SlideShare a Scribd company logo
Qualification of
Analytical Equipments
Prepared by: Dhawal Rajdev
M. Pharm (Q.A.)
2017-2019
Qualification of Analytical
Equipments
Gas chromatography
2
Introduction
 QUALIFICATION: Action of proving and documenting that
equipment or ancillary systems are properly installed, work
correctly, and actually lead to the expected results.
The entire qualification consists of four parts:
1. Design qualification(DQ).
2. Installation qualification(IQ).
3. Operational qualification(OQ).
4. Performance qualification(PQ).
3
 1.Design qualification(D.Q): It describe the user requirements and
defines the functional and operational specifications of the
instrument. DQ should ensure that instrument to be purchased have
the necessary functions and performance that will enable for
suitable intended application.
 2.Installation Qualification (I.Q):
The purpose of I.Q is to check the installation site/ environment,
confirms equipment specifications and verifies the condition of
installed equipment.
 3.Operational Qualification (O.Q):
O.Q includes procedures and documentation of O.Q of analytical
instrument.
When all procedures are executed and all items pass the
inspection, it is verified that the system operates to satisfy the
intended purpose.
4
 4.Performance Qualification (P.Q):
The objective is to ensure that the instrument is
performing within specified limits.
Hence documented verification that the equipment and
ancillary systems, as connected together, can perform
effectively and reproducibly based on the approved
process
method and specifications.
Qualification of Gas Chromatography
 Level I. Selection Of Instruments & Suppliers
 At level I of the qualification of a gc equipment(selection of
instruments and suppliers)
 It is recommended to select a manufacture of gc that can satisfy the
needs of the laboratory and works under ISO 9001 certification
 Level II of Equipment Qualification:
Installation and release for use
 It is recommended to check all requirements set during the selection
of the instrument, and
calibration should be performed before putting into service by an
accredited external service supplier, or Internally by appropriately
qualified personnel, using certified reference buffers according to an
approved procedure.
6
 Level III. Periodic and motivated instrument
Checks Examples of requirements for GC instruments with FID
7
instrument module
Parameter to be
checked
Typical tolerance limit
1. Inlet system
1.1 Injector leak test
1.2. Pressure/flow
accuracy and stability
1.3. Repeatability of
injection (overall test 1) -
In split mode
-In split less mode
1.4. Injector temperature
accuracy and stability
1.5. Carry-over (overall
test 3)
Pressure drop ≤ 15 kPa
within 5 minutes
Covered by overall test
1
RSD ≤ 3.0%
RSD ≤ 3.0%
Covered by overall test
2
≤ 0.2
instrument module Parameter to be
checked
Typical tolerance limit
2. Oven
2.1. Repeatability of
oven
temperature
characteristics
Covered by overall test
2
3. FID detector
3.1. Linearity (overall
test 3)
3.2. Constant detector
response
3.3. Noise
3.3. Drift
r 2 ≥ 0.999
Covered by overall
test 1 or 2
8
 Level III. Periodic and motivated instrument checks
 Practical examples of tests and their associated tolerance limits for several
parameters related to the performance of the different modules of a
GC are presented below.
 These examples can be considered by the OMCLs as possible
approaches to perform the Level III of the equipment qualification
process: “Periodic and motivated instrument checks”.
 Several tests are proposed to check various parameters at the
same time (overall tests).
 In order to run the tests in a more economical way, other suitable
solutions can be used, as for example, the “Grob Test” mixture,
available from different suppliers (e.g. Alltech, Sigma, Thames
Restek).
 This commercial solution should be appropriate to the column
material used.
It is recommended to run the overall tests by using always the
same test column, exclusively dedicated to qualification purposes,
to guarantee reproducible conditions 9
 1. Inlet system The following tests are proposed for the
periodic and motivated check of the GC Inlet System.
1.1. Injector leak test
Method:
If not otherwise specified by the instrument manufacturer,
the leak test is carried out according to the procedure laid
down in the instrument manual or by the built in automatic
leak check procedure of the instrument.
Otherwise use the test described below:
Disconnect the column from the injector and close the
injector outlet with a sealed cap.
Close the septum purge and the bypass.
Adjust the flow and pressure controller to the maximal
possible value of the pressure gauge.
10
Adjust the flow controller to zero.
Read the pressure after 1 minute and record the value.
Record the pressure after 5 minutes.
Limits:
Pressure drop ≤ 15 kPa within 5 minutes.
 1.2. Inlet pressure/flow accuracy and stability
A direct measurement of these parameters was not deemed
practical or necessary, but the optimal conditions of flow/pressure
can be verified by the overall test 1.
Limits: Refer to overall test 1
 1.3. Repeatability of injection
The verification of this parameter is covered by the overall
test 1.
This test is to be performed in both split and split less mode.
Limits: Refer to overall test 1.
 1.4. Injector temperature accuracy and stability
Due to the fact that the temperature cannot be reliably measured
without opening and modifying the system and due to the difficulties of
introducing a probe inside this module, the verification of this
parameter is considered to be covered by the overall test 2.
Limits: Refer to overall test 2.
 1.5. Injector carry over
After having injected the solutions for the linearity test of the FID
detector, in increasing order, inject the blank and measure the peaks
that correspond to the major peaks (= analytes) in the linearity
solutions.
The verification of this parameter is covered by the overall
test 3.
Limits: Refer to overall test 3
12
 2. OVEN
2.1. Repeatability of the oven temperature
characteristics
Due to the fact that the temperature cannot be reliably measured
without opening and modifying the system conditions and that even
when introducing a probe inside the oven, its location would not
reflect the real temperature conditions at all points, the verification
of this parameter is covered by the overall tests 2A and 2B.
Limits: Refer to overall test 2.
 3. FID DETECTOR
The following tests are proposed for the periodic and motivated
check of the GC FID detector.
3.1. FID detector linearity
Increasing amounts of analyte are injected and a linear response
should be obtained.
The verification of this parameter is covered by the overall test 3.
Limits: Refer to overall test 3. 13
3.2. Constant FID detector response
The proper and reproducible functioning of the FID can be
demonstrated by checking the peak areas obtained from a predefined
standard solution.
The verification of this parameter is covered by the overall test
1 or 2.
Limits: Refer to overall test 1 or 2.
3.3. Fid detector noise and drift
If the instrument has a built-in automatic system for the verification
of the noise and drift, follow the manufacturer’s instructions and
apply the defined acceptance criteria.
Otherwise, use the test described below:
Settings:
Column installed
Suitable flow, depending on column length/diameter
No injection
Oven temperature: 40°C
Detector on and heated at working temperature (270- 300°C)
 3.3. Fid detector noise and drift
If the instrument has a built-in automatic system for the
verification of the noise and drift, follow the manufacturer’s
instructions and apply the defined acceptance criteria.
Otherwise, use the test described below:
Settings:
Column installed
Suitable flow, depending on column length/diameter
No injection
Oven temperature: 40°C
Detector on and heated at working temperature (270- 300°C)15
 Method:
After stabilisation of the system, record the signal for 15
minutes.
Noise: evaluate 10 periods of 1 minute and calculate the mean
value.
Drift: Evaluate the slope of the baseline over the 15 minutes.
Limits:
The acceptance criteria for these parameters have to be
chosen in accordance with the instrument vendor’s instructions
and the intended use of the instrument.
If no instructions are given, the user has to pre-define these
acceptance criteria by taking into account the previous
experience and the intended use of the instrument.
No fixed values can be pre-defined in this guideline due to the
high variety of integration systems used and consequently the
acceptance criteria may be expressed in different units (voltage,
current, arbitrary units per time).
 OVERALL TEST 1
The overall test 1 covers the following parameters:
- Pressure/flow accuracy and stability in the inlet system:
Retention time repeatability
- Repeatability of injection: peak area precision
- In split mode
- In split less mode
The test may be combined with overall test 3.
 Split mode:
Test solution: 1-octanol in n-hexane 1% (v/v)
Settings:
Column: SPB-1 (30m x 0.32mm ID x 0.25µm film)
Carrier gas: He
Velocity: 25cm/sec
Split: 1:100
Injection: 1µl 17
Injector temperature: 220°C
Oven temperature: 100°C isotherm
Detector temperature: 300°C
Runtime: 8 min
Retention time of 1-octanol: about 5 min
 Split less mode:
Stock solution: 1-octanol in n-hexane 1% (v/v)
Test solution: Dilute 10 ml of the stock solution with nhexane
to 100 ml (corresponds to 1µl/ml of 1-octanol in nhexane)
Settings:
Column: SPB-1, 30m, 0.32mm ID, 0.25µm film
Carrier: He
Velocity: 30cm/sec
Split less injection: purge valve closed during 2 min
Injection: 0.2µl of the test solution
Injector Temperature: 220°C
Oven Temperature: Initial 60°C for 4 min, 15°C/min. up to
135°C, final time 1min
Detector temperature: 300°C
Runtime: 9.5 min
Retention time of 1-octanol: about 8 min
Method:
Carry out 6 consecutive injections of the test solution and
calculate the RSD of the different peak areas and retention
times.
Limits:
Retention time repeatability: the RSD of the retention times
should be ≤ 2.0%
Peak area precision (split and split less mode): the RSD of the
peak areas should be ≤ 3.0%
 OVERALL TEST 2
The overall test 2 covers the following parameters:
- Injector, oven and detector temperature accuracy and
stability: retention time repeatability
- Two alternative tests are proposed
1.Overall test 2A
Test solution:
0.035 ml 1-octanol
0.035 ml 2-octanone
0.035 ml 2,6-dimethylanilin
0.035 ml n-tridecane
0.035 ml n-tetradecane
35 mg n-eicosane
Dissolved in 50 ml Dichloromethane
Settings:
Column: SPB-1 (30m x 0.32mm ID x 0.25µm film)
Carrier gas: Helium
Velocity: 25 cm/s
Split: 1:100
Injection volume: 1 µl
Injector temperature: 220°C
Detector: FID
Detector temperature: 300°C
Gradient programme: 60°C (4 min), 5°C/min, 270°C (3 min)
Method:
Inject the solution twice and calculate the relative retention times in
relation to n-eicosane (RRT = 1)
The above table shows the approximately expected relative retention
times. 21
Method:
Inject the solution twice and calculate the relative retention
times in relation to n-eicosane (RRT = 1)
The above table shows the approximately expected relative
retention times.
Limits: The RSD of each RRT from two consecutive
injections
should be ≤ 1.0% 22
Analyte 1-octanol 2-octanone N-tridecane N-tetra
decan
RRT 0.30 0.22 0.52 0.60
 2.Overall test 2B
Test Solution: 1.0% (W/W) n-Nonane and Hexadecane in
Tetradecane.
Settings:
Column: Ultra-1 (25m x 0.32mm ID x 0.52µm film)
Injection volume: 1 µl
Solvent: Tetradecane
Oven temperature: 110°C
Gradient programme: 110°C, 20°C/min, 180°C (final time: 3.5
min)
Detector temperature: 250°C
Injector temperature: 200°C
Detector: FID
 Flow rates:
Carrier gas (Helium): 2 ± 0.2 ml/min
Hydrogen: 30 ± 1.0 ml/min
Air: 400 ± 20.0 ml/min
Makeup (Nitrogen): 28 ± 1.0 ml/min
Split ratio: 15
Split vent: 30 ± 3.0 ml/min
Septum purge: 3-5 ml/min
Method:
Allow the system to equilibrate
Injection sequence:
1) Blank (Tetradecane)
2) 6 replicates of the test solution.
24
 Calculate the mean of the retention times and peak areas and the
relative standard deviation of n-Nonane and n-Hexadecane
Limits:
Retention time repeatability: RSD of the peak retention times of the
6 replicates ≤ 2%
Retention time (Rt) accuracy: for this example, the retention time
ranges shown in the table below are proposed. Nevertheless, individual
ranges should be predefined by the laboratory depending on the
column used (e.g. Rt ± 0.2 min).
 OVERALL TEST 3
This test is a modified version of the overall test 1 to be used for
the verification of:
- Detector linearity: linearity of the areas recorded
- Injector carry-over: area recorded in the blank run
It is described for both split and split less mode and may be combined
with overall test 1.
Split mode:
Test solution: 1-octanol in n-hexane 1% (v/v)
Prepare further reference solutions by diluting the test solution as
described below.
Settings: see overall test 1
Injection sequence:
5.0 ml of the test solution diluted to 25.0 ml with n-hexane (2
µl/ml): 2 injections 10.0 ml of the test solution diluted to 25.0 ml with
nhexane (4 µl/ml): 2 injections
15.0 ml of the test solution diluted to 25.0 ml with n-hexane (6
µl/ml): 2 injections
20.0 ml of the test solution diluted to 25.0 ml with n-hexane (8
µl/ml): 2 injections
If combined with overall test 1 for repeatability: test solution (10
µl/ml): 6 injections n-hexane as blank (carry over) 26
Split less mode:
Stock solution: 1-octanol in n-hexane 1% (v/v)
Test solution: Dilute 10 ml of the stock solution with nhexane to 100 ml
(corresponds to 1µl/ml of 1-octanol in nhexane).
Prepare further reference solutions by diluting the test solution with n-
hexane.
Settings: see overall test 1
Injection sequence:
5.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.2 µl/ml): 2
injections
10.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.4 µl/ml): 2
injections
15.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.6
µl/ml): 2 injections
20.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.8 µl/ml): 2
injections
If combined with overall test 1 for repeatability: test solution (1 µl/ml): 6
injections n-hexane as blank (carry over)
Linearity: coefficient of correlation of the calibration line
obtained
with the reference solutions and the test solution: r 2 ≥ 0.999.
Carry-over: the percentage of the peak area corresponding to the
analyte in the blank solution should be ≤ 0.2% of the peak area of
this analyte in the chromatogram obtained with the solution with
the highest concentration within the sequence
28
 Level IV. In-use instrument checks Examples of requirements for
GC instruments with FID

