SlideShare a Scribd company logo
An- Najah National University
Rehabilitation of Nablus Electrical Network by adding a
new connection point
Submitted To :
Dr. Maher Khammash
Prepared By :
Ahmad HatemAbd-Albaqi
&
Ali Namrouti
2015-2016
1
Introduction
 Our project is to study the performance of Nablus
Network and to add a new connection point in the eastern
region of the city of Nablus at the village of " Huwwara
" with maximum capacity up to 20 MW.
 Analyzing and make a load flow study using ETAP
software and trying to achieve the optimum performance
for “Eastern Region” Network .
 Taking into consideration that there are 6 connection
points in the electrical network of the city of Nablus.
2
Objectives
 Collecting data for the new connection point including all parameters and
their specifications ( location, transmission lines , switchgear , load ).
 Designing the one line diagram in ETAP program for new condition by
adding the new supply bus .
 Improving the voltage level and reducing the losses and correcting of
power factor in the network .
 Making the system more protected by increasing reliability and stability .
 Analyzing the network under maximum load condition using load flow
analyses.
 To get economical benefit when improving the performance of network.
3
Why new connection point ?
 The main problem which faces Eastern Region Network is that the power
supplied by IEC ‫االسرائيلية‬ ‫القطرية‬ ‫الشركة‬) ) is not enough for the demand in the city,
especially in the summer season . And because the old connection point has a
capacity up to 20 MW which is not sufficient for the network demand because
the old connection point supplies more than one region, such as the industrial
area and “Al-Bathan” .
 To solve this problem , we add a new connection point with IEC in the eastern
region of the city of Nablus in the village of " Huwwara " through an over head
transmission line of 33 kV. The max demand is reached approximately to (20
MW) to cover the total demand .
4
Eastern Region Network
Before & After 5
Methodology
Collecting
data for
new C.P
and
elements
Plotting
one line
diagram
for new
network
Changing
the voltage
level to 11
kV instead
of 6.6 Kv
Analyzing
the
network
under max.
load case
Improve
p.f to
avoid
penalties
Making
Economical
study for
our project
6
 Plotting one-line diagram using ETAP
software for new Network
 We make a load flow study and analysis Network using ETAP
software .
 Components of the network :
1. Two sources (33 kV) .
2. ( 280 ) bus in this network .
3. ( 107 ) loads( residential, industrial, commercial).
4. Substation with ( 2 ) power transformer .
5. ( 108 ) Distribution transformers .
7
 Changing the Voltage Level from
6.6 to 11 kV
 In this case, each 6.6 kV low voltage side will be exchanged by 11 kV. The
same transformers are used because the transformers which are available
have two windings on the low voltage side of 6.6 kV and 11 kV.
 Distribution transformers of 11/0.4 and 6.6/0.4 kV will not be changed too .
So, no new transformers are needed .
 After raising the voltage to 11 kV , the voltage drop was decreased and a
slight improvement to the power factor was observed .
8
 The results of load flow in original
case
Operating Voltage(kV)Rated Voltage(kV)Bus
34.00034Bus 1
33.04333Bus 20
31.50333Bus 65
31.01633Bus 99
10.35511Bus 110
10.30211Bus 133
10.28011Bus 200
10.08711Bus 269
0.3650.4Bus 122
0.3620.4Bus 182
0.3560.4Bus 227
9
Some of under voltage buses : 10
Summary of results in original case
%PFMVAMVarMW
82.24 lag41.86423.81534.430Source (swing
bus)
--5.8762.700Apparent losses
11
 From the above results , there are many problems in the network .The P.F of the
swing bus = 82.24 Lagging , which causes high penalties and losses . So, we try to
increase the power factor of the busses and the voltage of the buses which is not
included in the acceptable range .
 Therefore ,we note that when we change the Voltage Level from 6.6 to 11 kV the
losses for network decrease from 8.9% to 7.8% .
Maximum load case
 The voltage should be within this range :
1.05 V nominal < V < 1.1 V nominal
