SlideShare a Scribd company logo
1 of 1
Download to read offline
1 2 3 4 5 6 7
Work Package
description
Mixed Gas Manifold Instrument Air & Dry Air Water System MV Distribution Substation EOT Cranes Lighting & Utility power Chiller Plant
Purpose
To provide Mixed gas as the
fuel for the Walking beam
furnace
To provide oxygen for gas
cutting and instrument air to
support various field
instruments in level -1
automation level
Providing direct & Indirect
cooling water for process needs
Providing power (11KV) to
variable loads as well as fixed
loads via two distinct Metalclad
Air Insulated Substations
For Maintenance of Mill
Equipments and Shipping of
materials from Storage Bay
Entire Plant illumination and
auxiliary power to Electrical
Overhaed cranes and Hoist
Water for plant Air Handling Unit
1 2 3 4 5 6 7
Design Supply Installation & Cold Trial Hot Trial Preliminary Acceptance Provisional Acceptance Final Acceptance
1) Assessment of project
requirements
1) Procuremnt of
Plant/equipment as per
approved drawing & scopeof
work
1) Completion of installation and
validation of scope & deliverables
1) To test the capacity of the
equipments to operate
smoothly with load
1) Beginning of transition from
project to operation through Start
up & Operation
1) Operation of plant by the
Client under supervision of
the Contractor
1) Start of Guarantee Period
2) Preparation of Billing
schedule for design & basic
engineering drawings
2)Prepare and finalize Billing
schedule in line with milestone
achievements
2) Completion of individual
system testing and certifying fit
for use
2) to ensure the operational
stability of electro-mechanical
systems
2) To achieve troble free
production of selected products
over asustained period as agreed
during contract
2) Commencement of Defect
liability period as stated in
the contract
2) Completion of liquidation of all
defects
3) Exchange of feedback data
3) Conduct Quality Inspection &
achieve Inspection Certificate
for Sl No 1 above
3) Checking of equipment
functionality & System
functionality
3) To ensure conformance with
Functional description &
sequence of process
3) Observation of process
performance
3) Rectification of defects
issed during PAC
3) Obtaining Financial closure,
Administrative & legal closure
4) Preparation of Detail
engineering
4) Submission of all third party
test reports of Sl No 1 above
4) Simulation of Automation
sequences of the process on a
stand alone basis
4) To perform integrated trial
run of the entire system over an
agreed period as per the terms
of contract
4) Issuance of defects and process
improvementcriteria
4) Preparation & submission
of As Built Drawings
indicating all changes that
occurred during execution.
4) Prepare & submit project
performance report
5) Review and approval of
drawings & documents
5) Procurement of
Plant/equipments as per
milestone and budget
5) Optimize the settings of
equipments & software for
trouble free operation
5) To perform endurance test to
conform quality and start
transition from project to
operation
5) Handingover the plant &
equipment to client & obtaining
Preliminary Acceptance Certificate
5) Undertaking Performance
Guarantee Test to show the
efficiency of the system
against the parameters
defined in the contract.
5) Archiving project documents &
collating lessons learned
6) Distribution of requisite
copies to concerned
department
6) Delivery & Storage at site
along with completion of
bailment agreement with client
6) Undertaking No Load trial for
an agreed period with validation
of the scope & deliverables
6) Validation of scope &
deliverables and obtaining
Provisional Acceptance
Certificate
6) Obtain feedback from client
700000 to 850000 TPY capacity having a 200 TPH Walking Beam furnace& equipped with Level-3 automation
Hot Rolling Steel Mill
Work Breakdown Structure of a Hot Rolling Steel Mill
Project Life Cycle of Steel Rolling Mill

More Related Content

What's hot

7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final ReportArissa Loh
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionRicardo Viana Vargas
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Managementjonash99
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management examJamil Faraj , PMP
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Procurement contract management
Procurement contract managementProcurement contract management
Procurement contract managementAavenir
 
