SlideShare a Scribd company logo
1 of 43
COURSE ON
POWER SYSTEM -I
ELECTRICAL ENGINEERING DEPT.
Presented By,
Prof. KHANDEKAR N.V.
ME(EPS)
SVERI’S COE, Pandharpur
Power System –I
UNIT-I
Economic Aspect of Power Generation
SYLLABUS:-
Review of terms used in system operation, variable load on power
system, peak load, base load, Diversity factor, plant utility factor,
maximum demand,load curve, load duration. Types of loads, Selection
of generation units, Interconnected grid systems, Cost of electrical
energy, Tariff & different types of tariff.
Teaching Scheme Examinations
Theory: - 3Hrs/Week,1 Credits ESE – 70 Marks
Tutorial: - 1Hrs/Week, 1 Credit CA-25Marks
ISE- 30Marks
INTRODUCTION TO POWER SYSTEM
 Power system is defined as the network of generating
stations, substations and power lines.
 Power system may be considered as one of the largest
and most expensive system of all manmade systems.
 Branch of Electrical Engineering which deal with the
Technology of
 Generation,
 Transmission and Distribution
 DC Power system Pearl Street Station in New York City,
1882 “Illuminating Companies” by Thomas A. Edison
 Three phase AC Power System, 1896 2 Generators &
Transmission line @ 25 Hz
Power System Structure
SINGLE LINE DIAGRAM OF POWER
SYSTEM
INTERCONECTED GRID SYSTEM
The connection of several generating stations in parallel is known as
interconnected grid system.
 Several Advantages
(i) Exchange of peak loads :
An important advantage of interconnected system is that the peak load of the
power station can be exchanged. If the load curve of a power station shows a
peak demand that is greater than the rated capacity of the plant, then the excess
load can be shared by other stations interconnected with it.
(ii) Use of older plants :
The interconnected system makes it possible to use the older and less efficient
plants to carry peak loads of short durations. Although such plants may be
inadequate when used alone, yet they have sufficient capacity to carry short
peaks of loads when interconnected with other modern plants. Therefore,
interconnected system gives a direct key to the use of obsolete plants.
(iii) Ensures economical operation :
The interconnected system makes the operation of concerned power
stations quite economical. It is because sharing of load among the
stations is arranged in such a way that more efficient stations work
continuously throughout the year at a high load factor and the less
efficient plants work for peak load hours only.
(iv) Increases diversity factor :
The load curves of different interconnected stations are generally
different. The result is that the maximum demand on the system is
much reduced as compared to the sum of individual maximum demands
on different stations. In other words, the diversity factor of the system
is improved, thereby increasing the effective capacity of the system.
(v) Reduces plant reserve capacity :
Every power station is required to have a standby unit for emergencies.
However, when several power stations are connected in parallel, the
reserve capacity of the system is much reduced. This increases the
efficiency of the system.
Components of Power System
 Generators:
Alternators, 3 phase, AC, 50 Hz, 11 – 22 KV
 Transformers: Voltage level conversion without
changing frequency and power Ex: 11KV to 220KV,
22KV to 132KV, 110KV to 11KV, 11 KV to 415V
 Substations: Control center for Distribution network
 Loads:
 Electrical Load: Motors, household appliances,
lighting
 Mechanical Load: Pulleys, Fans, Flooring machine,
blowers, etc. Transmission & Distribution V
Transmission & Distribution Voltage Levels
 Transmission Networks – EHV AC or HVDC Operates @
765 kV/ 400 kV/ 220 kV AC or ± 500 kV DC AC
 Sub-Transmission Networks Operates @ 132 kV/ 110
kV/ 66 kV/ 33 KV AC
 Distribution Network Primary side: 11 kV
 Secondary side: 415 V, 4 wire AC Household 230 V, 50
Hz, Single phase
Different Terms
Plant Utility Factor
The utilization factor or use factor is the ratio of the time
that a piece of equipment is in use to the total time that it
could be in use. It is often averaged over time in the
definition such that the ratio becomes the amount of energy
used divided by the maximum possible to be used. These
definitions are equivalent.
PUF= Time That A Piece Of Equipment Is In Use
Total Time That It Could Be In Use
LOAD CURVE
Definition: Load curve or chronological curve is the graphical
representation of load (in kW or MW) in proper time sequence and the
time in hours. It shows the variation of load on the power station.
When the load curve is plotted for 24 hours a day, then it is called daily
load curve. If the one year is considered then, it is called annual load
curve.
The load curve of the power system is not same all the day. It differs
from day to day and season to season. The load curve is mainly classified
into two types, i.e., the summer load curve and the winter load curve.
Importance of Load Curve
Information Obtained From Load
Curve
The following are the information obtained from load curves.
 Load duration curve determines the load variation during different hours of the
day.
 It indicates the peak load which determines the maximum demand on the power
station.
 The area under the load curve gives the total energy generated in the period
under consideration.
 The area under the curve divided by the total numbers of hours gives the load.