29
Parameter to be checked Typical tolerance limit
1. System suitability check for the
method
According to Ph. Eur. or MAH
dossier or validated in-house
method
2. Peak area precision
RSD ≤ 3.0% unless otherwise
prescribed*
3. Retention time repeatability RSD ≤ 2.0%
4. Sensitivity (where relevant, e.g.
for related substances tests)
According to Ph. Eur. or MAH dossier
or validated in-house method
 Reference:
Ph.Eur.2.2.35 chromatography; gas chromatography
Guidance on equipment qualification of analytical instruments
Journal of Perkin Elmer life & analytical science
Qualification of Analytical
Equipments
High Performance Liquid
Chromatography
31
Introduction
 QUALIFICATION: Action of proving and documenting that
equipment or ancillary systems are properly installed, work
correctly, and actually lead to the expected results.
The entire qualification consists of four parts:
1. Design qualification(DQ).
2. Installation qualification(IQ).
3. Operational qualification(OQ).
4. Performance qualification(PQ).
32
 1.Design qualification(D.Q): It describe the user requirements and
defines the functional and operational specifications of the
instrument. DQ should ensure that instrument to be purchased have
the necessary functions and performance that will enable for
suitable intended application.
 2.Installation Qualification (I.Q):
The purpose of I.Q is to check the installation site/ environment,
confirms equipment specifications and verifies the condition of
installed equipment.
 3.Operational Qualification (O.Q):
O.Q includes procedures and documentation of O.Q of analytical
instrument.
When all procedures are executed and all items pass the
inspection, it is verified that the system operates to satisfy the
intended purpose.
33
 4.Performance Qualification (P.Q):
The objective is to ensure that the instrument is
performing within specified limits.
Hence documented verification that the equipment and
ancillary systems, as connected together, can perform
effectively and reproducibly based on the approved
process method and specifications.
Qualification of HPLC
 1. Design qualification:
35
Design element example
Maintenance •Vendor must deliver maintenance
procedure and recommended schedule
•Instrument must include early
maintenance feedback for timely
exchange of most important
maintenance parts. •Maintenance
procedure must be supplied on
multimedia CD ROM
Intended use Analysis of drug components and
impurities.
Design element Examples
User requirements specification for the
HPLC analysis
•Up to 100 samples/day •Automated over
night analysis.
•Limit of quantitation:0.1% •Automated
confirmation of peak identity and purity
with diode-array detection
•Automated compound quantization and
printing of report.
FUNCTIONAL SPECIFICATION:
•Pump
•Detector
•Auto sampler
•Column compartment
•Computer
•Binary or higher gradient
•UV/VIS Diode array,190-900nm •100
samples, 0.5µl to 5ml sample volume
•15 to 60ºc controlled.
•System control, data acquisition for
signals and spectra, peak integration and
quantitation
4 36
Design element Examples
Operational specification •Detector: base line noise:<5 x 10-5 AU
•Sampler: precision inj. Volume : <0.5%
RSD. Sample carry over:<0.5%
•Pump: precision of retain time: <0.5%
RSD.
User instruction •Operation manual on paper •Computer
based tutorial
Qualification The vendor must provide procedures and
services for IQ and OQ
37
 2.INSTALLATION QUALIFICATION:
Installation qualification establishes that the instrument is received as
design and specified.
•It establishes that instrument is properly installed in the selected
environment and that environment should be suitable for operation of
the instrument.
•Run of test samples verifies correct installation of all modules,
electrical and fluid connections
 BEFORE INSTALLATION ?
 Obtain manufacturers recommendations for installation site
requirements
 Check the site for the fulfillment of the manufacturers
recommendation (utilities such as electricity and environment
condition such as humidity and temperature)
 Allow sufficient shelf space for the equipment, SOPs, operating
manual and software.
38
 DURING INSTALLATION ?
 Compare equipment as received , with purchase order
(including software, accessories, spare parts).
 Check documentation for completeness (operating manuals,
maintenance instruction, standard operating procedure for
testing , safety and validation certificate)
 Check equipment for any damage.
 Install hardware( computer, equipment, fittings and tubings, for
fluid connections , column in HPLC , power cables , data flow
and instrument control table)
 Switch on the instrument and ensure that all modules power up
and perform an electronic self test.
 Identify and a make a list with a description of all hardware,
include drawings where necessary
 Run test sample and compare chromatogram print out with
reference chromatogram.
 Prepare an installation report.
 3.OPERATIONAL QUALIFICATION:
It is the process of demonstrating that an instrument will function
according to its operational specification in the selected environment .
It verifies that the HPLC system compiles with key function and
operational requirements as specified in the design qualification .
In operational specification the supplier must define exactly the
conditions that must be observed with varying conditions. Eg: different
ambient temperature.
Before performing all other test first perform leak test if, it is failed
then most of the remaining test will get failed.
40
 Test parameters and acceptance criteria :
41
Parameter Procedure User limit
Leak testing Flow test by volume or
weight/time
±5%
Baseline drift ASTM (American society
for testing material)
method E19.09, 20 min
<2 x 10-3 AU
Baseline noise ASTM method E19.09, 20
min x 1
<5 x 10—5 AU
Precision of injection
volume
6 x injection of caffeine
standard, RSD of peak
areas
0.3% RSD
Precision of flow rate 6 x injection of caffeine
standard, RSD of
retention times
0.5% RSD
PARAMETER PROCEDURE USER LIMIT
Detector linearity Inject 5 standards >1.5 AU, 5% RSD
Wavelength accuracy Holmium oxide filter ±1 nm
Temperature accuracy Comparison with external
measuring device
± 1º c
Temperature precision Monitoring temperature
over 20 mins ±0.25 ºc
Auto sampler carry over Injection of large sample
after large concentration
< 0.5%
Mobile phase composition
accuracy
Step gradient from 4 to 7%
B, Step heights relative to
100% with acetone tracer
±1%
42
 Baseline noise and drift:
•Drift and baseline noise are important factors for UV detectors.
Increased baseline noise considerably reduces the sensitivity, as it is not
possible to distinguish between low-level signals and noise. With
increased drift, it is more difficult to integrate the signals correctly
because the less stable the baseline is, the more inaccurate is
integration.
•The baseline noise of the detector mainly depends on the lamp. There
is a considerable increase in noise if an old lamp with poor light intensity
is used. This is also true when the flow cells is dirty. In addition make
sure that the flow cells free from gas bubbles.
•To measure the drift of a UV detector, also make sure that all measuring
conditions are constant. In addition, it is very important that the lamp
has been burning for several hours in the detector environment, avoid
direct sunlight.
•The lamp intensity decreases while the lamp is burning. Besides, the
lamp ages when it is turned on and off very often.
43
 Evaluating baseline noise and drift:
•TO check noise, drift water is pumped through the cell at a flow
rate of 1ml/min. The UV signal is recorded at 254nm.
•To calculate noise the measuring signal is split into 20 intervals for
1min each. For each interval chromeleon calculates a regression
based on measured values, using the method of least square. The
limit should be between <2 x 103 AU.
•To calculate the drift, chromeleon calculates a regression line from
all data points with in a range of 1-21mins based on the method of
least square. The slope of the regression line is the calculated drift.
The limit should be between <5 x 10—5 AU.
44
 Precision of injection volume:
•Precision of injection volume is an important parameter for
accuracy of quantitation.
 Evaluating precision of injection volume:
•Inject 6 standard caffeine solution and calculate height, area,
average height, average area, %RSD of height and %RSD of area
which gives precision of volume and the limit should be in
between 0.3% RSD.
 Detector linearity:
•Linearity of a detector is a critical parameter to establish for
reliable and accurate quantitative results.
 Evaluating detector linearity:
•A series of 5 traceable standards (caffeine solution of
concentration about 0.00035 to 0.35mg/ml) are injected and
evaluated. The detector linearity is calculated by determining the
peak area vs concentration. %RSD can also be calculated for
checking the detector linearity. The limit should be in between >1.5
AU, 5% RSD.
 Wavelength accuracy:
•It is an important parameter for accuracy of quantitative and
qualitative analysis.
 Evaluating wavelength accuracy:
•Traceable caffeine standard is used to determine the wavelength
accuracy. Caffeine is trapped in the flow cell and a programmable
timetable is used to determine the wavelength maxima (205nm) and
minima (273nm). The wavelength accuracy is determined as the
absolute difference between the measured and certified wavelength
values
46
 Temperature accuracy: Temperature fluctuations of the solvent
and column can result in considerable retention time
fluctuations. Therefore, accuracy of the temperature is
important.
 Evaluating temperature accuracy: 4 measuring points are used
to check the temperature accuracy of the column compartment.
The check is performed with column oven sequence. The
achieved temperature is measured with external calibrated
thermometer.
The achieved temperatures are compared to the set values. The
difference indicates the temperature accuracy and the limit
should be in between ± 1º c
 Temperature precision: Monitor temperature for 20minutes and
limit should be in between ±0.25 ºc