 In first stage of the analysis of the network we have to take the
maximum load in daily load curve ,then applied it on ETAB .
 We started the study of this case after we applied the data
needed Like load factor and other data.
12
Load factor
 We have the average value of loads by using the load factor of
each load which we got from the real data of network and real
daily load curves from SCADA system
 The average demand load factor in our network is 75% that
means the average load to the maximum load ratio is 75% which
considered as a very good operating load factor .
13
Our goal is to improve the voltages within the range
by using the following steps :
 Tab changing in the transformers.
 Adding capacitors to produce reactive power.
 Changing and replacing transformer.
 Add another connection point .
The tap changer of the secondary side of the 2 power
transformers (33-11 kV) is raised to 10% , and tap change
in all distribution transformers by 5% .
14
Summary of results in maximum load
case
15
%PFMVAMVarMW
83.25 lag42.32023.44635.232Source (swing
bus)
--5.2422.415Apparent losses
 The losses in the network decrease . The losses before were = 2.700 MW,
but the losses after become =2.415 MW .
 For more improvement we add capacitor banks at the low voltage level and
this is a temporary solution but we need a major solution to cover the total
demand in the city. So , we choose to add a new connection point .
Add a new connection point
Comparing the voltages before and after adding the new connection point.
16
Voltage with two
connection point (kV)
Voltage with one
connection point (kV)
Bus
34.00034.000Bus 1
33.64933.043Bus 20
33.13431.503Bus 65
32.66631.016Bus 99
11.02410.355Bus 110
10.97310.302Bus 133
10.95210.280Bus 200
10.80610.087Bus 269
0.3900.365Bus 122
0.3870.362Bus 182
0.3830.356Bus 227
Some of under voltage buses : 17
Summary of results for new network 18
%PFMVAMVarMW
83.39 lag40.28822.23733.595Source (swing
bus)
--4.0971.168Apparent losses
 We note that when adding a new connection point the losses for
network decrease from 8.9% to 3.4% .
 The P.F of the swing bus = 83.39 lag , which is low and causes a lot of
penalties on both the company and consumers. So, we have to try to
increase the power factor of the busses .
Power Factor Improvement
 It is important to keep the P.F above 0.92 on the distribution transformer so as to
minimize the electrical losses and do not paying penalties.
 How to improve the P.F ??
19
We added shunt capacitor banks at the buses at both
transmission and distribution levels and loads with value :
( 300 , 400 , 1000 ) kVAR .
20
Summary of results after improvement the
network
%PFMVAMVarMW
92.09 lag36.51414.23333.626Source (swing
bus)
--3.6061.010Apparent losses
21
 After adding the capacitor banks the losses in the network decrease to 1.010 MW
 The P.F = 92.09% which it was achieved , since a P.F was lower than that , it would
lead to penalties on both the “NEDCO” and consumers .
Elements Of The Network
1- Sources :
Eastern Region are fed from 2 connection point by Israel Electrical
Company (IEC), at 33KV.
2- Transformers :
 Power Transformers :
This network consists of (2) power transformer (33/11) KV with ratings
10 MVA .
 Distribution transformers :
1. 41 distribution transformers (33/0.4)KV
2. 67 distribution transformers (11/0.4)KV
22
Number of
Transformers
Transformer
Ratings (KVA)
2 2000
1 1600
3 1000
43 630
34 400
16 250
8 160
1 100
108 Total
Elements Of The Network
3- Transmission Line & cable :
 Over Head Line:
The conductors used in the network are ACSR (Aluminum Conductor
Steel Reinforced)
 Under Ground Cable :
The underground cable used in the network are XLPE Cu .
4- Switch gear :
switchgears in substations are located on both the high and low
voltage sides of large power transformers .
Selection depends on : Voltage level ,Number of lines ,Location of
substation , Possibility of expansion
23
Elements Of The Network
 Switchgear contain of :
A. Circuit Breaker :
 How to choose CB :
• I C.B >= Ksafty * I max load .
• VC.B >= V system.
• I breaking capacity >= 1.2 * I S.C