 The ratio of the area under the load curve of the total area of the rectangle in
which it is contained gives the load factor.
 The ideal load curve is flat, but practically it is far from flat. For a flat load
curve, the load factor will be higher. Higher load factor means the more uniform
load pattern with fewer variations in load.
Load Duration Curve
Definition: The load duration curve is defined as the curve between the load and
time in which the ordinates representing the load, plotted in the order of decreasing
magnitude, i.e., with the greatest load at the left, lesser loads towards the rights and
the lowest loads at the time extreme right. The load duration curve is shown in the
figure below.
This curve represents the same data as that of the load curve. The load duration
curve is constructed by selecting the maximum peak points and connecting them by
a curve.
The load duration curve plotting for 24 hours of a day is called the daily load
duration curve. Similarly, the load duration curve plotted for a year is called the
annual load curve.
Procedure for Plotting the Load Duration Curve
1. From the data available from the load curve determines the
maximum load and the duration for which it occurs.
2. Now take the next load and the total time during which this and
the previous load occurs.
3. Plots the loads against the time during which it occurs.
4. The load duration curves can be drawn for any duration of time,
for example, a day or a month or a year. The whole duration is
taken as 100%
Example of how to plot LDC from Load Curve given In notes
Loads on Power System
Residential load:
Commercial Loads:
Industrial Loads:
Agricultural loads :
Municipal Loads :
Traction Loads :
Residential load:
Commercial Loads:
Industrial Loads:
Agricultural loads :
Municipal Loads :
Municipal loads consist of street lights, electricity required
for water supply pumps and drainage system. for water
supply water is pumped to the overhead tank using electric
pump, overhead water tank pumping is carried out during
off-peak time. like during night time. its improve load
factor of power system.
Traction Loads :
This types of loads mainly include trains, traction loads
has wide variation. during morning hours it reaches peak
value and during afternoon loads starts decreasing and
again rises to peak value during evening time.
COST OF ELECTRICAL
ENERGY
There are three kinds of expenditures involved in
generating electricity.
 fixed cost
 Semi-fixed cost
 Running or operating cost
FIXED COST
In every manufacturing unit there is some hidden expenditure which
fixed. This is same for manufacturing one unit or thousand units of
the items. In electric generating station like manufacturing unit,
there are some hidden costs which independent of the quantity of
electricity produced. These fixed expenditures are mainly due to an
annual cost to run the organization, interest on capital cost and tax
or rent of the land on which the organization established, salaries of
high officials and interests of loans (if any) on the capital cost of the
organization. Like these main costs, there are many others
expenditures which do not change whether the rate of production of
electrical energy units is less or more.
SEMI-FIXED COST
There is another type costing for any manufacturing or production or any similar
type of industries. These costs are not strictly fixed and also not fully dependent
on the number of items manufactured or produced. These costs depend on the
size of the plant. These actually depend on the assumption of a maximum
number of items which can be produced from the plant at a time during peak
demand period. That means the forecasted production demand of the plant
determines how big will be the manufacturing or production plant. Likewise, the
size of an electrical generating plant depends on the maximum demand of the
connected load of the system. If the maximum demand of the load is quite higher
than the average demand of the load, then the power generating plant should be
constructed and well equipped to fulfill that maximum demand of the system
even the peak demand lasts for less than an hour. This type of costs is referred as
semi-fixed cost. It is directly proportional to the maximum demand on the power
station. The annual interest and depreciation on capital investment of building
and equipment, taxes, salaries of management and clerical staff, expenditure for
installation etc. come under semi-fixed costs.
RUNNING OR OPERATING COST
The total cost of per unit generation of electrical energy can be expressed in the following ways.
First, we have to calculate the entire expenditure of the plant including the organization which is fixed throughout the
year and accounted for a fixed cost. Say this is a.
This is considered as fixed cost for entire electrical energy generated in the year.
In the same way, we have to calculate the total semi-fixed cost of the plant throughout the year.
The semi-fixed cost is proportional to maximum demand of the plant. So, we have to find the maximum demand of the
year. So the proportionality constant b can easily be calculated.
Therefore, the semi-fixed cost of the plant for the year is b(maximum demand kilowatt).
Now, we will calculate entire running expenses of the plant for producing total kWh units of energy generated in the
year.