 Gradient mobile phase composition accuracy: It is important for
accurate quantitative analysis.
 Evaluating gradient mobile phase composition accuracy: An
Acetone tracer is used to determine gradient mobile phase accuracy,
stability and linearity. Make 6 compositions of water+acetone in
concentration of 0%,20%,40%,60%,80% and 100% (20% increment).
Linear ramp down from 100% to 0% is performed where the
composition linearity is determined between ranges of 95,75 and
25%. All compositions accuracies are calculated as the absolute
difference between the mean composition at each set point and the
theoretical composition.
48
 4.Performance qualification:
 It is the process of demonstrating that an instrument consistently
performs according to a specification appropriate for its routine
use.
 Important here is the word consistently. The test frequency is
much higher than for OQ. Another difference is that PQ should
always be performed under conditions that are similar to routine
sample analysis. For a chromatogram this means using the same
column, the same analysis conditions and the same or similar test
compounds.
 PQ should be performed on a daily basis or whenever the
instrument is used.
 The test frequency of only depends on the stability of the
equipment but on everything in the system that may contribute to
analysis the result For a liquid chromatograph, this may be the
chromatographic column or a detectors lamp
49
 The test criteria and the frequency should be determined during
the development and the validation of the analytical method. In
practice PQ mean system stability testing , where critical key
system performance characteristic are measured and compared
with documented , preset limit.
 For example, a well characterized standard can be injected 5 or
6 times and the standard deviation of amounts are then
compared with predefined value
 If the limits of detection and quantifications are critical, the
lamps intensity profile or the base line should be tested they
should use the same column and chemicals for the real sample.
Test should include:
•Precision of the amounts
•Precision of retention times
•Resolution between two peaks
•Peak width at half height
•Peak tailing
•Baseline noise
•Wavelength accuracy of the uv/vis wavelength detector,
preferably using built-in holmium – oxide filters
 REFERENCES:
•Ph.Eur.2.2.35chromatography; High performance liquid chromatography
•Guidance on equipment qualification of analytical instruments
•Journal of Perkin Elmer life & analytical science
51
Qualification of Analytical
Equipments
Infra Rad
Spectrophotometer
52
Introduction
 QUALIFICATION: Action of proving and documenting that
equipment or ancillary systems are properly installed, work
correctly, and actually lead to the expected results.
The entire qualification consists of four parts:
1. Design qualification(DQ).
2. Installation qualification(IQ).
3. Operational qualification(OQ).
4. Performance qualification(PQ).
53
 1.Design qualification(D.Q): It describe the user requirements and
defines the functional and operational specifications of the
instrument. DQ should ensure that instrument to be purchased have
the necessary functions and performance that will enable for
suitable intended application.
 2.Installation Qualification (I.Q):
The purpose of I.Q is to check the installation site/ environment,
confirms equipment specifications and verifies the condition of
installed equipment.
 3.Operational Qualification (O.Q):
O.Q includes procedures and documentation of O.Q of analytical
instrument.
When all procedures are executed and all items pass the
inspection, it is verified that the system operates to satisfy the
intended purpose.
54
 4.Performance Qualification (P.Q):
The objective is to ensure that the instrument is
performing within specified limits.
Hence documented verification that the equipment and
ancillary systems, as connected together, can perform
effectively and reproducibly based on the approved
process
method and specifications.
55
QUALIFICATION OF IR
SPECTROPHOTOMETER
 INTRODUCTION
The present document explains about “Qualification of
Equipment(IR Spectrophotometer)”,
It should be used in combination with it when planning,
performing and documenting the IR spectrophotometer qualification
process.
The document contains the Introduction and general forms for
Level I and II of qualification, which are common to all type of
instruments.
For FTIR spectrometers, an example has been added to give
instrument-specific proposals that may be used in combination with
the general requirements presented in the core document
“Qualification of Equipment”, when drawing up a Level I checklist.
56
The present annex contains instrument-related recommendations
on parameters to be checked at Level III and IV of qualification and
the corresponding typical acceptance limits, as well as practical
examples on the methodology that can be used to carry out these
checks.
 Level I. Selection Of Instruments & Suppliers
Example of check-list (Non-Exhaustive)
Manufacturer:____________
Provider/ Distributor:___________
Name Of Instrument and Type: __________
57