Agility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBITAgility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBITPrzemek Wysota
 
Case study for project management-Triple constraints
Case study for project management-Triple constraintsCase study for project management-Triple constraints
Case study for project management-Triple constraintsminal0493
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementEdwinJacob5
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr. Pramod Deshpande
 
C1 introduction_of_project_management
C1  introduction_of_project_managementC1  introduction_of_project_management
C1 introduction_of_project_managementIzah Asmadi
 

What's hot (20)

7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final Report
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Management
 
Project Management Plan - Group Presentation
Project Management Plan - Group PresentationProject Management Plan - Group Presentation
Project Management Plan - Group Presentation
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Project management
Project managementProject management
Project management
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Procurement contract management
Procurement contract managementProcurement contract management
Procurement contract management
 
Agility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBITAgility under Control - SCRUM vs COBIT
Agility under Control - SCRUM vs COBIT
 
Case study for project management-Triple constraints
Case study for project management-Triple constraintsCase study for project management-Triple constraints
Case study for project management-Triple constraints
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract management
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
C1 introduction_of_project_management
C1  introduction_of_project_managementC1  introduction_of_project_management
C1 introduction_of_project_management
 

Similar to Work breakdown structure & project life cycle

ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)Vijayakumar Kumar
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installationswan saiful arini
 
Heating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationHeating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationMayur Unde
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013leo040490
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning pptDayasagar Govidaraju
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptxDayasagar Govidaraju
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Nicholas Naing
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
Engineering
EngineeringEngineering
EngineeringKomalia
 
Engineering
EngineeringEngineering
EngineeringKomalia
 
INSTRUMENT QA QC INSPECTOR
INSTRUMENT QA QC INSPECTORINSTRUMENT QA QC INSPECTOR
INSTRUMENT QA QC INSPECTORRegu Mkc
 
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptxEQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptxpraaditya2020
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemArpitSuralkar
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
369051174-Basic-of-Commissioning.pdf
369051174-Basic-of-Commissioning.pdf369051174-Basic-of-Commissioning.pdf
369051174-Basic-of-Commissioning.pdfPDVSA Petrodelta
 

Similar to Work breakdown structure & project life cycle (20)

hvac new cv mubeen
hvac new cv mubeenhvac new cv mubeen
hvac new cv mubeen
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Heating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationHeating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC Qualification
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning ppt
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptx
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
Engineering
EngineeringEngineering
Engineering
 
Engineering
EngineeringEngineering
Engineering
 
Engineering
EngineeringEngineering
Engineering
 
019113
019113019113
019113
 
INSTRUMENT QA QC INSPECTOR
INSTRUMENT QA QC INSPECTORINSTRUMENT QA QC INSPECTOR
INSTRUMENT QA QC INSPECTOR
 
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptxEQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
M Imran
M ImranM Imran
M Imran
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
369051174-Basic-of-Commissioning.pdf
369051174-Basic-of-Commissioning.pdf369051174-Basic-of-Commissioning.pdf
369051174-Basic-of-Commissioning.pdf
 

More from Sayandeep Dasgupta

Covid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentationCovid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentationSayandeep Dasgupta
 
Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Sayandeep Dasgupta
 
Rated diversity factor of a switchboard
Rated diversity factor of a switchboardRated diversity factor of a switchboard
Rated diversity factor of a switchboardSayandeep Dasgupta
 
Overiew of a hot rolling steel mill
Overiew of a hot rolling steel millOveriew of a hot rolling steel mill
Overiew of a hot rolling steel millSayandeep Dasgupta
 

More from Sayandeep Dasgupta (8)

Concession Agreement.pptx
Concession Agreement.pptxConcession Agreement.pptx
Concession Agreement.pptx
 
Force Majeure.pptx
Force Majeure.pptxForce Majeure.pptx
Force Majeure.pptx
 
Conditions Precedent.pptx
 Conditions Precedent.pptx Conditions Precedent.pptx
Conditions Precedent.pptx
 