If c is the running cost per unit of generated electricity then 0
Total cost of the plant for producing entire electric throughout the year is
= 𝑹𝒔(𝒂 + b kw+ c kw)
a –fixed cost
B- semi fixed cost
C running cost.
Sometimes it is assumed that entire capital cost and other costs except for the running expenses for producing electricity
entirely depend on the maximum demand of the plant. In that case, it is assumed that there is no absolute fixed cost.
The expression for the annual cost of energy then becomes= 𝑹𝑺(𝑨𝒌𝒘 + 𝑩𝒌𝒘)
Where A is the cost per unit /maximum demand and B is the running cost of producing one unit of electrical cost
TARIFF&DIFERENT TYPES OF TARIFF
Electricity Tariffs.
Definition: The amount of money frame by the supplier for the supply
of electrical energy to various types of consumers in known as an
electricity tariff.
In other words, the tariff is the methods of charging a consumer for
consuming electric power.
TYPES OF TARIFF
Flat Demand Rate tariff.
Straight-line Meter rate tariff.
Block meter Rate tariff.
Two-part tariff.
Power factor tariff.
Seasonal rate tariff.
Peak load tariff.
Three-part tariff.
The electricity tariffs depends on the following factors
 Type of load
 Time at which load is required.
 The power factor of the load.
 The amount of energy used.
The total bill of the consumer has three parts, namely, fixed charge D,
semi-fixed charge Ax and running charge By.
𝑪 = 𝑨𝒙 + 𝑩𝒚 + 𝑫
where, C – total charge for a period (say one month)
x – maximum demand during the period (kW or kVA)
y – Total energy consumed during te period (kW or kVA)
A – cost per kW or kVa of maximum demand.
B – cost per kWh of energy consumed.
D – fixed charge during each billing period.
This is known as three-part electricity tariff, and it is mainly applied to the big
consumer.
1.Flat Demand /Simple Rate tariff
The flat demand rate tariff is expressed by the equation
𝑪 = 𝑨𝒙.
In this type of tariff, the bill of the power consumption
depends only on the maximum demand of the load.
The generation of the bill is independent of the normal
energy consumption.
This type of tariff is used on the street light, sign lighting,
irrigation, etc., where the working hours of the equipment
are unknown.
The metering system is not used for calculating such type
of tariffs.
2.Straight-line Meter rate tariff.
This type of tariff is given by the equation
𝑪 = 𝑩𝒚.
The generation of the bills depends on the energy consumption
of the load. Thus, different types of bills are generated by the
consumers.
The charges for different types of consumption depends on the
load and diversity factors of the load.
For example, the tariff for small devices is less as compared to
the power loads. Hence different meters are used for measuring
the power consumption.
3.Block meter Rate tariff.
In this type of tariff, the energy consumption is distinguished
into blocks.
The per unit tariff of the individual block is fixed. The price of
the block is arranged in the decreasing order. The first block has
the highest cost, and it goes on decreasing accordingly.
The price and the energy consumption are divided into three
blocks. The first few units of energy at a certain rate, the next at
a slightly lower rate and the remaining unit at a very lower rate.
4.Two-part tariff.
In such type of tariff, the total bill is divided into two parts. The
first one is the fixed charge and the second is the running
charge. The fixed charge is because of the maximum demand
and the second charge depends on the energy consumption by
the load.
𝐶 = 𝐴𝑥 + 𝐵𝑦
𝐶 = 𝐴 𝑘𝑤 + (𝑘𝑤ℎ)
The factor A and B may be constant and vary according to some
sliding.
5.Power factor tariff.
The tariff, which depends on the power factor of the load is known as the
power factor tariff. The power factor tariff is mainly classified into two
types.
a. kVA maximum demand tariff – This is also a two-part tariff.
𝑻𝒐𝒕𝒂𝒍 𝒄𝒉𝒂𝒓𝒈𝒆𝒔 = 𝑨 𝑲𝑽𝑨 + 𝑩(𝑲𝑾𝒉)
The low power factor increases the KVA rating of the load.
b. kWh and kVarh tariff – The bill is calculated by the sum of the kVarh
and Kwh rating of the load
𝑻𝒐𝒕𝒂𝒍 𝐶ℎ𝒂𝒓𝒈𝒆𝒔 = 𝑨𝟏 𝑲𝑾𝒉 + 𝑩𝟏(𝑲𝑽𝑨𝒓𝒉)
The kVarh is inversely proportional to the power factor of the load.
c. Sliding Scale or Average power factor tariff – In Average power factor
tariff, the particular value of the power factor is taken as reference. If the
power factor at the consumer end is low, then the consumer has to pay the
additional charges. Similarly, if the power factor of the load is above from
the reference value, then the discount will be given to the consumer.
6.Seasonal rate tariff.
Such type of tariff measures the high price in kWh used by the consumer in
one complete year. It is also known as the on peak season tariff. If the low
consumption occurs in the year, then it called the off-peak season tariffs.
7. Peak-load tariff
Such type of tariff is similar to peak load tariffs. The only difference is that the
seasonal tariff measures the peak hour of the year and the peak tariff calculates it
for the day. If the power consumption is high, then it is known as the on-peak
tariff, and for low power consumption, it is called off-peak load tariffs.
The peak load and seasonal tariffs both are used for reducing the idle or standby
capacity of the load.
8. Three-part tariff
The three-part tariff is in the form of,
𝑪 = 𝑨𝒙 + 𝑩𝒚 + 𝑫
and it is applied to the big consumer.
Thank you….....!