58
Attribute
(This list may be
adapted if
necessary)
Specifications
Benefits
(Instrument/
supplier)
Assessment
(Pass/Fail)
SPECTROPHOTO
METER
Detector range
The optical bench shall include a
DTGS detector with a frequency
range of 7400 to 350 cm-1
It shall include a
compressed
air interferometer
Spectral resolution
The instrument shall
come
with an air-cooled
standard
infrared source.
Attribute
(This list may be
adapted if
necessary)
Specifications
Benefits
(Instrument/
supplier)
Assessment
(Pass/Fail)
Wave number accuracy
The instrument shall have a
spectral resolution not
exceeding 1.0 cm-1
The interferometer shall have at least
four basic velocity levels: software
shall permit the selection of a greater
number of velocities between the basic
levels.
Wave number
accuracy shall be
better than +- 0.01
cm-1
The mirror’s greatest velocity
shall allow a speed of at least five
sweeps per second
The laser and infrared beams must be
coaxial to enable rapid, easy alignment
of the system, depending on the
samples or accessories
59
ughjhjkjk
Attribute
(This list may be
adapted if
necessary)
Specifications
Benefits
(Instrument/
supplier)
Assessment
(Pass/Fail)
The optical bench shall have
main experimentation module
with a device to allow purging
with nitrogen
At purchase, the main
experimentation module shall be
designed so it can receive 13 and
5 mm potassium bromide pellets
60
Notes: -
This check-list, containing examples of technical attributes that can
be taken into account in the selection of an instrument and supplier,
can be used in combination with the general check-list presented in
Level I in the core document “Qualification of Equipment”.
Level II of Equipment Qualification:
Installation and Release for use
It is recommended to check all requirements set
during the selection of the instrument, and
calibration should be performed before putting into
service by an accredited external service supplier,
or
Internally by appropriately qualified personnel,
using certified reference buffers according to an
approved procedure.
61
 Level III. Periodic & Motivated Instrument
Checks
Examples of requirements for IR spectrophotometers
Parameters to be checked
1. Wave-number scale
2. Detector energy ratio
3. Signal/Noise ratio
4. Resolution
5. Zero test
6. Contamination check (only for ATR instruments)
7. Throughput check (only for ATR instruments)
62
 1.WAVE-NUMBER SCALE
Method and Limits:
The wave-number scale may be verified by recording the spectrum
of a polystyrene film, which has transmission minima (absorption
maxima) at the wave numbers (in cm-1 ) shown in the table below:
63
TRANSMISSION MINIMA
(cm -1)
ACCEPTABLE TOLERANCE (cm -1)
monochromatic
instruments
FTI±R instruments
3060.0 ±1.5 ±1.0
2849.5 ±2.0 ±1.0
1942.9 ±1.0 ±1.0
1601.2 ±1.0 ±1.0
1583.0 ±1.0 ±1.0
1154.5 ±1.0 ±1.0
1028.3 ±1.0 ±1.0
 2. DETECTOR ENERGY RATIO:
Method:
Record the minimum energy ratio value for at least one of the
following measurement points and compare it to the vendor’s
specifications: -
◦ Energy at 3990 cm-1 / energy at 2000 cm-1
◦ Energy at 4000 cm-1 / energy at 2000 cm-1
◦ Energy at 3400 cm-1 / energy at 1300 cm-1
◦ Energy at 2000 cm-1 / energy at 1000 cm-1
Limits:
Energy ratio test specifications vary for each spectrometer
configuration.
The optical bench shall include a DTGS detector with a frequency
range of 7400 to 350 cm-1
64
 3. SIGNAL/NOISE RATIO :
Method:
Record the maximum noise level for each of the following
regions:
Peak-to-peak noise between:
◦ 4050 cm-1 and 3950 cm-1
◦ 2050 cm-1 and 1950 cm-1
◦ 1050 cm-1 and 950 cm-1
◦ 550 cm-1 and 450 cm-1
(systems with DTGS detector only) RMS (root mean square) noise
between:
◦ 4050 cm-1 and 3950 cm-1
◦ 2050 cm-1 and 1950 cm-1
◦ 1050 cm-1 and 950 cm-1
◦ 550 cm-1 and 450 cm-1
(systems with DTGS detector only)
Limits (% T):
Noise level test specifications vary for each spectrometer
configuration.
65
 4. RESOLUTION :
Materials:
Certified polystyrene film of approximately 35 µm in thickness.
Method:
- For instruments having a monochromator, record the spectrum of the
polystyrene film.
- For Fourier-transform instruments, use suitable instrument resolution
with the appropriate apodisation prescribed by the manufacturer. The
resolution is checked by suitable means, for example by recording the
spectrum of a polystyrene film approximately 35 µm in thickness.
Limits:
-Difference between the absorbance's at the absorption minimum at 2870
cm-1 and the absorption maximum at
2849.5 cm-1 > 0.33.
- Difference between the absorbance's at the absorption minimum at 1589
cm-1 and the absorption maximum at
1583 cm-1 > 0.08.
66
 5. ZERO TEST
Method:
When using a polystyrene film of approximately 35 µm in thickness
as standard at the wavelength of 2925 cm-1 and 700 cm-1 , almost
complete absorption of the irradiated
energy can be observed.
With this test, the remaining transmission is measured. As the
maximum absorption can be observed at 700 cm-1 negative values
may be observed.
The objective of the test is to evaluate if, despite the fact that
there is almost complete absorption, energy is still detectable.
Non-valid results are an indication of a non-linear behaviour of the
detector and the electronic system.
 6. CONTAMINATION TEST
(Only for Attenuated Total Reflection (ATR) instruments)
Note: If an automated system is available, this test can be run more
frequently or it can be transferred to Level IV, to be run before each
analysis. 67
This test checks the presence of peaks that signal a contamination
problem.
Use the automated function of the instrument (if available)to
perform this test. If not available, record a background spectrum.
Limits:
Wave No.(cm-1) Upper limit(A)
3100-2800 0.1
1800-1600 0.1
1400-1100 0.2
68
 7. THROUGHPUT CHECK :
(Only for Attenuated Total Reflection (ATR) instruments)
Note: If an automated system is available, this test can be run more
frequently or it can be transferred to Level IV, to be run before each
analysis.
Method:
This test checks for an unexpected reduction of the transmittance.
An instrument specific automated test can be used.
A background spectrum is recorded and the transmittance is
measured at 3 wave numbers e.g. 4000, 2600 and 1000 cm-1 .
Limits:
The lower limit of the transmittance for the 3 wave numbers must
be 80 %
 REFERENCES:
Ph Eur. 2.2.24, Absorption spectrophotometer, Infrared.
Guidance on equipment qualification of analytical instruments.
Journal of perkinelmer life and analytical sciences.
69
Qualification of Analytical
Equipment
Liquid Chromatography
with Mass Spectrometer
(LC-MS)
Introduction
 QUALIFICATION: Action of proving and documenting that
equipment or ancillary systems are properly installed, work
correctly, and actually lead to the expected results.
The entire qualification consists of four parts:
1. Design qualification(DQ).
2. Installation qualification(IQ).
3. Operational qualification(OQ).
4. Performance qualification(PQ).
71
 1.Design qualification(D.Q): It describe the user requirements and
defines the functional and operational specifications of the
instrument. DQ should ensure that instrument to be purchased have
the necessary functions and performance that will enable for
suitable intended application.
 2.Installation Qualification (I.Q):
The purpose of I.Q is to check the installation site/ environment,
confirms equipment specifications and verifies the condition of
installed equipment.
 3.Operational Qualification (O.Q):
O.Q includes procedures and documentation of O.Q of analytical
instrument.
When all procedures are executed and all items pass the
inspection, it is verified that the system operates to satisfy the
intended purpose.
72
 4.Performance Qualification (P.Q):
The objective is to ensure that the instrument is
performing within specified limits.
Hence documented verification that the equipment and
ancillary systems, as connected together, can perform
effectively and reproducibly based on the approved
process
method and specifications.
73
Qualification of Mass
Spectroscopy
 The context of validation for mass spectrometry (MS)-based
methods is critically analysed. The focus is on the fitness for
purpose depending on the task of the method.
 Information is given on commonly accepted procedures for the
implementation and acceptance of analytical methods as
'confirmatory methods' according to EU criteria, and strategies
for measurement.
 Beneficial aspects of the qualification process to ensure the
suitability of the MS analytical system are also evaluated and
discussed.
 LEVEL I: Design Qualification:
 design qualification is is the documented collection of activities
that define the functional and operational specification of the
instrument and criteria for selection of vendor, based on
intended performance of the instrument.
 The user should ensure that commercial off the shelf(COTS)
instruments are suitable for their intended to application and
that the manufacturer should adopt the quality systemthat
provide for reliable equipment.
 All hardware and software laboratory products including
operating system and software used to deliver qualification
service are design, manufacturing and tested according to
company's life cycle development procedure.
 Level II: Operational Qualification:
 Temperature accuracy and stability of column heater/cooler
 Holmium oxide wavelength scan (if applicable)
 Detector lamp intensity and wavelength accuracy
 Detector noise and drift
 Pump flow rate accuracy and repeatability
 High and low pressure shutdown accuracy
 Injector precision
 Detector linearity and sample- to-sample carryover
 Injection volume linearity
 Gradient composition accuracy
 Linear gradient tested using IPA and 0.5% Acetone/IPA
 Five step gradient tested using IPA and 0.5% Acetone/IPA
 Level III. Periodic and motivated instrument checks
requirements for GC-EI-MS (examples)
 *) PFTBA (FC-43): Perfluoro-tributyl-amine (CAS NO.: 311-89-7)
**) In case of quantification purposes, these parameters have to be checked
Parameter to be checked Typical tolerance limits
Mass accuracy
PFTBA (FC-43)*)
or internal calibration gas
m/z = 69 ± 0.5
m/z = 219 ± 0.5
m/z = 502 ± 0.5
or defined masses of internal
calibration gas ± 0.5
Linearity**) r² ≥ 0.995
System/instrument precision**) ≤ 10.0%
 Level III contains practical examples of tests and their
associated tolerance limits for several parameters related to
the performance of GC-EI-MS.
These examples can be considered by the OMCLs (Official
Medicine Control Laboratory) as possible approaches to perform
the Level III of the equipment qualification process: “Periodic
and motivated instrument checks”.
GENERAL CONSIDERATIONS
- GC-MS is mainly used for the identification of unknown
substances or quantification of low concentrated substances
where high specificity is needed.
 MASS ACCURACY
Materials:
PFTBA (FC-43) or internal calibration gas
Method:
Internal instrument check or spectrum of PFTBA (FC-43) in full scan
mode
Limits:
m/z = 69 ± 0.5
m/z = 219 ± 0.5
m/z = 502 ± 0.5
 Note: the tolerance limits for mass accuracy are only valid for
quadrupole and ion trap mass spectrometers. Instruments like
Time-of-Flight (TOF) or hybrid instruments like quadrupole Time-
of-Flight (QTOF) have a much better mass accuracy and
adequate requirements should be applied by the laboratory.
 LINEARITY
Materials:
Stock solutions: 1-Octanol in dichloromethane 0.2, 0.4, 0.6,
0.8, 1.0 µL/mL
Method:
2 injections of each level (injection volume: 1.0 µL)
Limits:
r² ≥ 0.995
 SYSTEM/INSTRUMENT PRECISION
Materials:
Stock solution: 1-Octanol in dichloromethane 1.0 µL/mL
Method:
6 injections (injection volume: 1.0 µL)
Limits (minimum requirement):
RSD ≤ 10.0% (without internal standard)
 Level IV. In-use instrument checks Requirements for GC-EI-MS
Parameter to be checked Typical tolerance limits
As defined by the specific analysis
method or according to the Ph. Eur.
or
the MAH dossier
Identified by library
or with reference standard
 Level IV contains practical examples of tests and their associated
tolerance limits for several parameters related to the performance of GC-
EI-MS.
These examples can be considered by the OMCLs as possible
approaches to perform the Level IV of the equipment qualification
process: “In-use instrument checks”.
 SYSTEM/INSTRUMENT PRECISION **)
Materials: Any of the above-mentioned reference standard solutions used
for the identification
Method:
6 injections (injection volume: 1.0 µL)
Limits (minimum requirement):
RSD ≤ 10.0%
**) in case of use for quantification
Other tests according to the system suitability of the analysis method in use
Reference:
 https://shop.perkinelmer.com/Content/technicalinfo/tch_glpformatof
hplcandlcmssystems.pdf
 OMCL Network of the Council of Europe QUALITY MANAGEMENT
DOCUMENT PA/PH/OMCL (10) 86 2R
QUALIFICATION OF EQUIPMENT ANNEX 7: QUALIFICATION OF MASS
SPECTROMETERS
 Equipment Qualification Plan, Aligent Enterprice Edition Compliance
Services.

More Related Content

What's hot

Cleaning validation
Cleaning validationCleaning validation
Cleaning validation
RavichandraNadagouda
 
Water system validation
Water system validationWater system validation
Water system validation
Malla Reddy College of Pharmacy
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
PRANJAY PATIL
 
Qualification of instrumets
Qualification of instrumetsQualification of instrumets
Qualification of instrumets
ChowdaryPavani
 
Qualification of high performance liquid chromatography
Qualification of high performance liquid chromatographyQualification of high performance liquid chromatography
Qualification of high performance liquid chromatography
srikrupa institute of pharmaceutical analysis
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
ArpitSuralkar
 
Analytical method validation as per ich and usp
Analytical method validation as per ich and usp Analytical method validation as per ich and usp
Analytical method validation as per ich and usp
shreyas B R
 
Qualification of Weights and Measures
Qualification of Weights and MeasuresQualification of Weights and Measures
Qualification of manufacturing equipment.
Qualification of manufacturing equipment.Qualification of manufacturing equipment.
Qualification of manufacturing equipment.
KhushbooKunkulol
 
QUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTSQUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTS
ANKUSH JADHAV
 
Qualification of gc equipment
Qualification of gc equipmentQualification of gc equipment
Qualification of gc equipment
srikrupa institute of pharmaceutical analysis
 
Analytical methods validation as per ich & usp
Analytical methods validation as per ich & uspAnalytical methods validation as per ich & usp
Analytical methods validation as per ich & usp
GANESH NIGADE
 
Quality audit plan
Quality audit planQuality audit plan
Quality audit plan
Pravin Jadhao
 
Pharmaceutical validation of water system
Pharmaceutical validation of  water system Pharmaceutical validation of  water system
Pharmaceutical validation of water system
Raghavendra institute of pharmaceutical education and research .
 
Qualification of analytical instruments
Qualification of analytical instrumentsQualification of analytical instruments
Qualification of analytical instruments
Faris ameen
 
qualification of lcms
qualification of lcmsqualification of lcms
qualification of lcms
Ankush Sule
 
Qualification of analytical instruments
Qualification of analytical instrumentsQualification of analytical instruments
Qualification of analytical instruments
Sanathoiba Singha
 
Qualification of Dissolution Test Apparatus and Validation of Utility System
Qualification of Dissolution Test Apparatus and Validation of Utility SystemQualification of Dissolution Test Apparatus and Validation of Utility System
Qualification of Dissolution Test Apparatus and Validation of Utility System
Akshay Trivedi , Maliba Pharmacy College
 
FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST FACTORY ACCEPTANCE TEST
IPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptxIPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptx
Dhruvi50
 

What's hot (20)

Cleaning validation
Cleaning validationCleaning validation
Cleaning validation
 
Water system validation
Water system validationWater system validation
Water system validation
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Qualification of instrumets
Qualification of instrumetsQualification of instrumets
Qualification of instrumets
 
Qualification of high performance liquid chromatography
Qualification of high performance liquid chromatographyQualification of high performance liquid chromatography
Qualification of high performance liquid chromatography
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Analytical method validation as per ich and usp
Analytical method validation as per ich and usp Analytical method validation as per ich and usp
Analytical method validation as per ich and usp
 
Qualification of Weights and Measures
Qualification of Weights and MeasuresQualification of Weights and Measures
Qualification of Weights and Measures
 
Qualification of manufacturing equipment.
Qualification of manufacturing equipment.Qualification of manufacturing equipment.
Qualification of manufacturing equipment.
 
QUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTSQUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTS
 
Qualification of gc equipment
Qualification of gc equipmentQualification of gc equipment
Qualification of gc equipment
 
Analytical methods validation as per ich & usp
Analytical methods validation as per ich & uspAnalytical methods validation as per ich & usp
Analytical methods validation as per ich & usp
 
Quality audit plan
Quality audit planQuality audit plan
Quality audit plan
 
Pharmaceutical validation of water system
Pharmaceutical validation of  water system Pharmaceutical validation of  water system
Pharmaceutical validation of water system
 
Qualification of analytical instruments
Qualification of analytical instrumentsQualification of analytical instruments
Qualification of analytical instruments
 
qualification of lcms
qualification of lcmsqualification of lcms
qualification of lcms
 
Qualification of analytical instruments
Qualification of analytical instrumentsQualification of analytical instruments
Qualification of analytical instruments
 
Qualification of Dissolution Test Apparatus and Validation of Utility System
Qualification of Dissolution Test Apparatus and Validation of Utility SystemQualification of Dissolution Test Apparatus and Validation of Utility System
Qualification of Dissolution Test Apparatus and Validation of Utility System
 
FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST
 
IPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptxIPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptx
 

Similar to Qualification of Analytical Equipments

G.c power point by royal debnath
G.c power point by royal debnathG.c power point by royal debnath
G.c power point by royal debnath
husnatazeen
 
Qualification of gc equipment by manoj kumar
Qualification of gc equipment by manoj kumarQualification of gc equipment by manoj kumar
Qualification of gc equipment by manoj kumar
himaja donthula
 
Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)
magareasmi
 
Graphite 52 m mcerts certificate
Graphite 52 m mcerts certificateGraphite 52 m mcerts certificate
Graphite 52 m mcerts certificatea1-cbiss
 
Qualification of High Performance Liquid Chromatography(HPLC)
Qualification of High Performance Liquid Chromatography(HPLC)Qualification of High Performance Liquid Chromatography(HPLC)
Qualification of High Performance Liquid Chromatography(HPLC)
PRAVADA
 
Performance qualification of High performance liquid chromatography
Performance qualification of High performance liquid chromatography Performance qualification of High performance liquid chromatography
Performance qualification of High performance liquid chromatography
Atchaya Thalapathy
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Malla Reddy College of Pharmacy
 
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptxQUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
TaushifulHoque
 
Validation of gc instrument
Validation of gc instrumentValidation of gc instrument
Validation of gc instrument
Santhosh Kalakar dj
 
Qualification of GC & FTIR
Qualification of GC & FTIRQualification of GC & FTIR
Qualification of GC & FTIR
MehulJain143
 
Epa method 5(m-05)
Epa method 5(m-05)Epa method 5(m-05)
Epa method 5(m-05)HanSehyun
 
One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...
Palash Das
 
Sterile process validation
Sterile process validationSterile process validation
Sterile process validation
Sagar Savale
 
Turbine protection test u4
Turbine protection test u4Turbine protection test u4
Turbine protection test u4
Soumya Ranjan Behera
 
Understanding AMS2750E (intermediate) v2
Understanding AMS2750E (intermediate) v2Understanding AMS2750E (intermediate) v2
Understanding AMS2750E (intermediate) v2
Peter Sherwin
 
G 175 – 03 _RZE3NQ__.pdf
G 175 – 03  _RZE3NQ__.pdfG 175 – 03  _RZE3NQ__.pdf
G 175 – 03 _RZE3NQ__.pdf
Leo letter
 
292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure
shakeel Ahmad
 
Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .
Aditi Roy
 

Similar to Qualification of Analytical Equipments (20)

G.c power point by royal debnath
G.c power point by royal debnathG.c power point by royal debnath
G.c power point by royal debnath
 
Qualification of gc equipment by manoj kumar
Qualification of gc equipment by manoj kumarQualification of gc equipment by manoj kumar
Qualification of gc equipment by manoj kumar
 
Autoclave validation maliba
Autoclave validation malibaAutoclave validation maliba
Autoclave validation maliba
 
Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)
 
Graphite 52 m mcerts certificate
Graphite 52 m mcerts certificateGraphite 52 m mcerts certificate
Graphite 52 m mcerts certificate
 
Qualification of High Performance Liquid Chromatography(HPLC)
Qualification of High Performance Liquid Chromatography(HPLC)Qualification of High Performance Liquid Chromatography(HPLC)
Qualification of High Performance Liquid Chromatography(HPLC)
 
Performance qualification of High performance liquid chromatography
Performance qualification of High performance liquid chromatography Performance qualification of High performance liquid chromatography
Performance qualification of High performance liquid chromatography
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...
 
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptxQUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
QUALITY ASSURANCE TESTS OF REMOTE AFTERLOADING BRACHYTHERAPY UNIT 1.pptx
 
Validation of gc instrument
Validation of gc instrumentValidation of gc instrument
Validation of gc instrument
 
NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0
 
Qualification of GC & FTIR
Qualification of GC & FTIRQualification of GC & FTIR
Qualification of GC & FTIR
 
Epa method 5(m-05)
Epa method 5(m-05)Epa method 5(m-05)
Epa method 5(m-05)
 
One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...
 
Sterile process validation
Sterile process validationSterile process validation
Sterile process validation
 
Turbine protection test u4
Turbine protection test u4Turbine protection test u4
Turbine protection test u4
 
Understanding AMS2750E (intermediate) v2
Understanding AMS2750E (intermediate) v2Understanding AMS2750E (intermediate) v2
Understanding AMS2750E (intermediate) v2
 
G 175 – 03 _RZE3NQ__.pdf
G 175 – 03  _RZE3NQ__.pdfG 175 – 03  _RZE3NQ__.pdf
G 175 – 03 _RZE3NQ__.pdf
 
292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure
 
Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .
 

Recently uploaded

Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 

Recently uploaded (20)

Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 

Qualification of Analytical Equipments

  • 1. Qualification of Analytical Equipments Prepared by: Dhawal Rajdev M. Pharm (Q.A.) 2017-2019
  • 3. Introduction  QUALIFICATION: Action of proving and documenting that equipment or ancillary systems are properly installed, work correctly, and actually lead to the expected results. The entire qualification consists of four parts: 1. Design qualification(DQ). 2. Installation qualification(IQ). 3. Operational qualification(OQ). 4. Performance qualification(PQ). 3
  • 4.  1.Design qualification(D.Q): It describe the user requirements and defines the functional and operational specifications of the instrument. DQ should ensure that instrument to be purchased have the necessary functions and performance that will enable for suitable intended application.  2.Installation Qualification (I.Q): The purpose of I.Q is to check the installation site/ environment, confirms equipment specifications and verifies the condition of installed equipment.  3.Operational Qualification (O.Q): O.Q includes procedures and documentation of O.Q of analytical instrument. When all procedures are executed and all items pass the inspection, it is verified that the system operates to satisfy the intended purpose. 4
  • 5.  4.Performance Qualification (P.Q): The objective is to ensure that the instrument is performing within specified limits. Hence documented verification that the equipment and ancillary systems, as connected together, can perform effectively and reproducibly based on the approved process method and specifications.
  • 6. Qualification of Gas Chromatography  Level I. Selection Of Instruments & Suppliers  At level I of the qualification of a gc equipment(selection of instruments and suppliers)  It is recommended to select a manufacture of gc that can satisfy the needs of the laboratory and works under ISO 9001 certification  Level II of Equipment Qualification: Installation and release for use  It is recommended to check all requirements set during the selection of the instrument, and calibration should be performed before putting into service by an accredited external service supplier, or Internally by appropriately qualified personnel, using certified reference buffers according to an approved procedure. 6
  • 7.  Level III. Periodic and motivated instrument Checks Examples of requirements for GC instruments with FID 7 instrument module Parameter to be checked Typical tolerance limit 1. Inlet system 1.1 Injector leak test 1.2. Pressure/flow accuracy and stability 1.3. Repeatability of injection (overall test 1) - In split mode -In split less mode 1.4. Injector temperature accuracy and stability 1.5. Carry-over (overall test 3) Pressure drop ≤ 15 kPa within 5 minutes Covered by overall test 1 RSD ≤ 3.0% RSD ≤ 3.0% Covered by overall test 2 ≤ 0.2
  • 8. instrument module Parameter to be checked Typical tolerance limit 2. Oven 2.1. Repeatability of oven temperature characteristics Covered by overall test 2 3. FID detector 3.1. Linearity (overall test 3) 3.2. Constant detector response 3.3. Noise 3.3. Drift r 2 ≥ 0.999 Covered by overall test 1 or 2 8
  • 9.  Level III. Periodic and motivated instrument checks  Practical examples of tests and their associated tolerance limits for several parameters related to the performance of the different modules of a GC are presented below.  These examples can be considered by the OMCLs as possible approaches to perform the Level III of the equipment qualification process: “Periodic and motivated instrument checks”.  Several tests are proposed to check various parameters at the same time (overall tests).  In order to run the tests in a more economical way, other suitable solutions can be used, as for example, the “Grob Test” mixture, available from different suppliers (e.g. Alltech, Sigma, Thames Restek).  This commercial solution should be appropriate to the column material used. It is recommended to run the overall tests by using always the same test column, exclusively dedicated to qualification purposes, to guarantee reproducible conditions 9
  • 10.  1. Inlet system The following tests are proposed for the periodic and motivated check of the GC Inlet System. 1.1. Injector leak test Method: If not otherwise specified by the instrument manufacturer, the leak test is carried out according to the procedure laid down in the instrument manual or by the built in automatic leak check procedure of the instrument. Otherwise use the test described below: Disconnect the column from the injector and close the injector outlet with a sealed cap. Close the septum purge and the bypass. Adjust the flow and pressure controller to the maximal possible value of the pressure gauge. 10
  • 11. Adjust the flow controller to zero. Read the pressure after 1 minute and record the value. Record the pressure after 5 minutes. Limits: Pressure drop ≤ 15 kPa within 5 minutes.  1.2. Inlet pressure/flow accuracy and stability A direct measurement of these parameters was not deemed practical or necessary, but the optimal conditions of flow/pressure can be verified by the overall test 1. Limits: Refer to overall test 1  1.3. Repeatability of injection The verification of this parameter is covered by the overall test 1. This test is to be performed in both split and split less mode. Limits: Refer to overall test 1.
  • 12.  1.4. Injector temperature accuracy and stability Due to the fact that the temperature cannot be reliably measured without opening and modifying the system and due to the difficulties of introducing a probe inside this module, the verification of this parameter is considered to be covered by the overall test 2. Limits: Refer to overall test 2.  1.5. Injector carry over After having injected the solutions for the linearity test of the FID detector, in increasing order, inject the blank and measure the peaks that correspond to the major peaks (= analytes) in the linearity solutions. The verification of this parameter is covered by the overall test 3. Limits: Refer to overall test 3 12
  • 13.  2. OVEN 2.1. Repeatability of the oven temperature characteristics Due to the fact that the temperature cannot be reliably measured without opening and modifying the system conditions and that even when introducing a probe inside the oven, its location would not reflect the real temperature conditions at all points, the verification of this parameter is covered by the overall tests 2A and 2B. Limits: Refer to overall test 2.  3. FID DETECTOR The following tests are proposed for the periodic and motivated check of the GC FID detector. 3.1. FID detector linearity Increasing amounts of analyte are injected and a linear response should be obtained. The verification of this parameter is covered by the overall test 3. Limits: Refer to overall test 3. 13
  • 14. 3.2. Constant FID detector response The proper and reproducible functioning of the FID can be demonstrated by checking the peak areas obtained from a predefined standard solution. The verification of this parameter is covered by the overall test 1 or 2. Limits: Refer to overall test 1 or 2. 3.3. Fid detector noise and drift If the instrument has a built-in automatic system for the verification of the noise and drift, follow the manufacturer’s instructions and apply the defined acceptance criteria. Otherwise, use the test described below: Settings: Column installed Suitable flow, depending on column length/diameter No injection Oven temperature: 40°C Detector on and heated at working temperature (270- 300°C)
  • 15.  3.3. Fid detector noise and drift If the instrument has a built-in automatic system for the verification of the noise and drift, follow the manufacturer’s instructions and apply the defined acceptance criteria. Otherwise, use the test described below: Settings: Column installed Suitable flow, depending on column length/diameter No injection Oven temperature: 40°C Detector on and heated at working temperature (270- 300°C)15
  • 16.  Method: After stabilisation of the system, record the signal for 15 minutes. Noise: evaluate 10 periods of 1 minute and calculate the mean value. Drift: Evaluate the slope of the baseline over the 15 minutes. Limits: The acceptance criteria for these parameters have to be chosen in accordance with the instrument vendor’s instructions and the intended use of the instrument. If no instructions are given, the user has to pre-define these acceptance criteria by taking into account the previous experience and the intended use of the instrument. No fixed values can be pre-defined in this guideline due to the high variety of integration systems used and consequently the acceptance criteria may be expressed in different units (voltage, current, arbitrary units per time).
  • 17.  OVERALL TEST 1 The overall test 1 covers the following parameters: - Pressure/flow accuracy and stability in the inlet system: Retention time repeatability - Repeatability of injection: peak area precision - In split mode - In split less mode The test may be combined with overall test 3.  Split mode: Test solution: 1-octanol in n-hexane 1% (v/v) Settings: Column: SPB-1 (30m x 0.32mm ID x 0.25µm film) Carrier gas: He Velocity: 25cm/sec Split: 1:100 Injection: 1µl 17
  • 18. Injector temperature: 220°C Oven temperature: 100°C isotherm Detector temperature: 300°C Runtime: 8 min Retention time of 1-octanol: about 5 min  Split less mode: Stock solution: 1-octanol in n-hexane 1% (v/v) Test solution: Dilute 10 ml of the stock solution with nhexane to 100 ml (corresponds to 1µl/ml of 1-octanol in nhexane) Settings: Column: SPB-1, 30m, 0.32mm ID, 0.25µm film Carrier: He Velocity: 30cm/sec Split less injection: purge valve closed during 2 min Injection: 0.2µl of the test solution
  • 19. Injector Temperature: 220°C Oven Temperature: Initial 60°C for 4 min, 15°C/min. up to 135°C, final time 1min Detector temperature: 300°C Runtime: 9.5 min Retention time of 1-octanol: about 8 min Method: Carry out 6 consecutive injections of the test solution and calculate the RSD of the different peak areas and retention times. Limits: Retention time repeatability: the RSD of the retention times should be ≤ 2.0% Peak area precision (split and split less mode): the RSD of the peak areas should be ≤ 3.0%
  • 20.  OVERALL TEST 2 The overall test 2 covers the following parameters: - Injector, oven and detector temperature accuracy and stability: retention time repeatability - Two alternative tests are proposed 1.Overall test 2A Test solution: 0.035 ml 1-octanol 0.035 ml 2-octanone 0.035 ml 2,6-dimethylanilin 0.035 ml n-tridecane 0.035 ml n-tetradecane 35 mg n-eicosane Dissolved in 50 ml Dichloromethane
  • 21. Settings: Column: SPB-1 (30m x 0.32mm ID x 0.25µm film) Carrier gas: Helium Velocity: 25 cm/s Split: 1:100 Injection volume: 1 µl Injector temperature: 220°C Detector: FID Detector temperature: 300°C Gradient programme: 60°C (4 min), 5°C/min, 270°C (3 min) Method: Inject the solution twice and calculate the relative retention times in relation to n-eicosane (RRT = 1) The above table shows the approximately expected relative retention times. 21
  • 22. Method: Inject the solution twice and calculate the relative retention times in relation to n-eicosane (RRT = 1) The above table shows the approximately expected relative retention times. Limits: The RSD of each RRT from two consecutive injections should be ≤ 1.0% 22 Analyte 1-octanol 2-octanone N-tridecane N-tetra decan RRT 0.30 0.22 0.52 0.60
  • 23.  2.Overall test 2B Test Solution: 1.0% (W/W) n-Nonane and Hexadecane in Tetradecane. Settings: Column: Ultra-1 (25m x 0.32mm ID x 0.52µm film) Injection volume: 1 µl Solvent: Tetradecane Oven temperature: 110°C Gradient programme: 110°C, 20°C/min, 180°C (final time: 3.5 min) Detector temperature: 250°C Injector temperature: 200°C Detector: FID
  • 24.  Flow rates: Carrier gas (Helium): 2 ± 0.2 ml/min Hydrogen: 30 ± 1.0 ml/min Air: 400 ± 20.0 ml/min Makeup (Nitrogen): 28 ± 1.0 ml/min Split ratio: 15 Split vent: 30 ± 3.0 ml/min Septum purge: 3-5 ml/min Method: Allow the system to equilibrate Injection sequence: 1) Blank (Tetradecane) 2) 6 replicates of the test solution. 24
  • 25.  Calculate the mean of the retention times and peak areas and the relative standard deviation of n-Nonane and n-Hexadecane Limits: Retention time repeatability: RSD of the peak retention times of the 6 replicates ≤ 2% Retention time (Rt) accuracy: for this example, the retention time ranges shown in the table below are proposed. Nevertheless, individual ranges should be predefined by the laboratory depending on the column used (e.g. Rt ± 0.2 min).  OVERALL TEST 3 This test is a modified version of the overall test 1 to be used for the verification of: - Detector linearity: linearity of the areas recorded - Injector carry-over: area recorded in the blank run It is described for both split and split less mode and may be combined with overall test 1.
  • 26. Split mode: Test solution: 1-octanol in n-hexane 1% (v/v) Prepare further reference solutions by diluting the test solution as described below. Settings: see overall test 1 Injection sequence: 5.0 ml of the test solution diluted to 25.0 ml with n-hexane (2 µl/ml): 2 injections 10.0 ml of the test solution diluted to 25.0 ml with nhexane (4 µl/ml): 2 injections 15.0 ml of the test solution diluted to 25.0 ml with n-hexane (6 µl/ml): 2 injections 20.0 ml of the test solution diluted to 25.0 ml with n-hexane (8 µl/ml): 2 injections If combined with overall test 1 for repeatability: test solution (10 µl/ml): 6 injections n-hexane as blank (carry over) 26
  • 27. Split less mode: Stock solution: 1-octanol in n-hexane 1% (v/v) Test solution: Dilute 10 ml of the stock solution with nhexane to 100 ml (corresponds to 1µl/ml of 1-octanol in nhexane). Prepare further reference solutions by diluting the test solution with n- hexane. Settings: see overall test 1 Injection sequence: 5.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.2 µl/ml): 2 injections 10.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.4 µl/ml): 2 injections 15.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.6 µl/ml): 2 injections 20.0 ml of the test solution diluted to 25.0 ml with n-hexane (0.8 µl/ml): 2 injections If combined with overall test 1 for repeatability: test solution (1 µl/ml): 6 injections n-hexane as blank (carry over)
