDF for full members.
66. Copyright @ 2011. All rights reserved
Earned Value
What is Earned Value (EV)
Budget Cost of Work Performed (BCWP)
It is the value of the work actually done at a given
point in time. It takes the work that has been
done and the budget for each task and indicates
what portion of the budget should have been
spent to achieve it
67. Copyright @ 2011. All rights reserved
Actual Cost
The Actual Cost of Work Performed(ACWP) is the
cost of the work done.
It is the amount reported as actually expended in
completing the work accomplished within a given
time period
68. Copyright @ 2011. All rights reserved
Planned Value
Budgeted Cost of Work Scheduled (BCWS)
It is the value of the work that should have been
done at a given point in time.
It indicates the budget at a given point.
69. Copyright @ 2011. All rights reserved
Example
A builder estimates to build a wall will require 100 bricks at £1 each.
The builder can lay 10 bricks per hour. The builder charges £10 per
hour
70. Copyright @ 2011. All rights reserved
Example
After 4 hours the builder has laid 50 bricks
Earned Value = £100, Actual = £90
71. Copyright @ 2011. All rights reserved
Schedule Performance Index
SPI measures progress against the plan.
Greater than 1.0 is good (ahead of plan)
Less than 1.0 is bad (behind plan)
Equals 1.0 when we are on plan
SPI = BCWP / BCWS
Schedule Variance = BCWP – BCWS
72. Copyright @ 2011. All rights reserved
Example
In our example
Earned Value (BCWP) = £100
Planned value (BCWS) = £80
SPI = BCWP / BCWS
SPI = 1.25
The builder is ahead of schedule
SV = 100 – 80 = +20
73. Copyright @ 2011. All rights reserved
Cost Performance Index
CPI is a ratio of the value of work to actual cost
incurred.
Greater than 1.0 is good (under budget)
Less than 1.0 is bad (over budget)
Equals 1.0 when we are on budget
CPI = BCWP / ACWP
Cost Variance = BCWP – ACWP
74. Copyright @ 2011. All rights reserved
Example
In our example, after 4 hours the cost will be £40 for
labour plus £50 for brick = £90
Earned Value (BCWP) = £100
Actual cost (ACWP) = £90
CPI = BCWP / ACWP
CPI = 1.11
The cost is under budget
CV = 100 – 90 = +10
75. Copyright @ 2011. All rights reserved
EAC
Estimate at Completion
A forecast of the cost required to complete the
project based on current progress
EAC = Budget at Completion / CPI
EAC = £200 / 1.11
EAC = £180 (should finish under budget)
76. Copyright @ 2011. All rights reserved
Estimated Duration
A forecast of the time required to complete the
project based on current progress
Estimated Duration = Planned Duration / SPI
In our example = 10 hours / 1.25
Estimated Duration = 8 hours
Should finish ahead of schedule
77. Copyright @ 2011. All rights reserved
Summary
BAC = budget at Completion
Earned Value EV = %complete x BAC
Cost Variance CV = BCWP – ACWP
Schedule Variance SV = BCWP – BCWS
Cost Performance Index CPI = BCWP/ ACWP
Schedule Performance Index SPI = BCWP/ BCWS
EAC = Total Budget / CPI
Est. time at completion = Planned duration / SPI
78. Copyright @ 2011. All rights reserved
Benefits of Earned Value Analysis
Measures work done against expenditure
Control is achieved by calculating variances
Positive: good, negative: Bad
Indices give a summary of project health
>1.0: good, < 1.0: bad
Generates forecast to completion based on
current trends
SPI and CPI can be used as a measure of efficiency
79. Copyright @ 2011. All rights reserved
Good News or Bad News
Ahead of Schedule / Under Budget
80. Copyright @ 2011. All rights reserved
Good News or Bad News
Behind Schedule / Over Budget
81. Copyright @ 2011. All rights reserved
Earned Value Analysis is being used to monitor and control a 12 month
£200,000 capital project. The following values have been extracted for
four months of the project
Calculate cost & schedule variances and the SPI and CPI for each Period
At the end of month 4 what is the: Forecast completion and Estimated
cost at completion
How would you describe the projects performance and what corrective
action (if any) would you advise
Exercise 5
Month 1 2 3 4
Planned Value 16,000 32,000 48,000 64,000
Earned Value 14,000 28,000 40,000 54,000
Actual Cost 11,000 22,000 32,000 43,200
83. Copyright @ 2011. All rights reserved
Exercise 5 - Answer cont.
How would you describe the projects performance and what corrective
action (if any) would you advise
The project is behind schedule and under spending. This can be an
indication of lack of resources, i.e. the resource you have are
performing very efficiently and costing less than expected, however
they are behind schedule.
Corrective action would be to employ more resources to get back on
schedule, this will increase the SPI and reduce the CPI, as more
resource normally work less efficiently, i.e. 10 men do not produce
twice the output of 5 men.