More Related Content

What's hot

Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curvesSwapnil Gadgune
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curvesGPERI
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Power System Operation
 
IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...
IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...
IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...IRJET Journal
 
Load factor and demand factor
Load factor and demand factorLoad factor and demand factor
Load factor and demand factordhirajthakkar1
 
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid IJMER
 
Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...
Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...
Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...ijtsrd
 
Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...Kinnera Kin
 
Benefits of power flow control
Benefits of power flow controlBenefits of power flow control
Benefits of power flow controljgould03
 
A Review on Design and Development of high Reliable Hybrid Energy Systems wit...
A Review on Design and Development of high Reliable Hybrid Energy Systems wit...A Review on Design and Development of high Reliable Hybrid Energy Systems wit...
A Review on Design and Development of high Reliable Hybrid Energy Systems wit...IJPEDS-IAES
 
Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...
Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...
Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...IJAEMSJORNAL
 
Rated diversity factor of a switchboard
Rated diversity factor of a switchboardRated diversity factor of a switchboard
Rated diversity factor of a switchboardSayandeep Dasgupta
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingBIJAY NAYAK
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMASWATHYSANAND1
 
Preliminary electrical load calculation course share
Preliminary electrical load calculation course sharePreliminary electrical load calculation course share
Preliminary electrical load calculation course shareAli Hassan
 
Commercial load estimation for electrical
Commercial load estimation for electricalCommercial load estimation for electrical
Commercial load estimation for electricalasmjewel
 
Power electronics ieee 2012 2013
Power electronics ieee 2012 2013Power electronics ieee 2012 2013
Power electronics ieee 2012 2013Ecwayt
 

What's hot (18)

Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curves
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
 
IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...
IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...
IRJET-Power Quality Improvement in Grid Connected Wind Energy Conversion Syst...
 
Load factor and demand factor
Load factor and demand factorLoad factor and demand factor
Load factor and demand factor
 
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid STATCOM for Improved Dynamic Performance of Wind Farms  in Power Grid
STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid
 
Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...
Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...
Power Upgrading of Transmission Line by Combining AC DC Transmission and Anal...
 
Paperbus12
Paperbus12Paperbus12
Paperbus12
 
Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...Statcom control scheme for power quality improvement of grid connected wind e...
Statcom control scheme for power quality improvement of grid connected wind e...
 
Benefits of power flow control
Benefits of power flow controlBenefits of power flow control
Benefits of power flow control
 
A Review on Design and Development of high Reliable Hybrid Energy Systems wit...
A Review on Design and Development of high Reliable Hybrid Energy Systems wit...A Review on Design and Development of high Reliable Hybrid Energy Systems wit...
A Review on Design and Development of high Reliable Hybrid Energy Systems wit...
 
Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...
Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...
Improvement of Power Delivery Efficiency of 11KV Power Line using Power Capac...
 
Rated diversity factor of a switchboard
Rated diversity factor of a switchboardRated diversity factor of a switchboard
Rated diversity factor of a switchboard
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
 
Preliminary electrical load calculation course share
Preliminary electrical load calculation course sharePreliminary electrical load calculation course share
Preliminary electrical load calculation course share
 
Commercial load estimation for electrical
Commercial load estimation for electricalCommercial load estimation for electrical
Commercial load estimation for electrical
 
Power electronics ieee 2012 2013
Power electronics ieee 2012 2013Power electronics ieee 2012 2013
Power electronics ieee 2012 2013
 

Similar to Power system -Economic Aspect of Electric power Genration

Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generationMaharishi Tiwari
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxFelcherLayugan
 
Load on power system
Load on power systemLoad on power system
Load on power systemv Kalairajan
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docxArpitaBanik8
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfTheBlank5
 
Paper id 24201458
Paper id 24201458Paper id 24201458
Paper id 24201458IJRAT
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curvesSwapnil Gadgune
 
SodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptSodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptswathisriranjani1
 
Microogrid with diesel generator ,wind turbine and solar farm with optimistic...
Microogrid with diesel generator ,wind turbine and solar farm with optimistic...Microogrid with diesel generator ,wind turbine and solar farm with optimistic...
Microogrid with diesel generator ,wind turbine and solar farm with optimistic...MATLAB Solutions
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVECMathankumar S
 
Power-System.pdf
Power-System.pdfPower-System.pdf
Power-System.pdfAmerKhan85
 
Power system operation Question and answers
Power system operation Question and answersPower system operation Question and answers
Power system operation Question and answersAdhithyaS5
 
What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?Power System Operation
 

Similar to Power system -Economic Aspect of Electric power Genration (20)

Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Ch01-ESR-L01.pdf
Ch01-ESR-L01.pdfCh01-ESR-L01.pdf
Ch01-ESR-L01.pdf
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
load on power system
 load on power system load on power system
load on power system
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Load on power system
Load on power systemLoad on power system
Load on power system
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Paper id 24201458
Paper id 24201458Paper id 24201458
Paper id 24201458
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curves
 
SodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptSodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.ppt
 
Microogrid with diesel generator ,wind turbine and solar farm with optimistic...
Microogrid with diesel generator ,wind turbine and solar farm with optimistic...Microogrid with diesel generator ,wind turbine and solar farm with optimistic...
Microogrid with diesel generator ,wind turbine and solar farm with optimistic...
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVEC
 
C05321419
C05321419C05321419
C05321419
 
CH-2_PPEE.ppt
CH-2_PPEE.pptCH-2_PPEE.ppt
CH-2_PPEE.ppt
 
520planning
520planning520planning
520planning
 
Power-System.pdf
Power-System.pdfPower-System.pdf
Power-System.pdf
 
Power system operation Question and answers
Power system operation Question and answersPower system operation Question and answers
Power system operation Question and answers
 