 The Specifications of the Circuit Breaker that
we have used are as follows:
• Ur = 36 kV, Up = 170 kV , Ud = 70kV ; 1 min
• Ir = 1250 A , Ik = 25 kA ; tk = 1sec , Ip = 62.5 kA
24
Elements Of The Network
B. Bus-Bar :
The Bus-Bar modules are either with single phase or three phase
enclosure. Three phase enclosures are compact and have lesser eddy
current losses.
C. Isolator Switch :
Isolating Switches are normally switched only when No Load .
D. Earth Switch :
Earth switch is used to discharge the voltage on the circuit to the earth for
safety , earth switch is mounted on the frame of the isolaters
25
Elements Of The Network
5 - Measurement in the medium voltage :
 Current Transformers
 Potential Transformers
6 - Supervisory Control & Data Acquisition (SCADA) :
SCADA is a system for remote monitoring and control that
operates with coded signals over communication channels.
26
Economical Study
In this project it is important to study the economical calculation to find if our work is suitable
or not .
 Saving in penalties :
P.F before imp. = 0.83
P.F after imp. = 0.92
Pav = L.F * Pmax
= 0.75 * 33.626 = 25.21 MW
Total energy per year = Pav * 8760= 220839.6 MWH.
Total cost per year = Total energy * cost (NIS/KWH) = 132503760 NIS/year.
Saving in penalties of P.F = 115278.27 NIS/year.
 Saving in losses :
Saving in losses = cost of losses before – cost of losses after
= 1064340 – 398142
= 666198 NIS/year.
27
Power Factor P.F Penalties
P.F ≥ 0.92 No Penalties.
0.92 > P.F ≥ 0.8 1% of total bill for each one under 0.92
0.8 > P.F ≥ 0.7 1.25% of total bill for each one under 0.92
P.F < 0.7 1.5% of total bill for each one under 0.92
Economical Study
 Simple Pay Back Period :
Total fixed capacitor banks using = 7.3 MVAR.
Cost of fixed capacitor = 18000 NIS / MVAR .
Total cost of capacitor banks = 7.3 * 18000 = 131400 NIS.
The cost of under ground cable XLPE (1*240 mm2) = 100 NIS / 1 meter
Total cost = 100 * 8000 = 800000 NIS .
The cost of Infrastructure (such as: excavations, power source, accessories) = 100 NIS/1meter
Total cost = 100 * 8000 = 800000 NIS .
The cost of ( Links , wages of workers , equipment , Towers , installation cost and maintenance ) = 300000 NIS
The cost of ( Internal equipment, construction, measurement device , SCADA system ) = 500000 NIS .
Total capital cost = 131400 + 800000 + 800000 + 300000 + 500000 = 2531400 NIS
Total saving = saving in losses + saving in penalties
= 666198 + 115278.27 = 781476.27 NIS
S.P.B.P = Investment / Saving = 2531400 / 781476.27 = 3.23 years
28
How our new connection point will affect on
Nablus network ?
29
RehabilitationoftheNabluselectricalnetwork
Rehabilitation of the Nablus electrical network
Conclusions
 After the analysis and adding a new connection point , drop voltage was decreased ,
apparent losses was reduced too .
 When adding a new connection point the losses for network decrease
from 8.9% to 3.4% .
 The power factor was improved to over 92% which will reduce any penalties paid to
"IEC" on both "NEDCO" Company and consumers as will, and this is duo to adding a new
connection point .
 The network at full load need to 34 MW , but the availability of current two connection
point is 40 MW . So, now we in the save side .
 The time needed to recover the cost for the project is about 3 year . And the new
network will be feed the new growth of load for the period from now to 2025 ,
depending on the annual increase of the loads to cover the demand in the city.
30
Huwwara connection point 31
Rehabilitation of the Nablus electrical network
Askar substation 32
Rehabilitation of the Nablus electrical network
Switchgear in Askar substation 33
Rehabilitation of the Nablus electrical network
SCADA system 34
Rehabilitation of the Nablus electrical network
Recommendation
 Finally , we hope from NEDCO with which we have contributed in
gathering information and data about our project to take into
consideration our calculation and improvement of the electrical network
seriously . we also hope to see our project in Huwwara to be truly
applied on the ground of reality .
THANK YOU FOR YOUR ATTENTION
35
36