Covid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentationCovid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentation
 
Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis
 
Rated diversity factor of a switchboard
Rated diversity factor of a switchboardRated diversity factor of a switchboard
Rated diversity factor of a switchboard
 
Overiew of a hot rolling steel mill
Overiew of a hot rolling steel millOveriew of a hot rolling steel mill
Overiew of a hot rolling steel mill
 
Metalclad switchgear
Metalclad switchgearMetalclad switchgear
Metalclad switchgear
 

Recently uploaded

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 

Work breakdown structure & project life cycle

  • 1. 1 2 3 4 5 6 7 Work Package description Mixed Gas Manifold Instrument Air & Dry Air Water System MV Distribution Substation EOT Cranes Lighting & Utility power Chiller Plant Purpose To provide Mixed gas as the fuel for the Walking beam furnace To provide oxygen for gas cutting and instrument air to support various field instruments in level -1 automation level Providing direct & Indirect cooling water for process needs Providing power (11KV) to variable loads as well as fixed loads via two distinct Metalclad Air Insulated Substations For Maintenance of Mill Equipments and Shipping of materials from Storage Bay Entire Plant illumination and auxiliary power to Electrical Overhaed cranes and Hoist Water for plant Air Handling Unit 1 2 3 4 5 6 7 Design Supply Installation & Cold Trial Hot Trial Preliminary Acceptance Provisional Acceptance Final Acceptance 1) Assessment of project requirements 1) Procuremnt of Plant/equipment as per approved drawing & scopeof work 1) Completion of installation and validation of scope & deliverables 1) To test the capacity of the equipments to operate smoothly with load 1) Beginning of transition from project to operation through Start up & Operation 1) Operation of plant by the Client under supervision of the Contractor 1) Start of Guarantee Period 2) Preparation of Billing schedule for design & basic engineering drawings 2)Prepare and finalize Billing schedule in line with milestone achievements 2) Completion of individual system testing and certifying fit for use 2) to ensure the operational stability of electro-mechanical systems 2) To achieve troble free production of selected products over asustained period as agreed during contract 2) Commencement of Defect liability period as stated in the contract 2) Completion of liquidation of all defects 3) Exchange of feedback data 3) Conduct Quality Inspection & achieve Inspection Certificate for Sl No 1 above 3) Checking of equipment functionality & System functionality 3) To ensure conformance with Functional description & sequence of process 3) Observation of process performance 3) Rectification of defects issed during PAC 3) Obtaining Financial closure, Administrative & legal closure 4) Preparation of Detail engineering 4) Submission of all third party test reports of Sl No 1 above 4) Simulation of Automation sequences of the process on a stand alone basis 4) To perform integrated trial run of the entire system over an agreed period as per the terms of contract 4) Issuance of defects and process improvementcriteria 4) Preparation & submission of As Built Drawings indicating all changes that occurred during execution. 4) Prepare & submit project performance report 5) Review and approval of drawings & documents 5) Procurement of Plant/equipments as per milestone and budget 5) Optimize the settings of equipments & software for trouble free operation 5) To perform endurance test to conform quality and start transition from project to operation 5) Handingover the plant & equipment to client & obtaining Preliminary Acceptance Certificate 5) Undertaking Performance Guarantee Test to show the efficiency of the system against the parameters defined in the contract. 5) Archiving project documents & collating lessons learned 6) Distribution of requisite copies to concerned department 6) Delivery & Storage at site along with completion of bailment agreement with client 6) Undertaking No Load trial for an agreed period with validation of the scope & deliverables 6) Validation of scope & deliverables and obtaining Provisional Acceptance Certificate 6) Obtain feedback from client 700000 to 850000 TPY capacity having a 200 TPH Walking Beam furnace& equipped with Level-3 automation Hot Rolling Steel Mill Work Breakdown Structure of a Hot Rolling Steel Mill Project Life Cycle of Steel Rolling Mill