What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 

Power system -Economic Aspect of Electric power Genration

  • 1. COURSE ON POWER SYSTEM -I ELECTRICAL ENGINEERING DEPT. Presented By, Prof. KHANDEKAR N.V. ME(EPS) SVERI’S COE, Pandharpur
  • 2. Power System –I UNIT-I Economic Aspect of Power Generation SYLLABUS:- Review of terms used in system operation, variable load on power system, peak load, base load, Diversity factor, plant utility factor, maximum demand,load curve, load duration. Types of loads, Selection of generation units, Interconnected grid systems, Cost of electrical energy, Tariff & different types of tariff. Teaching Scheme Examinations Theory: - 3Hrs/Week,1 Credits ESE – 70 Marks Tutorial: - 1Hrs/Week, 1 Credit CA-25Marks ISE- 30Marks
  • 3. INTRODUCTION TO POWER SYSTEM  Power system is defined as the network of generating stations, substations and power lines.  Power system may be considered as one of the largest and most expensive system of all manmade systems.  Branch of Electrical Engineering which deal with the Technology of  Generation,  Transmission and Distribution  DC Power system Pearl Street Station in New York City, 1882 “Illuminating Companies” by Thomas A. Edison  Three phase AC Power System, 1896 2 Generators & Transmission line @ 25 Hz
  • 5.
  • 6. SINGLE LINE DIAGRAM OF POWER SYSTEM
  • 7. INTERCONECTED GRID SYSTEM The connection of several generating stations in parallel is known as interconnected grid system.  Several Advantages (i) Exchange of peak loads : An important advantage of interconnected system is that the peak load of the power station can be exchanged. If the load curve of a power station shows a peak demand that is greater than the rated capacity of the plant, then the excess load can be shared by other stations interconnected with it. (ii) Use of older plants : The interconnected system makes it possible to use the older and less efficient plants to carry peak loads of short durations. Although such plants may be inadequate when used alone, yet they have sufficient capacity to carry short peaks of loads when interconnected with other modern plants. Therefore, interconnected system gives a direct key to the use of obsolete plants.
  • 8. (iii) Ensures economical operation : The interconnected system makes the operation of concerned power stations quite economical. It is because sharing of load among the stations is arranged in such a way that more efficient stations work continuously throughout the year at a high load factor and the less efficient plants work for peak load hours only. (iv) Increases diversity factor : The load curves of different interconnected stations are generally different. The result is that the maximum demand on the system is much reduced as compared to the sum of individual maximum demands on different stations. In other words, the diversity factor of the system is improved, thereby increasing the effective capacity of the system. (v) Reduces plant reserve capacity : Every power station is required to have a standby unit for emergencies. However, when several power stations are connected in parallel, the reserve capacity of the system is much reduced. This increases the efficiency of the system.
  • 9. Components of Power System  Generators: Alternators, 3 phase, AC, 50 Hz, 11 – 22 KV  Transformers: Voltage level conversion without changing frequency and power Ex: 11KV to 220KV, 22KV to 132KV, 110KV to 11KV, 11 KV to 415V  Substations: Control center for Distribution network  Loads:  Electrical Load: Motors, household appliances, lighting  Mechanical Load: Pulleys, Fans, Flooring machine, blowers, etc. Transmission & Distribution V
  • 10. Transmission & Distribution Voltage Levels  Transmission Networks – EHV AC or HVDC Operates @ 765 kV/ 400 kV/ 220 kV AC or ± 500 kV DC AC  Sub-Transmission Networks Operates @ 132 kV/ 110 kV/ 66 kV/ 33 KV AC  Distribution Network Primary side: 11 kV  Secondary side: 415 V, 4 wire AC Household 230 V, 50 Hz, Single phase
  • 12.
  • 13.
  • 14. Plant Utility Factor The utilization factor or use factor is the ratio of the time that a piece of equipment is in use to the total time that it could be in use. It is often averaged over time in the definition such that the ratio becomes the amount of energy used divided by the maximum possible to be used. These definitions are equivalent. PUF= Time That A Piece Of Equipment Is In Use Total Time That It Could Be In Use
  • 15.
  • 16. LOAD CURVE Definition: Load curve or chronological curve is the graphical representation of load (in kW or MW) in proper time sequence and the time in hours. It shows the variation of load on the power station. When the load curve is plotted for 24 hours a day, then it is called daily load curve. If the one year is considered then, it is called annual load curve. The load curve of the power system is not same all the day. It differs from day to day and season to season. The load curve is mainly classified into two types, i.e., the summer load curve and the winter load curve.
  • 17.