More Related Content

What's hot

Automatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportAutomatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportSelf-employed
 
Ieee 2015 2014 power electronics project titles
Ieee 2015 2014 power electronics project titlesIeee 2015 2014 power electronics project titles
Ieee 2015 2014 power electronics project titlespowerprojects
 
Automatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.PptxAutomatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.PptxSveris COE Pandharpur
 
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Pradeep Avanigadda
 
power factor correction soham+niraj
power factor correction soham+nirajpower factor correction soham+niraj
power factor correction soham+nirajsoham patel
 
Amit new report
Amit new reportAmit new report
Amit new reportyadav amit
 
Automatic power factor correction
Automatic power factor correction Automatic power factor correction
Automatic power factor correction VIKAS KUMAR MANJHI
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 
Automatic power factor_improvement_and_monitoring_by_using_plc[1]
Automatic power factor_improvement_and_monitoring_by_using_plc[1]Automatic power factor_improvement_and_monitoring_by_using_plc[1]
Automatic power factor_improvement_and_monitoring_by_using_plc[1]ferozpatowary
 
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...Hardik Parikh, E.I.T.
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMASWATHYSANAND1
 
Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Mathankumar S
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final ReportJeff Ge
 
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC TransmissionImprovement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmissiontheijes
 
Benifits of power factor improvement for industry
Benifits of power factor improvement for industryBenifits of power factor improvement for industry
Benifits of power factor improvement for industryGovinda Neupane
 

What's hot (20)

Automatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportAutomatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino report
 
IEEE/NON-IEEE Projects For EEE branch
IEEE/NON-IEEE Projects For EEE branchIEEE/NON-IEEE Projects For EEE branch
IEEE/NON-IEEE Projects For EEE branch
 
main-project1
main-project1main-project1
main-project1
 
Ieee 2015 2014 power electronics project titles
Ieee 2015 2014 power electronics project titlesIeee 2015 2014 power electronics project titles
Ieee 2015 2014 power electronics project titles
 
Automatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.PptxAutomatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.Pptx
 
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
 
power factor correction soham+niraj
power factor correction soham+nirajpower factor correction soham+niraj
power factor correction soham+niraj
 
Two area system
Two area systemTwo area system
Two area system
 
Amit new report
Amit new reportAmit new report
Amit new report
 
Automatic power factor correction
Automatic power factor correction Automatic power factor correction
Automatic power factor correction
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
Automatic power factor_improvement_and_monitoring_by_using_plc[1]
Automatic power factor_improvement_and_monitoring_by_using_plc[1]Automatic power factor_improvement_and_monitoring_by_using_plc[1]
Automatic power factor_improvement_and_monitoring_by_using_plc[1]
 
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
 
Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier
 
Power Factor
Power FactorPower Factor
Power Factor
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final Report
 
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC TransmissionImprovement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
 
Benifits of power factor improvement for industry
Benifits of power factor improvement for industryBenifits of power factor improvement for industry
Benifits of power factor improvement for industry
 

Viewers also liked

Leadership versus management 1
Leadership versus management 1Leadership versus management 1
Leadership versus management 1vixian
 
From manager to leader
From manager to leaderFrom manager to leader
From manager to leaderRonie Protacio
 
Summer internship project on hdfc
Summer internship project on hdfcSummer internship project on hdfc
Summer internship project on hdfcProjects Kart
 

Viewers also liked (6)

Leadership versus management 1
Leadership versus management 1Leadership versus management 1
Leadership versus management 1
 
From manager to leader
From manager to leaderFrom manager to leader
From manager to leader
 
Leaders Or Managers
Leaders Or ManagersLeaders Or Managers
Leaders Or Managers
 
Leadership
LeadershipLeadership
Leadership
 
Managers vs leaders
Managers vs leadersManagers vs leaders
Managers vs leaders
 
Summer internship project on hdfc
Summer internship project on hdfcSummer internship project on hdfc
Summer internship project on hdfc
 

Similar to Rehabilitation of nablus electrical network by adding a new connection point

ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation Chandrabhan Sharma
 
Novel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatorNovel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatoreSAT Journals
 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfEngnr Kami Zeb
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...IJERA Editor
 
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...IJMTST Journal
 
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...IJPEDS-IAES
 
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...IRJET Journal
 
jeevan ppt 5.11.20.pptx
jeevan ppt 5.11.20.pptxjeevan ppt 5.11.20.pptx
jeevan ppt 5.11.20.pptxssuser7fea26
 
uppcl training in moradabad report
uppcl training in moradabad reportuppcl training in moradabad report
uppcl training in moradabad reportMONU KUMAR
 
Voltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution NetworkVoltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution Networkiosrjce
 
Analyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap softwareAnalyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap softwareArslan Sajjad
 
Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...IJAPEJOURNAL
 
Control of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridControl of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridSushil Aggarwal
 
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...IRJET Journal
 
Load Flow and PV Curve Analysis of a 220kV Substation
Load Flow and PV Curve Analysis of a 220kV SubstationLoad Flow and PV Curve Analysis of a 220kV Substation
Load Flow and PV Curve Analysis of a 220kV SubstationIRJET Journal
 
Novel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingNovel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingeSAT Publishing House
 

Similar to Rehabilitation of nablus electrical network by adding a new connection point (20)

ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation
 
CH1.ppt
CH1.pptCH1.ppt
CH1.ppt
 
Novel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatorNovel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulator
 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
 
High Gain Non Isolated DC-DC Step-up Converters Integrated with Active and Pa...
High Gain Non Isolated DC-DC Step-up Converters Integrated with Active and Pa...High Gain Non Isolated DC-DC Step-up Converters Integrated with Active and Pa...
High Gain Non Isolated DC-DC Step-up Converters Integrated with Active and Pa...
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
 
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
 
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
 
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
 
Islanding
IslandingIslanding
Islanding
 
jeevan ppt 5.11.20.pptx
jeevan ppt 5.11.20.pptxjeevan ppt 5.11.20.pptx
jeevan ppt 5.11.20.pptx
 
uppcl training in moradabad report
uppcl training in moradabad reportuppcl training in moradabad report
uppcl training in moradabad report
 
I010616064
I010616064I010616064
I010616064
 
Voltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution NetworkVoltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution Network
 
Analyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap softwareAnalyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap software
 
Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...Design and Development of Power Electronic Controller for Grid-connected PV A...
Design and Development of Power Electronic Controller for Grid-connected PV A...
 
Control of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridControl of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgrid
 
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
 
Load Flow and PV Curve Analysis of a 220kV Substation
Load Flow and PV Curve Analysis of a 220kV SubstationLoad Flow and PV Curve Analysis of a 220kV Substation
Load Flow and PV Curve Analysis of a 220kV Substation
 
Novel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingNovel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module using
 

More from slmnsvn

Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system slmnsvn
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system slmnsvn
 
Smart home
Smart homeSmart home
Smart homeslmnsvn
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detectorslmnsvn
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detectorslmnsvn
 
Rfid attendace system
Rfid attendace systemRfid attendace system
Rfid attendace systemslmnsvn
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicleslmnsvn
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicleslmnsvn
 
Power factor correction
Power factor correctionPower factor correction
Power factor correctionslmnsvn
 
Power factor correction
Power factor correctionPower factor correction
Power factor correctionslmnsvn
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallahslmnsvn
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallahslmnsvn
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkslmnsvn
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkslmnsvn
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2slmnsvn
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2slmnsvn
 
Optimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkOptimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkslmnsvn
 
Multi tone test
Multi tone testMulti tone test
Multi tone testslmnsvn
 
Multi tone test
Multi tone testMulti tone test
Multi tone testslmnsvn
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...slmnsvn
 

More from slmnsvn (20)

Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Smart home
Smart homeSmart home
Smart home
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
 
Rfid attendace system
Rfid attendace systemRfid attendace system
Rfid attendace system
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
 
Optimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkOptimum performance for aqraba electrical network
Optimum performance for aqraba electrical network
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...
 