  • 28. Linearity: coefficient of correlation of the calibration line obtained with the reference solutions and the test solution: r 2 ≥ 0.999. Carry-over: the percentage of the peak area corresponding to the analyte in the blank solution should be ≤ 0.2% of the peak area of this analyte in the chromatogram obtained with the solution with the highest concentration within the sequence 28
  • 29.  Level IV. In-use instrument checks Examples of requirements for GC instruments with FID  29 Parameter to be checked Typical tolerance limit 1. System suitability check for the method According to Ph. Eur. or MAH dossier or validated in-house method 2. Peak area precision RSD ≤ 3.0% unless otherwise prescribed* 3. Retention time repeatability RSD ≤ 2.0% 4. Sensitivity (where relevant, e.g. for related substances tests) According to Ph. Eur. or MAH dossier or validated in-house method
  • 30.  Reference: Ph.Eur.2.2.35 chromatography; gas chromatography Guidance on equipment qualification of analytical instruments Journal of Perkin Elmer life & analytical science
  • 31. Qualification of Analytical Equipments High Performance Liquid Chromatography 31
  • 32. Introduction  QUALIFICATION: Action of proving and documenting that equipment or ancillary systems are properly installed, work correctly, and actually lead to the expected results. The entire qualification consists of four parts: 1. Design qualification(DQ). 2. Installation qualification(IQ). 3. Operational qualification(OQ). 4. Performance qualification(PQ). 32
  • 33.  1.Design qualification(D.Q): It describe the user requirements and defines the functional and operational specifications of the instrument. DQ should ensure that instrument to be purchased have the necessary functions and performance that will enable for suitable intended application.  2.Installation Qualification (I.Q): The purpose of I.Q is to check the installation site/ environment, confirms equipment specifications and verifies the condition of installed equipment.  3.Operational Qualification (O.Q): O.Q includes procedures and documentation of O.Q of analytical instrument. When all procedures are executed and all items pass the inspection, it is verified that the system operates to satisfy the intended purpose. 33
  • 34.  4.Performance Qualification (P.Q): The objective is to ensure that the instrument is performing within specified limits. Hence documented verification that the equipment and ancillary systems, as connected together, can perform effectively and reproducibly based on the approved process method and specifications.
  • 35. Qualification of HPLC  1. Design qualification: 35 Design element example Maintenance •Vendor must deliver maintenance procedure and recommended schedule •Instrument must include early maintenance feedback for timely exchange of most important maintenance parts. •Maintenance procedure must be supplied on multimedia CD ROM Intended use Analysis of drug components and impurities.
  • 36. Design element Examples User requirements specification for the HPLC analysis •Up to 100 samples/day •Automated over night analysis. •Limit of quantitation:0.1% •Automated confirmation of peak identity and purity with diode-array detection •Automated compound quantization and printing of report. FUNCTIONAL SPECIFICATION: •Pump •Detector •Auto sampler •Column compartment •Computer •Binary or higher gradient •UV/VIS Diode array,190-900nm •100 samples, 0.5µl to 5ml sample volume •15 to 60ºc controlled. •System control, data acquisition for signals and spectra, peak integration and quantitation 4 36
  • 37. Design element Examples Operational specification •Detector: base line noise:<5 x 10-5 AU •Sampler: precision inj. Volume : <0.5% RSD. Sample carry over:<0.5% •Pump: precision of retain time: <0.5% RSD. User instruction •Operation manual on paper •Computer based tutorial Qualification The vendor must provide procedures and services for IQ and OQ 37
  • 38.  2.INSTALLATION QUALIFICATION: Installation qualification establishes that the instrument is received as design and specified. •It establishes that instrument is properly installed in the selected environment and that environment should be suitable for operation of the instrument. •Run of test samples verifies correct installation of all modules, electrical and fluid connections  BEFORE INSTALLATION ?  Obtain manufacturers recommendations for installation site requirements  Check the site for the fulfillment of the manufacturers recommendation (utilities such as electricity and environment condition such as humidity and temperature)  Allow sufficient shelf space for the equipment, SOPs, operating manual and software. 38
  • 39.  DURING INSTALLATION ?  Compare equipment as received , with purchase order (including software, accessories, spare parts).  Check documentation for completeness (operating manuals, maintenance instruction, standard operating procedure for testing , safety and validation certificate)  Check equipment for any damage.  Install hardware( computer, equipment, fittings and tubings, for fluid connections , column in HPLC , power cables , data flow and instrument control table)  Switch on the instrument and ensure that all modules power up and perform an electronic self test.  Identify and a make a list with a description of all hardware, include drawings where necessary  Run test sample and compare chromatogram print out with reference chromatogram.  Prepare an installation report.
  • 40.  3.OPERATIONAL QUALIFICATION: It is the process of demonstrating that an instrument will function according to its operational specification in the selected environment . It verifies that the HPLC system compiles with key function and operational requirements as specified in the design qualification . In operational specification the supplier must define exactly the conditions that must be observed with varying conditions. Eg: different ambient temperature. Before performing all other test first perform leak test if, it is failed then most of the remaining test will get failed. 40
  • 41.  Test parameters and acceptance criteria : 41 Parameter Procedure User limit Leak testing Flow test by volume or weight/time ±5% Baseline drift ASTM (American society for testing material) method E19.09, 20 min <2 x 10-3 AU Baseline noise ASTM method E19.09, 20 min x 1 <5 x 10—5 AU Precision of injection volume 6 x injection of caffeine standard, RSD of peak areas 0.3% RSD Precision of flow rate 6 x injection of caffeine standard, RSD of retention times 0.5% RSD
  • 42. PARAMETER PROCEDURE USER LIMIT Detector linearity Inject 5 standards >1.5 AU, 5% RSD Wavelength accuracy Holmium oxide filter ±1 nm Temperature accuracy Comparison with external measuring device ± 1º c Temperature precision Monitoring temperature over 20 mins ±0.25 ºc Auto sampler carry over Injection of large sample after large concentration < 0.5% Mobile phase composition accuracy Step gradient from 4 to 7% B, Step heights relative to 100% with acetone tracer ±1% 42
  • 43.  Baseline noise and drift: •Drift and baseline noise are important factors for UV detectors. Increased baseline noise considerably reduces the sensitivity, as it is not possible to distinguish between low-level signals and noise. With increased drift, it is more difficult to integrate the signals correctly because the less stable the baseline is, the more inaccurate is integration. •The baseline noise of the detector mainly depends on the lamp. There is a considerable increase in noise if an old lamp with poor light intensity is used. This is also true when the flow cells is dirty. In addition make sure that the flow cells free from gas bubbles. •To measure the drift of a UV detector, also make sure that all measuring conditions are constant. In addition, it is very important that the lamp has been burning for several hours in the detector environment, avoid direct sunlight. •The lamp intensity decreases while the lamp is burning. Besides, the lamp ages when it is turned on and off very often. 43
  • 44.  Evaluating baseline noise and drift: •TO check noise, drift water is pumped through the cell at a flow rate of 1ml/min. The UV signal is recorded at 254nm. •To calculate noise the measuring signal is split into 20 intervals for 1min each. For each interval chromeleon calculates a regression based on measured values, using the method of least square. The limit should be between <2 x 103 AU. •To calculate the drift, chromeleon calculates a regression line from all data points with in a range of 1-21mins based on the method of least square. The slope of the regression line is the calculated drift. The limit should be between <5 x 10—5 AU. 44
  • 45.  Precision of injection volume: •Precision of injection volume is an important parameter for accuracy of quantitation.  Evaluating precision of injection volume: •Inject 6 standard caffeine solution and calculate height, area, average height, average area, %RSD of height and %RSD of area which gives precision of volume and the limit should be in between 0.3% RSD.  Detector linearity: •Linearity of a detector is a critical parameter to establish for reliable and accurate quantitative results.
  • 46.  Evaluating detector linearity: •A series of 5 traceable standards (caffeine solution of concentration about 0.00035 to 0.35mg/ml) are injected and evaluated. The detector linearity is calculated by determining the peak area vs concentration. %RSD can also be calculated for checking the detector linearity. The limit should be in between >1.5 AU, 5% RSD.  Wavelength accuracy: •It is an important parameter for accuracy of quantitative and qualitative analysis.  Evaluating wavelength accuracy: •Traceable caffeine standard is used to determine the wavelength accuracy. Caffeine is trapped in the flow cell and a programmable timetable is used to determine the wavelength maxima (205nm) and minima (273nm). The wavelength accuracy is determined as the absolute difference between the measured and certified wavelength values 46
  • 47.  Temperature accuracy: Temperature fluctuations of the solvent and column can result in considerable retention time fluctuations. Therefore, accuracy of the temperature is important.  Evaluating temperature accuracy: 4 measuring points are used to check the temperature accuracy of the column compartment. The check is performed with column oven sequence. The achieved temperature is measured with external calibrated thermometer. The achieved temperatures are compared to the set values. The difference indicates the temperature accuracy and the limit should be in between ± 1º c  Temperature precision: Monitor temperature for 20minutes and limit should be in between ±0.25 ºc 
  • 48.  Gradient mobile phase composition accuracy: It is important for accurate quantitative analysis.  Evaluating gradient mobile phase composition accuracy: An Acetone tracer is used to determine gradient mobile phase accuracy, stability and linearity. Make 6 compositions of water+acetone in concentration of 0%,20%,40%,60%,80% and 100% (20% increment). Linear ramp down from 100% to 0% is performed where the composition linearity is determined between ranges of 95,75 and 25%. All compositions accuracies are calculated as the absolute difference between the mean composition at each set point and the theoretical composition. 48
  • 49.  4.Performance qualification:  It is the process of demonstrating that an instrument consistently performs according to a specification appropriate for its routine use.  Important here is the word consistently. The test frequency is much higher than for OQ. Another difference is that PQ should always be performed under conditions that are similar to routine sample analysis. For a chromatogram this means using the same column, the same analysis conditions and the same or similar test compounds.  PQ should be performed on a daily basis or whenever the instrument is used.  The test frequency of only depends on the stability of the equipment but on everything in the system that may contribute to analysis the result For a liquid chromatograph, this may be the chromatographic column or a detectors lamp 49
  • 50.  The test criteria and the frequency should be determined during the development and the validation of the analytical method. In practice PQ mean system stability testing , where critical key system performance characteristic are measured and compared with documented , preset limit.  For example, a well characterized standard can be injected 5 or 6 times and the standard deviation of amounts are then compared with predefined value  If the limits of detection and quantifications are critical, the lamps intensity profile or the base line should be tested they should use the same column and chemicals for the real sample.
  • 51. Test should include: •Precision of the amounts •Precision of retention times •Resolution between two peaks •Peak width at half height •Peak tailing •Baseline noise •Wavelength accuracy of the uv/vis wavelength detector, preferably using built-in holmium – oxide filters  REFERENCES: •Ph.Eur.2.2.35chromatography; High performance liquid chromatography •Guidance on equipment qualification of analytical instruments •Journal of Perkin Elmer life & analytical science 51
  • 53. Introduction  QUALIFICATION: Action of proving and documenting that equipment or ancillary systems are properly installed, work correctly, and actually lead to the expected results. The entire qualification consists of four parts: 1. Design qualification(DQ). 2. Installation qualification(IQ). 3. Operational qualification(OQ). 4. Performance qualification(PQ). 53
  • 54.  1.Design qualification(D.Q): It describe the user requirements and defines the functional and operational specifications of the instrument. DQ should ensure that instrument to be purchased have the necessary functions and performance that will enable for suitable intended application.  2.Installation Qualification (I.Q): The purpose of I.Q is to check the installation site/ environment, confirms equipment specifications and verifies the condition of installed equipment.  3.Operational Qualification (O.Q): O.Q includes procedures and documentation of O.Q of analytical instrument. When all procedures are executed and all items pass the inspection, it is verified that the system operates to satisfy the intended purpose. 54