  • 19. Information Obtained From Load Curve The following are the information obtained from load curves.  Load duration curve determines the load variation during different hours of the day.  It indicates the peak load which determines the maximum demand on the power station.  The area under the load curve gives the total energy generated in the period under consideration.  The area under the curve divided by the total numbers of hours gives the load.  The ratio of the area under the load curve of the total area of the rectangle in which it is contained gives the load factor.  The ideal load curve is flat, but practically it is far from flat. For a flat load curve, the load factor will be higher. Higher load factor means the more uniform load pattern with fewer variations in load.
  • 20. Load Duration Curve Definition: The load duration curve is defined as the curve between the load and time in which the ordinates representing the load, plotted in the order of decreasing magnitude, i.e., with the greatest load at the left, lesser loads towards the rights and the lowest loads at the time extreme right. The load duration curve is shown in the figure below. This curve represents the same data as that of the load curve. The load duration curve is constructed by selecting the maximum peak points and connecting them by a curve. The load duration curve plotting for 24 hours of a day is called the daily load duration curve. Similarly, the load duration curve plotted for a year is called the annual load curve.
  • 21.
  • 22. Procedure for Plotting the Load Duration Curve 1. From the data available from the load curve determines the maximum load and the duration for which it occurs. 2. Now take the next load and the total time during which this and the previous load occurs. 3. Plots the loads against the time during which it occurs. 4. The load duration curves can be drawn for any duration of time, for example, a day or a month or a year. The whole duration is taken as 100% Example of how to plot LDC from Load Curve given In notes
  • 23. Loads on Power System Residential load: Commercial Loads: Industrial Loads: Agricultural loads : Municipal Loads : Traction Loads :
  • 28. Municipal Loads : Municipal loads consist of street lights, electricity required for water supply pumps and drainage system. for water supply water is pumped to the overhead tank using electric pump, overhead water tank pumping is carried out during off-peak time. like during night time. its improve load factor of power system.
  • 29. Traction Loads : This types of loads mainly include trains, traction loads has wide variation. during morning hours it reaches peak value and during afternoon loads starts decreasing and again rises to peak value during evening time.
  • 30. COST OF ELECTRICAL ENERGY There are three kinds of expenditures involved in generating electricity.  fixed cost  Semi-fixed cost  Running or operating cost
  • 31. FIXED COST In every manufacturing unit there is some hidden expenditure which fixed. This is same for manufacturing one unit or thousand units of the items. In electric generating station like manufacturing unit, there are some hidden costs which independent of the quantity of electricity produced. These fixed expenditures are mainly due to an annual cost to run the organization, interest on capital cost and tax or rent of the land on which the organization established, salaries of high officials and interests of loans (if any) on the capital cost of the organization. Like these main costs, there are many others expenditures which do not change whether the rate of production of electrical energy units is less or more.
  • 32. SEMI-FIXED COST There is another type costing for any manufacturing or production or any similar type of industries. These costs are not strictly fixed and also not fully dependent on the number of items manufactured or produced. These costs depend on the size of the plant. These actually depend on the assumption of a maximum number of items which can be produced from the plant at a time during peak demand period. That means the forecasted production demand of the plant determines how big will be the manufacturing or production plant. Likewise, the size of an electrical generating plant depends on the maximum demand of the connected load of the system. If the maximum demand of the load is quite higher than the average demand of the load, then the power generating plant should be constructed and well equipped to fulfill that maximum demand of the system even the peak demand lasts for less than an hour. This type of costs is referred as semi-fixed cost. It is directly proportional to the maximum demand on the power station. The annual interest and depreciation on capital investment of building and equipment, taxes, salaries of management and clerical staff, expenditure for installation etc. come under semi-fixed costs.
  • 33. RUNNING OR OPERATING COST The total cost of per unit generation of electrical energy can be expressed in the following ways. First, we have to calculate the entire expenditure of the plant including the organization which is fixed throughout the year and accounted for a fixed cost. Say this is a. This is considered as fixed cost for entire electrical energy generated in the year. In the same way, we have to calculate the total semi-fixed cost of the plant throughout the year. The semi-fixed cost is proportional to maximum demand of the plant. So, we have to find the maximum demand of the year. So the proportionality constant b can easily be calculated. Therefore, the semi-fixed cost of the plant for the year is b(maximum demand kilowatt). Now, we will calculate entire running expenses of the plant for producing total kWh units of energy generated in the year. If c is the running cost per unit of generated electricity then 0 Total cost of the plant for producing entire electric throughout the year is = 𝑹𝒔(𝒂 + b kw+ c kw) a –fixed cost B- semi fixed cost C running cost. Sometimes it is assumed that entire capital cost and other costs except for the running expenses for producing electricity entirely depend on the maximum demand of the plant. In that case, it is assumed that there is no absolute fixed cost. The expression for the annual cost of energy then becomes= 𝑹𝑺(𝑨𝒌𝒘 + 𝑩𝒌𝒘) Where A is the cost per unit /maximum demand and B is the running cost of producing one unit of electrical cost