Recently uploaded

Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfKamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdfKamal Acharya
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdfKamal Acharya
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfNurvisNavarroSanchez
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxViniHema
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxVishalDeshpande27
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 

Recently uploaded (20)

Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 

Rehabilitation of nablus electrical network by adding a new connection point

  • 1. An- Najah National University Rehabilitation of Nablus Electrical Network by adding a new connection point Submitted To : Dr. Maher Khammash Prepared By : Ahmad HatemAbd-Albaqi & Ali Namrouti 2015-2016 1
  • 2. Introduction  Our project is to study the performance of Nablus Network and to add a new connection point in the eastern region of the city of Nablus at the village of " Huwwara " with maximum capacity up to 20 MW.  Analyzing and make a load flow study using ETAP software and trying to achieve the optimum performance for “Eastern Region” Network .  Taking into consideration that there are 6 connection points in the electrical network of the city of Nablus. 2
  • 3. Objectives  Collecting data for the new connection point including all parameters and their specifications ( location, transmission lines , switchgear , load ).  Designing the one line diagram in ETAP program for new condition by adding the new supply bus .  Improving the voltage level and reducing the losses and correcting of power factor in the network .  Making the system more protected by increasing reliability and stability .  Analyzing the network under maximum load condition using load flow analyses.  To get economical benefit when improving the performance of network. 3
  • 4. Why new connection point ?  The main problem which faces Eastern Region Network is that the power supplied by IEC ‫االسرائيلية‬ ‫القطرية‬ ‫الشركة‬) ) is not enough for the demand in the city, especially in the summer season . And because the old connection point has a capacity up to 20 MW which is not sufficient for the network demand because the old connection point supplies more than one region, such as the industrial area and “Al-Bathan” .  To solve this problem , we add a new connection point with IEC in the eastern region of the city of Nablus in the village of " Huwwara " through an over head transmission line of 33 kV. The max demand is reached approximately to (20 MW) to cover the total demand . 4
  • 6. Methodology Collecting data for new C.P and elements Plotting one line diagram for new network Changing the voltage level to 11 kV instead of 6.6 Kv Analyzing the network under max. load case Improve p.f to avoid penalties Making Economical study for our project 6
  • 7.  Plotting one-line diagram using ETAP software for new Network  We make a load flow study and analysis Network using ETAP software .  Components of the network : 1. Two sources (33 kV) . 2. ( 280 ) bus in this network . 3. ( 107 ) loads( residential, industrial, commercial). 4. Substation with ( 2 ) power transformer . 5. ( 108 ) Distribution transformers . 7
  • 8.  Changing the Voltage Level from 6.6 to 11 kV  In this case, each 6.6 kV low voltage side will be exchanged by 11 kV. The same transformers are used because the transformers which are available have two windings on the low voltage side of 6.6 kV and 11 kV.  Distribution transformers of 11/0.4 and 6.6/0.4 kV will not be changed too . So, no new transformers are needed .  After raising the voltage to 11 kV , the voltage drop was decreased and a slight improvement to the power factor was observed . 8
  • 9.  The results of load flow in original case Operating Voltage(kV)Rated Voltage(kV)Bus 34.00034Bus 1 33.04333Bus 20 31.50333Bus 65 31.01633Bus 99 10.35511Bus 110 10.30211Bus 133 10.28011Bus 200 10.08711Bus 269 0.3650.4Bus 122 0.3620.4Bus 182 0.3560.4Bus 227 9
  • 10. Some of under voltage buses : 10
  • 11. Summary of results in original case %PFMVAMVarMW 82.24 lag41.86423.81534.430Source (swing bus) --5.8762.700Apparent losses 11  From the above results , there are many problems in the network .The P.F of the swing bus = 82.24 Lagging , which causes high penalties and losses . So, we try to increase the power factor of the busses and the voltage of the buses which is not included in the acceptable range .  Therefore ,we note that when we change the Voltage Level from 6.6 to 11 kV the losses for network decrease from 8.9% to 7.8% .