  • 55.  4.Performance Qualification (P.Q): The objective is to ensure that the instrument is performing within specified limits. Hence documented verification that the equipment and ancillary systems, as connected together, can perform effectively and reproducibly based on the approved process method and specifications. 55
  • 56. QUALIFICATION OF IR SPECTROPHOTOMETER  INTRODUCTION The present document explains about “Qualification of Equipment(IR Spectrophotometer)”, It should be used in combination with it when planning, performing and documenting the IR spectrophotometer qualification process. The document contains the Introduction and general forms for Level I and II of qualification, which are common to all type of instruments. For FTIR spectrometers, an example has been added to give instrument-specific proposals that may be used in combination with the general requirements presented in the core document “Qualification of Equipment”, when drawing up a Level I checklist. 56
  • 57. The present annex contains instrument-related recommendations on parameters to be checked at Level III and IV of qualification and the corresponding typical acceptance limits, as well as practical examples on the methodology that can be used to carry out these checks.  Level I. Selection Of Instruments & Suppliers Example of check-list (Non-Exhaustive) Manufacturer:____________ Provider/ Distributor:___________ Name Of Instrument and Type: __________ 57
  • 58.  58 Attribute (This list may be adapted if necessary) Specifications Benefits (Instrument/ supplier) Assessment (Pass/Fail) SPECTROPHOTO METER Detector range The optical bench shall include a DTGS detector with a frequency range of 7400 to 350 cm-1 It shall include a compressed air interferometer Spectral resolution The instrument shall come with an air-cooled standard infrared source.
  • 59. Attribute (This list may be adapted if necessary) Specifications Benefits (Instrument/ supplier) Assessment (Pass/Fail) Wave number accuracy The instrument shall have a spectral resolution not exceeding 1.0 cm-1 The interferometer shall have at least four basic velocity levels: software shall permit the selection of a greater number of velocities between the basic levels. Wave number accuracy shall be better than +- 0.01 cm-1 The mirror’s greatest velocity shall allow a speed of at least five sweeps per second The laser and infrared beams must be coaxial to enable rapid, easy alignment of the system, depending on the samples or accessories 59
  • 60. ughjhjkjk Attribute (This list may be adapted if necessary) Specifications Benefits (Instrument/ supplier) Assessment (Pass/Fail) The optical bench shall have main experimentation module with a device to allow purging with nitrogen At purchase, the main experimentation module shall be designed so it can receive 13 and 5 mm potassium bromide pellets 60 Notes: - This check-list, containing examples of technical attributes that can be taken into account in the selection of an instrument and supplier, can be used in combination with the general check-list presented in Level I in the core document “Qualification of Equipment”.
  • 61. Level II of Equipment Qualification: Installation and Release for use It is recommended to check all requirements set during the selection of the instrument, and calibration should be performed before putting into service by an accredited external service supplier, or Internally by appropriately qualified personnel, using certified reference buffers according to an approved procedure. 61
  • 62.  Level III. Periodic & Motivated Instrument Checks Examples of requirements for IR spectrophotometers Parameters to be checked 1. Wave-number scale 2. Detector energy ratio 3. Signal/Noise ratio 4. Resolution 5. Zero test 6. Contamination check (only for ATR instruments) 7. Throughput check (only for ATR instruments) 62
  • 63.  1.WAVE-NUMBER SCALE Method and Limits: The wave-number scale may be verified by recording the spectrum of a polystyrene film, which has transmission minima (absorption maxima) at the wave numbers (in cm-1 ) shown in the table below: 63 TRANSMISSION MINIMA (cm -1) ACCEPTABLE TOLERANCE (cm -1) monochromatic instruments FTI±R instruments 3060.0 ±1.5 ±1.0 2849.5 ±2.0 ±1.0 1942.9 ±1.0 ±1.0 1601.2 ±1.0 ±1.0 1583.0 ±1.0 ±1.0 1154.5 ±1.0 ±1.0 1028.3 ±1.0 ±1.0
  • 64.  2. DETECTOR ENERGY RATIO: Method: Record the minimum energy ratio value for at least one of the following measurement points and compare it to the vendor’s specifications: - ◦ Energy at 3990 cm-1 / energy at 2000 cm-1 ◦ Energy at 4000 cm-1 / energy at 2000 cm-1 ◦ Energy at 3400 cm-1 / energy at 1300 cm-1 ◦ Energy at 2000 cm-1 / energy at 1000 cm-1 Limits: Energy ratio test specifications vary for each spectrometer configuration. The optical bench shall include a DTGS detector with a frequency range of 7400 to 350 cm-1 64
  • 65.  3. SIGNAL/NOISE RATIO : Method: Record the maximum noise level for each of the following regions: Peak-to-peak noise between: ◦ 4050 cm-1 and 3950 cm-1 ◦ 2050 cm-1 and 1950 cm-1 ◦ 1050 cm-1 and 950 cm-1 ◦ 550 cm-1 and 450 cm-1 (systems with DTGS detector only) RMS (root mean square) noise between: ◦ 4050 cm-1 and 3950 cm-1 ◦ 2050 cm-1 and 1950 cm-1 ◦ 1050 cm-1 and 950 cm-1 ◦ 550 cm-1 and 450 cm-1 (systems with DTGS detector only) Limits (% T): Noise level test specifications vary for each spectrometer configuration. 65
  • 66.  4. RESOLUTION : Materials: Certified polystyrene film of approximately 35 µm in thickness. Method: - For instruments having a monochromator, record the spectrum of the polystyrene film. - For Fourier-transform instruments, use suitable instrument resolution with the appropriate apodisation prescribed by the manufacturer. The resolution is checked by suitable means, for example by recording the spectrum of a polystyrene film approximately 35 µm in thickness. Limits: -Difference between the absorbance's at the absorption minimum at 2870 cm-1 and the absorption maximum at 2849.5 cm-1 > 0.33. - Difference between the absorbance's at the absorption minimum at 1589 cm-1 and the absorption maximum at 1583 cm-1 > 0.08. 66
  • 67.  5. ZERO TEST Method: When using a polystyrene film of approximately 35 µm in thickness as standard at the wavelength of 2925 cm-1 and 700 cm-1 , almost complete absorption of the irradiated energy can be observed. With this test, the remaining transmission is measured. As the maximum absorption can be observed at 700 cm-1 negative values may be observed. The objective of the test is to evaluate if, despite the fact that there is almost complete absorption, energy is still detectable. Non-valid results are an indication of a non-linear behaviour of the detector and the electronic system.  6. CONTAMINATION TEST (Only for Attenuated Total Reflection (ATR) instruments) Note: If an automated system is available, this test can be run more frequently or it can be transferred to Level IV, to be run before each analysis. 67
  • 68. This test checks the presence of peaks that signal a contamination problem. Use the automated function of the instrument (if available)to perform this test. If not available, record a background spectrum. Limits: Wave No.(cm-1) Upper limit(A) 3100-2800 0.1 1800-1600 0.1 1400-1100 0.2 68
  • 69.  7. THROUGHPUT CHECK : (Only for Attenuated Total Reflection (ATR) instruments) Note: If an automated system is available, this test can be run more frequently or it can be transferred to Level IV, to be run before each analysis. Method: This test checks for an unexpected reduction of the transmittance. An instrument specific automated test can be used. A background spectrum is recorded and the transmittance is measured at 3 wave numbers e.g. 4000, 2600 and 1000 cm-1 . Limits: The lower limit of the transmittance for the 3 wave numbers must be 80 %  REFERENCES: Ph Eur. 2.2.24, Absorption spectrophotometer, Infrared. Guidance on equipment qualification of analytical instruments. Journal of perkinelmer life and analytical sciences. 69
  • 70. Qualification of Analytical Equipment Liquid Chromatography with Mass Spectrometer (LC-MS)
  • 71. Introduction  QUALIFICATION: Action of proving and documenting that equipment or ancillary systems are properly installed, work correctly, and actually lead to the expected results. The entire qualification consists of four parts: 1. Design qualification(DQ). 2. Installation qualification(IQ). 3. Operational qualification(OQ). 4. Performance qualification(PQ). 71
  • 72.  1.Design qualification(D.Q): It describe the user requirements and defines the functional and operational specifications of the instrument. DQ should ensure that instrument to be purchased have the necessary functions and performance that will enable for suitable intended application.  2.Installation Qualification (I.Q): The purpose of I.Q is to check the installation site/ environment, confirms equipment specifications and verifies the condition of installed equipment.  3.Operational Qualification (O.Q): O.Q includes procedures and documentation of O.Q of analytical instrument. When all procedures are executed and all items pass the inspection, it is verified that the system operates to satisfy the intended purpose. 72
  • 73.  4.Performance Qualification (P.Q): The objective is to ensure that the instrument is performing within specified limits. Hence documented verification that the equipment and ancillary systems, as connected together, can perform effectively and reproducibly based on the approved process method and specifications. 73
  • 74. Qualification of Mass Spectroscopy  The context of validation for mass spectrometry (MS)-based methods is critically analysed. The focus is on the fitness for purpose depending on the task of the method.  Information is given on commonly accepted procedures for the implementation and acceptance of analytical methods as 'confirmatory methods' according to EU criteria, and strategies for measurement.  Beneficial aspects of the qualification process to ensure the suitability of the MS analytical system are also evaluated and discussed.
  • 75.  LEVEL I: Design Qualification:  design qualification is is the documented collection of activities that define the functional and operational specification of the instrument and criteria for selection of vendor, based on intended performance of the instrument.  The user should ensure that commercial off the shelf(COTS) instruments are suitable for their intended to application and that the manufacturer should adopt the quality systemthat provide for reliable equipment.  All hardware and software laboratory products including operating system and software used to deliver qualification service are design, manufacturing and tested according to company's life cycle development procedure.
  • 76.  Level II: Operational Qualification:  Temperature accuracy and stability of column heater/cooler  Holmium oxide wavelength scan (if applicable)  Detector lamp intensity and wavelength accuracy  Detector noise and drift  Pump flow rate accuracy and repeatability  High and low pressure shutdown accuracy  Injector precision  Detector linearity and sample- to-sample carryover  Injection volume linearity  Gradient composition accuracy  Linear gradient tested using IPA and 0.5% Acetone/IPA  Five step gradient tested using IPA and 0.5% Acetone/IPA
  • 77.  Level III. Periodic and motivated instrument checks requirements for GC-EI-MS (examples)  *) PFTBA (FC-43): Perfluoro-tributyl-amine (CAS NO.: 311-89-7) **) In case of quantification purposes, these parameters have to be checked Parameter to be checked Typical tolerance limits Mass accuracy PFTBA (FC-43)*) or internal calibration gas m/z = 69 ± 0.5 m/z = 219 ± 0.5 m/z = 502 ± 0.5 or defined masses of internal calibration gas ± 0.5 Linearity**) r² ≥ 0.995 System/instrument precision**) ≤ 10.0%
  • 78.  Level III contains practical examples of tests and their associated tolerance limits for several parameters related to the performance of GC-EI-MS. These examples can be considered by the OMCLs (Official Medicine Control Laboratory) as possible approaches to perform the Level III of the equipment qualification process: “Periodic and motivated instrument checks”. GENERAL CONSIDERATIONS - GC-MS is mainly used for the identification of unknown substances or quantification of low concentrated substances where high specificity is needed.
  • 79.  MASS ACCURACY Materials: PFTBA (FC-43) or internal calibration gas Method: Internal instrument check or spectrum of PFTBA (FC-43) in full scan mode Limits: m/z = 69 ± 0.5 m/z = 219 ± 0.5 m/z = 502 ± 0.5  Note: the tolerance limits for mass accuracy are only valid for quadrupole and ion trap mass spectrometers. Instruments like Time-of-Flight (TOF) or hybrid instruments like quadrupole Time- of-Flight (QTOF) have a much better mass accuracy and adequate requirements should be applied by the laboratory.
  • 80.  LINEARITY Materials: Stock solutions: 1-Octanol in dichloromethane 0.2, 0.4, 0.6, 0.8, 1.0 µL/mL Method: 2 injections of each level (injection volume: 1.0 µL) Limits: r² ≥ 0.995  SYSTEM/INSTRUMENT PRECISION Materials: Stock solution: 1-Octanol in dichloromethane 1.0 µL/mL Method: 6 injections (injection volume: 1.0 µL) Limits (minimum requirement): RSD ≤ 10.0% (without internal standard)
  • 81.  Level IV. In-use instrument checks Requirements for GC-EI-MS Parameter to be checked Typical tolerance limits As defined by the specific analysis method or according to the Ph. Eur. or the MAH dossier Identified by library or with reference standard
  • 82.  Level IV contains practical examples of tests and their associated tolerance limits for several parameters related to the performance of GC- EI-MS. These examples can be considered by the OMCLs as possible approaches to perform the Level IV of the equipment qualification process: “In-use instrument checks”.  SYSTEM/INSTRUMENT PRECISION **) Materials: Any of the above-mentioned reference standard solutions used for the identification Method: 6 injections (injection volume: 1.0 µL) Limits (minimum requirement): RSD ≤ 10.0% **) in case of use for quantification Other tests according to the system suitability of the analysis method in use
  • 83. Reference:  https://shop.perkinelmer.com/Content/technicalinfo/tch_glpformatof hplcandlcmssystems.pdf  OMCL Network of the Council of Europe QUALITY MANAGEMENT DOCUMENT PA/PH/OMCL (10) 86 2R QUALIFICATION OF EQUIPMENT ANNEX 7: QUALIFICATION OF MASS SPECTROMETERS  Equipment Qualification Plan, Aligent Enterprice Edition Compliance Services.