  • 34. TARIFF&DIFERENT TYPES OF TARIFF Electricity Tariffs. Definition: The amount of money frame by the supplier for the supply of electrical energy to various types of consumers in known as an electricity tariff. In other words, the tariff is the methods of charging a consumer for consuming electric power.
  • 35. TYPES OF TARIFF Flat Demand Rate tariff. Straight-line Meter rate tariff. Block meter Rate tariff. Two-part tariff. Power factor tariff. Seasonal rate tariff. Peak load tariff. Three-part tariff.
  • 36. The electricity tariffs depends on the following factors  Type of load  Time at which load is required.  The power factor of the load.  The amount of energy used. The total bill of the consumer has three parts, namely, fixed charge D, semi-fixed charge Ax and running charge By. 𝑪 = 𝑨𝒙 + 𝑩𝒚 + 𝑫 where, C – total charge for a period (say one month) x – maximum demand during the period (kW or kVA) y – Total energy consumed during te period (kW or kVA) A – cost per kW or kVa of maximum demand. B – cost per kWh of energy consumed. D – fixed charge during each billing period. This is known as three-part electricity tariff, and it is mainly applied to the big consumer.
  • 37. 1.Flat Demand /Simple Rate tariff The flat demand rate tariff is expressed by the equation 𝑪 = 𝑨𝒙. In this type of tariff, the bill of the power consumption depends only on the maximum demand of the load. The generation of the bill is independent of the normal energy consumption. This type of tariff is used on the street light, sign lighting, irrigation, etc., where the working hours of the equipment are unknown. The metering system is not used for calculating such type of tariffs.
  • 38. 2.Straight-line Meter rate tariff. This type of tariff is given by the equation 𝑪 = 𝑩𝒚. The generation of the bills depends on the energy consumption of the load. Thus, different types of bills are generated by the consumers. The charges for different types of consumption depends on the load and diversity factors of the load. For example, the tariff for small devices is less as compared to the power loads. Hence different meters are used for measuring the power consumption.
  • 39. 3.Block meter Rate tariff. In this type of tariff, the energy consumption is distinguished into blocks. The per unit tariff of the individual block is fixed. The price of the block is arranged in the decreasing order. The first block has the highest cost, and it goes on decreasing accordingly. The price and the energy consumption are divided into three blocks. The first few units of energy at a certain rate, the next at a slightly lower rate and the remaining unit at a very lower rate.
  • 40. 4.Two-part tariff. In such type of tariff, the total bill is divided into two parts. The first one is the fixed charge and the second is the running charge. The fixed charge is because of the maximum demand and the second charge depends on the energy consumption by the load. 𝐶 = 𝐴𝑥 + 𝐵𝑦 𝐶 = 𝐴 𝑘𝑤 + (𝑘𝑤ℎ) The factor A and B may be constant and vary according to some sliding.
  • 41. 5.Power factor tariff. The tariff, which depends on the power factor of the load is known as the power factor tariff. The power factor tariff is mainly classified into two types. a. kVA maximum demand tariff – This is also a two-part tariff. 𝑻𝒐𝒕𝒂𝒍 𝒄𝒉𝒂𝒓𝒈𝒆𝒔 = 𝑨 𝑲𝑽𝑨 + 𝑩(𝑲𝑾𝒉) The low power factor increases the KVA rating of the load. b. kWh and kVarh tariff – The bill is calculated by the sum of the kVarh and Kwh rating of the load 𝑻𝒐𝒕𝒂𝒍 𝐶ℎ𝒂𝒓𝒈𝒆𝒔 = 𝑨𝟏 𝑲𝑾𝒉 + 𝑩𝟏(𝑲𝑽𝑨𝒓𝒉) The kVarh is inversely proportional to the power factor of the load. c. Sliding Scale or Average power factor tariff – In Average power factor tariff, the particular value of the power factor is taken as reference. If the power factor at the consumer end is low, then the consumer has to pay the additional charges. Similarly, if the power factor of the load is above from the reference value, then the discount will be given to the consumer.
  • 42. 6.Seasonal rate tariff. Such type of tariff measures the high price in kWh used by the consumer in one complete year. It is also known as the on peak season tariff. If the low consumption occurs in the year, then it called the off-peak season tariffs. 7. Peak-load tariff Such type of tariff is similar to peak load tariffs. The only difference is that the seasonal tariff measures the peak hour of the year and the peak tariff calculates it for the day. If the power consumption is high, then it is known as the on-peak tariff, and for low power consumption, it is called off-peak load tariffs. The peak load and seasonal tariffs both are used for reducing the idle or standby capacity of the load. 8. Three-part tariff The three-part tariff is in the form of, 𝑪 = 𝑨𝒙 + 𝑩𝒚 + 𝑫 and it is applied to the big consumer.