  • 12. Maximum load case  The voltage should be within this range : 1.05 V nominal < V < 1.1 V nominal  In first stage of the analysis of the network we have to take the maximum load in daily load curve ,then applied it on ETAB .  We started the study of this case after we applied the data needed Like load factor and other data. 12
  • 13. Load factor  We have the average value of loads by using the load factor of each load which we got from the real data of network and real daily load curves from SCADA system  The average demand load factor in our network is 75% that means the average load to the maximum load ratio is 75% which considered as a very good operating load factor . 13
  • 14. Our goal is to improve the voltages within the range by using the following steps :  Tab changing in the transformers.  Adding capacitors to produce reactive power.  Changing and replacing transformer.  Add another connection point . The tap changer of the secondary side of the 2 power transformers (33-11 kV) is raised to 10% , and tap change in all distribution transformers by 5% . 14
  • 15. Summary of results in maximum load case 15 %PFMVAMVarMW 83.25 lag42.32023.44635.232Source (swing bus) --5.2422.415Apparent losses  The losses in the network decrease . The losses before were = 2.700 MW, but the losses after become =2.415 MW .  For more improvement we add capacitor banks at the low voltage level and this is a temporary solution but we need a major solution to cover the total demand in the city. So , we choose to add a new connection point .
  • 16. Add a new connection point Comparing the voltages before and after adding the new connection point. 16 Voltage with two connection point (kV) Voltage with one connection point (kV) Bus 34.00034.000Bus 1 33.64933.043Bus 20 33.13431.503Bus 65 32.66631.016Bus 99 11.02410.355Bus 110 10.97310.302Bus 133 10.95210.280Bus 200 10.80610.087Bus 269 0.3900.365Bus 122 0.3870.362Bus 182 0.3830.356Bus 227
  • 17. Some of under voltage buses : 17
  • 18. Summary of results for new network 18 %PFMVAMVarMW 83.39 lag40.28822.23733.595Source (swing bus) --4.0971.168Apparent losses  We note that when adding a new connection point the losses for network decrease from 8.9% to 3.4% .  The P.F of the swing bus = 83.39 lag , which is low and causes a lot of penalties on both the company and consumers. So, we have to try to increase the power factor of the busses .
  • 19. Power Factor Improvement  It is important to keep the P.F above 0.92 on the distribution transformer so as to minimize the electrical losses and do not paying penalties.  How to improve the P.F ?? 19
  • 20. We added shunt capacitor banks at the buses at both transmission and distribution levels and loads with value : ( 300 , 400 , 1000 ) kVAR . 20
  • 21. Summary of results after improvement the network %PFMVAMVarMW 92.09 lag36.51414.23333.626Source (swing bus) --3.6061.010Apparent losses 21  After adding the capacitor banks the losses in the network decrease to 1.010 MW  The P.F = 92.09% which it was achieved , since a P.F was lower than that , it would lead to penalties on both the “NEDCO” and consumers .
  • 22. Elements Of The Network 1- Sources : Eastern Region are fed from 2 connection point by Israel Electrical Company (IEC), at 33KV. 2- Transformers :  Power Transformers : This network consists of (2) power transformer (33/11) KV with ratings 10 MVA .  Distribution transformers : 1. 41 distribution transformers (33/0.4)KV 2. 67 distribution transformers (11/0.4)KV 22 Number of Transformers Transformer Ratings (KVA) 2 2000 1 1600 3 1000 43 630 34 400 16 250 8 160 1 100 108 Total
  • 23. Elements Of The Network 3- Transmission Line & cable :  Over Head Line: The conductors used in the network are ACSR (Aluminum Conductor Steel Reinforced)  Under Ground Cable : The underground cable used in the network are XLPE Cu . 4- Switch gear : switchgears in substations are located on both the high and low voltage sides of large power transformers . Selection depends on : Voltage level ,Number of lines ,Location of substation , Possibility of expansion 23
  • 24. Elements Of The Network  Switchgear contain of : A. Circuit Breaker :  How to choose CB : • I C.B >= Ksafty * I max load . • VC.B >= V system. • I breaking capacity >= 1.2 * I S.C  The Specifications of the Circuit Breaker that we have used are as follows: • Ur = 36 kV, Up = 170 kV , Ud = 70kV ; 1 min • Ir = 1250 A , Ik = 25 kA ; tk = 1sec , Ip = 62.5 kA 24
  • 25. Elements Of The Network B. Bus-Bar : The Bus-Bar modules are either with single phase or three phase enclosure. Three phase enclosures are compact and have lesser eddy current losses. C. Isolator Switch : Isolating Switches are normally switched only when No Load . D. Earth Switch : Earth switch is used to discharge the voltage on the circuit to the earth for safety , earth switch is mounted on the frame of the isolaters 25
  • 26. Elements Of The Network 5 - Measurement in the medium voltage :  Current Transformers  Potential Transformers 6 - Supervisory Control & Data Acquisition (SCADA) : SCADA is a system for remote monitoring and control that operates with coded signals over communication channels. 26
  • 27. Economical Study In this project it is important to study the economical calculation to find if our work is suitable or not .  Saving in penalties : P.F before imp. = 0.83 P.F after imp. = 0.92 Pav = L.F * Pmax = 0.75 * 33.626 = 25.21 MW Total energy per year = Pav * 8760= 220839.6 MWH. Total cost per year = Total energy * cost (NIS/KWH) = 132503760 NIS/year. Saving in penalties of P.F = 115278.27 NIS/year.  Saving in losses : Saving in losses = cost of losses before – cost of losses after = 1064340 – 398142 = 666198 NIS/year. 27 Power Factor P.F Penalties P.F ≥ 0.92 No Penalties. 0.92 > P.F ≥ 0.8 1% of total bill for each one under 0.92 0.8 > P.F ≥ 0.7 1.25% of total bill for each one under 0.92 P.F < 0.7 1.5% of total bill for each one under 0.92
  • 28. Economical Study  Simple Pay Back Period : Total fixed capacitor banks using = 7.3 MVAR. Cost of fixed capacitor = 18000 NIS / MVAR . Total cost of capacitor banks = 7.3 * 18000 = 131400 NIS. The cost of under ground cable XLPE (1*240 mm2) = 100 NIS / 1 meter Total cost = 100 * 8000 = 800000 NIS . The cost of Infrastructure (such as: excavations, power source, accessories) = 100 NIS/1meter Total cost = 100 * 8000 = 800000 NIS . The cost of ( Links , wages of workers , equipment , Towers , installation cost and maintenance ) = 300000 NIS The cost of ( Internal equipment, construction, measurement device , SCADA system ) = 500000 NIS . Total capital cost = 131400 + 800000 + 800000 + 300000 + 500000 = 2531400 NIS Total saving = saving in losses + saving in penalties = 666198 + 115278.27 = 781476.27 NIS S.P.B.P = Investment / Saving = 2531400 / 781476.27 = 3.23 years 28
  • 29. How our new connection point will affect on Nablus network ? 29 RehabilitationoftheNabluselectricalnetwork Rehabilitation of the Nablus electrical network
  • 30. Conclusions  After the analysis and adding a new connection point , drop voltage was decreased , apparent losses was reduced too .  When adding a new connection point the losses for network decrease from 8.9% to 3.4% .  The power factor was improved to over 92% which will reduce any penalties paid to "IEC" on both "NEDCO" Company and consumers as will, and this is duo to adding a new connection point .  The network at full load need to 34 MW , but the availability of current two connection point is 40 MW . So, now we in the save side .  The time needed to recover the cost for the project is about 3 year . And the new network will be feed the new growth of load for the period from now to 2025 , depending on the annual increase of the loads to cover the demand in the city. 30
  • 31. Huwwara connection point 31 Rehabilitation of the Nablus electrical network
  • 32. Askar substation 32 Rehabilitation of the Nablus electrical network
  • 33. Switchgear in Askar substation 33 Rehabilitation of the Nablus electrical network
  • 34. SCADA system 34 Rehabilitation of the Nablus electrical network
  • 35. Recommendation  Finally , we hope from NEDCO with which we have contributed in gathering information and data about our project to take into consideration our calculation and improvement of the electrical network seriously . we also hope to see our project in Huwwara to be truly applied on the ground of reality . THANK YOU FOR YOUR ATTENTION 35
  • 36. 36